Composite liquid plug, preparation method and casing deformation well shaft segmented temporary plugging method
By using composite liquid plugs in the sheath-changing well, the problem of the sheath-changing well cannot be temporarily blocked in segments, achieving effective sealing of the wellbore and smooth progress of large-scale fracturing.
Patent Information
- Application Number
- CN202310637866.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2023-05-31
- Publication Date
- 2024-12-03
AI Technical Summary
The prior art cannot effectively block the sheath-changing wells in sections, resulting in the inability to carry out large-scale volume fracturing construction.
A composite liquid plug is adopted, including a continuous oil pipe filled with a first soft plug, a hard plug and a second soft plug, and a squeezing the sealing member through a pushing member to press it out from the outlet end in sequence, for The segments of the wellbore are temporarily blocked.
The composite liquid plug can be smoothly down into the sleeve and transformed into the wellbore, and replace the original liquid through the first soft plug and the second soft plug, clean the wellbore, prevent the material from slurrying, and provide pressure and sealing after solidification, so as to achieve Effective segmentation temporary blockage and subsequent large volume fracturing.
Smart Images

Figure CN119062274A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of casing change well plugging, and in particular to a composite liquid plug, a preparation method and a casing change well shaft segmented temporary plugging method. Background Art
[0002] In order to achieve high production of shale gas wells, the construction site usually needs to carry out two treatments: temporary plugging of wellbore segments and large-scale volume fracturing. During the construction process, some wells have the phenomenon of oil layer casing deformation or even damage (referred to as casing deformation). After the casing deformation occurs, the wellbore diameter is reduced, and the mechanical temporary plugging tools that need to be lowered later cannot pass through, resulting in the inability to carry out temporary plugging of wellbore segments and volume fracturing construction as designed.
[0003] At present, there are three main ways to deal with the above problems. The first is combined fracturing, that is, without temporary plugging of segments, general volume fracturing is directly carried out. The disadvantage of this method is that the initial segmented fracturing design requirements are not implemented, which has an impact on the subsequent gas well production. The second is temporary formation plugging, that is, the well section that has been volume fracturing is plugged with temporary plugging liquid or material. The disadvantage of this method is that the formation plugging effect and subsequent backflow effect are difficult to guarantee, which has an impact on the subsequent gas well production. The third is the use of a new type of small-diameter bridge plug. The disadvantage of this method is that the minimum diameter of the bridge plug has a certain lower limit, and it cannot be lowered into wells with too small a diameter or complex casing deformation and damage. Summary of the invention
[0004] The object of the present invention is to provide a composite liquid plug to solve the technical problem that the existing temporary plugging cannot effectively implement segmented temporary plugging of casing change wells, thereby failing to effectively perform large-scale volume fracturing.
[0005] The present invention is achieved through the following technical solutions:
[0006] A composite liquid plug comprises: a continuous oil pipe, wherein the continuous oil pipe is filled with a first soft plug, a hard plug and a second soft plug in sequence; a plugging member, wherein the plugging member is arranged at the outlet end of the continuous oil pipe and is used to plug the outlet end of the continuous oil pipe; and a pushing member, wherein the pushing member is slidably arranged at the inlet end of the continuous oil pipe and is used to squeeze the first soft plug to indirectly fracture the plugging member so that the second soft plug, the hard plug and the first soft plug are pressed out of the plugging member in sequence.
[0007] Optionally, the pushing piece is a sphere, and the diameter of the pushing piece is slightly smaller than the inner diameter of the coiled tubing; the pushing piece is soluble, and the dissolution time of the pushing piece is 3-6 hours.
[0008] Optionally, a positioning piece is connected between the outlet end of the coiled tubing and the blocking piece, a through hole is opened in the middle of the positioning piece to connect the coiled tubing and the blocking piece, and a diameter of the through hole is smaller than a diameter of the pushing piece.
[0009] Optionally, a ball groove is formed on one side of the positioning member connected to the coiled tubing, the size of the ball groove matches the size of the blocking member, and the through hole is formed at the bottom of the ball groove.
[0010] Optionally, the blocking member is disc-shaped, and a disc edge is provided on the circumference of the blocking member, and the disc edge is arranged at an obtuse angle with the disc bottom of the blocking member so that the disc edge is inclined toward the positioning member.
[0011] Optionally, an annular sealing valve is sleeved outside the coiled tubing, and the sealing valve is used to seal or open the annular space between the coiled tubing and the wellbore.
[0012] Optionally, a plurality of spray guns are provided in a ring shape at the outlet end of the coiled tubing, and the spray guns are used to spray a breaker.
[0013] Optionally, the components of the first soft plug and the second soft plug include: any one or more combinations of gel, jelly and calcium carbonate powder; the components of the hard plug include: cement, calcium carbonate powder, retarder, drag reducer, fluid loss additive and reinforcing agent.
[0014] A method for preparing the composite liquid plug comprises the following steps:
[0015] The pushing piece, the first soft plug, the hard plug and the second soft plug are prepared respectively;
[0016] Injecting the pushing piece, the first soft plug, the hard plug, and the second soft plug into the coiled tubing in sequence from the outlet end of the coiled tubing;
[0017] The plugging piece is used to plug the outlet end of the coiled tubing to obtain the composite liquid plug.
[0018] A method for temporary plugging of a casing change wellbore in sections, comprising the following steps:
[0019] Insert any one of the above composite liquid plugs into the casing change wellbore, so that the outlet end of the coiled tubing is lowered to a preset segmented position of the wellbore;
[0020] Fixing the coiled tubing to the wellbore and sealing the annular space between the wellbore and the coiled tubing;
[0021] Pumping clean water into the inlet end of the coiled tubing until the plugging member is compressed and ruptured;
[0022] Continuously pumping clean water at the inlet end of the coiled tubing so that the second soft plug, the hard plug and the first soft plug are sequentially injected into the preset segmented positions of the wellbore;
[0023] The coiled tubing is pulled out, and after the hard plug solidifies, the wellbore can be temporarily plugged in sections.
[0024] Compared with the prior art, the present invention has the following advantages and beneficial effects:
[0025] The present invention provides a composite liquid plug, which, by setting a continuous oil pipe, can cooperate with a plugging member to seal the unsolidified first soft plug, hard plug and second soft plug therein, so as to prevent the three from leaking in advance before being sent to the preset segmented temporary plugging position; secondly, it provides a certain structural support, so that the composite liquid plug can be easily lowered into the wellbore of the casing change well; thirdly, it provides an extrusion structure, which can cooperate with a pushing member to press the unsolidified first soft plug, hard plug and second soft plug out of the continuous oil pipe, so as to facilitate the implementation of fixed-point operation; on this basis, by setting the first soft plug, The hard plug and the second soft plug, and the three have not yet solidified, so the permeability of the three is not affected by the spatial morphology of the casing change wellbore, and can be smoothly injected into the preset segmented position of the casing change wellbore, wherein the first soft plug and the second soft plug can displace the original liquid in the wellbore, clean the wellbore, and prevent the material in the wellbore from mixing with the hard plug, and the two are colloids after solidification, which can assist the hard plug in pressure bearing and isolation, and the hard plug has sufficient pressure bearing performance after solidification, thereby realizing effective plugging and support of the preset segmented position, so that the subsequent large-scale volume fracturing can proceed smoothly. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] The drawings described herein are used to provide a further understanding of the embodiments of the present invention, constitute a part of this application, and do not constitute a limitation of the embodiments of the present invention. In the drawings:
[0027] Figure 1 A schematic diagram of a composite liquid plug provided by an embodiment of the present invention;
[0028] Figure 2 A schematic diagram of a composite fluid provided in an embodiment of the present invention when it is located in a wellbore;
[0029] Figure 3 A flow chart of a method for preparing a composite liquid plug provided in an embodiment of the present invention;
[0030] Figure 4 A flow chart of a method for temporary plugging of a casing-changing wellbore in sections provided in an embodiment of the present invention.
[0031] Marks and corresponding parts names in the attached drawings:
[0032] 1-wellbore; 10-coiled tubing; 11-first soft plug; 12-hard plug; 13-second soft plug; 30-blocking member; 31-disc edge; 20-pushing member; 40-positioning member; 41-through hole; 42-ball groove; 50-sealing valve; 60-spray gun. DETAILED DESCRIPTION
[0033] In order to make the objectives, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with embodiments and drawings. The exemplary embodiments of the present invention and their description are only used to explain the present invention and are not intended to limit the present invention.
[0034] Please refer to Figure 1 and Figure 2 The embodiment of the present invention provides a composite liquid plug, comprising: a coiled tubing 10, wherein the coiled tubing 10 is sequentially filled with a first soft plug 11, a hard plug 12 and a second soft plug 13; a second plugging member 30, wherein the plugging member 30 is disposed at the outlet end of the coiled tubing 10, and the plugging member 30 is used to plug the outlet end of the coiled tubing 10; and a third member 20, wherein the push member 20 is slidably disposed at the inlet end of the coiled tubing 10, and the push member 20 is used to squeeze the first soft plug 11 to indirectly fracture the plugging member 30, so that the second soft plug 13, the hard plug 12 and the first soft plug 11 are sequentially pressed out of the plugging member 30.
[0035] The present invention provides a composite liquid plug, which, by setting a continuous oil pipe 10, can cooperate with a plugging member 30 to seal the unsolidified first soft plug 11, hard plug 12 and second soft plug 13 therein, to prevent the three from leaking in advance before being sent to the preset segmented temporary plugging position; secondly, it provides a certain structural support, so that the composite liquid plug is easy to be lowered into the wellbore 1 of the casing change well; thirdly, it provides an extrusion structure, which can cooperate with a push member 20 to press the unsolidified first soft plug 11, hard plug 12 and second soft plug 13 out of the continuous oil pipe 10, so as to facilitate the implementation of fixed-point operations; on this basis, by setting the first soft plug 1 1, the hard plug 12 and the second soft plug 13, and the three have not yet solidified, so the permeability of the three is not affected by the spatial shape of the casing change wellbore 1, and can be smoothly injected into the preset segmented position of the casing change wellbore 1, wherein the first soft plug 11 and the second soft plug 13 can replace the original liquid in the wellbore 1, clean the wellbore 1, and prevent the material in the wellbore 1 from mixing with the hard plug 12, and the two are colloids after solidification, which can assist the hard plug 12 in pressure bearing and isolation, and the hard plug 12 has sufficient pressure bearing performance after solidification, thereby realizing effective plugging and support of the preset segmented position, so that the subsequent large-scale volume fracturing can be carried out smoothly.
[0036] In order to facilitate the pushing piece 20 to slide along the coiled tubing 10, the pushing piece 20 is a sphere, and the diameter of the pushing piece 20 is slightly smaller than the inner diameter of the coiled tubing 10; the pushing piece 20 is soluble, and the dissolution time of the pushing piece 20 is 3-6 hours.
[0037] By setting the pushing piece 20 to be spherical, when the pumped clean water is squeezed against the pushing piece 20, the pushing piece 20 can slide smoothly along the continuous oil pipe 10 regardless of the angle at which it is tilted; by setting the pushing piece 20 to be made of soluble material and the dissolution time to be 3-6 hours, it has a good shape and structural performance when pushing is implemented, and after the pushing is completed, especially after the subsequent large-scale volume fracturing is completed, it can be fully dissolved and will not hinder the release of the first soft plug 11, the hard plug 12 and the second soft plug 13.
[0038] In order to position during the pushing process and prevent the first soft plug 11, the hard plug 12 and the second soft plug 13 from deviating from the preset segmented positions due to excessive pushing, a positioning member 40 is connected between the outlet end of the coiled tubing 10 and the blocking member 30. A through hole 41 is opened in the middle of the positioning member 40 to connect the coiled tubing 10 and the blocking member 30. The diameter of the through hole 41 is smaller than the diameter of the pushing member 20.
[0039] By setting the positioning member 40, when the clean water is continuously pumped and pushed, the pushing member 20 continues to slide along the continuous oil pipe 10. When the first soft plug 11, the hard plug 12 and the second soft plug 13 are all pressed out from the continuous oil pipe 10, the pushing member 20 contacts the positioning member 40. On the one hand, after the two contact, the positioning member 40 will limit the pushing member 20 so that it can no longer move along the length direction of the continuous oil pipe 10. On the other hand, when the pushing member 20 contacts and squeezes the positioning member 40, the through hole 41 will be closed, so that the pressurized clean water is sealed in the continuous oil pipe 10, and will not be pressed out from the squeezed and ruptured sealing member 30 and continue to push the first soft plug 11, the hard plug 12 and the second soft plug 13 to move along the wellbore 1, effectively preventing the three from deviating from the preset segmented position.
[0040] Preferably, a pressure sensor (not shown) is provided in the pushing member 20 or in the continuous oil pipe 10. When the pushing member 20 contacts and squeezes the positioning member 40, causing the through hole 41 to be closed, the pressure parameter collected by the pressure sensor will suddenly increase. At this time, the signal of the pressure sensor can be received by the receiver, or the pressure sensor can be connected to the control system of the clean water pump, and the moment of the sudden pressure increase is used as the pump stop time to further improve the control accuracy.
[0041] For further precise positioning, a ball groove 42 is formed on one side of the positioning member 40 communicating with the coiled tubing 10 . The size of the ball groove 42 matches the size of the blocking member 30 . The through hole 41 is formed at the bottom of the ball groove 42 .
[0042] By setting the ball groove 42, the push piece 20 is embedded in the ball groove 42 when contacting the positioning piece 40, which further improves the shielding effect of the through hole 41 on the one hand, and effectively limits the push piece 20 in multiple directions on the other hand, so that it can move accurately to a certain position.
[0043] In order to further explain the specific shape of the blocking member 30 , the blocking member 30 is disc-shaped, and a disc edge 31 is provided on the circumference of the blocking member 30 . The disc edge 31 is arranged at an obtuse angle with the disc bottom of the blocking member 30 so that the disc edge 31 is inclined toward the positioning member 40 .
[0044] Through the above arrangement, the plugging member 30 is in a hood shape, which can effectively bear the pressure of the unsolidified second soft plug 13, thereby facilitating its extrusion and rupture. It should be noted that in order to reduce costs, the rupture mode of the plugging member 30 is irreversible, for example, its overall pressure bearing performance is balanced, and the whole is broken when the pressure exceeds its upper pressure bearing limit, or the upper pressure bearing limit of its disc body is weaker than the upper pressure bearing limit of the disc edge 31, and only the disc body is broken when the pressure exceeds the upper pressure bearing limit of the disc body.
[0045] In order to prevent the first soft plug 11, the hard plug 12, the second soft plug 13 and the pressurized clean water from flowing back to the wellhead from the annular gap between the outer wall of the coiled tubing 10 and the inner wall of the wellbore 1, an annular sealing valve 50 is provided on the outside of the coiled tubing 10. The sealing valve 50 is used to seal or open the annular space between the coiled tubing 10 and the wellbore 1.
[0046] By setting a sealing valve 50, the annular gap between the coiled tubing 10 and the wellbore 1 is blocked to prevent the backflow of the above-mentioned liquid. It should be noted that the sealing valve 50 can adopt any structure in the prior art, such as a base body that is an annular base, which has a plurality of through holes along the thickness direction, and each through hole is provided with a valve; for example, a stacked double-layer annular structure, and a plurality of through holes are symmetrically and correspondingly opened on the two layers of the annular structure along the thickness direction, and then the corresponding holes are controlled to be connected or staggered and closed through relative rotation of the two, so as to achieve the effect of a valve.
[0047] In order to release the solidified first soft plug 11, hard plug 12 and second soft plug 13 in the wellbore 1 after completing large-scale volume fracturing, a plurality of spray guns 60 are provided in an annular manner at the outlet end of the coiled tubing 10, and the spray guns 60 are used to spray a breaker.
[0048] By setting a plurality of spray guns 60 in a ring at the outlet end of the coiled tubing 10, after completing the large-scale volume fracturing, the coiled tubing 10 is re-lowered into the wellbore 1 until the outlet end contacts the first soft plug 11, and then a breaker or acid is sprayed through the spray guns 60 to dissolve the first soft plug 11, the hard plug 12 and the second soft plug 13.
[0049] Preferably, before the spray gun 60 sprays the breaker, it is best to open the sealing valve 50 to allow the breaker to flow back along the annular gap between the coiled tubing 10 and the wellbore 1 to prevent excessive pressure in the wellbore 1, which is not conducive to breaking the breaker.
[0050] In order to facilitate the subsequent dissolution of the first soft plug 11, the hard plug 12 and the second soft plug 13 while ensuring their mechanical properties, the components of the first soft plug 11 and the second soft plug 13 include: any one or more combinations of gel, jelly and calcium carbonate powder; the components of the hard plug 12 include: cement, calcium carbonate powder, retarder, drag reducer, fluid loss additive and reinforcing agent.
[0051] The embodiment of the present invention further provides a method for preparing any one of the above-mentioned composite liquid plugs, comprising the following steps:
[0052] S1. Prepare the pushing member 20, the first soft plug 11, the hard plug 12 and the second soft plug 13 respectively.
[0053] S2, injecting the pushing member 20, the first soft plug 11, the hard plug 12, and the second soft plug 13 into the coiled tubing 10 from the outlet end of the coiled tubing 10 in sequence.
[0054] S3. Use the plugging member 30 to plug the outlet end of the coiled tubing 10 to obtain the composite liquid plug.
[0055] The embodiment of the present invention further provides a method for temporary plugging of a casing change wellbore 1 in sections, comprising the following steps:
[0056] SS1. Insert any one of the above composite liquid plugs into the casing change wellbore 1, so that the outlet end of the coiled tubing 10 is lowered to the preset segment position of the wellbore 1.
[0057] SS2. Fix the coiled tubing 10 to the wellbore 1 and close the sealing valve 50 to seal the annular space between the wellbore 1 and the coiled tubing 10 .
[0058] SS3. Pump clean water into the inlet end of the coiled tubing 10 until the plugging member 30 is compressed and ruptured.
[0059] SS4. Continue to pump clean water into the inlet end of the coiled tubing 10 so that the second soft plug 13, the hard plug 12 and the first soft plug 11 are sequentially injected into the preset segmented positions of the wellbore 1 until the push member 20 falls into the ball groove 42 of the positioning member 40.
[0060] SS5. Pull out the coiled tubing 10, and after the hard plug 12 solidifies, the wellbore 1 can be temporarily plugged in sections.
[0061] SS6. After the large-scale volume fracturing is successfully implemented, the coiled tubing 10 is reinserted until its outlet end contacts the solidified first soft plug 11;
[0062] SS7. Open the sealing valve 50 and spray the breaker through the spray gun 60 until the first soft plug 11, the hard plug 12 and the second soft straight plug 12 are dissolved, and then the coiled tubing 10 is pulled out again, and the construction is completed.
[0063] The specific implementation methods described above further illustrate the objectives, technical solutions and beneficial effects of the present invention in detail. It should be understood that the above description is only a specific implementation method of the present invention and is not intended to limit the scope of protection of the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.
Claims
1. A composite liquid plug, characterized in that: include: A coiled tubing (10), wherein the coiled tubing (10) is sequentially filled with a first soft plug (11), a hard plug (12) and a second soft plug (13); A plugging member (30), the plugging member (30) being arranged at the outlet end of the coiled tubing (10), the plugging member (30) being used to plug the outlet end of the coiled tubing (10); A pushing piece (20) is slidably disposed at the inlet end of the coiled tubing (10), and is used to squeeze the first soft plug (11) to indirectly fracture the plugging piece (30), so that the second soft plug (13), the hard plug (12) and the first soft plug (11) are pressed out of the plugging piece (30) in sequence.
2. The composite liquid plug according to claim 1, characterized in that: The pushing piece (20) is a sphere, and the diameter of the pushing piece (20) is slightly smaller than the inner diameter of the coiled tubing (10); The pushing piece (20) is soluble, and the dissolution time of the pushing piece (20) is 3-6 hours.
3. The composite liquid plug according to claim 2, characterized in that: A positioning member (40) is connected between the outlet end of the coiled tubing (10) and the blocking member (30), and a through hole (41) is opened in the middle of the positioning member (40) so that the coiled tubing (10) and the blocking member (30) are connected, and the diameter of the through hole (41) is smaller than the diameter of the pushing member (20).
4. The composite liquid plug according to claim 3, characterized in that: A ball groove (42) is formed on one side of the positioning member (40) communicating with the coiled tubing (10). The size of the ball groove (42) matches the size of the blocking member (30). The through hole (41) is formed at the bottom of the ball groove (42).
5. The composite liquid plug according to claim 4, characterized in that: The blocking member (30) is disc-shaped, and a disc edge (31) is provided on the circumference of the blocking member (30). The disc edge (31) and the bottom of the blocking member (30) are arranged at an obtuse angle so that the disc edge (31) is inclined toward the positioning member (40).
6. The composite liquid plug according to claim 1, characterized in that: The coiled tubing (10) is sheathed with an annular sealing valve (50), and the sealing valve (50) is used to seal or open the annular space between the coiled tubing (10) and the wellbore.
7. The composite liquid plug according to claim 1, characterized in that: A plurality of spray guns (60) are provided in a ring shape at the outlet end of the coiled oil pipe (10), and the spray guns (60) are used to spray a gel breaker.
8. The composite liquid plug according to any one of claims 1 to 7, characterized in that: The components of the first soft plug (11) and the second soft plug (13) include any one or more combinations of gel, jelly and calcium carbonate powder; The components of the hard plug (12) include cement, calcium carbonate powder, retarder, drag reducer, fluid loss reducer and reinforcing agent.
9. A method for preparing a composite liquid plug according to any one of claims 1 to 8, characterized in that: The steps include: The pushing piece (20), the first soft plug (11), the hard plug (12) and the second soft plug (13) are prepared respectively; Injecting the pushing piece (20), the first soft plug (11), the hard plug (12), and the second soft plug (13) into the coiled tubing (10) in sequence from the outlet end of the coiled tubing (10); The plugging member (30) is used to plug the outlet end of the coiled tubing (10) to obtain the composite liquid plug.
10. A method for temporary plugging of casing change wellbore in sections, characterized in that: The steps include: Inserting the composite liquid plug as claimed in any one of claims 1 to 8 into the casing-change wellbore, so that the outlet end of the coiled tubing (10) is lowered to a preset segmented position of the wellbore; Fixing the coiled tubing (10) to the wellbore, and sealing the annular space between the wellbore and the coiled tubing (10); Pumping clean water into the inlet end of the coiled tubing (10) until the plugging member (30) is compressed and ruptured; Continuously pumping clean water at the inlet end of the coiled tubing (10) so that the second soft plug (13), the hard plug (12) and the first soft plug (11) are sequentially injected into the preset segmented positions of the wellbore; The coiled tubing (10) is pulled out, and after the hard plug (12) solidifies, the wellbore can be temporarily plugged in sections.