Long-distance saturated clay pipe jacking construction technology

Through detailed preliminary preparation and construction steps, and using appropriate equipment and technical means, the problems of traditional pipe construction in long-distance saturated clay environments have been solved, stable and precise construction has been achieved, and cost and surface impact have been reduced.

CN119062344APending Publication Date: 2024-12-03ANHUI HIGHWAY BRIDGE ENG CO LTD
View PDF 0 Cites 3 Cited by

Patent Information

Application Number
CN202411209405.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-30
Publication Date
2024-12-03

AI Technical Summary

Technical Problem

Traditional pipe top construction technology is difficult to achieve in long-distance saturated clay environments, requiring high technical level and expensive equipment, resulting in high construction costs and unsuitable for complex geological conditions.

Method used

Detailed preliminary preparation and construction steps, including geological survey, equipment selection, real-time monitoring and quality control, construction parameter setting and post-processing, and use suitable pipe ejectors, mud pumps and automatic control systems to ensure construction stability and accuracy .

Benefits of technology

Achieve stable and precise pipe top construction under long-distance saturated clay conditions, reducing surface impact and construction costs, and is suitable for large-scale engineering projects under complex geological conditions.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure BDA0005019944610000131
    Figure BDA0005019944610000131
  • Figure BDA0005019944610000141
    Figure BDA0005019944610000141
  • Figure BDA0005019944610000231
    Figure BDA0005019944610000231
Patent Text Reader

Abstract

The invention relates to the technical field of pipe-jacking construction, in particular to a long-distance saturated clay pipe-jacking construction process which comprises the following steps: S1, early-stage preparation: investigating the thickness, water content, soil structure and underground water level of a long-distance saturated clay layer in detail, determining the specific parameters of pipe diameter, jacking force, jacking distance and pipe joint material according to investigation data, cleaning and leveling a construction site, and performing construction; smooth working sites and transportation channels are ensured, and a constructor rest area, a mechanical equipment storage area and a material storage area are built; the long-distance saturated clay pipe-jacking construction technology has the remarkable advantages in the aspects of adapting to complex geological conditions, reducing the ground surface influence and improving the construction precision, the stability and precision of pipe-jacking construction can be kept under the long-distance condition, the technology is suitable for large-scale engineering projects, construction can be conducted under the complex geological conditions such as saturated clay, and the construction efficiency is improved. The geologic problem difficult to deal with by traditional pipe jacking is solved, in the construction process, ground surface settlement and environmental damage are small, and the method is suitable for underground engineering in urban dense areas.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of pipe jacking construction, in particular to a long-distance saturated clay pipe jacking construction process. Background Art

[0002] Pipe jacking is a trenchless underground pipeline construction technology that uses a pipe jacking machine (such as an earth pressure balance pipe jacking machine or a mud water balance pipe jacking machine) to push the pipeline into the ground section by section in a working well excavated on the ground, passing through the soil layer to reach the receiving well. This construction method can install underground pipelines without damaging the surface environment, and is widely used in municipal engineering, water supply and drainage engineering, gas, electricity, telecommunications and other pipeline projects.

[0003] The application scenarios of pipe jacking construction technology include urban pipeline laying, installation of water supply, drainage, gas, electricity and communication pipelines underground in urban roads, rivers, railways, etc., to avoid impact on surface traffic and buildings, and use in environmental protection projects such as the construction of sewage pipes and rainwater pipes to reduce damage to the surface environment. It is suitable for areas with high groundwater levels and soft soil, such as coastal cities and near lakes, to avoid groundwater influx and ground subsidence problems.

[0004] However, in general, traditional pipe jacking construction technology has high requirements, requiring a high level of technology and professional equipment. Construction personnel need to have professional skills and experience. Due to the complexity of the technology and expensive equipment, the construction cost is higher than that of traditional pipe jacking construction, and it is not suitable for operations in long-distance saturated clay environments.

[0005] In summary, it is necessary to propose a long-distance saturated clay pipe jacking construction technology to solve the above problems. Summary of the invention

[0006] The purpose of the present invention is to provide a long-distance saturated clay pipe jacking construction process to solve the problems raised in the above background technology.

[0007] To achieve the above object, the present invention provides the following technical solutions:

[0008] A long-distance saturated clay pipe jacking construction process comprises the following steps:

[0009] S1. Preliminary preparation: Detailed investigation of the thickness, water content, soil structure and groundwater level of the long-distance saturated clay layer; based on the survey data, determine the specific parameters of pipe diameter, top force, top distance and pipe joint materials; clean and level the construction site; ensure that the work site and transportation channels are unobstructed; and build a rest area for construction personnel, a storage area for machinery and equipment, and a storage area for materials;

[0010] S2. Construction equipment selection: Choose a pipe jacking machine suitable for long-distance pipe jacking, consider earth pressure balance pipe jacking machine or mud water balance pipe jacking machine to adapt to saturated clay conditions, including mud pump, mud circulation system, pipe segment transportation equipment and automatic control system;

[0011] S3. Carry out monitoring and quality control before construction. By installing monitoring equipment, various parameters in the jacking process, including jacking force, speed, inclination and mud pressure, are monitored in real time. Quality inspections are carried out regularly to ensure the installation quality of each section of the pipeline and problems are dealt with in a timely manner;

[0012] S4. Set construction parameters, reasonably control the jacking force according to the pipe diameter and soil conditions, control it within the allowable range of pipe design, control the jacking speed to avoid soil disturbance caused by excessive speed, and control it within 2-4 meters / hour. According to the characteristics of saturated clay, adjust the mud ratio to ensure the lubrication and support of the mud. During the jacking process, record data every 1-2 meters to ensure the stability and controllability of the jacking process;

[0013] S5. Implement construction steps. According to the design drawings, determine the location of the guide hole, and build working wells and receiving wells at both ends. Use guide drilling equipment to drill holes to ensure the accuracy of the guide hole. Install the pipe jacking machine in the working well and debug the equipment to ensure its normal operation. Connect the mud circulation system to ensure the normal transportation and recovery of mud. Use an automatic control system to monitor the jacking speed, jacking force and direction in real time to ensure that the jacking pipe moves along the designed route. According to soil conditions, adjust the mud ratio and pressure to ensure the stable operation of the pipe jacking machine and the support of the hole wall. Ensure the depth and position of the receiving well are accurate to facilitate the smooth reception of the jacking pipe. At the joints of the pipe sections, use waterproof materials and reinforcement measures to ensure the sealing and strength of the interface;

[0014] S6. After the pipe jacking construction is completed, the pipe jacking equipment is dismantled, the construction site is cleaned up, and the construction area is restored to ensure that the environmental impact is minimized;

[0015] S7. Conduct safety measures training and guidance in real time. Before implementing each step from step S2 to step S6, all construction personnel need to receive safety training to ensure that they understand and comply with the construction safety regulations of that step, and develop detailed emergency plans to deal with emergencies.

[0016] Preferably, the implementation steps of the preliminary preparation of step S1 are as follows:

[0017] S1.1. Geological survey: drilling operations, sampling and analysis, groundwater level monitoring, and data aggregation and analysis. Multiple exploration holes are drilled in the construction area with an electric drill rig to a depth of 50 meters. Soil samples are taken from each borehole for indoor analysis to determine soil thickness, water content, soil structure and porosity. Pore water pressure gauges are installed to continuously monitor groundwater level changes. Three-dimensional geological models are generated by inputting exploration data into RockWorks or GEO5 geological modeling software;

[0018] S1.2. Determination of design parameters: Conduct preliminary design, mechanical calculation, material selection and design review. Draw preliminary design drawings using AutoCAD Civil 3D, determine pipe diameter, top force and top distance parameters, perform detailed calculations of top force and top distance using PLAXIS 3D, select reinforced concrete pipe as the pipe segment material and calculate its bearing capacity and durability, organize experts to conduct design review, and modify and optimize the design plan;

[0019] S1.3. Site cleaning: Conduct site survey, mechanical equipment, cleaning work and site acceptance. The construction team will conduct site survey, mark the areas and obstacles that need to be cleaned, mobilize excavators and bulldozers to the site, use mechanical equipment to clean the ground, remove debris, vegetation and obstacles, and conduct site acceptance by the construction supervisor to ensure that the construction requirements are met;

[0020] S1.4. Transportation corridor preparation: corridor planning, ground leveling, signage and corridor inspection. Design the transportation corridor by using ArcGIS to determine the best route. Use bulldozers and rollers to level and compact the ground of the transportation corridor. Set up warning signs and signboards on both sides of the corridor to ensure transportation safety. Accept the transportation corridor through construction supervision to ensure that the corridor is flat, solid and clearly marked.

[0021] S1.5. Construction of rest area for construction workers: site selection and design, material preparation, construction work, acceptance and management, by selecting the location of the rest area and using SketchUp for layout design, by purchasing and transporting necessary construction materials, including tents, prefabricated houses, and sanitary facilities, by organizing construction workers to build the rest area according to the design drawings, installing sanitary facilities and rest equipment, by acceptance after the rest area is built, and formulating a management system;

[0022] S1.6. Construction of mechanical equipment storage area: After planning the storage area, hardening the ground, marking and marking the equipment, the mechanical equipment storage area is designed by using AutoCAD, and the equipment placement and passage are determined. The storage area floor is hardened by using concrete to ensure the floor is flat and durable. The equipment storage location and passage are marked on the ground, and relevant signs are set. The mechanical equipment is placed in an orderly manner according to the planned location, and the equipment is inspected and maintained.

[0023] S1.7. Construction of material storage area: Design the storage area, build scaffolding, and set up safety measures before materials are brought in. Design the material storage area using Revit to ensure reasonable layout and safe storage. Build material storage scaffolding to ensure that materials are classified and stored, protected from rain and sun. Set up fire prevention and anti-theft safety measures in the storage area to ensure material safety. Organize materials to be stored in an orderly manner according to classification, and regularly check the storage status of materials.

[0024] S1.8. Comprehensive acceptance and commissioning: Carry out overall acceptance, equipment commissioning, prepare reports and hold pre-construction meetings. Organize construction supervision to conduct a comprehensive acceptance of construction preparation work. Carry out comprehensive commissioning of pipe jacking equipment, auxiliary equipment and monitoring equipment. Write a construction preparation report to record the specific circumstances and acceptance results of each preparation work. Confirm the completion of each preparation work and arrange specific construction tasks by holding a pre-construction meeting.

[0025] Preferably, the construction equipment selection implementation steps in step S2 are as follows:

[0026] S2.1. Selection of pipe jacking machine. Through research on domestic and foreign pipe jacking machine manufacturers, we selected equipment suitable for long-distance saturated clay pipe jacking construction. We used Google Scholar and engineering magazine databases to build a comparison table of pipe jacking machine technical parameters through Excel, and compared the parameters of different types of earth pressure balance pipe jacking machines and slurry balance pipe jacking machines, including jacking force, jacking distance, and mud flow rate. The earth pressure balance pipe jacking machine has a jacking force of 5000kN and a jacking distance of 3000mm, while the slurry balance pipe jacking machine has a jacking force of 4500kN and a jacking distance of 3200mm. We used GeoStudio software to simulate geological conditions and verify the applicability of different pipe jacking machines in saturated clay. The parameters were set to 18° internal friction angle of saturated clay, 25kPa cohesion, and 0.65 porosity. We selected the earth pressure balance pipe jacking machine based on comprehensive technical parameters and simulation results.

[0027] S2.2. Mud pump selection: determine the specifications of the mud pump by calculating the required mud flow and pressure. The mud flow requirement is 50m 3 / h, the mud pressure requirement is 1.5MPa. The mud pump is selected by using the equipment selection software PumpSelect, and the final model is Warman 450DT. The performance and reliability of the mud pump are reviewed by technical experts to confirm the rationality of the selection.

[0028] S2.3. Design of mud circulation system: Use AutoCAD to design the layout of the mud circulation system, determine the location of the mud pipeline, mud storage tank and mud separator, and use CFD software to simulate the mud circulation system, optimize the mud flow path and ensure smooth mud circulation;

[0029] S2.4. Segment transportation equipment selection: By calculating the segment size and weight, determine the required transportation equipment specifications. The segment size is 1.5mx1.5mx0.2m, and the segment weight is 1.2 tons. Use the logistics equipment selection software to select the appropriate transportation equipment. Use the logistics simulation software FlexSim to simulate the segment transportation and optimize the transportation path and efficiency. The simulation parameters are transportation distance 1000m and transportation speed 1m / s.

[0030] S2.5. Automatic control system design: by analyzing the automation requirements during pipe jacking construction, determine the functions and parameters of the automatic control system;

[0031] S2.6. Equipment commissioning and installation: transport the pipe jacking machine, mud pump, mud circulation system, segment transport equipment and automatic control system to the construction site by mobilizing construction machinery and equipment; install the equipment by using cranes and hoists to ensure that the equipment is accurately positioned, connected firmly, and installed with an accuracy of ±5mm; and coordinate the entire equipment system by using automatic control systems to ensure that all equipment works in coordination;

[0032] S2.7. Operator training: by formulating a detailed equipment operation training plan, ensure that operators master the equipment use and maintenance methods; by organizing equipment manufacturer technicians to conduct on-site training for operators, providing detailed operation manuals and maintenance guides, and by assessing operators, ensure that they can operate the equipment proficiently and respond to emergencies;

[0033] S2.8. Final acceptance and preparation: All equipment shall be inspected and accepted by the construction supervisor to ensure that the equipment installation and commissioning meet the requirements. A detailed construction plan shall be prepared to prepare all the materials and tools required for construction. A comprehensive final inspection shall be conducted to ensure that all equipment and systems are ready and meet the construction requirements. A construction kick-off meeting shall be organized to confirm that all preparatory work is completed and the construction shall be officially started.

[0034] Preferably, the implementation steps of the monitoring and quality control before construction in step S3 are as follows:

[0035] S3.1. Installation of monitoring equipment, select appropriate monitoring equipment, including top force sensor, velocity sensor, inclination sensor and mud pressure sensor; use the equipment selection software InstrumentSelect, the top force sensor is model TFS-5000, with a range of 0-5000kN, the velocity sensor is model VSS-100, with a range of 0-10m / s, the inclination sensor is model IS-200, with a range of ±10°, and the mud pressure sensor is model MPS-150, with a range of 0-2MPa. Develop a detailed installation plan and determine the installation location and method of each sensor; use AutoCAD to draw an installation schematic diagram, install each monitoring device as planned at the construction site, ensure that the installation location is accurate, the connection is firm, and the installation accuracy is ±5mm; conduct joint adjustment and testing of the monitoring equipment through the automatic control system to ensure that the equipment works normally. The test result shows that the sensor error is less than 1%;

[0036] S3.2. Monitoring data acquisition and processing, using SCADA system for data acquisition and monitoring, setting sampling frequency and data transmission rate, sampling frequency is 1Hz, data transmission rate is 10Mbps, using Matlab for data processing and analysis, real-time monitoring of various parameters in the jacking process, jacking force fluctuation range is 4000-4500kN, speed range is 1-2m / min, inclination range is ±2°, mud pressure range is 1.2-1.5MPa, setting alarm function in SCADA system, when monitoring parameters exceed the preset range, the system automatically alarms and records, the alarm threshold is jacking force>4500kN, speed>2m / min, inclination>±2°, mud pressure>1.5MPa;

[0037] S3.3. Conduct regular quality inspections, formulate a detailed quality inspection plan, determine the inspection frequency and inspection items for each section of the pipeline, and conduct an inspection every 10 meters. The inspection items include pipeline connection quality, sealing, and alignment. Use special inspection tools for quality inspection, including laser alignment instrument and sealing tester. The accuracy of the laser alignment instrument is ±1mm, and the range of the sealing tester is 0-1MPa. Conduct quality inspections at the construction site as planned, and record the inspection results in an Excel table format, including the inspection date, inspection items, inspection results, and treatment measures;

[0038] S3.4. Problem handling and feedback: Identify problems in construction through monitoring data and quality inspection results, and record them in time. The recording tool is the fault recording module of the SCADA system. According to the type of problem, formulate corresponding treatment measures and handle them in time. The treatment measures include realignment, adjustment of mud pressure, and replacement of damaged pipes. The processing time is completed within 2 hours, and the processing results are fed back to the construction team to ensure that the problem is completely solved. The feedback tool is the internal communication system, including corporate WeChat and email;

[0039] S3.5. Data recording and reporting: All monitoring data and inspection results during the construction process are recorded in detail through the SCADA system and Excel spreadsheets. The recording format includes time, parameters, values, and treatment measures. Matlab is used to analyze the recorded data and generate a construction quality report. The analysis content includes parameter fluctuations, locations where quality problems frequently occur, and construction efficiency. The construction quality report is written through Word or LaTeX, recording the monitoring data and quality inspection results during the construction process in detail. The report content includes construction overview, monitoring data analysis, quality inspection results, and problem handling;

[0040] S3.6. Continuous improvement and optimization. According to the construction quality report, formulate an improvement plan for the next stage of construction and optimize the construction process. The improvement content includes adding monitoring equipment, adjusting construction parameters, strengthening quality inspection, establishing a construction feedback mechanism, and regularly organizing construction team meetings to summarize experience and lessons and put forward improvement suggestions. The meeting frequency is once a week. According to the feedback and improvement plan, continuously optimize the construction process and quality control measures to improve the construction quality and efficiency;

[0041] S3.7. Equipment maintenance and care. Develop a detailed equipment maintenance and care plan to ensure the normal operation of monitoring equipment and construction equipment. The maintenance frequency is once a month. Maintain and care the monitoring equipment and construction equipment as planned, record the maintenance results, and use the equipment maintenance log as the recording tool. Handle equipment failures in a timely manner to ensure that they do not affect the construction progress and quality. The handling time is completed within 24 hours;

[0042] S3.8. Construction summary and evaluation. After the construction is completed, a comprehensive construction summary shall be conducted to record the experiences and lessons learned during the construction process. The summary content shall include construction progress, quality, problem handling, and improvement suggestions. Performance evaluation shall be conducted on the construction team, outstanding teams and individuals shall be commended, and the construction team shall be motivated. The evaluation criteria shall be construction quality, efficiency, and safety. A detailed construction summary report shall be written to record various data and results of the entire construction process. The report format shall be PDF or paper version. Construction technology exchange meetings shall be organized to share experiences and technologies with other construction projects to improve the overall construction level.

[0043] Preferably, the implementation steps of setting the construction parameters in step S4 are as follows:

[0044] S4.1. Preliminary parameter setting: GPR and CPTu were used to conduct on-site soil surveys to obtain soil type, water content and other relevant data. The GPR parameters were 100 MHz frequency and 15 m detection depth. The CPTu parameters were 2 cm / s penetration rate and 20 m penetration depth. GeoStudio software was used to analyze the survey data and determine the physical properties and mechanical parameters of saturated clay. The soil water content was 45%, the cohesion was 20 kPa, and the internal friction angle was 15°.

[0045] S4.2. Force control: Use ANSYS software to simulate the strength of the pipe and determine the maximum force allowed by the pipe design. The pipe diameter is 1500mm and the design allowable force is 4500kN. Use the SCADA system to set the force control parameters to ensure that the force is within the design allowable range. The initial force is 4000kN and the force fluctuation range is 3900-4100kN.

[0046] S4.3. Jacking speed control: Use Excel to calculate the jacking speed according to the soil conditions and pipe diameter to avoid soil disturbance caused by too fast speed. The target speed is 3 meters per hour. Set the jacking speed parameters in the SCADA system to ensure a smooth jacking process. The speed range is 2-4 meters per hour, and the initial speed is 3 meters per hour.

[0047] S4.4. Adjust the mud ratio. The mud ratio suitable for saturated clay is determined through laboratory tests to ensure lubrication and support. The test tool is a Brookfield viscometer. The mud ratio is 30% bentonite and 70% water. The viscosity and rheological properties of the mud are tested using a Brookfield viscometer to ensure that they meet the requirements. The viscosity range is 20-25cP, and the rheological properties are plastic flow. The mud is prepared according to the ratio at the construction site and stirred evenly using a mud mixer for 30 minutes.

[0048] S4.5. Data recording and monitoring. Develop a data recording plan. Record data every 1-2 meters of jacking to ensure the stability and controllability of the jacking process. The recording frequency is once every 1.5 meters of jacking. Use the SCADA system for automatic data recording and use Excel to organize and analyze the data. The recorded content includes jacking force, speed, inclination, mud pressure, and the data format is CSV file;

[0049] S4.6. Real-time monitoring of the construction process. Use the SCADA system to monitor various parameters in the construction process in real time to ensure the stability of the construction process. The monitoring parameters are jacking force, speed, inclination, and mud pressure. The update frequency is once per second. According to the real-time monitoring data, the jacking force, speed and mud ratio are adjusted in time to ensure the stability of the construction process. The adjustment frequency is real-time;

[0050] S4.7. Quality control and inspection: a quality inspection is carried out every 10 meters to ensure the installation quality of each section of the pipeline. The inspection tools are laser centering instruments and sealing testers. The inspection items are pipeline connection quality, sealing, and centering. Excel is used to record the inspection results and quality reports are generated regularly to ensure that the construction quality is controllable. The reporting frequency is once a day and the report format is PDF file;

[0051] S4.8. Problem handling and improvement: timely identify problems existing in construction through monitoring data and quality inspection results, and record them in the SCADA system. The record content includes problem type, occurrence time, and treatment measures. According to the type of problem, formulate corresponding treatment measures and handle them in time. The processing time is completed within 2 hours. According to the problems found in construction, formulate improvement measures, optimize construction technology and quality control measures. The improvement content includes adjusting mud ratio, optimizing top force control, and strengthening speed management;

[0052] S4.9. Data analysis and summary. Use Matlab to analyze the data recorded during the construction process and evaluate the rationality of the construction parameters. The analysis content includes the fluctuation of top force, speed change, and mud pressure change. After the construction is completed, write a detailed summary report to record the data and results of the construction process. The report content includes construction overview, parameter setting, data analysis, quality inspection results, and problem handling. The report format is Word or LaTeX. Organize construction technology exchange meetings to share experiences and technologies with other construction projects to improve the overall construction level.

[0053] Preferably, the construction process of step S5 includes the following steps:

[0054] S5.1. Determine the location of the pilot hole and establish the working well and receiving well. Review the design drawings with AutoCAD software to determine the precise location of the pilot hole. The location of the pilot hole is marked according to the design drawings with an error of no more than 5 cm. Use a total station for on-site positioning and calibrate the location of the working well and receiving well. The location accuracy is no more than 3 cm. The measurement frequency is one measurement every 10 meters. The well location is constructed according to the measurement results. Steel sheet pile support is used to ensure construction safety. The working well size is 6 meters × 6 meters × 8 meters long × wide × deep, and the receiving well size is 6 meters × 6 meters × 8 meters long × wide × deep;

[0055] S5.2. Guided drilling equipment is used for drilling. Ditch Witch JT100 guided drilling equipment is used for equipment preparation and commissioning. The commissioning time is 2 hours. The drill bit diameter is 150mm. The drilling accuracy is monitored in real time by DigiTrak Falcon F5 guidance system. The monitoring frequency is one measurement every 0.5 meters. The accuracy requirement is that the vertical error does not exceed 1° and the horizontal error does not exceed 1.5°.

[0056] S5.3. Install and debug the pipe jacking machine. Install the Herrenknecht AVN1500 pipe jacking machine in the working pit and connect the relevant pipelines. The installation time is 8 hours. The equipment weight is 25 tons. Debug the pipe jacking machine through the SCADA system to ensure the normal operation of the equipment. The debugging content includes the jacking force, speed, and mud pressure. The debugging time is 4 hours;

[0057] S5.4. Mud circulation system connection: connect the mud circulation system according to the on-site pipeline layout to ensure the normal transportation and recovery of mud. The pipeline diameter is 100mm, the mud pump model is Graco 3900, and the Brookfield DV2T viscometer is used to test the mud viscosity to ensure that it meets the requirements. The viscosity requirement is 20-25cP, and the pumping pressure is 4MPa;

[0058] S5.5. Real-time monitoring of the jacking process. The control parameters of jacking speed, jacking force and direction are set through the SCADA system. The target speed is 3 m / h, the jacking force control range is 3900-4100 kN, and the direction deviation is no more than 1.5°. The SCADA system is used to monitor various parameters in the jacking process in real time to ensure that the jacking pipe moves along the designed route. The monitoring frequency is once per second, and data is recorded once every 1.5 m of jacking.

[0059] S5.6. Adjust the mud ratio and pressure. According to the real-time monitoring data, adjust the mud ratio through laboratory tests to ensure its lubrication and support functions. The mud ratio is 30% bentonite and 70% water. The test tool is Brookfield viscometer. The mud pressure is adjusted through the SCADA system to ensure the stable operation of the pipe jacking machine. The target pressure is 4MPa and the adjustment frequency is once an hour.

[0060] S5.7. Receiving well construction: Use a total station to measure the receiving well depth and position to ensure accuracy, with a depth error of no more than 5 cm and a position error of no more than 3 cm. Use steel sheet pile support to construct the receiving well to ensure safe and smooth receiving of the jacking pipe. The construction time is 5 days, and the construction equipment is a hydraulic excavator;

[0061] S5.8. Pipe joint splicing and sealing: Use a hydraulic pipe jacking machine to splice the pipe joints into place to ensure a tight connection with a splicing error of no more than 1cm. Use EPDM waterproof material to seal the pipe joints and use steel plates for reinforcement to ensure the sealing and strength of the interface. The thickness of the sealing material is 5mm and the thickness of the reinforcement steel plate is 10mm. Use a pressure tester to check the sealing of the pipe joints to ensure there is no water leakage. The test pressure is 2MPa and the test time is 2 hours.

[0062] Preferably, the implementation steps of the post-processing in step S6 are as follows:

[0063] S6.1. Remove the pipe jacking equipment, stop the operation of the pipe jacking machine through the SCADA system, ensure that all power supplies are cut off, and conduct equipment safety inspections. The downtime is 2 hours. The power off inspection is to confirm the power off through the Fluke 117 electrical multimeter. Use a hydraulic crane to dismantle the pipe jacking machine in the order of component disassembly. The dismantling time is 8 hours, and the lifting capacity is 100 tons. The order of components is cutting head, mud pump system, and drive unit. The disassembled pipe jacking machine components are transported to the designated storage location by flatbed trucks for cleaning and maintenance. The component transportation time is 4 hours, and the cleaning tool is a high-pressure cleaner;

[0064] S6.2. Cleaning of the construction site: use an excavator to clean up the earth and waste at the construction site and transport it to the designated waste disposal site. The cleaning time is 12 hours. The waste is transported by a 10-ton dump truck for 5 times. Use a sludge suction truck to clean up the residual mud at the construction site to ensure that the ground is clean. The suction time is 6 hours and the cleaning volume is 10 cubic meters. Use industrial cleaning equipment to flush the ground to ensure that there is no residual mud and pollutants. The cleaning area is 1,000 square meters and the cleaning time is 4 hours;

[0065] S6.3. Restoration of the construction area. Use a small loader to level the ground in the construction area to restore the original appearance of the ground. The leveling area is 1,000 square meters and the leveling time is 8 hours. Use a seeder to sow grass seeds and restore vegetation in the construction area to ensure greening. The sowing area is 500 square meters. The grass type is tall fescue and the sowing time is 2 hours. Use a portable environmental monitor to monitor the environment in the construction area to ensure that there is no pollution. The monitoring items are air quality and soil pollution. The monitoring time is 1 hour and the monitoring frequency is once a week for 4 consecutive weeks.

[0066] Preferably, the implementation steps of step S7 are:

[0067] S7.1. Safety training plan development. The training content and schedule are developed by using Microsoft Project, covering all safety regulations from S2 to S6. The training time is 1 hour before each construction step. The training content is operational safety, equipment use, and emergency plans. PowerPoint is used to create training presentations that describe in detail the safety measures and emergency response for each step. The content is text, pictures, and videos. An experienced safety engineer is designated as the person in charge of training. The training notice is issued through the company's internal OA system. There are 3 people in charge of training. The notice time is 2 days before each construction step.

[0068] S7.2. Safety training implementation: book the construction site conference room as the training venue through the enterprise management system to ensure the safety of the venue and the facilities are complete. The person in charge of the training will use the prepared PowerPoint presentation to explain in detail the safety measures and emergency plans for each step. The explanation time is 1 hour before each construction step.

[0069] S7.3. Safety drills: through on-site demonstrations and practice, train construction workers on the correct use of personal protective equipment. The drill time is 30 minutes before each construction step. The number of equipment is 20 sets. Simulate emergencies and conduct emergency plan drills to ensure that construction workers are familiar with the emergency response process. The drill frequency is 1. Evaluate the drill effect through video recording and on-site observation, and issue an evaluation report after the drill.

[0070] S7.4. Training effect evaluation: Use the online testing platform to test the construction personnel on the training content and evaluate their mastery of the training content. The test time is 30 minutes after each training session. The test questions are 20. The test results are analyzed through Excel to identify the weak links in the training and formulate improvement measures. The analysis time is 1 hour after each test. The analysis report collects the feedback of the construction personnel on the training through the system, conducts satisfaction surveys and collects improvement suggestions. The feedback time is 1 hour after each training session.

[0071] S7.5. Archive training records. Use the enterprise management system to electronically archive all training records, test results and feedback forms to ensure that the information is complete and traceable. The archiving time is 1 hour after each training session. The archived information includes training plans, sign-in sheets, drill records, evaluation reports, test results, and feedback forms.

[0072] Preferably, the simulation parameters in step S2.3 are mud viscosity 0.1 Pa·s and flow rate 2 m / s; the system pressure loss is ensured to be less than 0.2 MPa, and the construction drawings of the mud circulation system are generated by using Revit to ensure the accuracy of the position and connection of each component.

[0073] Preferably, the functional requirement of the automatic control system in step S2.5 is real-time monitoring of the top force, top distance, and mud flow, and the system parameters are a sampling frequency of 1 Hz and a data transmission rate of 10 Mbps. The design and selection are carried out by using the control system design software Simulink, and a suitable PLC and sensor equipment, model Siemens S7-1500, is selected. The automatic control system is tested in a laboratory environment to ensure the reliability and accuracy of the system. The test parameters are that the top force error is less than 1%, and the mud flow error is less than 2%.

[0074] Compared with the prior art, the beneficial effects of the present invention are: DETAILED DESCRIPTION

[0075] 1. Equipment:

[0076] Before construction, prepare the construction equipment, see Table 1;

[0077] Table 1 Long distance saturated clay pipe jacking construction equipment

[0078] Device Name model quantity Main parameters Total Station Leica TS16 2 Distance measurement accuracy: ±1.5mm GPS Trimble R10 2 Positioning accuracy: ±1cm Pipe jacking machine AVN6000 2 Thrust: 6000kN Mud mixer MB-300 1 Capacity: 300L Mud pump SJB-100 2 Flow rate: 100m3 / h

[0079] 2. Set the construction parameters, see Table 2;

[0080] Table 2 Equipment parameters

[0081]

[0082]

[0083] 3. Long distance saturated clay pipe jacking construction process, specifically, the steps are:

[0084] A long-distance saturated clay pipe jacking construction process comprises the following steps:

[0085] S1.Preliminary preparation:

[0086] S1.1. Geological survey: drilling operations, sampling and analysis, groundwater level monitoring, and data aggregation and analysis. Multiple exploration holes are drilled in the construction area with an electric drill rig to a depth of 50 meters. Soil samples are taken from each borehole for indoor analysis to determine soil thickness, water content, soil structure and porosity. Pore water pressure gauges are installed to continuously monitor groundwater level changes. Three-dimensional geological models are generated by inputting exploration data into RockWorks or GEO5 geological modeling software;

[0087] S1.2. Determination of design parameters: Conduct preliminary design, mechanical calculation, material selection and design review. Draw preliminary design drawings using AutoCAD Civil 3D, determine pipe diameter, top force and top distance parameters, perform detailed calculations of top force and top distance using PLAXIS 3D, select reinforced concrete pipe as the pipe segment material and calculate its bearing capacity and durability, organize experts to conduct design review, and modify and optimize the design plan;

[0088] S1.3. Site cleaning: Conduct site survey, mechanical equipment, cleaning work and site acceptance. The construction team will conduct site survey, mark the areas and obstacles that need to be cleaned, mobilize excavators and bulldozers to the site, use mechanical equipment to clean the ground, remove debris, vegetation and obstacles, and conduct site acceptance by the construction supervisor to ensure that the construction requirements are met;

[0089] S1.4. Transportation corridor preparation: corridor planning, ground leveling, signage and corridor inspection. Design the transportation corridor by using ArcGIS to determine the best route. Use bulldozers and rollers to level and compact the ground of the transportation corridor. Set up warning signs and signboards on both sides of the corridor to ensure transportation safety. Accept the transportation corridor through construction supervision to ensure that the corridor is flat, solid and clearly marked.

[0090] S1.5. Construction of rest area for construction workers: site selection and design, material preparation, construction work, acceptance and management, by selecting the location of the rest area and using SketchUp for layout design, by purchasing and transporting necessary construction materials, including tents, prefabricated houses, and sanitary facilities, by organizing construction workers to build the rest area according to the design drawings, installing sanitary facilities and rest equipment, by acceptance after the rest area is built, and formulating a management system;

[0091] S1.6. Construction of mechanical equipment storage area: After planning the storage area, hardening the ground, marking and marking the equipment, the mechanical equipment storage area is designed by using AutoCAD, and the equipment placement and passage are determined. The storage area floor is hardened by using concrete to ensure the floor is flat and durable. The equipment storage location and passage are marked on the ground, and relevant signs are set. The mechanical equipment is placed in an orderly manner according to the planned location, and the equipment is inspected and maintained.

[0092] S1.7. Construction of material storage area: Design the storage area, build scaffolding, and set up safety measures before materials are brought in. Design the material storage area using Revit to ensure reasonable layout and safe storage. Build material storage scaffolding to ensure that materials are classified and stored, protected from rain and sun. Set up fire prevention and anti-theft safety measures in the storage area to ensure material safety. Organize materials to be stored in an orderly manner according to classification, and regularly check the storage status of materials.

[0093] S1.8. Comprehensive acceptance and commissioning: Conduct overall acceptance, equipment commissioning, prepare reports and hold pre-construction meetings. Organize construction supervision to conduct comprehensive acceptance of construction preparation work. Comprehensively commission pipe jacking equipment, auxiliary equipment and monitoring equipment. Write a construction preparation report to record the specific conditions and acceptance results of various preparations. Confirm the completion of various preparations and arrange specific construction tasks by holding pre-construction meetings.

[0094] S2. Construction equipment selection:

[0095] S2.1. Selection of pipe jacking machine. Through research on domestic and foreign pipe jacking machine manufacturers, we selected equipment suitable for long-distance saturated clay pipe jacking construction. We used Google Scholar and engineering magazine databases to build a comparison table of pipe jacking machine technical parameters through Excel, and compared the parameters of different types of earth pressure balance pipe jacking machines and slurry balance pipe jacking machines, including jacking force, jacking distance, and mud flow rate. The earth pressure balance pipe jacking machine has a jacking force of 5000kN and a jacking distance of 3000mm, while the slurry balance pipe jacking machine has a jacking force of 4500kN and a jacking distance of 3200mm. We used GeoStudio software to simulate geological conditions and verify the applicability of different pipe jacking machines in saturated clay. The parameters were set to 18° internal friction angle of saturated clay, 25kPa cohesion, and 0.65 porosity. We selected the earth pressure balance pipe jacking machine based on comprehensive technical parameters and simulation results.

[0096] S2.2. Mud pump selection: determine the specifications of the mud pump by calculating the required mud flow and pressure. The mud flow requirement is 50m 3 / h, the mud pressure requirement is 1.5MPa. The mud pump is selected by using the equipment selection software PumpSelect, and the final model is Warman 450DT. The performance and reliability of the mud pump are reviewed by technical experts to confirm the rationality of the selection.

[0097] S2.3. Design of mud circulation system: Use AutoCAD to design the layout of the mud circulation system, determine the location of the mud pipeline, mud storage tank and mud separator, simulate the mud circulation system by using CFD software, optimize the mud flow path, ensure smooth mud circulation, and use the simulation parameters of mud viscosity 0.1Pa·s and flow rate 2m / s; ensure that the system pressure loss is less than 0.2MPa, and use Revit to generate the construction drawings of the mud circulation system to ensure the accuracy of the location and connection of each component;

[0098] S2.4. Segment transportation equipment selection: By calculating the segment size and weight, determine the required transportation equipment specifications. The segment size is 1.5mx1.5mx0.2m, and the segment weight is 1.2 tons. Use the logistics equipment selection software to select the appropriate transportation equipment. Use the logistics simulation software FlexSim to simulate the segment transportation and optimize the transportation path and efficiency. The simulation parameters are transportation distance 1000m and transportation speed 1m / s.

[0099] S2.5. Automatic control system design. By analyzing the automation requirements during pipe jacking construction, the functions and parameters of the automatic control system are determined. The functional requirements of the automatic control system are real-time monitoring of the jacking force, jacking distance, and mud flow. The system parameters are sampling frequency 1Hz and data transmission rate 10Mbps. By using the control system design software Simulink for design and selection, the appropriate PLC and sensor equipment are selected, model Siemens S7-1500. The automatic control system is tested in a laboratory environment to ensure the reliability and accuracy of the system. The test parameters are jacking force error less than 1% and mud flow error less than 2%;

[0100] S2.6. Equipment commissioning and installation: transport the pipe jacking machine, mud pump, mud circulation system, segment transport equipment and automatic control system to the construction site by mobilizing construction machinery and equipment; install the equipment by using cranes and hoists to ensure that the equipment is accurately positioned, connected firmly, and installed with an accuracy of ±5mm; and coordinate the entire equipment system by using automatic control systems to ensure that all equipment works in coordination;

[0101] S2.7. Operator training: by formulating a detailed equipment operation training plan, ensure that operators master the equipment use and maintenance methods; by organizing equipment manufacturer technicians to conduct on-site training for operators, providing detailed operation manuals and maintenance guides, and by assessing operators, ensure that they can operate the equipment proficiently and respond to emergencies;

[0102] S2.8. Final acceptance and preparation: All equipment shall be accepted by the construction supervisor to ensure that the equipment installation and commissioning meet the requirements; all materials and tools required for construction shall be prepared by writing a detailed construction plan; all equipment and systems shall be ready to meet the construction requirements by conducting a comprehensive final inspection; all preparations shall be confirmed to be completed by organizing a construction start-up meeting and the construction shall be officially started;

[0103] S3. Monitoring and quality control before construction:

[0104] S3.1. Installation of monitoring equipment, select appropriate monitoring equipment, including top force sensor, velocity sensor, inclination sensor and mud pressure sensor; use the equipment selection software InstrumentSelect, the top force sensor is model TFS-5000, with a range of 0-5000kN, the velocity sensor is model VSS-100, with a range of 0-10m / s, the inclination sensor is model IS-200, with a range of ±10°, and the mud pressure sensor is model MPS-150, with a range of 0-2MPa. Develop a detailed installation plan and determine the installation location and method of each sensor; use AutoCAD to draw an installation schematic diagram, install each monitoring device as planned at the construction site, ensure that the installation location is accurate, the connection is firm, and the installation accuracy is ±5mm; conduct joint adjustment and testing of the monitoring equipment through the automatic control system to ensure that the equipment works normally. The test result shows that the sensor error is less than 1%;

[0105] S3.2. Monitoring data acquisition and processing, using SCADA system for data acquisition and monitoring, setting sampling frequency and data transmission rate, sampling frequency is 1Hz, data transmission rate is 10Mbps, using Matlab for data processing and analysis, real-time monitoring of various parameters in the jacking process, jacking force fluctuation range is 4000-4500kN, speed range is 1-2m / min, inclination range is ±2°, mud pressure range is 1.2-1.5MPa, setting alarm function in SCADA system, when monitoring parameters exceed the preset range, the system automatically alarms and records, the alarm threshold is jacking force>4500kN, speed>2m / min, inclination>±2°, mud pressure>1.5MPa;

[0106] S3.3. Conduct regular quality inspections, formulate a detailed quality inspection plan, determine the inspection frequency and inspection items for each section of the pipeline, and conduct an inspection every 10 meters. The inspection items include pipeline connection quality, sealing, and alignment. Use special inspection tools for quality inspection, including laser alignment instrument and sealing tester. The accuracy of the laser alignment instrument is ±1mm, and the range of the sealing tester is 0-1MPa. Conduct quality inspections at the construction site as planned, and record the inspection results in an Excel table format, including the inspection date, inspection items, inspection results, and treatment measures;

[0107] S3.4. Problem handling and feedback: Identify problems in construction through monitoring data and quality inspection results, and record them in time. The recording tool is the fault recording module of the SCADA system. According to the type of problem, formulate corresponding treatment measures and handle them in time. The treatment measures include realignment, adjustment of mud pressure, and replacement of damaged pipes. The processing time is completed within 2 hours, and the processing results are fed back to the construction team to ensure that the problem is completely solved. The feedback tool is the internal communication system, including corporate WeChat and email;

[0108] S3.5. Data recording and reporting: All monitoring data and inspection results during the construction process are recorded in detail through the SCADA system and Excel spreadsheets. The recording format includes time, parameters, values, and treatment measures. Matlab is used to analyze the recorded data and generate a construction quality report. The analysis content includes parameter fluctuations, locations where quality problems frequently occur, and construction efficiency. The construction quality report is written through Word or LaTeX, recording the monitoring data and quality inspection results during the construction process in detail. The report content includes construction overview, monitoring data analysis, quality inspection results, and problem handling;

[0109] S3.6. Continuous improvement and optimization. According to the construction quality report, formulate an improvement plan for the next stage of construction and optimize the construction process. The improvement content includes adding monitoring equipment, adjusting construction parameters, strengthening quality inspection, establishing a construction feedback mechanism, and regularly organizing construction team meetings to summarize experience and lessons and put forward improvement suggestions. The meeting frequency is once a week. According to the feedback and improvement plan, continuously optimize the construction process and quality control measures to improve the construction quality and efficiency;

[0110] S3.7. Equipment maintenance and care. Develop a detailed equipment maintenance and care plan to ensure the normal operation of monitoring equipment and construction equipment. The maintenance frequency is once a month. Maintain and care the monitoring equipment and construction equipment as planned, record the maintenance results, and use the equipment maintenance log as the recording tool. Handle equipment failures in a timely manner to ensure that they do not affect the construction progress and quality. The handling time is completed within 24 hours;

[0111] S3.8. Construction summary and evaluation. After the construction is completed, a comprehensive construction summary is conducted to record the experience and lessons learned during the construction process. The summary content includes construction progress, quality, problem handling, and improvement suggestions. The performance of the construction team is evaluated, outstanding teams and individuals are commended, and the construction team is motivated. The evaluation criteria are construction quality, efficiency, and safety. A detailed construction summary report is written to record various data and results of the entire construction process. The report format is PDF or paper version. A construction technology exchange meeting is organized to share experience and technology with other construction projects to improve the overall construction level.

[0112] S4. Set construction parameters:

[0113] S4.1. Preliminary parameter setting: GPR and CPTu were used to conduct on-site soil surveys to obtain soil type, water content and other relevant data. The GPR parameters were 100 MHz frequency and 15 m detection depth. The CPTu parameters were 2 cm / s penetration rate and 20 m penetration depth. GeoStudio software was used to analyze the survey data and determine the physical properties and mechanical parameters of saturated clay. The soil water content was 45%, the cohesion was 20 kPa, and the internal friction angle was 15°.

[0114] S4.2. Force control: Use ANSYS software to simulate the strength of the pipe and determine the maximum force allowed by the pipe design. The pipe diameter is 1500mm and the design allowable force is 4500kN. Use the SCADA system to set the force control parameters to ensure that the force is within the design allowable range. The initial force is 4000kN and the force fluctuation range is 3900-4100kN.

[0115] S4.3. Jacking speed control: Use Excel to calculate the jacking speed according to the soil conditions and pipe diameter to avoid soil disturbance caused by too fast speed. The target speed is 3 meters per hour. Set the jacking speed parameters in the SCADA system to ensure a smooth jacking process. The speed range is 2-4 meters per hour, and the initial speed is 3 meters per hour.

[0116] S4.4. Adjust the mud ratio. The mud ratio suitable for saturated clay is determined through laboratory tests to ensure lubrication and support. The test tool is a Brookfield viscometer. The mud ratio is 30% bentonite and 70% water. The viscosity and rheological properties of the mud are tested using a Brookfield viscometer to ensure that they meet the requirements. The viscosity range is 20-25cP, and the rheological properties are plastic flow. The mud is prepared according to the ratio at the construction site and stirred evenly using a mud mixer for 30 minutes.

[0117] S4.5. Data recording and monitoring. Develop a data recording plan. Record data every 1-2 meters of jacking to ensure the stability and controllability of the jacking process. The recording frequency is once every 1.5 meters of jacking. Use the SCADA system for automatic data recording and use Excel to organize and analyze the data. The recorded content includes jacking force, speed, inclination, mud pressure, and the data format is CSV file;

[0118] S4.6. Real-time monitoring of the construction process. Use the SCADA system to monitor various parameters in the construction process in real time to ensure the stability of the construction process. The monitoring parameters are jacking force, speed, inclination, and mud pressure. The update frequency is once per second. According to the real-time monitoring data, the jacking force, speed and mud ratio are adjusted in time to ensure the stability of the construction process. The adjustment frequency is real-time;

[0119] S4.7. Quality control and inspection: a quality inspection is carried out every 10 meters to ensure the installation quality of each section of the pipeline. The inspection tools are laser centering instruments and sealing testers. The inspection items are pipeline connection quality, sealing, and centering. Excel is used to record the inspection results and quality reports are generated regularly to ensure that the construction quality is controllable. The reporting frequency is once a day and the report format is PDF file;

[0120] S4.8. Problem handling and improvement: timely identify problems existing in construction through monitoring data and quality inspection results, and record them in the SCADA system. The record content includes problem type, occurrence time, and treatment measures. According to the type of problem, formulate corresponding treatment measures and handle them in time. The processing time is completed within 2 hours. According to the problems found in construction, formulate improvement measures, optimize construction technology and quality control measures. The improvement content includes adjusting mud ratio, optimizing top force control, and strengthening speed management;

[0121] S4.9. Data analysis and summary: Use Matlab to analyze the data recorded during the construction process and evaluate the rationality of the construction parameters. The analysis content includes the fluctuation of the top force, the change of speed, and the change of mud pressure. After the construction is completed, write a detailed summary report to record the data and results of the construction process. The report content includes construction overview, parameter setting, data analysis, quality inspection results, and problem handling. The report format is Word or LaTeX. Organize construction technology exchange meetings to share experiences and technologies with other construction projects to improve the overall construction level.

[0122] S5. Implementation steps:

[0123] S5.1. Determine the location of the pilot hole and establish the working well and receiving well. Review the design drawings with AutoCAD software to determine the precise location of the pilot hole. The location of the pilot hole is marked according to the design drawings with an error of no more than 5 cm. Use a total station for on-site positioning and calibrate the location of the working well and receiving well. The location accuracy is no more than 3 cm. The measurement frequency is one measurement every 10 meters. The well location is constructed according to the measurement results. Steel sheet pile support is used to ensure construction safety. The working well size is 6 meters × 6 meters × 8 meters long × wide × deep, and the receiving well size is 6 meters × 6 meters × 8 meters long × wide × deep;

[0124] S5.2. Guided drilling equipment is used for drilling. Ditch Witch JT100 guided drilling equipment is used for equipment preparation and commissioning. The commissioning time is 2 hours. The drill bit diameter is 150mm. The drilling accuracy is monitored in real time by DigiTrak Falcon F5 guidance system. The monitoring frequency is one measurement every 0.5 meters. The accuracy requirement is that the vertical error does not exceed 1° and the horizontal error does not exceed 1.5°.

[0125] S5.3. Install and debug the pipe jacking machine. Install the Herrenknecht AVN1500 pipe jacking machine in the working pit and connect the relevant pipelines. The installation time is 8 hours. The equipment weight is 25 tons. Debug the pipe jacking machine through the SCADA system to ensure the normal operation of the equipment. The debugging content includes the jacking force, speed, and mud pressure. The debugging time is 4 hours;

[0126] S5.4. Mud circulation system connection: connect the mud circulation system according to the on-site pipeline layout to ensure the normal transportation and recovery of mud. The pipeline diameter is 100mm, the mud pump model is Graco 3900, and the Brookfield DV2T viscometer is used to test the mud viscosity to ensure that it meets the requirements. The viscosity requirement is 20-25cP, and the pumping pressure is 4MPa;

[0127] S5.5. Real-time monitoring of the jacking process. The control parameters of jacking speed, jacking force and direction are set through the SCADA system. The target speed is 3 m / h, the jacking force control range is 3900-4100 kN, and the direction deviation is no more than 1.5°. The SCADA system is used to monitor various parameters in the jacking process in real time to ensure that the jacking pipe moves along the designed route. The monitoring frequency is once per second, and data is recorded once every 1.5 m of jacking.

[0128] S5.6. Adjust the mud ratio and pressure. According to the real-time monitoring data, adjust the mud ratio through laboratory tests to ensure its lubrication and support functions. The mud ratio is 30% bentonite and 70% water. The test tool is Brookfield viscometer. The mud pressure is adjusted through the SCADA system to ensure the stable operation of the pipe jacking machine. The target pressure is 4MPa and the adjustment frequency is once an hour.

[0129] S5.7. Receiving well construction: Use a total station to measure the receiving well depth and position to ensure accuracy, with a depth error of no more than 5 cm and a position error of no more than 3 cm. Use steel sheet pile support to construct the receiving well to ensure safe and smooth receiving of the jacking pipe. The construction time is 5 days, and the construction equipment is a hydraulic excavator;

[0130] S5.8. Pipe joint splicing and sealing: Use a hydraulic pipe jacking machine to splice the pipe joints in place to ensure tight connections. The splicing error is no more than 1 cm. Use EPDM waterproof material to seal the pipe joints and use steel plates to reinforce them to ensure the sealing and strength of the interface. The thickness of the sealing material is 5 mm and the thickness of the reinforcement steel plate is 10 mm. Use a pressure tester to check the sealing of the pipe joints to ensure there is no water leakage. The test pressure is 2 MPa and the test time is 2 hours.

[0131] S6. Perform post-processing:

[0132] S6.1. Remove the pipe jacking equipment, stop the operation of the pipe jacking machine through the SCADA system, ensure that all power supplies are cut off, and conduct equipment safety inspections. The downtime is 2 hours. The power off inspection is to confirm the power off through the Fluke 117 electrical multimeter. Use a hydraulic crane to dismantle the pipe jacking machine in the order of component disassembly. The dismantling time is 8 hours, and the lifting capacity is 100 tons. The order of components is cutting head, mud pump system, and drive unit. The disassembled pipe jacking machine components are transported to the designated storage location by flatbed trucks for cleaning and maintenance. The component transportation time is 4 hours, and the cleaning tool is a high-pressure cleaner;

[0133] S6.2. Cleaning of the construction site: use an excavator to clean up the earth and waste at the construction site and transport it to the designated waste disposal site. The cleaning time is 12 hours. The waste is transported by a 10-ton dump truck for 5 times. Use a sludge suction truck to clean up the residual mud at the construction site to ensure that the ground is clean. The suction time is 6 hours and the cleaning volume is 10 cubic meters. Use industrial cleaning equipment to flush the ground to ensure that there is no residual mud and pollutants. The cleaning area is 1,000 square meters and the cleaning time is 4 hours;

[0134] S6.3. Restoration of the construction area. Use a small loader to level the ground in the construction area to restore the original appearance of the ground. The leveling area is 1,000 square meters and the leveling time is 8 hours. Use a seeder to sow grass seeds and restore vegetation in the construction area to ensure greening. The sowing area is 500 square meters. The grass type is tall fescue and the sowing time is 2 hours. Use a portable environmental monitor to monitor the environment in the construction area to ensure that there is no pollution. The monitoring items are air quality and soil pollution. The monitoring time is 1 hour and the monitoring frequency is once a week for 4 consecutive weeks.

[0135] 4. Before the end of construction, real-time monitoring of the line setting accuracy, baseline error, mud flow, jacking direction, and pipeline is performed, see Table 3 and Table 4;

[0136] Table 3 Various test tables

[0137] Test items equipment parameter result Pay-off accuracy Total Station ±1.5mm qualified Baseline error Laser Level ±1mm qualified Mud flow Flow Meter <![CDATA[100m 3 / h]]> qualified Pipe jacking direction Monitoring system ±2° qualified Pipeline Inspection CCTV No damage qualified

[0138] Table 4 Summary comparison table

[0139]

[0140]

[0141] 5. Construction standards:

[0142] The long-distance saturated clay pipe jacking construction process of the present invention is carried out in accordance with the following standards:

[0143] Technical specification for pipe jacking construction (CECS246:2008);

[0144] Specification for construction of underground continuous walls (GB / T 50108-2008);

[0145] Code for Design of Building Foundations (GB 50007-2011);

[0146] Specification for Construction and Acceptance of Urban Water Supply and Drainage Projects (GB 50268-2008);

[0147] Technical specification for bored cast-in-place piles with slurry wall protection (JGJ 94-2008).

[0148] In summary, the long-distance saturated clay pipe jacking construction process of the present invention has significant advantages in adapting to complex geological conditions, reducing surface impacts and improving construction accuracy. It can maintain the stability and accuracy of pipe jacking construction over long distances, is suitable for large-scale engineering projects, and can be constructed under complex geological conditions such as saturated clay. It can solve geological problems that traditional pipe jacking is difficult to deal with. During the construction process, surface settlement and environmental damage are small, and it is suitable for underground projects in densely populated urban areas.

[0149] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A long-distance saturated clay pipe jacking construction process, characterized in that: The following steps are involved: S1. Preliminary preparation: Detailed investigation of the thickness, water content, soil structure and groundwater level of the long-distance saturated clay layer; based on the survey data, determine the specific parameters of pipe diameter, top force, top distance and pipe joint materials; clean and level the construction site; ensure that the work site and transportation channels are unobstructed; and build a rest area for construction personnel, a storage area for machinery and equipment, and a storage area for materials; S2. Construction equipment selection: Choose a pipe jacking machine suitable for long-distance pipe jacking, consider earth pressure balance pipe jacking machine or mud water balance pipe jacking machine to adapt to saturated clay conditions, including mud pump, mud circulation system, pipe segment transportation equipment and automatic control system; S3. Carry out monitoring and quality control before construction. By installing monitoring equipment, various parameters in the jacking process, including jacking force, speed, inclination and mud pressure, are monitored in real time. Quality inspections are carried out regularly to ensure the installation quality of each section of the pipeline and problems are dealt with in a timely manner; S4. Set construction parameters, reasonably control the jacking force according to the pipe diameter and soil conditions, control it within the allowable range of pipe design, control the jacking speed to avoid soil disturbance caused by excessive speed, and control it within 2-4 meters / hour. According to the characteristics of saturated clay, adjust the mud ratio to ensure the lubrication and support of the mud. During the jacking process, record data every 1-2 meters to ensure the stability and controllability of the jacking process; S5. Implement construction steps. According to the design drawings, determine the location of the guide hole, and build working wells and receiving wells at both ends. Use guide drilling equipment to drill holes to ensure the accuracy of the guide hole. Install the pipe jacking machine in the working well and debug the equipment to ensure its normal operation. Connect the mud circulation system to ensure the normal transportation and recovery of mud. Use an automatic control system to monitor the jacking speed, jacking force and direction in real time to ensure that the jacking pipe moves along the designed route. According to soil conditions, adjust the mud ratio and pressure to ensure the stable operation of the pipe jacking machine and the support of the hole wall. Ensure the depth and position of the receiving well are accurate to facilitate the smooth reception of the jacking pipe. At the joints of the pipe sections, use waterproof materials and reinforcement measures to ensure the sealing and strength of the interface; S6. After the pipe jacking construction is completed, the pipe jacking equipment is dismantled, the construction site is cleaned up, and the construction area is restored to ensure that the environmental impact is minimized; S7. Conduct safety measures training and guidance in real time. Before implementing each step from step S2 to step S6, all construction personnel need to receive safety training to ensure that they understand and comply with the construction safety regulations of that step, and develop detailed emergency plans to deal with emergencies.

2. A long-distance saturated clay pipe jacking construction process according to claim 1, characterized in that: The implementation steps of the preliminary preparation of step S1 are as follows: S1.

1. Geological survey: drilling operations, sampling and analysis, groundwater level monitoring, and data aggregation and analysis. Multiple exploration holes are drilled in the construction area with an electric drill rig to a depth of 50 meters. Soil samples are taken from each borehole for indoor analysis to determine soil thickness, water content, soil structure and porosity. Pore water pressure gauges are installed to continuously monitor groundwater level changes. Three-dimensional geological models are generated by inputting exploration data into RockWorks or GEO5 geological modeling software; S1.

2. Determination of design parameters: Conduct preliminary design, mechanical calculation, material selection and design review. Draw preliminary design drawings using AutoCAD Civil 3D, determine pipe diameter, top force and top distance parameters, perform detailed calculations of top force and top distance using PLAXIS 3D, select reinforced concrete pipe as the pipe segment material and calculate its bearing capacity and durability, organize experts to conduct design review, and modify and optimize the design plan; S1.

3. Site cleaning: Conduct site survey, mechanical equipment, cleaning work and site acceptance. The construction team will conduct site survey, mark the areas and obstacles that need to be cleaned, mobilize excavators and bulldozers to the site, use mechanical equipment to clean the ground, remove debris, vegetation and obstacles, and conduct site acceptance by the construction supervisor to ensure that the construction requirements are met; S1.

4. Transportation corridor preparation: corridor planning, ground leveling, signage and corridor inspection. Design the transportation corridor by using ArcGIS to determine the best route. Use bulldozers and rollers to level and compact the ground of the transportation corridor. Set up warning signs and signboards on both sides of the corridor to ensure transportation safety. Accept the transportation corridor through construction supervision to ensure that the corridor is flat, solid and clearly marked. S1.

5. Construction of rest area for construction workers: site selection and design, material preparation, construction work, acceptance and management, by selecting the location of the rest area and using SketchUp for layout design, by purchasing and transporting necessary construction materials, including tents, prefabricated houses, and sanitary facilities, by organizing construction workers to build the rest area according to the design drawings, installing sanitary facilities and rest equipment, by acceptance after the rest area is built, and formulating a management system; S1.

6. Construction of mechanical equipment storage area: After planning the storage area, hardening the ground, marking and marking the equipment, the mechanical equipment storage area is designed by using AutoCAD, and the equipment placement and passage are determined. The storage area floor is hardened by using concrete to ensure the floor is flat and durable. The equipment storage location and passage are marked on the ground, and relevant signs are set. The mechanical equipment is placed in an orderly manner according to the planned location, and the equipment is inspected and maintained. S1.

7. Construction of material storage area: Design the storage area, build scaffolding, and set up safety measures before materials are brought in. Design the material storage area using Revit to ensure reasonable layout and safe storage. Build material storage scaffolding to ensure that materials are classified and stored, protected from rain and sun. Set up fire prevention and anti-theft safety measures in the storage area to ensure material safety. Organize materials to be stored in an orderly manner according to classification, and regularly check the storage status of materials. S1.

8. Comprehensive acceptance and commissioning: Carry out overall acceptance, equipment commissioning, prepare reports and hold pre-construction meetings. Organize construction supervision to conduct a comprehensive acceptance of construction preparation work. Carry out comprehensive commissioning of pipe jacking equipment, auxiliary equipment and monitoring equipment. Write a construction preparation report to record the specific circumstances and acceptance results of each preparation work. Confirm the completion of each preparation work and arrange specific construction tasks by holding a pre-construction meeting.

3. A long-distance saturated clay pipe jacking construction process according to claim 2, characterized in that , the implementation steps of step S2 construction equipment selection are as follows: S2.

1. Selection of pipe jacking machine. Through research on domestic and foreign pipe jacking machine manufacturers, we selected equipment suitable for long-distance saturated clay pipe jacking construction. We used Google Scholar and engineering magazine databases to build a comparison table of pipe jacking machine technical parameters through Excel, and compared the parameters of different types of earth pressure balance pipe jacking machines and slurry balance pipe jacking machines, including jacking force, jacking distance, and mud flow rate. The earth pressure balance pipe jacking machine has a jacking force of 5000kN and a jacking distance of 3000mm, while the slurry balance pipe jacking machine has a jacking force of 4500kN and a jacking distance of 3200mm. We used GeoStudio software to simulate geological conditions and verify the applicability of different pipe jacking machines in saturated clay. The parameters were set to 18° internal friction angle of saturated clay, 25kPa cohesion, and 0.65 porosity. We selected the earth pressure balance pipe jacking machine based on comprehensive technical parameters and simulation results. S2.

2. Mud pump selection: determine the specifications of the mud pump by calculating the required mud flow and pressure. The mud flow requirement is 50m 3 / h, the mud pressure requirement is 1.5MPa. The mud pump is selected by using the equipment selection software PumpSelect, and the final model is Warman 450DT. The performance and reliability of the mud pump are reviewed by technical experts to confirm the rationality of the selection. S2.

3. Design of mud circulation system: Use AutoCAD to design the layout of the mud circulation system, determine the location of the mud pipeline, mud storage tank and mud separator, and use CFD software to simulate the mud circulation system, optimize the mud flow path and ensure smooth mud circulation; S2.

4. Segment transportation equipment selection: By calculating the segment size and weight, determine the required transportation equipment specifications. The segment size is 1.5mx1.5mx0.2m, and the segment weight is 1.2 tons. Use the logistics equipment selection software to select the appropriate transportation equipment. Use the logistics simulation software FlexSim to simulate the segment transportation and optimize the transportation path and efficiency. The simulation parameters are transportation distance 1000m and transportation speed 1m / s. S2.

5. Automatic control system design: by analyzing the automation requirements during pipe jacking construction, determine the functions and parameters of the automatic control system; S2.

6. Equipment commissioning and installation: transport the pipe jacking machine, mud pump, mud circulation system, segment transport equipment and automatic control system to the construction site by mobilizing construction machinery and equipment; install the equipment by using cranes and hoists to ensure that the equipment is accurately positioned, connected firmly, and installed with an accuracy of ±5mm; and coordinate the entire equipment system by using automatic control systems to ensure that all equipment works in coordination; S2.

7. Operator training: by formulating a detailed equipment operation training plan, ensure that operators master the equipment use and maintenance methods; by organizing equipment manufacturer technicians to conduct on-site training for operators, providing detailed operation manuals and maintenance guides, and by assessing operators, ensure that they can operate the equipment proficiently and respond to emergencies; S2.

8. Final acceptance and preparation: All equipment shall be inspected and accepted by the construction supervisor to ensure that the equipment installation and commissioning meet the requirements. A detailed construction plan shall be prepared to prepare all the materials and tools required for construction. A comprehensive final inspection shall be conducted to ensure that all equipment and systems are ready and meet the construction requirements. A construction kick-off meeting shall be organized to confirm that all preparatory work is completed and the construction shall be officially started.

4. A long-distance saturated clay pipe jacking construction process according to claim 3, characterized in that: The implementation steps of the monitoring and quality control before construction in step S3 are as follows: S3.

1. Installation of monitoring equipment, select appropriate monitoring equipment, including top force sensor, velocity sensor, inclination sensor and mud pressure sensor; use the equipment selection software InstrumentSelect, the top force sensor is model TFS-5000, with a range of 0-5000kN, the velocity sensor is model VSS-100, with a range of 0-10m / s, the inclination sensor is model IS-200, with a range of ±10°, and the mud pressure sensor is model MPS-150, with a range of 0-2MPa. Develop a detailed installation plan and determine the installation location and method of each sensor; use AutoCAD to draw an installation schematic diagram, install each monitoring device as planned at the construction site, ensure that the installation location is accurate, the connection is firm, and the installation accuracy is ±5mm; conduct joint adjustment and testing of the monitoring equipment through the automatic control system to ensure that the equipment works normally. The test result shows that the sensor error is less than 1%; S3.

2. Monitoring data acquisition and processing, using SCADA system for data acquisition and monitoring, setting sampling frequency and data transmission rate, sampling frequency is 1Hz, data transmission rate is 10Mbps, using Matlab for data processing and analysis, real-time monitoring of various parameters in the jacking process, jacking force fluctuation range is 4000-4500kN, speed range is 1-2m / min, inclination range is ±2°, mud pressure range is 1.2-1.5MPa, setting alarm function in SCADA system, when monitoring parameters exceed the preset range, the system automatically alarms and records, the alarm threshold is jacking force>4500kN, speed>2m / min, inclination>±2°, mud pressure>1.5MPa; S3.

3. Conduct regular quality inspections, formulate a detailed quality inspection plan, determine the inspection frequency and inspection items for each section of the pipeline, and conduct an inspection every 10 meters. The inspection items include pipeline connection quality, sealing, and alignment. Use special inspection tools for quality inspection, including laser alignment instrument and sealing tester. The accuracy of the laser alignment instrument is ±1mm, and the range of the sealing tester is 0-1MPa. Conduct quality inspections at the construction site as planned, and record the inspection results in an Excel table format, including the inspection date, inspection items, inspection results, and treatment measures; S3.

4. Problem handling and feedback: Identify problems in construction through monitoring data and quality inspection results, and record them in time. The recording tool is the fault recording module of the SCADA system. According to the type of problem, formulate corresponding treatment measures and handle them in time. The treatment measures include realignment, adjustment of mud pressure, and replacement of damaged pipes. The processing time is completed within 2 hours, and the processing results are fed back to the construction team to ensure that the problem is completely solved. The feedback tool is the internal communication system, including corporate WeChat and email; S3.

5. Data recording and reporting: All monitoring data and inspection results during the construction process are recorded in detail through the SCADA system and Excel spreadsheets. The recording format includes time, parameters, values, and treatment measures. Matlab is used to analyze the recorded data and generate a construction quality report. The analysis content includes parameter fluctuations, locations where quality problems frequently occur, and construction efficiency. The construction quality report is written through Word or LaTeX, recording the monitoring data and quality inspection results during the construction process in detail. The report content includes construction overview, monitoring data analysis, quality inspection results, and problem handling; S3.

6. Continuous improvement and optimization. According to the construction quality report, formulate an improvement plan for the next stage of construction and optimize the construction process. The improvement content includes adding monitoring equipment, adjusting construction parameters, strengthening quality inspection, establishing a construction feedback mechanism, and regularly organizing construction team meetings to summarize experience and lessons and put forward improvement suggestions. The meeting frequency is once a week. According to the feedback and improvement plan, continuously optimize the construction process and quality control measures to improve the construction quality and efficiency; S3.

7. Equipment maintenance and care. Develop a detailed equipment maintenance and care plan to ensure the normal operation of monitoring equipment and construction equipment. The maintenance frequency is once a month. Maintain and care the monitoring equipment and construction equipment as planned, record the maintenance results, and use the equipment maintenance log as the recording tool. Handle equipment failures in a timely manner to ensure that they do not affect the construction progress and quality. The handling time is completed within 24 hours; S3.

8. Construction summary and evaluation. After the construction is completed, a comprehensive construction summary shall be conducted to record the experiences and lessons learned during the construction process. The summary content shall include construction progress, quality, problem handling, and improvement suggestions. Performance evaluation shall be conducted on the construction team, outstanding teams and individuals shall be commended, and the construction team shall be motivated. The evaluation criteria shall be construction quality, efficiency, and safety. A detailed construction summary report shall be written to record various data and results of the entire construction process. The report format shall be PDF or paper version. Construction technology exchange meetings shall be organized to share experiences and technologies with other construction projects to improve the overall construction level.

5. A long-distance saturated clay pipe jacking construction process according to claim 4, characterized in that: The implementation steps of setting the construction parameters in step S4 are as follows: S4.

1. Preliminary parameter setting: GPR and CPTu were used to conduct on-site soil surveys to obtain soil type, water content and other relevant data. The GPR parameters were 100 MHz frequency and 15 m detection depth. The CPTu parameters were 2 cm / s penetration rate and 20 m penetration depth. GeoStudio software was used to analyze the survey data and determine the physical properties and mechanical parameters of saturated clay. The soil water content was 45%, the cohesion was 20 kPa, and the internal friction angle was 15°. S4.

2. Force control: Use ANSYS software to simulate the strength of the pipe and determine the maximum force allowed by the pipe design. The pipe diameter is 1500mm and the design allowable force is 4500kN. Use the SCADA system to set the force control parameters to ensure that the force is within the design allowable range. The initial force is 4000kN and the force fluctuation range is 3900-4100kN. S4.

3. Jacking speed control: Use Excel to calculate the jacking speed according to the soil conditions and pipe diameter to avoid soil disturbance caused by too fast speed. The target speed is 3 meters per hour. Set the jacking speed parameters in the SCADA system to ensure a smooth jacking process. The speed range is 2-4 meters per hour, and the initial speed is 3 meters per hour. S4.

4. Adjust the mud ratio. The mud ratio suitable for saturated clay is determined through laboratory tests to ensure lubrication and support. The test tool is a Brookfield viscometer. The mud ratio is 30% bentonite and 70% water. The viscosity and rheological properties of the mud are tested using a Brookfield viscometer to ensure that they meet the requirements. The viscosity range is 20-25cP, and the rheological properties are plastic flow. The mud is prepared according to the ratio at the construction site and stirred evenly using a mud mixer for 30 minutes. S4.

5. Data recording and monitoring. Develop a data recording plan. Record data every 1-2 meters of jacking to ensure the stability and controllability of the jacking process. The recording frequency is once every 1.5 meters of jacking. Use the SCADA system for automatic data recording and use Excel to organize and analyze the data. The recorded content includes jacking force, speed, inclination, mud pressure, and the data format is CSV file; S4.

6. Real-time monitoring of the construction process. Use the SCADA system to monitor various parameters in the construction process in real time to ensure the stability of the construction process. The monitoring parameters are jacking force, speed, inclination, and mud pressure. The update frequency is once per second. According to the real-time monitoring data, the jacking force, speed and mud ratio are adjusted in time to ensure the stability of the construction process. The adjustment frequency is real-time; S4.

7. Quality control and inspection: a quality inspection is carried out every 10 meters to ensure the installation quality of each section of the pipeline. The inspection tools are laser centering instruments and sealing testers. The inspection items are pipeline connection quality, sealing, and centering. Excel is used to record the inspection results and quality reports are generated regularly to ensure that the construction quality is controllable. The reporting frequency is once a day and the report format is PDF file; S4.

8. Problem handling and improvement: timely identify problems existing in construction through monitoring data and quality inspection results, and record them in the SCADA system. The record content includes problem type, occurrence time, and treatment measures. According to the type of problem, formulate corresponding treatment measures and handle them in time. The processing time is completed within 2 hours. According to the problems found in construction, formulate improvement measures, optimize construction technology and quality control measures. The improvement content includes adjusting mud ratio, optimizing top force control, and strengthening speed management; S4.

9. Data analysis and summary. Use Matlab to analyze the data recorded during the construction process and evaluate the rationality of the construction parameters. The analysis content includes the fluctuation of top force, speed change, and mud pressure change. After the construction is completed, write a detailed summary report to record the data and results of the construction process. The report content includes construction overview, parameter setting, data analysis, quality inspection results, and problem handling. The report format is Word or LaTeX. Organize construction technology exchange meetings to share experiences and technologies with other construction projects to improve the overall construction level.

6. A long-distance saturated clay pipe jacking construction process according to claim 5, characterized in that: The construction process of step S5 includes the following steps: S5.

1. Determine the location of the guide hole and establish the working well and receiving well. Review the design drawings with AutoCAD software to determine the precise location of the guide hole. The location of the guide hole is marked according to the design drawings with an error of no more than 5 cm. Use a total station for on-site positioning and calibrate the location of the working well and receiving well. The location accuracy is no more than 3 cm. The measurement frequency is one measurement every 10 meters. The well location is constructed according to the measurement results. Steel sheet pile support is used to ensure construction safety. The working well size is 6m×6m×8m (length×width×depth), and the receiving well size is 6m×6m×8m (length×width×depth); S5.

2. Guided drilling equipment is used for drilling. Ditch Witch JT100 guided drilling equipment is used for equipment preparation and commissioning. The commissioning time is 2 hours. The drill bit diameter is 150mm. The drilling accuracy is monitored in real time by DigiTrak Falcon F5 guidance system. The monitoring frequency is one measurement every 0.5 meters. The accuracy requirement is that the vertical error does not exceed 1° and the horizontal error does not exceed 1.5°. S5.

3. Install and debug the pipe jacking machine. Install the Herrenknecht AVN1500 pipe jacking machine in the working pit and connect the relevant pipelines. The installation time is 8 hours. The equipment weight is 25 tons. Debug the pipe jacking machine through the SCADA system to ensure the normal operation of the equipment. The debugging content includes the jacking force, speed, and mud pressure. The debugging time is 4 hours; S5.

4. Mud circulation system connection: connect the mud circulation system according to the on-site pipeline layout to ensure the normal transportation and recovery of mud. The pipeline diameter is 100mm, the mud pump model is Graco 3900, and the Brookfield DV2T viscometer is used to test the mud viscosity to ensure that it meets the requirements. The viscosity requirement is 20-25cP, and the pumping pressure is 4MPa; S5.

5. Real-time monitoring of the jacking process. The control parameters of jacking speed, jacking force and direction are set through the SCADA system. The target speed is 3 m / h, the jacking force control range is 3900-4100 kN, and the direction deviation is no more than 1.5°. The SCADA system is used to monitor various parameters in the jacking process in real time to ensure that the jacking pipe moves along the designed route. The monitoring frequency is once per second, and data is recorded once every 1.5 m of jacking. S5.

6. Adjust the mud ratio and pressure. According to the real-time monitoring data, adjust the mud ratio through laboratory tests to ensure its lubrication and support functions. The mud ratio is 30% bentonite and 70% water. The test tool is Brookfield viscometer. The mud pressure is adjusted through the SCADA system to ensure the stable operation of the pipe jacking machine. The target pressure is 4MPa and the adjustment frequency is once an hour. S5.

7. Receiving well construction: Use a total station to measure the receiving well depth and position to ensure accuracy, with a depth error of no more than 5 cm and a position error of no more than 3 cm. Use steel sheet pile support to construct the receiving well to ensure safe and smooth receiving of the jacking pipe. The construction time is 5 days, and the construction equipment is a hydraulic excavator; S5.

8. Pipe joint splicing and sealing: Use a hydraulic pipe jacking machine to splice the pipe joints into place to ensure a tight connection with a splicing error of no more than 1cm. Use EPDM waterproof material to seal the pipe joints and use steel plates for reinforcement to ensure the sealing and strength of the interface. The thickness of the sealing material is 5mm and the thickness of the reinforcement steel plate is 10mm. Use a pressure tester to check the sealing of the pipe joints to ensure there is no water leakage. The test pressure is 2MPa and the test time is 2 hours.

7. A long distance saturated clay pipe jacking construction process according to claim 6, characterized in that: The implementation steps of the post-processing of step S6 are as follows: S6.

1. Remove the pipe jacking equipment, stop the operation of the pipe jacking machine through the SCADA system, ensure that all power supplies are cut off, and conduct equipment safety inspections. The downtime is 2 hours. The power off inspection is to confirm the power off through the Fluke 117 electrical multimeter. Use a hydraulic crane to dismantle the pipe jacking machine in the order of component disassembly. The dismantling time is 8 hours, and the lifting capacity is 100 tons. The order of components is cutting head, mud pump system, and drive unit. The disassembled pipe jacking machine components are transported to the designated storage location by flatbed trucks for cleaning and maintenance. The component transportation time is 4 hours, and the cleaning tool is a high-pressure cleaner; S6.

2. Cleaning of the construction site: use an excavator to clean up the earth and waste at the construction site and transport it to the designated waste disposal site. The cleaning time is 12 hours. The waste is transported by a 10-ton dump truck for 5 times. Use a sludge suction truck to clean up the residual mud at the construction site to ensure that the ground is clean. The suction time is 6 hours and the cleaning volume is 10 cubic meters. Use industrial cleaning equipment to flush the ground to ensure that there is no residual mud and pollutants. The cleaning area is 1,000 square meters and the cleaning time is 4 hours; S6.

3. Restoration of the construction area. Use a small loader to level the ground in the construction area to restore the original appearance of the ground. The leveling area is 1,000 square meters and the leveling time is 8 hours. Use a seeder to sow grass seeds and restore vegetation in the construction area to ensure greening. The sowing area is 500 square meters. The grass type is tall fescue and the sowing time is 2 hours. Use a portable environmental monitor to monitor the environment in the construction area to ensure that there is no pollution. The monitoring items are air quality and soil pollution. The monitoring time is 1 hour and the monitoring frequency is once a week for 4 consecutive weeks.

8. A long-distance saturated clay pipe jacking construction process according to claim 7, characterized in that: The implementation steps of step S7 are: S7.

1. Safety training plan development. The training content and schedule are developed by using Microsoft Project, covering all safety regulations from S2 to S6. The training time is 1 hour before each construction step. The training content is operational safety, equipment use, and emergency plans. PowerPoint is used to create training presentations that describe in detail the safety measures and emergency response for each step. The content is text, pictures, and videos. An experienced safety engineer is designated as the person in charge of training. The training notice is issued through the company's internal OA system. There are 3 people in charge of training. The notice time is 2 days before each construction step. S7.

2. Safety training implementation: book the construction site conference room as the training venue through the enterprise management system to ensure the safety of the venue and the facilities are complete. The person in charge of the training will use the prepared PowerPoint presentation to explain in detail the safety measures and emergency plans for each step. The explanation time is 1 hour before each construction step. S7.

3. Safety drills: through on-site demonstrations and practice, train construction workers on the correct use of personal protective equipment. The drill time is 30 minutes before each construction step. The number of equipment is 20 sets. Simulate emergencies and conduct emergency plan drills to ensure that construction workers are familiar with the emergency response process. The drill frequency is 1. Evaluate the drill effect through video recording and on-site observation, and issue an evaluation report after the drill. S7.

4. Training effect evaluation: Use the online testing platform to test the construction personnel on the training content and evaluate their mastery of the training content. The test time is 30 minutes after each training session. The test questions are 20. The test results are analyzed through Excel to identify the weak links in the training and formulate improvement measures. The analysis time is 1 hour after each test. The analysis report collects the feedback of the construction personnel on the training through the system, conducts satisfaction surveys and collects improvement suggestions. The feedback time is 1 hour after each training session. S7.

5. Archive training records. Use the enterprise management system to electronically archive all training records, test results and feedback forms to ensure that the information is complete and traceable. The archiving time is 1 hour after each training session. The archived information includes training plans, sign-in sheets, drill records, evaluation reports, test results, and feedback forms.

9. A long-distance saturated clay pipe jacking construction process according to claim 8, characterized in that: The simulation parameters in step S2.3 are mud viscosity 0.1 Pa·s and flow rate 2 m / s; the system pressure loss is ensured to be less than 0.2 MPa, and the construction drawings of the mud circulation system are generated by using Revit to ensure the accuracy of the position and connection of each component.

10. A long distance saturated clay pipe jacking construction process according to claim 9, characterized in that: The functional requirement of the automatic control system in step S2.5 is to monitor the top force, top distance and mud flow in real time. The system parameters are sampling frequency 1Hz and data transmission rate 10Mbps. The control system design software Simulink is used for design and selection. The appropriate PLC and sensor equipment are selected, model Siemens S7-1500. The automatic control system is tested in a laboratory environment to ensure the reliability and accuracy of the system. The test parameters are top force error less than 1% and mud flow error less than 2%.

Citation Information

Cited By

  • Intelligent management system and optimization method for water conservancy and hydropower construction process

    CN121860578A

  • Methods for real-time deviation monitoring of miniature pipe roofing jacking pipe of spiral soil-discharging

    US12392609B2

  • Methods for real-time deviation monitoring of miniature pipe roofing jacking pipe of spiral soil-discharging

    US20250231026A1