Distributed energy storage and dynamic reconstruction double-layer coordination optimization method and device
Through the dual-layer coordination optimization method of distributed energy storage and dynamic reconstruction, combined with the advantages of distributed energy storage and dynamic reconstruction, the economy of the distribution network and the power supply reliability under fault conditions are optimized, and intermittent and volatility are solved. The issue of renewable energy management has improved the economy and reliability of the distribution network.
Patent Information
- Application Number
- CN202411293293.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-14
- Publication Date
- 2024-12-03
AI Technical Summary
The existing technology is difficult to effectively dispatch and manage intermittent and volatile renewable energy, which has affected the economy and reliability of the distribution network, and lacks research on combining distributed energy storage and distribution network failure reliability.
A two-layer coordination optimization method for distributed energy storage and dynamic reconstruction is proposed. By solving the pre-constructed operation layer model and planning layer model, the site selection location, installation capacity and dynamic reconstruction scheme of distributed energy storage are obtained, combined with distribution The advantages of energy storage and dynamic reconstruction optimize the economics of the distribution network and the power supply reliability in the fault state.
It improves the economics of the distribution network under normal conditions and the power supply reliability of the fault conditions, reduces the total operating costs, and fully utilizes the application potential of distributed energy storage and network reconstruction.
Smart Images

Figure CN119070347A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of power grid planning, and in particular to a distributed energy storage and dynamic reconstruction double-layer coordinated optimization method and device. Background Art
[0002] With the high proportion of new energy sources such as wind and solar, the distribution network faces increasingly complex planning and operation challenges. The rapid expansion of renewable energy installed capacity has led to serious wind and solar abandonment, resulting in a large waste of resources. On the other hand, due to their intermittent and volatile nature, the economy and reliability of the distribution network are seriously affected. In this context, how to effectively dispatch and manage these intermittent energy sources has become a key issue.
[0003] The rapid development of energy storage technology provides an effective means to solve the above problems. Energy storage has become a key technology to promote the consumption of renewable energy because of its ability to separate the production and consumption of electricity in time and space, effectively smooth load fluctuations, improve power quality, and provide emergency power support. Distributed Energy Storage System (DESS) has broad application prospects because it takes into account both controllability and economy, can overcome the lack of flexibility of large-scale centralized energy storage. The flexible deployment and modular design of DESS enable it to better adapt to the dynamic needs of distribution networks and achieve more efficient energy management and scheduling. Although distributed energy storage systems have the potential to solve these problems, existing research mainly focuses on economic optimization scheduling and improving the resilience of distribution networks, and lacks research that combines energy storage economic planning with distribution network fault reliability.
[0004] Dynamic reconstruction can optimize the power transmission path, reduce line losses, and improve the system's operating efficiency and reliability by adjusting the topological structure of the distribution network. It has the advantages of simple operation and low cost, and has become a key technology for active network management of distribution systems. However, the network structure of the distribution network in existing research remains unchanged, and dynamic reconstruction cannot add additional capacity to the power grid like energy storage systems. Therefore, how to coordinate and optimize the advantages of distributed energy storage and network dynamic reconstruction is of great significance to promoting the consumption of renewable energy and ensuring the safe and economical operation of the distribution network system. Summary of the invention
[0005] In order to overcome the above-mentioned defects, the present invention proposes a distributed energy storage and dynamic reconstruction double-layer coordinated optimization method and device.
[0006] In a first aspect, a distributed energy storage and dynamic reconstruction dual-layer coordinated optimization method is provided, and the distributed energy storage and dynamic reconstruction dual-layer coordinated optimization method comprises:
[0007] Solving the pre-built operation layer model to obtain a first optimization result;
[0008] Substituting the function value of the objective function in the pre-constructed operation layer model into the pre-constructed planning layer model to obtain a second optimization result;
[0009] Based on the first optimization result and the second optimization result, a two-layer coordinated optimization scheme of distributed energy storage and dynamic reconstruction is obtained;
[0010] Among them, the first optimization result includes at least one of the following: the site selection location of distributed energy storage and the installed capacity of distributed energy storage, and the second optimization result includes at least one of the following: the active power of distributed energy storage and a dynamic reconstruction scheme composed of the switch status of distribution network nodes.
[0011] Preferably, the pre-constructed operating layer model includes: an operating layer objective function and operating layer constraints, wherein the operating layer objective function includes: a first objective function aimed at minimizing the operating cost of the distribution network under normal conditions and / or a second objective function aimed at minimizing the operating cost of the distribution network under fault conditions.
[0012] Furthermore, the first objective function is as follows:
[0013]
[0014] In the above formula, F 1 is the function value of the first objective function, Y OM is the operation and maintenance cost of distributed energy storage, Y D is the cost of dynamic reconstruction of the distribution network, Y L is the network loss cost, λ OM is the operation and maintenance cost coefficient of distributed energy storage per unit power, M is the total number of typical wind and solar output scenarios, T is the total number of optimized time periods, and F D is the set of installation nodes for distributed energy storage. is the equipment purchase cost of distributed energy storage per unit power, is the active power of distributed energy storage d in the mth typical wind and solar output scenario during period t, c sw is the single cost of distribution network reconstruction, w ij,t is the switch state of the branch between node i and node j during period t, w ij,t-1 is the switch status of the branch between node i and node j in period t-1, D is the number of statistical days, c B For electricity price, is the active power loss of the branch between node i and node j in period t of the mth typical wind and solar power output scenario, p m is the probability of the mth typical wind and solar power output scenario.
[0015] Furthermore, the process of acquiring the typical wind-solar output scene includes: reducing the wind-solar output scene by using a synchronous back-substitution elimination algorithm to obtain the typical wind-solar output scene.
[0016] Furthermore, the synchronous back-generation elimination algorithm is used to reduce the wind and solar power output scenarios to obtain typical wind and solar power output scenarios, including:
[0017] Step a: Initialize the number of scenes in the deleted scene set n=0, and the probability of each scene in the original scene set is 1 / N;
[0018] Step b determines whether the number of scenes in the original scene set is less than or equal to a threshold value. If so, the scenes in the original scene set are used as typical wind and solar output scenes. Otherwise, step c is executed.
[0019] Step c: Selecting the scene with the smallest reduction degree from the original scene set as the deleted scene, and adding it to the deleted scene set;
[0020] Step d: updating the probability of the scenes in the original scene set based on the Kantorovich distance between the scenes in the original scene set and the deleted scenes, updating the probability of each scene in the deleted scene set to 1 / n, and returning to step b;
[0021] Where N is the number of scenes in the original scene set.
[0022] Furthermore, the reduction degree D of the scene s in the original scene set is s as follows:
[0023]
[0024] In the above formula, p s is the probability of scene s in the original scene set, p v is the probability of scene v in the original scene set, and d(s,v) is the Kantorovich distance between scene s and scene v.
[0025] Furthermore, the updating of the probability of scenes in the original scene set based on the Kantorovich distance between the scenes in the original scene set and the deleted scenes includes: obtaining a scene in the original scene set that has a closest Kantorovich distance to the deleted scene, and updating the probability of the scene to be the sum of the original probability of the scene and the probability of the deleted scene in the original scene set.
[0026] Furthermore, the second objective function is as follows:
[0027]
[0028] In the above formula, F2 is the function value of the second objective function, N e is the annual average number of faults in the distribution network, t 0 is the fault start time, T e is the fault duration, Ω N is the set of distribution network nodes, c l is the load importance value coefficient, is the load loss amount at node j at time t.
[0029] Furthermore, the operation layer constraint conditions include at least one of the following: distributed energy storage capacity constraint, distributed energy storage power constraint, distribution network voltage constraint, and distribution network power flow safety operation constraint.
[0030] Furthermore, the pre-constructed planning layer model includes: a third objective function with the goal of minimizing the investment cost of distributed energy storage and planning layer constraints.
[0031] Furthermore, the third objective function is as follows:
[0032]
[0033] In the above formula, F is the function value of the third objective function, Y IC is the construction cost of distributed energy storage, F 1 is the function value of the first objective function, F 2 is the function value of the second objective function, μ is the discount rate, y DES is the economic service life of distributed energy storage, is the equipment cost of distributed energy storage per unit capacity, c CON.D is the construction cost of DESS per unit capacity, is the capacity of distributed energy storage d, is the active power of distributed energy storage d.
[0034] Furthermore, the operation layer constraint conditions include at least one of the following: distributed energy storage capacity constraint, distributed energy storage power constraint, distribution network voltage constraint, and distribution network power flow safety operation constraint.
[0035] In a second aspect, a distributed energy storage and dynamic reconstruction dual-layer coordinated optimization device is provided, wherein the distributed energy storage and dynamic reconstruction dual-layer coordinated optimization device comprises:
[0036] A first analysis module is used to solve a pre-built operation layer model to obtain a first optimization result;
[0037] A second analysis module is used to substitute the function value of the objective function in the pre-constructed operation layer model into the pre-constructed planning layer model to obtain a second optimization result;
[0038] A third analysis module is used to obtain a distributed energy storage and dynamic reconstruction double-layer coordinated optimization solution based on the first optimization result and the second optimization result;
[0039] Among them, the first optimization result includes at least one of the following: the site selection location of distributed energy storage and the installed capacity of distributed energy storage, and the second optimization result includes at least one of the following: the active power of distributed energy storage and a dynamic reconstruction scheme composed of the switch status of distribution network nodes.
[0040] Preferably, the pre-constructed operating layer model includes: an operating layer objective function and operating layer constraints, wherein the operating layer objective function includes: a first objective function aimed at minimizing the operating cost of the distribution network under normal conditions and / or a second objective function aimed at minimizing the operating cost of the distribution network under fault conditions.
[0041] Furthermore, the first objective function is as follows:
[0042]
[0043] In the above formula, F 1 is the function value of the first objective function, Y OM is the operation and maintenance cost of distributed energy storage, Y D is the cost of dynamic reconstruction of the distribution network, Y L is the network loss cost, λ OM is the operation and maintenance cost coefficient of distributed energy storage per unit power, M is the total number of typical wind and solar output scenarios, T is the total number of optimized time periods, and F D is the set of installation nodes for distributed energy storage. is the equipment purchase cost of distributed energy storage per unit power, is the active power of distributed energy storage d in the mth typical wind and solar output scenario during period t, c sw is the single cost of distribution network reconstruction, w ij,t is the switch state of the branch between node i and node j during period t, w ij,t-1 is the switch status of the branch between node i and node j in period t-1, D is the number of statistical days, c B For electricity price, is the active power loss of the branch between node i and node j in period t of the mth typical wind and solar power output scenario, p m is the probability of the mth typical wind and solar power output scenario.
[0044] Furthermore, the process of acquiring the typical wind-solar output scene includes: reducing the wind-solar output scene by using a synchronous back-substitution elimination algorithm to obtain the typical wind-solar output scene.
[0045] Furthermore, the synchronous back-generation elimination algorithm is used to reduce the wind and solar power output scenarios to obtain typical wind and solar power output scenarios, including:
[0046] Step a: Initialize the number of scenes in the deleted scene set n=0, and the probability of each scene in the original scene set is 1 / N;
[0047] Step b determines whether the number of scenes in the original scene set is less than or equal to a threshold value. If so, the scenes in the original scene set are used as typical wind and solar output scenes. Otherwise, step c is executed.
[0048] Step c: Selecting the scene with the smallest reduction degree from the original scene set as the deleted scene, and adding it to the deleted scene set;
[0049] Step d: updating the probability of the scenes in the original scene set based on the Kantorovich distance between the scenes in the original scene set and the deleted scenes, updating the probability of each scene in the deleted scene set to 1 / n, and returning to step b;
[0050] Where N is the number of scenes in the original scene set.
[0051] Furthermore, the reduction degree D of the scene s in the original scene set is s as follows:
[0052]
[0053] In the above formula, p s is the probability of scene s in the original scene set, p v is the probability of scene v in the original scene set, and d(s,v) is the Kantorovich distance between scene s and scene v.
[0054] Furthermore, the updating of the probability of scenes in the original scene set based on the Kantorovich distance between the scenes in the original scene set and the deleted scenes includes: obtaining a scene in the original scene set that has a closest Kantorovich distance to the deleted scene, and updating the probability of the scene to be the sum of the original probability of the scene and the probability of the deleted scene in the original scene set.
[0055] Furthermore, the second objective function is as follows:
[0056]
[0057] In the above formula, F 2 is the function value of the second objective function, N e is the annual average number of faults in the distribution network, t 0 is the fault start time, T e is the fault duration, ΩN is the set of distribution network nodes, c l is the load importance value coefficient, is the load loss amount at node j at time t.
[0058] Furthermore, the operation layer constraint conditions include at least one of the following: distributed energy storage capacity constraint, distributed energy storage power constraint, distribution network voltage constraint, and distribution network power flow safety operation constraint.
[0059] Furthermore, the pre-constructed planning layer model includes: a third objective function with the goal of minimizing the investment cost of distributed energy storage and planning layer constraints.
[0060] Furthermore, the third objective function is as follows:
[0061]
[0062] In the above formula, F is the function value of the third objective function, Y IC is the construction cost of distributed energy storage, F 1 is the function value of the first objective function, F 2 is the function value of the second objective function, μ is the discount rate, y DES is the economic service life of distributed energy storage, is the equipment cost of distributed energy storage per unit capacity, c CON.D is the construction cost of DESS per unit capacity, is the capacity of distributed energy storage d, is the active power of distributed energy storage d.
[0063] Furthermore, the operation layer constraint conditions include at least one of the following: distributed energy storage capacity constraint, distributed energy storage power constraint, distribution network voltage constraint, and distribution network power flow safety operation constraint.
[0064] In a third aspect, a computer device is provided, comprising: one or more processors;
[0065] The processor is configured to execute one or more programs;
[0066] When the one or more programs are executed by the one or more processors, the distributed energy storage and dynamic reconstruction two-layer coordinated optimization method is implemented.
[0067] In a fourth aspect, a computer-readable storage medium is provided, on which a computer program is stored. When the computer program is executed, the distributed energy storage and dynamic reconstruction two-layer coordinated optimization method is implemented.
[0068] The above one or more technical solutions of the present invention have at least one or more of the following beneficial effects:
[0069] The present invention provides a method and device for two-layer coordinated optimization of distributed energy storage and dynamic reconstruction, including: solving a pre-constructed operation layer model to obtain a first optimization result; substituting the function value of the objective function in the pre-constructed operation layer model into the pre-constructed planning layer model to obtain a second optimization result; based on the first optimization result and the second optimization result, obtaining a two-layer coordinated optimization scheme of distributed energy storage and dynamic reconstruction; wherein the first optimization result includes at least one of the following: the site selection location of the distributed energy storage, the installed capacity of the distributed energy storage, and the second optimization result includes at least one of the following: the active power of the distributed energy storage, and the dynamic reconstruction scheme composed of the switch status of the distribution network nodes. The technical solution provided by the present invention constructs a two-layer coordinated optimization framework based on distributed energy storage and dynamic reconstruction, combining the advantages of distributed energy storage and dynamic reconstruction to give full play to the application potential of distributed energy storage and network reconstruction; constructs a coordinated optimization model of the planning layer and the operation layer based on the two-layer coordinated optimization framework to improve the economy of the distribution network under normal conditions and the power supply reliability under fault conditions. BRIEF DESCRIPTION OF THE DRAWINGS
[0070] Figure 1 It is a schematic flow chart of the main steps of the distributed energy storage and dynamic reconstruction double-layer coordinated optimization method according to an embodiment of the present invention;
[0071] Figure 2 is a schematic diagram of an IEEE 33-node distribution network calculation example of an embodiment of the present invention;
[0072] Figure 3 It is a schematic diagram of the planning and configuration results of Solution 4 of an embodiment of the present invention. DETAILED DESCRIPTION
[0073] The specific implementation modes of the present invention will be further described in detail below in conjunction with the accompanying drawings.
[0074] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0075] As disclosed in the background technology, with the high proportion of access to new energy sources such as wind and light, the distribution network faces increasingly complex planning and operation challenges. The rapid expansion of renewable energy installed capacity has, on the one hand, led to serious wind and light abandonment, resulting in a large amount of resource waste; on the other hand, due to its intermittent and volatile nature, the economy and reliability of the distribution network are seriously affected. In this context, how to effectively dispatch and manage these intermittent energy sources has become a key issue.
[0076] The rapid development of energy storage technology provides an effective means to solve the above problems. Energy storage has become a key technology to promote the consumption of renewable energy because of its ability to separate the production and consumption of electricity in time and space, effectively smooth load fluctuations, improve power quality, and provide emergency power support. Distributed Energy Storage System (DESS) has broad application prospects because it takes into account both controllability and economy, can overcome the lack of flexibility of large-scale centralized energy storage. The flexible deployment and modular design of DESS enable it to better adapt to the dynamic needs of distribution networks and achieve more efficient energy management and scheduling. Although distributed energy storage systems have the potential to solve these problems, existing research mainly focuses on economic optimization scheduling and improving the resilience of distribution networks, and lacks research that combines energy storage economic planning with distribution network fault reliability.
[0077] Dynamic reconstruction can optimize the power transmission path, reduce line losses, and improve the system's operating efficiency and reliability by adjusting the topological structure of the distribution network. It has the advantages of simple operation and low cost, and has become a key technology for active network management of distribution systems. However, the network structure of the distribution network in existing research remains unchanged, and dynamic reconstruction cannot add additional capacity to the power grid like energy storage systems. Therefore, how to coordinate and optimize the advantages of distributed energy storage and network dynamic reconstruction is of great significance to promoting the consumption of renewable energy and ensuring the safe and economical operation of the distribution network system.
[0078] In order to improve the above problems, the present invention provides a distributed energy storage and dynamic reconstruction double-layer coordinated optimization method and device, including: solving a pre-constructed operation layer model to obtain a first optimization result; substituting the function value of the objective function in the pre-constructed operation layer model into the pre-constructed planning layer model to obtain a second optimization result; based on the first optimization result and the second optimization result, a distributed energy storage and dynamic reconstruction double-layer coordinated optimization scheme is obtained; wherein, the first optimization result includes at least one of the following: the site selection location of the distributed energy storage, the installed capacity of the distributed energy storage, and the second optimization result includes at least one of the following: the active power of the distributed energy storage, and the dynamic reconstruction scheme composed of the switch status of the distribution network nodes. The technical solution provided by the present invention constructs a double-layer coordinated optimization framework based on distributed energy storage and dynamic reconstruction, combining the advantages of distributed energy storage and dynamic reconstruction to give full play to the application potential of distributed energy storage and network reconstruction; based on the double-layer coordinated optimization framework, a coordinated optimization model of the planning layer and the operation layer is constructed to improve the economy of the distribution network under normal conditions and the power supply reliability under fault conditions.
[0079] The above scheme is described in detail below.
[0080] Example 1
[0081] See attached Figure 1 , Figure 1 FIG. 1 is a flow chart showing the main steps of a two-layer coordinated optimization method for distributed energy storage and dynamic reconstruction according to an embodiment of the present invention. Figure 1 As shown, the distributed energy storage and dynamic reconstruction dual-layer coordinated optimization method in the embodiment of the present invention mainly includes the following steps:
[0082] Step S101: solving a pre-built operation layer model to obtain a first optimization result;
[0083] Step S102: Substituting the function value of the objective function in the pre-constructed operation layer model into the pre-constructed planning layer model to obtain a second optimization result;
[0084] Step S103: Based on the first optimization result and the second optimization result, a distributed energy storage and dynamic reconstruction double-layer coordinated optimization scheme is obtained;
[0085] Among them, the first optimization result includes at least one of the following: the site selection location of distributed energy storage and the installed capacity of distributed energy storage, and the second optimization result includes at least one of the following: the active power of distributed energy storage and a dynamic reconstruction scheme composed of the switch status of distribution network nodes.
[0086] In this embodiment, the pre-constructed operation layer model includes: an operation layer objective function and an operation layer constraint condition, wherein the operation layer objective function includes: a first objective function aiming at minimizing the operation cost of the distribution network under normal conditions and / or a second objective function aiming at minimizing the operation cost of the distribution network under fault conditions.
[0087] In one embodiment, the first objective function is as follows:
[0088]
[0089] In the above formula, F 1 is the function value of the first objective function, Y OM is the operation and maintenance cost of distributed energy storage, Y D is the cost of dynamic reconstruction of the distribution network, Y L is the network loss cost, λ OM is the operation and maintenance cost coefficient of distributed energy storage per unit power, M is the total number of typical wind and solar output scenarios, T is the total number of optimized time periods, and F D is the set of installation nodes for distributed energy storage. is the equipment purchase cost of distributed energy storage per unit power, is the active power of distributed energy storage d in the mth typical wind and solar output scenario during period t, c sw is the single cost of distribution network reconstruction, w ij,t is the switch state of the branch between node i and node j during period t, w ij,t-1 is the switch status of the branch between node i and node j in period t-1, D is the number of statistical days, c B For electricity price, is the active power loss of the branch between node i and node j in period t of the mth typical wind and solar power output scenario, p m is the probability of the mth typical wind and solar power output scenario.
[0090] In one embodiment, the process of acquiring the typical wind-solar output scene includes: reducing the wind-solar output scene by using a synchronous back-substitution elimination algorithm to obtain the typical wind-solar output scene.
[0091] In one embodiment, the synchronous back-generation elimination algorithm is used to reduce the wind and solar power output scenarios to obtain typical wind and solar power output scenarios, including:
[0092] Step a: Initialize the number of scenes in the deleted scene set n=0, and the probability of each scene in the original scene set is 1 / N;
[0093] Step b determines whether the number of scenes in the original scene set is less than or equal to a threshold value. If so, the scenes in the original scene set are used as typical wind and solar output scenes. Otherwise, step c is executed.
[0094] Step c: Selecting the scene with the smallest reduction degree from the original scene set as the deleted scene, and adding it to the deleted scene set;
[0095] Step d: updating the probability of the scenes in the original scene set based on the Kantorovich distance between the scenes in the original scene set and the deleted scenes, updating the probability of each scene in the deleted scene set to 1 / n, and returning to step b;
[0096] Where N is the number of scenes in the original scene set.
[0097] In one embodiment, the reduction degree D of the scene s in the original scene set is s as follows:
[0098]
[0099] In the above formula, p s is the probability of scene s in the original scene set, p v is the probability of scene v in the original scene set, and d(s,v) is the Kantorovich distance between scene s and scene v.
[0100] In one embodiment, updating the probability of scenes in the original scene set based on the Kantorovich distance between the scenes in the original scene set and the deleted scenes includes: obtaining a scene in the original scene set that has a closest Kantorovich distance to the deleted scene, and updating the probability of the scene to be the sum of the original probability of the scene and the probability of the deleted scene in the original scene set.
[0101] In one embodiment, the second objective function is as follows:
[0102]
[0103] In the above formula, F 2 is the function value of the second objective function, N e is the annual average number of faults in the distribution network, t 0 is the fault start time, T e is the fault duration, Ω N is the set of distribution network nodes, c l is the load importance value coefficient, is the load loss amount at node j at time t.
[0104] In one embodiment, the operation layer constraint condition includes at least one of the following: distributed energy storage capacity constraint, distributed energy storage power constraint, distribution network voltage constraint, and distribution network power flow safety operation constraint.
[0105] In one embodiment, the pre-constructed planning layer model includes: a third objective function with the goal of minimizing the investment cost of distributed energy storage and planning layer constraints.
[0106] In one embodiment, the third objective function is as follows:
[0107]
[0108] In the above formula, F is the function value of the third objective function, Y IC is the construction cost of distributed energy storage, F 1 is the function value of the first objective function, F 2 is the function value of the second objective function, μ is the discount rate, y DES is the economic service life of distributed energy storage, is the equipment cost of distributed energy storage per unit capacity, c CON.D is the construction cost of DESS per unit capacity, is the capacity of distributed energy storage d, is the active power of distributed energy storage d.
[0109] In one embodiment, the operation layer constraint condition includes at least one of the following: distributed energy storage capacity constraint, distributed energy storage power constraint, distribution network voltage constraint, and distribution network power flow safety operation constraint.
[0110] In a specific implementation, the present invention adopts the Skyhawk optimization algorithm to solve the pre-built operation layer model and the pre-built planning layer model, which specifically includes:
[0111] a. High-altitude search: In this strategy, the eagle flies high in the sky to determine the search space and find the best hunting area. The position of the eagle in the next iteration is calculated by a formula that takes into account the location of the prey, the average position of the eagle population, the random number, and the population size.
[0112] b. Flying around the prey: After determining the range of the prey, the Eagle hovers above it and prepares to land and attack. The mathematical formula involves the current population position, dimension, random number, and flight function randomly selected by the Eagle. The flight function depends on the constant s, random numbers u and v, constant 1.5, and the search space coefficient and constant 0.005.
[0113] c. Low-altitude flight attack: The Skyhawk descends vertically to make a preliminary attack to detect the prey's response. The expression includes the adaptation parameter and the upper and lower bounds of the population.
[0114] d. Ground close-range attack: The eagle follows the prey's movement on the ground and catches it randomly. The mathematical expression involves the mass function of the balanced search strategy, the prey's movement parameters, the flight slope (linearly decreasing from 2 to 0), and multiple random numbers.
[0115] In a specific implementation, the present invention demonstrates the effect of the invention through example analysis, and selects IEEE 33-node distribution network for simulation, such as Figure 2 As shown in the figure, S represents a switch. The example is equipped with 5 photovoltaic units and 4 wind turbines, and 3 fault lines are set. The fault period of branch 15-16 is 14:00-17:00, the fault period of branch 7-8 is 15:00-18:00, and the fault period of branch 29-30 is 16:00-19:00. The number of iterations of the Tianying optimization algorithm is set to 150. The following 4 schemes are set:
[0116] Solution 1: No dynamic reconstruction and no DESS configuration.
[0117] Solution 2: No dynamic reconstruction, but DESS is configured. However, DESS only works when the distribution network is in normal condition and exits when a fault occurs.
[0118] Solution 3: Dynamic reconstruction and configuration of DESS, but DESS only works when the distribution network is in normal condition and exits when a fault occurs.
[0119] Solution 4: Dynamically reconfigure and configure DESS, and adopt the coordinated optimization method proposed in the present invention, taking into account both the normal state and the fault state of the distribution network.
[0120] The total cost comparison of the planning results of the four schemes is shown in Table 1. Scheme 1 has the highest total operating cost of the distribution network due to the lack of DESS and network reconstruction, which ultimately affects the total cost of the distribution network. In Scheme 2, DESS is connected at nodes 13, 22, and 28 respectively. These three locations are all locations with large source-load power. This configuration can minimize the load peak-valley difference to the greatest extent, making the distribution network economical in the normal state the best, and reducing the total operating cost by 188,700 yuan; Scheme 3 considers the dynamic reconstruction of the distribution network on the basis of Scheme 2, changes the grid structure of the original distribution network, improves the power flow distribution from the spatial dimension, and reduces the investment cost and total operating cost of DESS. Compared with Scheme 2, its total cost is reduced by 891,400 yuan, a decrease of 27.63%; Compared with Scheme 3, Scheme 4 has an additional total capacity of 1.32MWh and a total power of 0.98MW in DESS configuration. This is because the coordinated optimization method proposed in this paper uses DESS in the normal and fault states of the distribution network. In order to give full play to the fault protection capability of DESS, the rated power and capacity of DESS are increased. Although Scheme 4 increased the investment cost of DESS by RMB 113,100, the total operating cost was reduced. The final total cost was still RMB 659,600 less than that of Scheme 3, a year-on-year decrease of 28.26%, which comprehensively improved the economy and power supply reliability of the distribution network.
[0121] Table 1
[0122]
[0123] Table 2 compares the operating costs of the three schemes. Since Scheme 1 does not configure any supply guarantee resources, when the line fails and there are many faults, all critical loads will be cut off, and the resulting failure cost is much greater than the network loss cost during normal operation, accounting for 80.91% of the total operating cost. Schemes 2-4 are all configured with DESS. It can be seen from the table that configuring DESS has a significant effect on reducing network loss costs. Among them, Scheme 2 only considers the operation of DESS under normal conditions of the distribution network, transfers the source load power from the time dimension, and thus reduces the overall network loss cost of the distribution network, but the failure cost of power failure remains unchanged. In addition, on this basis, Schemes 3 and 4 dynamically reconstruct the distribution network, flexibly transfer the power flow from the spatial dimension, and further reduce the network loss cost, indicating that the combination of DESS and network dynamic reconstruction has better economy. The planning configuration results of Scheme 4 are shown in the following figure. Figure 3 shown.
[0124] Table 2
[0125]
[0126] Example 2
[0127] Based on the same inventive concept, the present invention also provides a distributed energy storage and dynamic reconstruction double-layer coordinated optimization device, the distributed energy storage and dynamic reconstruction double-layer coordinated optimization device comprising:
[0128] A first analysis module is used to solve a pre-built operation layer model to obtain a first optimization result;
[0129] A second analysis module is used to substitute the function value of the objective function in the pre-constructed operation layer model into the pre-constructed planning layer model to obtain a second optimization result;
[0130] A third analysis module is used to obtain a distributed energy storage and dynamic reconstruction double-layer coordinated optimization solution based on the first optimization result and the second optimization result;
[0131] Among them, the first optimization result includes at least one of the following: the site selection location of distributed energy storage and the installed capacity of distributed energy storage, and the second optimization result includes at least one of the following: the active power of distributed energy storage and a dynamic reconstruction scheme composed of the switch status of distribution network nodes.
[0132] Preferably, the pre-constructed operating layer model includes: an operating layer objective function and operating layer constraints, wherein the operating layer objective function includes: a first objective function aimed at minimizing the operating cost of the distribution network under normal conditions and / or a second objective function aimed at minimizing the operating cost of the distribution network under fault conditions.
[0133] Furthermore, the first objective function is as follows:
[0134]
[0135] In the above formula, F 1 is the function value of the first objective function, Y OM is the operation and maintenance cost of distributed energy storage, Y D is the cost of dynamic reconstruction of the distribution network, Y L is the network loss cost, λ OM is the operation and maintenance cost coefficient of distributed energy storage per unit power, M is the total number of typical wind and solar output scenarios, T is the total number of optimized time periods, and F D is the set of installation nodes for distributed energy storage. is the equipment purchase cost of distributed energy storage per unit power, is the active power of distributed energy storage d in the mth typical wind and solar output scenario during period t, c sw is the single cost of distribution network reconstruction, w ij,t is the switch state of the branch between node i and node j during period t, w ij,t-1 is the switch status of the branch between node i and node j in period t-1, D is the number of statistical days, cB For electricity price, is the active power loss of the branch between node i and node j in period t of the mth typical wind and solar power output scenario, p m is the probability of the mth typical wind and solar power output scenario.
[0136] Furthermore, the process of acquiring the typical wind-solar output scene includes: reducing the wind-solar output scene by using a synchronous back-substitution elimination algorithm to obtain the typical wind-solar output scene.
[0137] Furthermore, the synchronous back-generation elimination algorithm is used to reduce the wind and solar power output scenarios to obtain typical wind and solar power output scenarios, including:
[0138] Step a: Initialize the number of scenes in the deleted scene set n=0, and the probability of each scene in the original scene set is 1 / N;
[0139] Step b determines whether the number of scenes in the original scene set is less than or equal to a threshold value. If so, the scenes in the original scene set are used as typical wind and solar output scenes. Otherwise, step c is executed.
[0140] Step c: Selecting the scene with the smallest reduction degree from the original scene set as the deleted scene, and adding it to the deleted scene set;
[0141] Step d: updating the probability of the scenes in the original scene set based on the Kantorovich distance between the scenes in the original scene set and the deleted scenes, updating the probability of each scene in the deleted scene set to 1 / n, and returning to step b;
[0142] Where N is the number of scenes in the original scene set.
[0143] Furthermore, the reduction degree D of the scene s in the original scene set is s as follows:
[0144]
[0145] In the above formula, p s is the probability of scene s in the original scene set, p v is the probability of scene v in the original scene set, and d(s,v) is the Kantorovich distance between scene s and scene v.
[0146] Furthermore, the updating of the probability of scenes in the original scene set based on the Kantorovich distance between the scenes in the original scene set and the deleted scenes includes: obtaining a scene in the original scene set that has a closest Kantorovich distance to the deleted scene, and updating the probability of the scene to be the sum of the original probability of the scene and the probability of the deleted scene in the original scene set.
[0147] Furthermore, the second objective function is as follows:
[0148]
[0149] In the above formula, F 2 is the function value of the second objective function, N e is the annual average number of faults in the distribution network, t 0 is the fault start time, T e is the fault duration, Ω N is the set of distribution network nodes, c l is the load importance value coefficient, is the load loss amount at node j at time t.
[0150] Furthermore, the operation layer constraint conditions include at least one of the following: distributed energy storage capacity constraint, distributed energy storage power constraint, distribution network voltage constraint, and distribution network power flow safety operation constraint.
[0151] Furthermore, the pre-constructed planning layer model includes: a third objective function with the goal of minimizing the investment cost of distributed energy storage and planning layer constraints.
[0152] Furthermore, the third objective function is as follows:
[0153]
[0154] In the above formula, F is the function value of the third objective function, Y IC is the construction cost of distributed energy storage, F 1 is the function value of the first objective function, F 2 is the function value of the second objective function, μ is the discount rate, y DES is the economic service life of distributed energy storage, is the equipment cost of distributed energy storage per unit capacity, c CON.D is the construction cost of DESS per unit capacity, is the capacity of distributed energy storage d, is the active power of distributed energy storage d.
[0155] Furthermore, the operation layer constraint conditions include at least one of the following: distributed energy storage capacity constraint, distributed energy storage power constraint, distribution network voltage constraint, and distribution network power flow safety operation constraint.
[0156] Example 3
[0157] Based on the same inventive concept, the present invention also provides a computer device, which includes a processor and a memory, wherein the memory is used to store a computer program, the computer program includes program instructions, and the processor is used to execute the program instructions stored in the computer storage medium. The processor may be a central processing unit (CPU), or other general-purpose processors, digital signal processors (DSP), application-specific integrated circuits (ASIC), field-programmable gate arrays (FPGA) or other programmable logic devices, discrete gates or transistor logic devices, discrete hardware components, etc. It is the computing core and control core of the terminal, which is suitable for implementing one or more instructions, and is specifically suitable for loading and executing one or more instructions in a computer storage medium to implement the corresponding method flow or corresponding function, so as to implement the steps of a distributed energy storage and dynamic reconstruction double-layer coordinated optimization method in the above embodiment.
[0158] Example 4
[0159] Based on the same inventive concept, the present invention also provides a storage medium, specifically a computer-readable storage medium (Memory), which is a memory device in a computer device for storing programs and data. It can be understood that the computer-readable storage medium here can include both built-in storage media in a computer device and, of course, extended storage media supported by the computer device. The computer-readable storage medium provides a storage space that stores the operating system of the terminal. In addition, one or more instructions suitable for being loaded and executed by a processor are also stored in the storage space, and these instructions can be one or more computer programs (including program codes). It should be noted that the computer-readable storage medium here can be a high-speed RAM memory or a non-volatile memory, such as at least one disk memory. The processor can load and execute one or more instructions stored in the computer-readable storage medium to implement the steps of a distributed energy storage and dynamic reconstruction dual-layer coordinated optimization method in the above embodiment.
[0160] Those skilled in the art will appreciate that embodiments of the present invention may be provided as methods, systems, or computer program products. Therefore, the present invention may take the form of a complete hardware embodiment, a complete software embodiment, or an embodiment combining software and hardware. Moreover, the present invention may take the form of a computer program product implemented on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program code.
[0161] The present invention is described with reference to flowcharts and / or block diagrams of methods, devices (systems), and computer program products according to embodiments of the present invention. It should be understood that each process and / or block in the flowchart and / or block diagram, as well as the combination of processes and / or blocks in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to produce a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.
[0162] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.
[0163] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.
[0164] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the above embodiments, ordinary technicians in the relevant field should understand that the specific implementation methods of the present invention can still be modified or replaced by equivalents. Any modification or equivalent replacement that does not depart from the spirit and scope of the present invention should be covered within the scope of protection of the claims of the present invention.
Claims
1. A distributed energy storage and dynamic reconstruction two-layer coordinated optimization method, characterized in that: The method comprises: Solving the pre-built operation layer model to obtain a first optimization result; Substituting the function value of the objective function in the pre-constructed operation layer model into the pre-constructed planning layer model to obtain a second optimization result; Based on the first optimization result and the second optimization result, a two-layer coordinated optimization scheme of distributed energy storage and dynamic reconstruction is obtained; Among them, the first optimization result includes at least one of the following: the site selection location of distributed energy storage and the installed capacity of distributed energy storage, and the second optimization result includes at least one of the following: the active power of distributed energy storage and a dynamic reconstruction scheme composed of the switch status of distribution network nodes.
2. The method according to claim 1, characterized in that The pre-constructed operation layer model includes: an operation layer objective function and an operation layer constraint condition, wherein the operation layer objective function includes: a first objective function aiming at minimizing the operation cost of the distribution network under normal conditions and / or a second objective function aiming at minimizing the operation cost of the distribution network under fault conditions.
3. The method according to claim 2, characterized in that The first objective function is as follows: In the above formula, F1 is the function value of the first objective function, Y OM is the operation and maintenance cost of distributed energy storage, Y D is the cost of dynamic reconstruction of the distribution network, Y L is the network loss cost, λ OM is the operation and maintenance cost coefficient of distributed energy storage per unit power, M is the total number of typical wind and solar output scenarios, T is the total number of optimized time periods, and F D is the set of installation nodes for distributed energy storage. is the equipment purchase cost of distributed energy storage per unit power, is the active power of distributed energy storage d in the mth typical wind and solar output scenario during period t, c sw The single cost of reconfiguring the distribution network, ω ij,t is the switch state of the branch between node i and node j during period t, ω ij,t-1 is the switch status of the branch between node i and node j in period t-1, D is the number of statistical days, c B For electricity price, is the active power loss of the branch between node i and node j in period t of the mth typical wind and solar power output scenario, p m is the probability of the mth typical wind and solar power output scenario.
4. The method according to claim 3, characterized in that The process of acquiring the typical wind-solar output scene includes: reducing the wind-solar output scene by using a synchronous back-substitution elimination algorithm to obtain the typical wind-solar output scene.
5. The method according to claim 4, characterized in that The synchronous back-generation elimination algorithm is used to reduce the wind and solar power output scenarios to obtain typical wind and solar power output scenarios, including: Step a: Initialize the number of scenes in the deleted scene set n=0, and the probability of each scene in the original scene set is 1 / N; Step b determines whether the number of scenes in the original scene set is less than or equal to a threshold value. If so, the scenes in the original scene set are used as typical wind and solar output scenes. Otherwise, step c is executed. Step c: Selecting the scene with the smallest reduction degree from the original scene set as the deleted scene, and adding it to the deleted scene set; Step d: updating the probability of the scenes in the original scene set based on the Kantorovich distance between the scenes in the original scene set and the deleted scenes, updating the probability of each scene in the deleted scene set to 1 / n, and returning to step b; Where N is the number of scenes in the original scene set.
6. The method according to claim 5, characterized in that The reduction degree D of scene s in the original scene set s as follows: In the above formula, p s is the probability of scene s in the original scene set, p v is the probability of scene v in the original scene set, and d(s,v) is the Kantorovich distance between scene s and scene v.
7. The method according to claim 6, characterized in that The updating of the probability of the scenes in the original scene set based on the Kantorovich distance between the scenes in the original scene set and the deleted scenes includes: obtaining the scene in the original scene set with the closest Kantorovich distance to the deleted scene, and updating the probability of the scene to the sum of the original probability of the scene and the probability of the deleted scene in the original scene set.
8. The method according to claim 2, characterized in that The second objective function is as follows: In the above formula, F2 is the function value of the second objective function, N e is the annual average number of faults in the distribution network, t0 is the time when the fault starts, T e is the fault duration, Ω N is the set of distribution network nodes, c l is the load importance value coefficient, is the load loss amount at node j at time t.
9. The method according to claim 2, characterized in that The operation layer constraint conditions include at least one of the following: distributed energy storage capacity constraint, distributed energy storage power constraint, distribution network voltage constraint, and distribution network power flow safety operation constraint.
10. The method according to claim 3, characterized in that The pre-built planning layer model includes: a third objective function with the goal of minimizing the investment cost of distributed energy storage and planning layer constraints.
11. The method according to claim 10, characterized in that The third objective function is as follows: In the above formula, F is the function value of the third objective function, Y IC is the construction cost of distributed energy storage, F1 is the function value of the first objective function, F2 is the function value of the second objective function, μ is the discount rate, y DES is the economic service life of distributed energy storage, is the equipment cost of distributed energy storage per unit capacity, c CON.D is the construction cost of DESS per unit capacity, is the capacity of distributed energy storage d, is the active power of distributed energy storage d.
12. The method according to claim 10, characterized in that The operation layer constraint conditions include at least one of the following: distributed energy storage capacity constraint, distributed energy storage power constraint, distribution network voltage constraint, and distribution network power flow safety operation constraint.
13. A distributed energy storage and dynamic reconstruction double-layer coordinated optimization device, characterized in that: The device comprises: A first analysis module is used to solve a pre-built operation layer model to obtain a first optimization result; A second analysis module is used to substitute the function value of the objective function in the pre-constructed operation layer model into the pre-constructed planning layer model to obtain a second optimization result; A third analysis module is used to obtain a distributed energy storage and dynamic reconstruction double-layer coordinated optimization solution based on the first optimization result and the second optimization result; Among them, the first optimization result includes at least one of the following: the site selection location of distributed energy storage and the installed capacity of distributed energy storage, and the second optimization result includes at least one of the following: the active power of distributed energy storage and a dynamic reconstruction scheme composed of the switch status of distribution network nodes.
14. The device according to claim 13, characterized in that The pre-constructed operation layer model includes: an operation layer objective function and an operation layer constraint condition, wherein the operation layer objective function includes: a first objective function aiming at minimizing the operation cost of the distribution network under normal conditions and / or a second objective function aiming at minimizing the operation cost of the distribution network under fault conditions.
15. The device according to claim 14, characterized in that The first objective function is as follows: In the above formula, F1 is the function value of the first objective function, Y OM is the operation and maintenance cost of distributed energy storage, Y D is the cost of dynamic reconstruction of the distribution network, Y L is the network loss cost, λ OM is the operation and maintenance cost coefficient of distributed energy storage per unit power, M is the total number of typical wind and solar output scenarios, T is the total number of optimized time periods, and F D is the set of installation nodes for distributed energy storage. is the equipment purchase cost of distributed energy storage per unit power, is the active power of distributed energy storage d in the mth typical wind and solar output scenario during period t, c sw The single cost of reconfiguring the distribution network, ω ij,t is the switch state of the branch between node i and node j during period t, ω ij,t-1 is the switch status of the branch between node i and node j in period t-1, D is the number of statistical days, c B For electricity price, is the active power loss of the branch between node i and node j in period t of the mth typical wind and solar power output scenario, p m is the probability of the mth typical wind and solar power output scenario.
16. The device according to claim 15, characterized in that The process of acquiring the typical wind-solar output scene includes: reducing the wind-solar output scene by using a synchronous back-substitution elimination algorithm to obtain the typical wind-solar output scene.
17. The device according to claim 16, characterized in that The synchronous back-generation elimination algorithm is used to reduce the wind and solar power output scenarios to obtain typical wind and solar power output scenarios, including: Step a: Initialize the number of scenes in the deleted scene set n=0, and the probability of each scene in the original scene set is 1 / N; Step b determines whether the number of scenes in the original scene set is less than or equal to a threshold value. If so, the scenes in the original scene set are used as typical wind and solar output scenes. Otherwise, step c is executed. Step c: Selecting the scene with the smallest reduction degree from the original scene set as the deleted scene, and adding it to the deleted scene set; Step d: updating the probability of the scenes in the original scene set based on the Kantorovich distance between the scenes in the original scene set and the deleted scenes, updating the probability of each scene in the deleted scene set to 1 / n, and returning to step b; Where N is the number of scenes in the original scene set.
18. The device according to claim 17, characterized in that The reduction degree D of scene s in the original scene set s as follows: In the above formula, p s is the probability of scene s in the original scene set, p v is the probability of scene v in the original scene set, and d(s,v) is the Kantorovich distance between scene s and scene v.
19. The device according to claim 18, characterized in that The updating of the probability of the scenes in the original scene set based on the Kantorovich distance between the scenes in the original scene set and the deleted scenes includes: obtaining the scene in the original scene set with the closest Kantorovich distance to the deleted scene, and updating the probability of the scene to the sum of the original probability of the scene and the probability of the deleted scene in the original scene set.
20. The device according to claim 14, characterized in that The second objective function is as follows: In the above formula, F2 is the function value of the second objective function, N e is the annual average number of faults in the distribution network, t0 is the time when the fault starts, T e is the fault duration, Ω N is the set of distribution network nodes, c l is the load importance value coefficient, is the load loss amount at node j at time t.
21. The device according to claim 14, characterized in that The operation layer constraint conditions include at least one of the following: distributed energy storage capacity constraint, distributed energy storage power constraint, distribution network voltage constraint, and distribution network power flow safety operation constraint.
22. The device according to claim 15, characterized in that The pre-built planning layer model includes: a third objective function with the goal of minimizing the investment cost of distributed energy storage and planning layer constraints.
23. The device according to claim 22, characterized in that The third objective function is as follows: In the above formula, F is the function value of the third objective function, Y IC is the construction cost of distributed energy storage, F1 is the function value of the first objective function, F2 is the function value of the second objective function, μ is the discount rate, y DES is the economic service life of distributed energy storage, is the equipment cost of distributed energy storage per unit capacity, c CON.D is the construction cost of DESS per unit capacity, is the capacity of distributed energy storage d, P d DES is the active power of distributed energy storage d.
24. The device according to claim 22, characterized in that The operation layer constraint conditions include at least one of the following: distributed energy storage capacity constraint, distributed energy storage power constraint, distribution network voltage constraint, and distribution network power flow safety operation constraint.
25. A computer device, characterized in that: include: one or more processors; The processor is configured to execute one or more programs; When the one or more programs are executed by the one or more processors, the distributed energy storage and dynamic reconstruction two-layer coordinated optimization method as described in any one of claims 1 to 12 is implemented.
26. A computer-readable storage medium, characterized in that: A computer program is stored thereon, and when the computer program is executed, the distributed energy storage and dynamic reconstruction double-layer coordinated optimization method as described in any one of claims 1 to 12 is implemented.