Device and method for sinking water steel pipeline

Through the automatic installation and unbinding mechanism of the magnetic levitation box unit and electromagnetic suction cup, the safety hazards and low efficiency of the divers' hydrotight floating box are solved, and the automatic sinking and release of the pipe section and safe and reliable underwater transportation are achieved.

CN119062829APending Publication Date: 2024-12-03SDC WATERWAY CONSTR
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411072521.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-06
Publication Date
2024-12-03

AI Technical Summary

Technical Problem

The existing water steel pipeline sinking technology requires divers to untied the floating box in water, which poses safety hazards and is inefficient, so it is impossible to untied the floating box on the water surface after being transported to the destination.

Method used

Multiple magnetic levitation box units are adopted to automatically install and unbind the floating box through electromagnetic suction cups. The magnetic adsorption and disengagement mechanism of arc-shaped levitation box and electromagnetic suction cup are used to automatically sink and float the pipe section to avoid divers’ draining operations.

Benefits of technology

It improves operating efficiency, ensures the safety of staff, can adjust buoyancy according to the length and weight of the pipe section, meets the floating requirements of different pipe sections, and facilitates consignment through unified wire connections.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119062829A_ABST
    Figure CN119062829A_ABST
Patent Text Reader

Abstract

The invention relates to a device and method for sinking a water steel pipeline, and the device mainly comprises a plurality of magnetic attraction type floating box units which are arranged on a pipe section at intervals and are fixed with or separated from the pipe section in a magnetic attraction manner; each magnetic type buoyancy tank unit comprises multiple layers of arc-shaped buoyancy tanks which are sequentially attached from inside to outside, an electromagnetic chuck is fixed to the inner wall of each layer of arc-shaped buoyancy tank, the pipe sections and the arc-shaped buoyancy tanks are magnetically attracted or fixed through the electromagnetic chucks, and the arc-shaped buoyancy tanks are magnetically attracted or fixed through the electromagnetic chucks. According to the device and method for sinking the water steel pipeline, water sinking of the pipe section can be automatically completed, and safety and reliability are achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of water supply and drainage pipeline immersed pipe construction, in particular to a device and method for sinking steel pipes above water. Background Art

[0002] With the development of coastal cities, the demand for natural resources such as gas, oil, and tap water is increasing day by day. These important natural resources are often transported through cross-sea pipelines. Commonly used methods for laying submarine pipelines include jacking pipe method, S-shaped pipe laying method, J-shaped pipe laying method, reel-type pipe laying method, pipe towing ship method, and immersed pipe method. Among them, the immersed pipe method has become the main means of laying cross-sea pipelines due to its advantages such as simple pipeline processing, conventional equipment required, high laying efficiency, strong adaptability to underwater terrain, and little impact on water navigation.

[0003] The immersed pipe method is an underwater pipeline laying method in which sealed pipe sections assembled into a certain length are sunk into the water or into trenches excavated underwater. It is also called the buried method or the buried method of prefabricated pipe sections. According to the design requirements, on-site conditions and construction capabilities, immersed pipe construction can be subdivided into the surface floating method, the pipe laying ship method and the bottom towing method. The surface floating method is that the pipeline is manufactured at an onshore processing and manufacturing site and assembled into the required length and number of pipe sections, then launched into the water, floated, and towed in the water by a tugboat to the pipeline laying site. Finally, the pipeline is sunk and laid at the predetermined seabed location or in the submarine pipeline trench.

[0004] If the buoyancy of the pipe section is too small to float on the water, a buoyancy box needs to be tied to the pipe section to increase the buoyancy and ensure that the pipe section floats. After the pipe section floats to the predetermined sea area, water is injected into the pipe section to make it sink to the seabed, and then divers go into the water to untie the buoyancy box. Divers' underwater operations are highly dangerous.

[0005] The existing method cannot achieve untying on the water surface after being transported to the destination. Instead, it has to wait until it sinks to the bottom of the sea to untie it. The reason is that on the water surface, if one end is untied first, this end will suddenly sink and tilt, and the other end will tilt up, and the pipe section will be unbalanced in the water and out of control. The pipe section is 100 meters long and 1.8 meters in diameter. It is heavy and huge. It is very dangerous to lose control in the water and may injure the divers nearby. Therefore, water must be injected to make the pipe section sink slowly. After it is in place, the buoys are untied layer by layer. Summary of the invention

[0006] The technical problem to be solved by the present invention is to provide a device and method for sinking steel pipes on water, which can automatically complete the installation and unbinding of buoys by using electromagnetic suction cups, and can automatically complete the underwater sinking of pipe sections without the need for divers to go into the water for operation, which is safe and reliable.

[0007] In order to solve the above technical problems, the technical solution adopted by the present invention is: A device for sinking a steel pipeline on water, comprising a plurality of magnetic buoyancy units, which are arranged at intervals on a pipe section and are fixed or detached from the pipe section by magnetic adsorption; The magnetic pontoon unit comprises multiple layers of arc-shaped pontoons which are sequentially attached from inside to outside, and an electromagnetic suction cup is fixed to the inner wall of each layer of arc-shaped pontoons. The pipe section and the arc-shaped pontoons, and the arc-shaped pontoons are magnetically adsorbed or fixed by the electromagnetic suction cups.

[0008] The arc-shaped buoyancy box is a fan-shaped annular cavity structure, and the angle between the two outer sides of the fan-shaped annular cavity structure is less than or equal to 180 degrees.

[0009] The electromagnetic suction cups on the same layer are connected by electric wires and are powered on and off at the same time.

[0010] A method for sinking a steel pipeline on water, comprising the following steps: Step 1: According to the needs of the project, the standard pipeline is processed into pipe sections on shore, and both ends of the pipe sections are sealed with flange blind plates; Step 2: According to the weight, length and buoyancy of the pipe section, the number of groups and spacing of magnetic buoyancy units and the number of layers of each group of magnetic buoyancy units are calculated to ensure that the pipe section can float on the water during floating transportation; Step 3, placing multiple groups of magnetic buoyancy tank units on the pipe section at intervals according to design requirements; Step 4: After the electromagnetic chuck on the first layer is powered on, the arc-shaped buoyancy box on the first layer is adsorbed and installed on the upper surface of the pipe section; Step 5: After the electromagnetic chuck of the second layer is powered on, the arc pontoon of the second layer is adsorbed and installed on the upper surface of the arc pontoon of the first layer; Step 6: After the electromagnetic chuck of the third layer is powered on, the arc-shaped pontoon of the third layer is adsorbed and installed on the upper surface of the arc-shaped pontoon of the second layer; Step 7: Continue to adsorb and fix the arc buoys of other layers according to the operations of steps 4 to 6; Step 8: Lift the pipe section and the connected magnetic buoy unit from the shore into the water, and then tow it in the water to the sea area where the pipeline is laid by a tugboat; Step 9, remove the blind plate of the pipe section, and let water into the pipe section; Step 10, after the pipe section is completely filled with water, determine the movement state of the pipe section: 1), if the pipe section sinks, wait until it sinks to the bottom of the sea, disconnect the power supply of the electromagnetic suction cup of the first layer, make all the magnetic buoyancy unit detach from the pipe section and float to the water surface, and complete the sinking and untying of the pipe section; 2), if the pipe section does not sink after being completely filled with water, first disconnect the power supply of the outermost electromagnetic suction cup, make the outermost multiple arc-shaped buoyancy boxes detach from the pipe section and float; then determine the movement state of the pipe section: if the pipe section sinks, wait until it sinks to the bottom of the sea, disconnect the power supply of the electromagnetic suction cup of the first layer, make all the magnetic buoyancy unit detach from the pipe section and float to the water surface, and complete the sinking and untying of the pipe section; if disconnect After the outermost electromagnetic suction cup, if the pipe section has not sunk, continue to disconnect the electromagnetic suction cup of the second outermost layer, so that the arc-shaped buoy of the second outermost layer is separated from the pipe section and floats up; judge the movement state of the pipe section, if the pipe section sinks, wait until it sinks to the seabed, disconnect the power supply of the electromagnetic suction cup of the first layer, so that all the magnetic suction buoy units are separated from the pipe section and float to the water surface, and the sinking and unbinding of the pipe section is completed; if the pipe section has not sunk, repeat the above operation, disconnect the power supply of the electromagnetic suction cups of other layers in turn, and then operate after judgment until the pipe section sinks, and finally disconnect the power supply of the electromagnetic suction cup of the first layer, so that all the magnetic suction buoy units are separated from the pipe section and float to the water surface, and the sinking and unbinding of the pipe section is completed; Step 11: When multiple magnetic pontoon units float to the water surface, they are connected in series with wires and then recovered by a tugboat.

[0011] The present invention provides a device and method for sinking a steel pipeline on water, which has the following technical effects: 1) By adopting the magnetic buoy unit, the arc-shaped buoy is fixed on the pipe section by using the electromagnetic suction cup. After the pipe section sinks, the electromagnetic suction cup is powered off, and the arc-shaped buoy can automatically float to the surface of the water. There is no need for people to dive to the seabed to untie the buoy, which not only improves the working efficiency but also ensures the safety of the staff.

[0012] 2) By adopting a multi-layer arrangement of magnetic buoyancy units, different layers of magnetic buoyancy units can be installed according to the length and weight of the pipe section, so that the buoyancy can be adjusted to accurately meet the floating requirements of different pipe sections.

[0013] 3) By using electromagnetic suction cups, the electromagnetic suction cups of the same layer of multiple magnetic buoyancy units are connected by wires, which not only ensures electrical connectivity, but also allows the multiple magnetic buoyancy units to form a whole, making it convenient to ship them uniformly by tugboat in the later stage. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] The present invention will be further described below in conjunction with the accompanying drawings and embodiments: Figure 1 It is a schematic diagram of the present invention.

[0015] Figure 2 It is a schematic diagram of the magnetic floating box unit in the present invention.

[0016] In the figure: pipe section 1, arc-shaped buoyancy box 2, electromagnetic suction cup 3, electric wire 4, connector 5. DETAILED DESCRIPTION

[0017] In this embodiment, the pipe section 1 is formed by welding a plurality of sections of a standard steel pipe having a length of 12 m, and has a diameter of generally 1 to 3 m and a circular cross section.

[0018] like Figure 1 As shown, a device for sinking steel pipelines on water includes a plurality of magnetic buoyancy units, which are arranged at intervals on a pipe section 1 and are fixed or detached from the pipe section 1 by magnetic attraction.

[0019] Each magnetic pontoon unit includes a plurality of groups of arc-shaped pontoons 2 which are sequentially attached from the inside to the outside. The cross section of each group of arc-shaped pontoons 2 is semi-circular, and the interior of the arc-shaped pontoons 2 is a cavity structure, which can generate buoyancy. An electromagnetic suction cup 3 is fixed on the inner wall of each group of arc-shaped pontoons 2. The electromagnetic suction cup 3 (indicated by a) of the first layer can be attached to the outer wall of the pipe section 1, and the electromagnetic suction cup 3 (indicated by b) of the second layer can be attached to the outer wall of the arc-shaped pontoon 2 (indicated by a') of the first layer; the electromagnetic suction cup 3 (indicated by c) of the third layer can be attached to the outer wall of the arc-shaped pontoon 2 (indicated by b') of the second layer. In this way, when the electromagnetic suction cup 3 of the first layer is energized, a strong suction force can be generated to firmly hold the pipe section 1. Similarly, when the electromagnetic suction cup 3 of the second layer is energized, the arc-shaped pontoon 2 of the second layer is adsorbed on the arc-shaped pontoon 2 of the first layer; when the electromagnetic suction cup 3 of the third layer is energized, the arc-shaped pontoon 2 of the third layer is adsorbed on the arc-shaped pontoon 2 of the second layer. Thereby, the magnetic buoyancy unit is adsorbed and fixed on the pipe section 1.

[0020] The number of layers of the arc pontoon 2 is selected and determined according to the weight of the pipe section 1, the spacing of the arc pontoon 2 and other conditions. When the power is turned off, the magnetic force disappears and is no longer adsorbed on the pipe section 1. Under the action of buoyancy, it can float to the surface of the water.

[0021] Here, the electromagnetic suction cups 3 of the same layer of multiple magnetic buoyancy units are connected by wires 4, which are finally connected to the power supply and opened and closed by corresponding control buttons. The power supply, control buttons, etc. are all arranged on the control box of the tugboat.

[0022] The electric wire 4 includes a part located inside the arc-shaped buoyancy box 2 and a part located outside the arc-shaped buoyancy box 2. The electric wire 4 between the inner and outer parts is sealed and connected by a joint. Specifically, the joint can adopt a structure similar to a male head and a female head.

[0023] For example, the portion of the wire 4 inside the arc-shaped pontoon 2 is connected in series with the electromagnetic suction cup 3 inside the arc-shaped pontoon 2 . The outer ends of the wire 4 at both ends of the electromagnetic suction cup 3 are respectively provided with a male head and a female head, which are installed on the left and right end surfaces of the arc-shaped pontoon 2 .

[0024] A male head and a female head are respectively provided at both ends of the part of the electric wire 4 outside the arc-shaped pontoon 2. The male head of the electric wire 4 outside the arc-shaped pontoon 2 can be directly fixed or disassembled with the female head on the arc-shaped pontoon 2 through a nut and a waterproof gasket; the female head of the electric wire 4 outside the arc-shaped pontoon 2 can also be directly sealed and connected with the male head on the arc-shaped pontoon 2.

[0025] In this way, multiple electromagnetic chucks 3 on the same layer are connected in series, the male connector on the arc-shaped buoy 2 at the head end is connected to the positive pole of the power supply, and the female connector on the arc-shaped buoy 2 at the tail end is connected to the negative pole of the power supply. Thus, multiple electromagnetic chucks 3 on the same layer form a complete series circuit, which can be powered on or off at the same time.

[0026] A method for sinking a steel pipeline on water, comprising the following steps: Step 1: According to the needs of the project, the standard pipeline is processed onshore into pipe section 1 (generally 100 meters long), and both ends of the pipe section 1 are sealed with flange blind plates.

[0027] Step 2: According to the weight, length, buoyancy and other conditions of the pipe section 1, calculate and determine the number of groups, spacing and number of layers of each group of magnetic buoyancy units to ensure that the pipe section 1 can float on the water during floating transportation.

[0028] Step 3, placing multiple groups of magnetic buoyancy chamber units on pipe section 1 at intervals according to design requirements; Step 4: After the electromagnetic suction cup 3 of the first layer is powered on, the arc-shaped buoyancy box 2 of the first layer can be adsorbed and installed on the upper surface of the pipe section 1.

[0029] Step 5: After the electromagnetic suction cup 3 of the second layer is powered on, the arc pontoon 2 of the second layer is adsorbed and installed on the upper surface of the arc pontoon 2 of the first layer.

[0030] Step 6: After the electromagnetic suction cup 3 of the third layer is powered on, the arc-shaped pontoon 2 of the third layer is adsorbed and installed on the upper surface of the arc-shaped pontoon 2 of the second layer.

[0031] Step 7: Follow the operations of steps 4 to 6 to complete the adsorption and fixation of the arc-shaped buoyancy boxes 2 of other layers.

[0032] Step 8: lift the pipe section 1 and the connected magnetic buoy unit from the shore into the water, and then tow them in the water by a tugboat to the top of the sea area where the pipeline is laid.

[0033] Step 9: Remove the blind plate of pipe section 1 and allow water to flow into pipe section 1.

[0034] Step 10, after the pipe section 1 is completely filled with water, the movement state of the pipe section is determined: 1), if the pipe section 1 sinks, wait until it sinks to the bottom of the sea, disconnect the power supply of the electromagnetic suction cup 3 of the first layer, so that the entire magnetic buoyancy unit is separated from the pipe section 1 and floats to the water surface, and the sinking and unbinding of the pipe section 1 are completed; 2), if the pipe section 1 does not sink after being completely filled with water, first disconnect the power supply of the outermost electromagnetic suction cup 3, so that the outermost arc-shaped buoyancy box 2 is separated from the pipe section 1 and floats; then determine the movement state of the pipe section 1: if the pipe section 1 sinks, wait until it sinks to the bottom of the sea, disconnect the power supply of the electromagnetic suction cup 3 of the first layer, so that the magnetic buoyancy unit is separated from the pipe section 1 and floats to the water surface, and the sinking and unbinding of the pipe section 1 are completed; If the pipe section 1 has not sunk after the outermost electromagnetic suction cup 3 is disconnected, continue to disconnect the electromagnetic suction cup 3 of the second outer layer, so that the arc-shaped buoy 2 of the second outer layer detaches from the pipe section 1 and floats up; judge the movement state of the pipe section, if the pipe section sinks, wait until it sinks to the bottom of the sea, disconnect the power supply of the first layer of electromagnetic suction cups, so that the entire buoyancy box group detaches from the pipe section and floats to the water surface, completing the sinking and unbinding of the pipe section; if the pipe section 1 has not sunk yet, repeat the above operation, disconnect the power supply of the electromagnetic suction cups of other layers in turn, and then operate after judgment until the pipe section 1 sinks, and finally disconnect the power supply of the electromagnetic suction cup 3 of the first layer, so that the magnetic suction buoy unit detaches from the pipe section 1 and floats to the water surface, completing the sinking and unbinding of the pipe section 1.

[0035] Step 11: When multiple magnetic pontoon units float to the water surface, they are connected in series with wires and then recovered by a tugboat.

Claims

1. A device for sinking steel pipes on water, characterized in that: It comprises a plurality of magnetic buoyancy units, which are arranged at intervals on the pipe section (1) and are fixed to or detached from the pipe section (1) by magnetic attraction; The magnetic buoyancy unit comprises multiple layers of arc-shaped buoyancy (2) which are sequentially attached from inside to outside, an electromagnetic suction cup (3) being fixed to the inner wall of each layer of the arc-shaped buoyancy (2), and the pipe section (1) and the arc-shaped buoyancy (2) and the arc-shaped buoyancy (2) are magnetically attracted or fixed by the electromagnetic suction cup (3).

2. The device for sinking steel pipes on water according to claim 1, characterized in that: The arc-shaped buoyancy box (2) is a fan-shaped annular cavity structure, and the angle between the two outer sides of the fan-shaped annular cavity structure is less than or equal to 180 degrees.

3. The device for sinking steel pipes on water according to claim 1, characterized in that: The electromagnetic suction cups (3) on the same layer are connected via electric wires (4) and are powered on and off at the same time.

4. A method for sinking a steel pipeline on water according to any one of claims 1 to 3, comprising the following steps: Step 1: Based on the needs of the project, a standard pipeline is processed onshore to form a pipe section (1), and both ends of the pipe section (1) are sealed with flange blind plates; Step 2: according to the weight, length and buoyancy of the pipe section (1), the number of groups and spacing of magnetic buoyancy units and the number of layers of each group of magnetic buoyancy units are calculated and determined to ensure that the pipe section (1) can float on the water surface during floating transportation; Step 3, placing multiple groups of magnetic buoyancy chamber units on the pipe section (1) at intervals according to design requirements; Step 4: After the electromagnetic suction cup (3) of the first layer is powered on, the arc-shaped buoyancy box (2) of the first layer is adsorbed and installed on the upper surface of the pipe section (1); Step 5: After the electromagnetic suction cup (3) of the second layer is powered on, the arc-shaped pontoon (2) of the second layer is adsorbed and installed on the upper surface of the arc-shaped pontoon (2) of the first layer; Step 6, after the electromagnetic suction cup (3) of the third layer is powered on, the arc-shaped buoyancy box (2) of the third layer is adsorbed and installed on the upper surface of the arc-shaped buoyancy box (2) of the second layer; Step 7, continue to complete the adsorption and fixation of the arc-shaped buoyancy boxes (2) of other layers according to the operations of steps 4 to 6; Step 8, lifting the pipe section (1) and the connected magnetic buoy unit from the shore into the water, and then towing it in the water by a tugboat to the top of the sea area where the pipeline is laid; Step 9, removing the blind plate of the pipe section (1), and allowing water to flow into the pipe section (1); Step 10, after the pipe section (1) is completely filled with water, the movement state of the pipe section is determined: 1) If the pipe section (1) sinks, after it sinks to the seabed, the power supply of the electromagnetic suction cup (3) of the first layer is disconnected, so that all the magnetic buoyancy units are separated from the pipe section (1) and float to the water surface, and the sinking and unbinding of the pipe section (1) is completed; 2) If the pipe section (1) does not sink after being completely filled with water, the power supply of the outermost electromagnetic suction cup (3) is first disconnected, so that the outermost multiple arc-shaped buoyancy boxes (2) are separated from the pipe section (1) and float up; then the movement state of the pipe section (1) is determined: if the pipe section (1) sinks, after it sinks to the seabed, the power supply of the electromagnetic suction cup (3) of the first layer is disconnected, so that all the magnetic buoyancy units are separated from the pipe section (1) and float to the water surface, and the sinking and unbinding of the pipe section (1) is completed; if the power supply of the electromagnetic suction cup (3) of the first layer is disconnected, so that all the magnetic buoyancy units are separated from the pipe section (1) and float to the water surface, and the sinking and unbinding of the pipe section (1) is completed; After the outermost electromagnetic suction cup (3) is opened, if the pipe section (1) has not yet sunk, the electromagnetic suction cup (3) of the second outermost layer is disconnected, so that the arc-shaped buoy (2) of the second outermost layer is separated from the pipe section (1) and floats up; the movement state of the pipe section is judged, and if the pipe section sinks, after it sinks to the seabed, the power supply of the electromagnetic suction cup of the first layer is disconnected, so that all the magnetic buoy units are separated from the pipe section (1) and float to the water surface, thereby completing the sinking and unbinding of the pipe section (1); if the pipe section (1) has not yet sunk, the above operation is repeated, and the power supplies of the electromagnetic suction cups (3) of other layers are disconnected in turn, and the operation is performed after judgment again until the pipe section (1) sinks, and finally the power supply of the electromagnetic suction cup (3) of the first layer is disconnected, so that all the magnetic buoy units are separated from the pipe section (1) and float to the water surface, thereby completing the sinking and unbinding of the pipe section (1); Step 11: When multiple magnetic pontoon units float to the water surface, they are connected in series with wires and then recovered by a tugboat.