Beam lifting type jacking deviation correction pre-control mechanism for pseudo-classic architecture and mounting method of beam lifting type jacking deviation correction pre-control mechanism
By using a lift-beam-type lifting correction and pre-control mechanism in antique buildings, and using mortise and tenon components and correction and pre-control components to connect wooden columns and wooden beams, the problem of cross beam skew caused by settlement and other factors in antique buildings is solved, and wooden beams are realized The horizontal bearing and overall structural stability avoid the risk of collapse.
Patent Information
- Application Number
- CN202411401042.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-09
- Publication Date
- 2024-12-03
AI Technical Summary
During long-term use of antique buildings, columns are settled in steady state due to factors such as settlement and earthquakes, and the beams are prone to be crooked, which affects the aesthetics and may lead to overall collapse.
The lifting beam-type lifting bias correction pre-control mechanism is adopted to connect wooden columns and wooden beams through mortise and tenon components and bias correction pre-control components. The horse teeth joint structure and steel-wood composite structure are used to ensure that the wooden beams are always in a horizontal load-bearing state and are passed through springs. The damping holes are corrected and adjusted to reduce shear stress and linear expansion deformation.
It effectively improves the integrity and connection stability of wooden beams and wooden columns, ensures that wooden beams are always in a horizontal state, improves the stress system of antique buildings, reduces the risk of collapse and maintains aesthetics.
Smart Images

Figure CN119062149A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of antique buildings, and in particular to a beam-lifting jacking deviation correction pre-control mechanism for antique buildings and an installation method thereof. Background Art
[0002] Antique architecture refers to buildings that are specifically used to imitate and replace ancient buildings, traditional religious temples, traditional landscaping, historical buildings, cultural relics buildings, and ancient villages, and to restore the historical features and appearance; this architectural style focuses on inheriting and promoting ancient culture, not only reproducing the style of ancient buildings in appearance, but also incorporating ancient cultural symbols and stories.
[0003] At present, in order to achieve the effect of natural ventilation and temperature regulation, antique buildings are generally constructed with wood; among them, the columns and beams in antique buildings generally play the role of bearing loads.
[0004] However, during long-term use, antique buildings are prone to steady-state settlement of columns due to the influence of settlement, earthquakes, large vibrations near the buildings, etc., which can easily cause the beams to tilt, affecting the aesthetics; even if not improved in time, it is easy to cause overall collapse. Summary of the invention
[0005] In order to improve the problems existing in the above-mentioned technology, the present application provides a beam-lifting jacking deviation correction pre-control mechanism for antique buildings and an installation method thereof.
[0006] In the first aspect, the present application provides a beam lifting and deviation correction pre-control mechanism for antique buildings and an installation method thereof, which adopts the following technical solutions: A beam-lifting jacking deviation correction pre-control mechanism for antique buildings, comprising: a wooden column and two wooden beams, wherein the wooden beams are connected to the wooden column by a mortise and tenon assembly, and a deviation correction pre-control assembly is arranged between the wooden beams and the wooden column; The mortise and tenon assembly includes: two convex half-mortises, and a half-mortise groove is opened through the wooden column, one of the convex half-mortises is fixed on one of the wooden beams, and the other convex half-mortise is fixed on the other wooden beam, and the convex half-mortise is arranged in the half-mortise groove.
[0007] By adopting the above technical solution, when a wooden column undergoes a significant settlement, the wooden beam on the side that needs to be corrected corresponding to the settled wooden column is lifted by the jacking equipment, and the correction pre-control component can ensure that the wooden beam that transmits force is always in a horizontal bearing state, so as to improve the overall force system state of the antique building.
[0008] Optionally, the connection between the two convex half-tenons is in a horse-tooth joint structure.
[0009] By adopting the above technical solution and connecting two wooden beams and wooden columns by means of a tooth joint structure, the integrity of the wooden beams and wooden columns and the stability of the connection between the wooden beams and wooden columns can be effectively improved.
[0010] Optionally, the mortise and tenon assembly further includes: a replacement wood strip and an anchoring replacement wood. An anchoring groove is provided at the bottom of the half-mortise groove, and the anchoring replacement wood is arranged in the anchoring groove. A through-mortise replacement wood groove is provided through the wooden beam, one end of the replacement wood strip passes through the through-mortise replacement wood groove, and the other end is connected to the anchoring replacement wood.
[0011] By adopting the above technical solution, after the wooden beams are connected to the wooden columns, the replacement wood strips are passed through the tenon replacement wood grooves, and the replacement wood strips are connected to the anchor replacement wood, thereby not only realizing the horizontal constraint of the wooden beams, but also strengthening the lateral connection between the wooden columns and the wooden beams.
[0012] Optionally, the deviation correction and pre-control component includes: a pressure-bearing part, which includes: a pressure-bearing steel plate and a pressure-bearing wooden board, the pressure-bearing wooden board is arranged on the top wall of the anchoring replacement wood, the pressure-bearing steel plate is arranged on the pressure-bearing wooden board, and a constraint groove is opened on the supporting steel plate, and the end of the replacement wood bar away from the wooden beam is arranged in the constraint groove.
[0013] By adopting the above technical solution and using a steel-wood composite method, not only can local stiffness be ensured so that the end load of the wooden beam can be effectively and evenly transferred to the wooden column, but also flexible protection can be provided for the contact surface below the wooden beam, which not only makes it difficult for the edge of the pressure-bearing steel plate to directly crush the wooden column locally, but also provides flexible operating space for subsequent correction.
[0014] Optionally, the deviation correction pre-control component also includes: a limiting part, the limiting part includes: an upper plate, a lower plate and a spring, the upper plate and the lower plate are both embedded in the half-tenon groove, and the lower plate is fixed on the convex half-tenon, and the spring is fixed between the upper plate and the lower plate.
[0015] By adopting the above technical solution, when correcting the deviation, the wooden beam on the side that needs to be corrected is lifted up. During this process, the spring compresses itself to achieve the effective height of raising the wooden beam on the side that needs to be corrected, thereby ensuring that the wooden beam is always in a horizontal load-bearing state.
[0016] Optionally, the deviation correction and pre-control component also includes: a sticking pot part, which includes: a disc, a metal rod and a friction sleeve, the upper plate and the lower plate are both provided with damping holes, the disc is arranged in the damping hole, the friction sleeve is fixedly sleeved on the circumferential wall of the disc, one end of the metal rod is fixed to the disc, and the other end is fixed to the upper plate and the lower plate.
[0017] By adopting the above technical solution, the friction between the disk and the inner wall of the damping hole generates a damping force to reversely restrain the movement trend of the spring, thereby achieving the goal that no excess gap is likely to appear as a whole after the wooden beam is lifted and displaced.
[0018] Optionally, the width of the anchoring groove is equal to 1 / 4-1 / 3 of the diameter of the wooden column.
[0019] By adopting the above technical solution, such a setting method can effectively reduce the shear stress along the grain transmitted from the wooden beam to the wooden column, thereby improving the connection stability between the wooden beam and the wooden column.
[0020] Optionally, the upper plate and the lower plate are both made of peeled and glued wood.
[0021] By adopting the above technical solution, such an arrangement can ensure that deformation joints with excessively large differences in linear expansion coefficients are unlikely to occur between the upper plate, the lower plate, and the wooden columns and beams during normal use.
[0022] Optionally, the cross-section of the replacement wood strip is trapezoidal or semicircular.
[0023] By adopting the above technical solution, such a setting method can not only realize horizontal constraint on the wooden beam, but also increase the contact surface between the replacement wood strips and the wooden beams, thereby reducing the influence of the replacement wood strips on the overall strength and rigidity of the wooden columns and wooden beams.
[0024] In a second aspect, the present application also provides an installation method of a beam lifting and deviation correction pre-control mechanism for antique buildings, which adopts the following technical solution: A method for installing a beam lifting and deviation correction pre-control mechanism for antique buildings comprises the following steps: S1: Make wooden columns and position and open half-mortise and tenon grooves and anchor grooves on them; S2: production of wooden beams and convex half-mortises; S3: Install the pressure-bearing part onto the anchoring wood, install the anchoring wood into the anchoring groove, and adjust the entire top surface to be horizontal; S4: Install the limiting part to the top of the convex half tenon, and apply pressure to the limiting part as a whole until the top of the limiting part and the top of the wooden beam are at the same horizontal height, so as to embed the convex half tenon into the half tenon groove; S5: Fix the replacement wood strip between the wooden beam and the pressure-bearing part to achieve the purpose of horizontal restraint of the wooden beam.
[0025] By adopting the above technical solution, the deviation correction pre-control component can be quickly installed between the wooden column and the wooden beam, so as to subsequently correct the deviation of the wooden beam.
[0026] In summary, the present application includes at least one of the following beneficial effects: 1. When a wooden column undergoes a significant settlement, the wooden beam on the side that needs to be corrected corresponding to the settled wooden column is lifted by the lifting equipment, and the correction pre-control component can ensure that the force-transmitting wooden beam is always in a horizontal bearing state, so as to improve the overall force system state of the antique building.
[0027] 2. Using the tooth joint structure to connect two wooden beams and wooden columns can effectively improve the integrity of the wooden beams and wooden columns, as well as the stability of the connection between the wooden beams and wooden columns.
[0028] 3. This setting method can not only realize horizontal constraint on the wooden beams, but also increase the contact area between the replacement strips and the wooden beams, thereby reducing the impact of the replacement strips on the overall strength and stiffness of the wooden columns and wooden beams. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] Figure 1 is a schematic diagram of the structure according to an embodiment of the present application; Figure 2 yes Figure 1 A schematic top view of Figure 3 is along Figure 2 A schematic cross-sectional view taken along the cutting line AA in FIG. Figure 4 yes Figure 3 Schematic partial enlarged view of part B.
[0030] In the figure: 1. wooden column; 11. half mortise and tenon groove; 12. anchoring groove; 2. mortise and tenon assembly; 21. convex half mortise and tenon; 22. substitute wood strip; 23. anchoring substitute wood; 3. pressure-bearing part; 31. pressure-bearing steel plate; 311. constraint groove; 32. pressure-bearing wooden board; 4. limiting part; 41. upper plate; 42. lower plate; 43. spring; 44. damping hole; 5. sticking pot part; 51. disc; 52. metal rod; 53. friction sleeve; 6. wooden beam; 61. through mortise and tenon substitute wood groove. DETAILED DESCRIPTION
[0031] The present application provides a beam lifting and deviation correction pre-control mechanism for antique buildings.
[0032] See also Figure 1 A lifting beam type jacking and deviation correction pre-control mechanism for antique buildings includes: a wooden column 1 and two wooden beams 6, the wooden beams 6 are connected to the wooden column 1 through a mortise and tenon assembly 2, and the mortise and tenon assembly 2 can quickly connect the wooden column 1 and the wooden beam 6.
[0033] See also Figure 2 and Figure 3The mortise and tenon assembly 2 includes: two convex half-mortises 21, and a half-mortise groove 11 is formed through the side wall of the wooden column 1; in the embodiment of the present application, the two convex half-mortises 21 correspond to the two wooden beams 6 one by one, and the convex half-mortises 21 are fixed on the side walls of the corresponding wooden beams 6, the convex half-mortises 21 are mortised in the half-mortise groove 11, and the two convex half-mortises 21 abut against each other. During installation, the convex half-mortise 21 is inserted into the half-mortise groove 11 to quickly complete the connection between the wooden beam 6 and the wooden column 1.
[0034] See also Figure 3 Furthermore, in the embodiment of the present application, the connection between the two convex half-tenons 21 is a tooth-shaped structure. The two wooden beams 6 and the wooden column 1 are connected by the tooth-shaped structure, which can effectively improve the integrity of the wooden beams 6 and the wooden column 1, as well as the stability of the connection between the wooden beams 6 and the wooden column 1.
[0035] See also Figure 3 Furthermore, the mortise and tenon assembly 2 also includes: a replacement wood strip 22 and an anchoring replacement wood 23. The bottom of the half mortise and tenon groove 11 is provided with an anchoring groove 12, and the anchoring replacement wood 23 is arranged in the anchoring groove 12. In the embodiment of the present application, the two ends of the anchoring replacement wood 23 extend out of the anchoring groove 12, and the width of the two ends of the anchoring replacement wood 23 is greater than the width of the middle section of the anchoring replacement wood 23.
[0036] See also Figure 3 The top wall of the wooden beam 6 is penetrated by a through-tenon replacement groove 61, and the shape of the through-tenon replacement groove 61 is consistent with the cross-sectional shape of the replacement wood strip 22. One end of the replacement wood strip 22 is penetrated by the through-tenon replacement groove 61, and the other end is connected to the anchor replacement wood 23. After the wooden beam 6 is connected to the wooden column 1, the replacement wood strip 22 is penetrated by the through-tenon replacement groove 61, and the replacement wood strip 22 is connected to the anchor replacement wood 23, thereby not only realizing the horizontal constraint of the wooden beam 6, but also strengthening the lateral connection between the wooden column 1 and the wooden beam 6.
[0037] See also Figure 3 Furthermore, in the embodiment of the present application, the width of the anchor groove 12 is equal to 1 / 4-1 / 3 of the diameter of the wooden column 1, so as to effectively reduce the shear stress along the grain transmitted from the wooden beam 6 to the wooden column 1, thereby improving the connection stability between the wooden beam 6 and the wooden column 1.
[0038] See also Figure 3 Furthermore, in the embodiment of the present application, the cross-section of the replacement strip 22 is trapezoidal or semicircular. Such a setting can not only achieve horizontal constraint on the wooden beam 6, but also increase the contact area between the replacement strip 22 and the wooden beam 6, thereby reducing the influence of the replacement strip 22 on the overall strength and stiffness of the wooden column 1 and the wooden beam 6.
[0039] See also Figure 3A deviation correction pre-control component is arranged between the wooden beam 6 and the wooden column 1. When it is found that any wooden column 1 in the antique building has a large settlement, the wooden beam 6 on the side that needs to be corrected corresponding to the settled wooden column 1 is lifted by a lifting device to ensure that the force-transmitting wooden beam 6 is always in a horizontal bearing state, so as to improve the overall force system state of the antique building.
[0040] See also Figure 3 and Figure 4 The deviation correction and pre-control component includes: a pressure-bearing part 3, a limiting part 4 and a pot-sticking part 5.
[0041] See also Figure 3 The pressure-bearing part 3 includes: a pressure-bearing steel plate 31 and a pressure-bearing wooden board 32, and the pressure-bearing wooden board 32 is mounted on the top wall of the anchoring replacement wood 23. The pressure-bearing steel plate 31 is mounted on the top wall of the pressure-bearing wooden board 32, and a restraining groove 311 is opened on the top wall of the pressure-bearing steel plate 31. The shape of the restraining groove 311 is consistent with the shape of the through-tenon replacement wood groove 61. The end of the replacement wood strip 22 away from the wood beam 6 is arranged in the restraining groove 311. The pressure-bearing steel plate 31 and the pressure-bearing wooden board 32 can provide better support for the wood beam 6; The use of a steel-wood composite method can not only ensure local rigidity so that the end load of the wooden beam 6 can be effectively and evenly transferred to the wooden column 1; it can also provide flexible protection for the contact surface below the wooden beam 6, so that the edge of the pressure-bearing steel plate 31 is not easy to directly and locally crush the wooden column 1, and provide a flexible operating space for subsequent correction.
[0042] See also Figure 3 The limiting part 4 includes: an upper plate 41, a lower plate 42 and a spring 43. The upper plate 41 and the lower plate 42 are embedded in the half-mortise groove 11, and the lower plate 42 is fixed on the top wall of the convex half-mortise 21. The spring 43 is fixed between the upper plate 41 and the lower plate 42. When installing the wooden beam 6, it is necessary to first apply pressure to the upper plate 41 so that the height of the top of the upper plate 41 is flush with the height of the top of the wooden beam 6, so as to facilitate the insertion of the convex half-mortise 21 into the half-mortise groove 11; at the same time, the upper plate 41 and the lower plate 42 will also be embedded in the half-mortise groove 11; in the embodiment of the present application, two lower plates 42 are provided, and the lengths are inconsistent, while the upper plate 41 is provided as a whole.
[0043] When correcting the deviation, the wooden beam 6 on the side that needs to be corrected is lifted. During this process, the spring 43 compresses itself to achieve the effective height of the wooden beam 6 on the side that needs to be corrected, thereby ensuring that the wooden beam 6 is always in a horizontal load-bearing state; and when the correction adjustment is completed, the detached gap between the bottom of the wooden beam 6 and the pressure-bearing steel plate 31 can be timely mortise and tenon jointed to ensure that the connection point between the wooden beam 6 and the wooden column 1 is still strong and reliable as a whole; and the corresponding replacement wooden strips 22 are replaced; if necessary, the pressure-bearing wooden board 32 of appropriate size can be replaced in time, which is more convenient.
[0044] See also Figure 3Furthermore, in the embodiment of the present application, the upper plate 41 and the lower plate 42 are both made of peeled and glued wood. This arrangement ensures that deformation joints with excessively large differences in linear expansion coefficients are not easily generated between the upper plate 41 and the lower plate 42 and the wooden columns 1 and the wooden beams 6 during normal use.
[0045] See also Figure 3 and Figure 4 The top wall of the upper plate 41 and the top wall of the lower plate 42 are both provided with damping holes 44 along the length direction, and the damping holes 44 of the upper plate 41 and the damping holes 44 of the lower plate 42 are arranged at staggered intervals; the sticking pot part 5 is arranged between the inner wall of the damping hole 44 of the upper plate 41 and the lower plate 42 and between the inner wall of the damping hole 44 of the lower plate 42 and the upper plate 41.
[0046] See also Figure 4 The pot sticking part 5 includes: a disc 51, a metal rod 52 and a friction sleeve 53. The disc 51 is arranged in the damping hole 44. One end of the metal rod 52 is fixed to the disc 51, and the other end corresponds to the upper plate 41 or the lower plate 42. The friction between the disc 51 and the inner wall of the damping hole 44 generates a damping force to restrain the movement trend of the spring 43 in the opposite direction, so that the wooden beam 6 is not likely to have excess gaps after the jacking displacement.
[0047] See also Figure 4 The friction sleeve 53 is fixedly mounted on the peripheral wall of the disc 51, and the friction sleeve 53 is tightly pressed against the inner wall of the damping hole 44. In the embodiment of the present application, the friction sleeve 53 is made of rubber material. The friction sleeve 53 can increase the friction between the disc 51 and the inner wall of the damping hole 44, thereby better generating the damping force to reversely restrain the movement trend of the spring 43.
[0048] The working principle of the beam-lifting jacking and deviation correction pre-control mechanism for antique buildings of the present application is as follows: during deviation correction, the wooden beam 6 on the side that needs to be corrected is lifted. During this process, the spring 43 compresses itself to achieve the effective height of the wooden beam 6 on the side that needs to be corrected, thereby ensuring that the wooden beam 6 is always in a horizontal load-bearing state.
[0049] The present application also provides an installation method of a beam-lifting, deviation-correcting and pre-control mechanism for antique buildings.
[0050] A method for installing a beam lifting and deviation correction pre-control mechanism for antique buildings comprises the following steps: S1: manufacturing a wooden column 1, and positioning and opening a half mortise and tenon groove 11 and an anchor groove 12 on the wooden column 1; S2: Making the wooden beam 6 and the convex half tenon 21; S3: Install the pressure-bearing part 3 onto the anchoring wood 23, and install the anchoring wood 23 into the anchoring groove 12, and adjust the entire top surface to be horizontal; S4: Install the limiting part 4 to the top of the convex half tenon 21, and apply pressure to the limiting part 4 as a whole until the top of the limiting part 4 and the top of the wooden beam 6 are at the same horizontal height, so as to embed the convex half tenon 21 into the half tenon groove 11; S5: Fix the replacement wood strip 22 between the wood beam 6 and the pressure-bearing part 3 to achieve the purpose of horizontally restraining the wood beam 6.
[0051] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A beam lifting and deviation correction pre-control mechanism for antique buildings. It is characterized in that include: A wooden column (1) and two wooden beams (6), wherein the wooden beams (6) are connected to the wooden column (1) via a mortise and tenon assembly (2), and a deviation correction pre-control assembly is provided between the wooden beams (6) and the wooden column (1); The mortise and tenon assembly (2) comprises: two convex half-mortises (21); a half-mortise groove (11) is provided through the wooden column (1); one of the convex half-mortise (21) is fixed to one of the wooden beams (6); the other convex half-mortise (21) is fixed to another of the wooden beams (6); and the convex half-mortise (21) is arranged in the half-mortise groove (11).
2. The beam lifting and deviation correction pre-control mechanism for antique buildings according to claim 1, It is characterized in that The connection between the two convex half tenons (21) is in a horse tooth joint structure.
3. The beam lifting and deviation correction pre-control mechanism for antique buildings according to claim 2, It is characterized in that The mortise and tenon assembly (2) further comprises: a replacement wood strip (22) and an anchoring replacement wood strip (23); an anchoring groove (12) is provided at the bottom of the half mortise groove (11); the anchoring replacement wood strip (23) is arranged in the anchoring groove (12); a through-mortise replacement wood strip (61) is provided through the wooden beam (6); one end of the replacement wood strip (22) passes through the through-mortise replacement wood strip (61) and the other end is connected to the anchoring replacement wood strip (23).
4. The beam lifting and deviation correction pre-control mechanism for antique buildings according to claim 3, It is characterized in that The deviation correction and pre-control component comprises: a pressure-bearing part (3), the pressure-bearing part (3) comprises: a pressure-bearing steel plate (31) and a pressure-bearing wooden board (32), the pressure-bearing wooden board (32) is arranged on the top wall of the anchoring replacement wood (23), the pressure-bearing steel plate (31) is arranged on the pressure-bearing wooden board (32), and a restraining groove (311) is opened on the receiving steel plate, and the end of the replacement wood strip (22) away from the wooden beam (6) is arranged in the restraining groove (311).
5. The beam lifting and deviation correction pre-control mechanism for antique buildings according to claim 4, It is characterized in that The deviation correction pre-control component also includes: a limiting part (4), the limiting part (4) includes: an upper plate (41), a lower plate (42) and a spring (43), the upper plate (41) and the lower plate (42) are both embedded in the half-mortise (11), and the lower plate (42) is fixed on the convex half-mortise (21), and the spring (43) is fixed between the upper plate (41) and the lower plate (42).
6. The beam lifting and deviation correction pre-control mechanism for antique buildings according to claim 5, It is characterized in that The deviation correction pre-control component also includes: a sticking pot part (5), the sticking pot part (5) includes: a disc (51), a metal rod (52) and a friction sleeve (53), the upper plate (41) and the lower plate (42) are both provided with a damping hole (44), the disc (51) is arranged in the damping hole (44), the friction sleeve (53) is fixedly sleeved on the peripheral wall of the disc (51), one end of the metal rod (52) is fixed to the disc (51), and the other end is fixed to the upper plate (41) and the lower plate (42).
7. The beam lifting and deviation correction pre-control mechanism for antique buildings according to claim 3, It is characterized in that The width of the anchoring groove (12) is equal to 1 / 4-1 / 3 of the diameter of the wooden column (1).
8. The beam lifting and deviation correction pre-control mechanism for antique buildings according to claim 5, It is characterized in that The upper plate (41) and the lower plate (42) are both made of peeled and glued wood.
9. The beam lifting and deviation correction pre-control mechanism for antique buildings according to claim 3, It is characterized in that The cross section of the replacement wood strip (22) is trapezoidal or semicircular.
10. A method for installing the beam lifting and deviation correction pre-control mechanism for antique buildings according to any one of claims 1 to 9, It is characterized in that The following steps are involved: S1: manufacturing a wooden column (1), and positioning and opening a half-mortise and tenon groove (11) and an anchor groove (12) on the wooden column (1); S2: manufacturing the wooden beam (6) and the convex half tenon (21); S3: installing the pressure-bearing part (3) onto the anchoring replacement wood (23), installing the anchoring replacement wood (23) into the anchoring groove (12), and adjusting the entire top surface to be in a horizontal state; S4: Install the limiting part (4) to the top of the convex half tenon (21), and apply pressure to the limiting part (4) as a whole until the top of the limiting part (4) and the top of the wooden beam (6) are at the same level, so as to embed the convex half tenon (21) into the half tenon groove (11); S5: Fixing the replacement wood strip (22) between the wood beam (6) and the pressure-bearing part (3) to achieve the purpose of horizontally restraining the wood beam (6).