Efficient cooling structure of blister equipment for producing medical blister products

The high-efficiency cooling structure for blister equipment addresses instability and flexibility issues by rapidly cooling feed pipelines and preheating structures, stabilizing and enhancing the blister production process efficiency.

CN119078156APending Publication Date: 2024-12-06NANJING SHUANGWEI INFORMATION SYST ENG CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202411200661.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-29
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

Existing blister equipment lacks efficient cooling structures for feed pipelines and preheating structures, leading to instability and reduced flexibility in cooling blister parts during production.

Method used

A high-efficiency cooling structure comprising a cooling mechanism with a conveying component, liquid supply component, and temperature reduction mechanism, including a processing component, heat dissipation component, and heat transfer component, to rapidly cool and stabilize the feeding pipeline and preheating structure.

Benefits of technology

The cooling structure improves the stability and flexibility of cooling blister parts by quickly cooling the feeding pipeline and preheating structure, enhancing the overall efficiency of the blister production process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119078156A_ABST
    Figure CN119078156A_ABST
Patent Text Reader

Abstract

The invention discloses a plastic uptake equipment efficient cooling structure for medical plastic uptake product production, which is applied to the technical field of medical instrument production, and is provided with a cooling mechanism, a processing assembly can be matched with a heat dissipation assembly, and the heat dissipation assembly is driven by the processing assembly, so that the positions of a heat conduction assembly and a heat transfer assembly can be changed; therefore, the connection mode between the heat conduction assembly and the heat transfer assembly is changed, a preheating structure is formed when the heat transfer assembly and the heat conduction assembly are connected, the machining assembly can be preheated when the machining assembly is externally connected with heating equipment, and after the heat conduction assembly and the heat transfer assembly are separated, the heat dissipation assembly can cool the heat conduction assembly and the heat transfer assembly. And the flexibility during heat dissipation is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of medical device production, and in particular relates to a high-efficiency cooling structure of a blister device used for producing medical blister products. Background Art

[0002] In a broad sense, blister products refer to all bubble shells, which are formed into structures such as plastic boxes by blistering sheets. Blister products used in the medical field are usually containers for medicines. During the processing of blister products, the flat plastic hard sheet is heated and softened, then vacuum-adsorbed on the mold surface and cooled to form.

[0003] At present, the Chinese invention with the publication number of CN109955464A discloses a continuously cooled blister mold, which is designed and installed in a cooling device inside a mold barrel similar to a cylindrical shape, and is connected to the outside through a special structure. A cooling medium is introduced from this special structure, and after forming on the mold barrel, a rapid heat exchange is performed, and then the heat is taken away through the blister pipe, thereby achieving the effect of cooling the mold barrel and stabilizing the surface temperature of the mold. By adopting this production process of the continuous cooling mold, the sheet can be directly blister-shaped and cooled after being extruded from the extrusion mold, shortening the intermediate turnover of the sheet and the large investment in the back-end process equipment, which is of great help in reducing costs and production difficulty.

[0004] The existing efficient cooling structure of the blister equipment used in the production of medical blister products has the following disadvantages when in use:

[0005] 1. When cooling the blister parts at the blister equipment, due to the lack of a cooling structure for the feed pipeline, the feed pipeline cannot be cooled quickly, thereby reducing the stability of cooling the blister parts;

[0006] 2. When cooling the blister parts at the blister equipment, due to the lack of a rapid cooling structure for the preheating structure, the preheating structure cannot be cooled quickly, thereby reducing the flexibility of cooling the blister parts. Summary of the invention

[0007] The purpose of the present invention is to provide an efficient cooling structure for an existing blister equipment used in the production of medical blister products, which has the following advantages:

[0008] 1. When cooling the blister parts at the blister equipment, the feeding pipeline can be cooled quickly due to the cooling structure of the feeding pipeline, thereby improving the stability of cooling the blister parts;

[0009] 2. When cooling the blister parts at the blister equipment, the preheating structure can be cooled quickly due to the fast cooling structure of the preheating structure, thereby improving the flexibility of cooling the blister parts.

[0010] The above technical objectives of the present invention are achieved through the following technical solutions: a high-efficiency cooling and temperature reduction structure of a blister equipment for the production of medical blister products, comprising a cooling mechanism and a temperature reduction mechanism, wherein the temperature reduction mechanism is bolted to the top of the cooling mechanism, the cooling mechanism comprises a conveying component, a moving component, a liquid supply component, a cooling component and a feeding component, the moving component is bolted to the top of the conveying component, the liquid supply component is bolted to both sides of the conveying component, the inner side of the liquid supply component is connected to the moving component, the cooling component is bolted to the top of the liquid supply component, the feeding component is bolted to the top of the moving component, the top of the conveying component is connected to the feeding component, the temperature reduction mechanism comprises a processing component, a heat dissipation component, a heat conduction component and a heat transfer component, the processing component is bolted to the top of the moving component, the heat dissipation component is bolted to the top of the processing component, the heat conduction component is bolted to the top of the processing component, and the heat transfer component is bolted to the bottom of the heat dissipation component.

[0011] By adopting the above technical solution, a cooling mechanism and a temperature reduction mechanism are provided. The cooling mechanism can reduce the temperature of the feeding place, and the temperature reduction mechanism can quickly reduce the temperature of the preheating mechanism.

[0012] The present invention is further configured as follows: the conveying assembly includes a material storage box, a material extraction pump and a material feeding pipe, the material extraction pump is connected to the top of the material storage box, and the material feeding pipe is connected to the output end of the top of the material extraction pump.

[0013] By adopting the above technical solution and setting a conveying component, the material storage box can cooperate with the material extraction pump to convey the material required for adsorption processing to the feeding pipe.

[0014] The present invention is further configured as follows: the moving assembly includes a positioning plate, a guide port and a moving hydraulic rod, the positioning plate is bolted to the top of the material storage box, the guide port is opened at the top of the positioning plate, the moving hydraulic rod is bolted to both sides of the positioning plate, and the inner side of the guide port contacts the surface of the feeding pipe.

[0015] By adopting the above technical solution, by setting a moving component, the positioning plate can cooperate with the guide port to limit the feeding pipe, and the moving hydraulic rod can drive the processing component to move, so that the blister plastic can be processed.

[0016] The present invention is further configured as follows: the liquid supply assembly includes a liquid storage box, a liquid pump and a liquid delivery pipe, the liquid storage box is bolted to both sides of the material storage box, the liquid pump is connected to the top of the liquid storage box, the liquid delivery pipe is connected to the top of the liquid pump, and the liquid delivery pipe is connected to the positioning plate.

[0017] By adopting the above technical solution, a liquid supply component is set up, the liquid storage tank can store the coolant, and the liquid pump can cooperate with the liquid delivery pipe to deliver the coolant to the positioning plate, so that the positioning plate can be cooled, and the positioning plate can cool the feeding pipe.

[0018] The present invention is further configured as follows: the cooling assembly includes a connecting shell, a heat conduction plate and a refrigerator, the connecting shell is bolted to the top of the liquid storage box, the heat conduction plate is bolted to the inner side of the connecting shell, and the refrigerator is bolted to the top of the heat conduction plate.

[0019] By adopting the above technical solution and arranging a cooling assembly, the connecting shell can support and limit the heat conduction plate, and the heat conduction plate can cooperate with the refrigerator to cool the coolant.

[0020] The present invention is further configured as follows: the feeding assembly includes a loading plate, a heat transfer plate and a lower mold, the loading plate is bolted to the top of the positioning plate, the heat transfer plate is bolted to the top of the loading plate, and the lower mold is clamped to the top of the loading plate.

[0021] By adopting the above technical solution and setting a processing component, the material placement plate can cooperate with the heat transfer plate, and the positioning plate can cool the lower mold, thereby cooling the blister parts that have completed the blister processing in the lower mold.

[0022] The present invention is further configured as follows: the processing assembly includes an upper mold, a cooling mesh plate and an adjustment hydraulic rod, the upper mold is bolted to the top of the movable hydraulic rod, the cooling mesh plate is bolted to the top of the upper mold, and the adjustment hydraulic rod is bolted to both sides of the upper mold.

[0023] By adopting the above technical solution and setting up a processing component, the upper mold can cooperate with the cooling mesh plate, and the heat of the upper mold can be transferred to the heat conduction component through the cooling mesh plate. Adjusting the hydraulic rod can drive the heat dissipation component to move, thereby increasing the efficiency of cooling the preheating structure.

[0024] The present invention is further configured as follows: the heat dissipation assembly includes a transmission plate, a guide plate and an exhaust fan, the transmission plate is bolted to the top of the adjustment hydraulic rod, the guide plate is bolted to the top of the transmission plate, and the exhaust fan is bolted to the top of the guide plate.

[0025] By adopting the above technical solution and setting up a heat dissipation component, the transmission plate can drive the heat transfer component to move as the hydraulic rod is adjusted, thereby changing the connection method between the heat transfer component and the heat conductive component. The guide plate can cooperate with the exhaust fan to bring out the hot air at the heat conductive component and the heat transfer component for heat dissipation.

[0026] The present invention is further configured as follows: the heat conducting component includes a heat conducting sheet, heat conducting fins and an assembly slot, the heat conducting sheet is bolted to the top of the cooling mesh plate, the heat conducting fins are welded to the top of the heat conducting sheet, and the assembly slot is opened on the top of the heat conducting fins.

[0027] By adopting the above technical solution, a heat-conducting component is set up, and the heat-conducting sheet can cooperate with the heat-conducting fins to dissipate the heat at the cooling mesh plate into the surrounding air, thereby cooling the cooling mesh plate. The assembly slot can connect the heat-conducting fins with the heat transfer component to form a preheating structure.

[0028] The present invention is further configured as follows: the heat transfer component includes a heat transfer sheet, a heat transfer fin and an assembly plug-in plate, the heat transfer sheet is bolted to the bottom of the guide plate, the heat transfer fin is welded to the bottom of the heat transfer sheet, the assembly plug-in plate is bolted to the bottom of the heat transfer fin, and the surface of the assembly plug-in plate contacts the inner side of the assembly slot.

[0029] By adopting the above technical solution, by setting up a heat transfer component, the heat transfer sheet can cooperate with the heat transfer fins to bring out the heat at the transmission plate, and the assembly plug plate can be connected to the assembly slot to form a preheating structure.

[0030] In summary, the present invention has the following beneficial effects:

[0031] 1. By setting a cooling mechanism, the conveying component can cooperate with the moving component and the feeding component, and the raw materials are conveyed to the feeding component through the conveying component through the moving component, so that the raw materials for blister processing can be conveyed and processed. The moving component can cooperate with the liquid supply component, and the cooling component can cool the coolant in the liquid supply component, and the liquid supply component can convey the coolant to the moving component, so as to cool the moving component and the feeding component, thereby improving the stability of cooling the blister parts;

[0032] 2. By setting up a cooling mechanism, the processing component can cooperate with the heat dissipation component. By driving the heat dissipation component through the processing component, the positions of the heat conductive component and the heat transfer component can be changed, thereby changing the connection method between the heat conductive component and the heat transfer component, so that the heat transfer component and the heat conductive component form a preheating structure when connected, and the processing component can be preheated when an external heating device is connected. After the heat conductive component and the heat transfer component are separated, the heat dissipation component can be used to cool down the heat conductive component and the heat transfer component, thereby improving the flexibility of heat dissipation. BRIEF DESCRIPTION OF THE DRAWINGS

[0033] Figure 1 It is a schematic diagram of the overall structure of the present invention;

[0034] Figure 2 It is a schematic diagram of the cooling mechanism structure of the present invention;

[0035] Figure 3It is a schematic diagram of the structure of the conveying assembly of the present invention;

[0036] Figure 4 It is a schematic diagram of the structure of the mobile assembly of the present invention;

[0037] Figure 5 It is a schematic diagram of the structure of the liquid supply component and the cooling component of the present invention;

[0038] Figure 6 It is a schematic diagram of the structure of the feeding assembly of the present invention;

[0039] Figure 7 It is a schematic diagram of the cooling mechanism structure of the present invention;

[0040] Figure 8 It is a schematic diagram of the processing assembly structure of the present invention;

[0041] Fig. 9 It is a schematic diagram of the structure of the heat dissipation assembly of the present invention;

[0042] Fig.10 It is a schematic diagram of the structure of the heat conduction component of the present invention;

[0043] Fig.11 It is a schematic diagram of the structure of the heat transfer component of the present invention.

[0044] Reference numerals: 1, cooling mechanism; 101, conveying assembly; 1011, material storage box; 1012, material pump; 1013, material feeding pipe; 102, moving assembly; 1021, positioning plate; 1022, guide port; 1023, moving hydraulic rod; 103, liquid supply assembly; 1031, liquid storage box; 1032, liquid pump; 1033, liquid feeding pipe; 104, cooling assembly; 1041, connecting shell; 1042, temperature conduction plate; 1043, refrigerator; 105, feeding assembly; 1051, material placement plate; 1052, heat transfer plate; 1053, lower mold; 2, cooling mechanism; 201, processing assembly; 2011, upper mold; 2012, cooling mesh; 2013, adjustment hydraulic rod; 202, heat dissipation assembly; 2021, transmission plate; 2022, guide plate; 2023, exhaust fan; 203, heat conduction assembly; 2031, heat conduction sheet; 2032, heat conduction fins; 2033, assembly slot; 204, heat transfer assembly; 2041, heat transfer sheet; 2042, heat transfer fins; 2043, assembly plug-in board. DETAILED DESCRIPTION

[0045] The present invention is further described in detail below in conjunction with the accompanying drawings.

[0046] Embodiment 1:

[0047] refer to Figure 1-6A high-efficiency cooling and temperature reduction structure of a blister device for producing medical blister products, comprising a cooling mechanism 1, the cooling mechanism 1 comprising a conveying component 101, a moving component 102, a liquid supply component 103, a cooling component 104 and a feeding component 105, the moving component 102 is bolted to the top of the conveying component 101, the liquid supply component 103 is bolted to both sides of the conveying component 101, the inner side of the liquid supply component 103 is connected to the moving component 102, the cooling component 104 is bolted to the top of the liquid supply component 103, the feeding component 105 is bolted to the top of the moving component 102, the top of the conveying component 101 is connected to the feeding component 105 By setting up the cooling mechanism 1, the conveying component 101 can cooperate with the moving component 102 and the feeding component 105, and the raw materials are conveyed to the feeding component 105 through the moving component 102 by the conveying component 101, so that the raw materials for blister processing can be conveyed and processed, and the moving component 102 can cooperate with the liquid supply component 103, and the cooling liquid in the liquid supply component 103 can be cooled by the cooling component 104, and the liquid supply component 103 can convey the cooling liquid to the moving component 102, so as to cool the moving component 102 and the feeding component 105, thereby improving the stability of cooling the blister parts.

[0048] like Figure 3 As shown, the conveying component 101 includes a material storage box 1011, a material extraction pump 1012 and a feed pipe 1013. The material extraction pump 1012 is connected to the top of the material storage box 1011, and the feed pipe 1013 is connected to the output end of the top of the material extraction pump 1012. By setting the conveying component 101, the material storage box 1011 can cooperate with the material extraction pump 1012 to transport the material required for adsorption processing to the feed pipe 1013.

[0049] like Figure 4 As shown, the moving component 102 includes a positioning plate 1021, a guide port 1022 and a moving hydraulic rod 1023. The positioning plate 1021 is bolted to the top of the storage box 1011, the guide port 1022 is opened at the top of the positioning plate 1021, and the moving hydraulic rod 1023 is bolted to both sides of the positioning plate 1021. The inner side of the guide port 1022 contacts the surface of the feeding tube 1013. By setting the moving component 102, the positioning plate 1021 can cooperate with the guide port 1022 to limit the feeding tube 1013, and the moving hydraulic rod 1023 can drive the processing component 201 to move, so that the blister plastic can be processed.

[0050] like Figure 5As shown, the liquid supply component 103 includes a liquid storage box 1031, a liquid pump 1032 and a liquid delivery pipe 1033. The liquid storage box 1031 is bolted to both sides of the material storage box 1011, the liquid pump 1032 is connected to the top of the liquid storage box 1031, the liquid delivery pipe 1033 is connected to the top of the liquid pump 1032, and the liquid delivery pipe 1033 is connected to the positioning plate 1021. By setting up the liquid supply component 103, the liquid storage box 1031 can store the cooling liquid, the liquid pump 1032 can cooperate with the liquid delivery pipe 1033 to transport the cooling liquid to the positioning plate 1021, so that the positioning plate 1021 can be cooled, and the positioning plate 1021 can cool the delivery pipe 1013.

[0051] like Figure 5 As shown, the cooling component 104 includes a connecting shell 1041, a heat conduction plate 1042 and a refrigerator 1043. The connecting shell 1041 is bolted to the top of the liquid storage tank 1031, the heat conduction plate 1042 is bolted to the inner side of the connecting shell 1041, and the refrigerator 1043 is bolted to the top of the heat conduction plate 1042. By setting the cooling component 104, the connecting shell 1041 can support and limit the heat conduction plate 1042, and the heat conduction plate 1042 can cooperate with the refrigerator 1043 to cool the coolant.

[0052] like Figure 6 As shown, the feeding component 105 includes a placing plate 1051, a heat transfer plate 1052 and a lower mold 1053. The placing plate 1051 is bolted to the top of the positioning plate 1021, the heat transfer plate 1052 is bolted to the top of the placing plate 1051, and the lower mold 1053 is clamped to the top of the placing plate 1051. By setting the processing component 201, the placing plate 1051 can cooperate with the heat transfer plate 1052. As the positioning plate 1021 cools down the lower mold 1053, the blister parts that have completed the blister processing in the lower mold 1053 can be cooled.

[0053] Brief description of the use process: First, the conveying component 101 is energized and started, and then the material pump 1012 will pump the raw materials in the storage box 1011 to the feeding pipe 1013, and then the raw materials will flow to the lower mold 1053 through the feeding pipe 1013. After that, after the cooling mechanism 2 and the lower mold 1053 perform blister processing on the blister raw materials, the refrigerator 1043 will absorb the heat from the heat conduction plate 1042, thereby cooling the coolant in the liquid storage box 1031, and then the liquid pump 1032 will transport the coolant in the liquid storage box 1031 to the positioning plate 1021 through the liquid feeding pipe 1033, and the positioning plate 1021 will cool the raw materials in the feeding pipe 1013 through the coolant, and can cool the heat transfer plate 1052, so that the blister parts after the blister processing can be cooled. After cooling, the hydraulic rod 1023 is moved to lift the cooling mechanism 2, and then the blister parts can be taken out.

[0054] Embodiment 2:

[0055] refer to Figure 7-11 , a high-efficiency cooling and temperature reduction structure of a blister equipment for producing medical blister products, including a cooling mechanism 2, the cooling mechanism 2 is bolted to the top of a cooling mechanism 1, the cooling mechanism 2 includes a processing component 201, a heat dissipation component 202, a heat conduction component 203 and a heat transfer component 204, the processing component 201 is bolted to the top of a moving component 102, the heat dissipation component 202 is bolted to the top of the processing component 201, the heat conduction component 203 is bolted to the top of the processing component 201, and the heat transfer component 204 is bolted to the bottom of the heat dissipation component 202. By setting the cooling mechanism 2, the processing component 201 can be connected with the heat dissipation component 202. The heat component 202 cooperates with the processing component 201 to drive the heat dissipation component 202, so that the positions of the heat conductive component 203 and the heat transfer component 204 can be changed, thereby changing the connection method between the heat conductive component 203 and the heat transfer component 204, so that the heat transfer component 204 and the heat conductive component 203 form a preheating structure when connected, and the processing component 201 can be preheated when an external heating device is connected. After the heat conductive component 203 and the heat transfer component 204 are separated, the heat dissipation component 202 can cool down the heat conductive component 203 and the heat transfer component 204, thereby improving the flexibility of heat dissipation.

[0056] like Figure 8 As shown, the processing component 201 includes an upper mold 2011, a cooling mesh plate 2012 and an adjusting hydraulic rod 2013. The upper mold 2011 is bolted to the top of the movable hydraulic rod 1023, the cooling mesh plate 2012 is bolted to the top of the upper mold 2011, and the adjusting hydraulic rod 2013 is bolted to both sides of the upper mold 2011. By setting the processing component 201, the upper mold 2011 can cooperate with the cooling mesh plate 2012, and the heat of the upper mold 2011 can be transferred to the heat conducting component 203 through the cooling mesh plate 2012. The adjusting hydraulic rod 2013 can drive the heat dissipation component 202 to move, thereby increasing the efficiency of cooling the preheating structure.

[0057] like Fig. 9 As shown, the heat dissipation component 202 includes a transmission plate 2021, a guide plate 2022 and an exhaust fan 2023. The transmission plate 2021 is bolted to the top of the adjustment hydraulic rod 2013, the guide plate 2022 is bolted to the top of the transmission plate 2021, and the exhaust fan 2023 is bolted to the top of the guide plate 2022. By setting the heat dissipation component 202, the transmission plate 2021 can drive the heat transfer component 204 to move with the movement of the adjustment hydraulic rod 2013, thereby changing the connection mode between the heat transfer component 204 and the heat conductive component 203. The guide plate 2022 can cooperate with the exhaust fan 2023 to bring out the hot air at the heat conductive component 203 and the heat transfer component 204 for heat dissipation.

[0058] like Fig.10 As shown, the heat-conducting component 203 includes a heat-conducting sheet 2031, a heat-conducting fin 2032 and an assembly slot 2033. The heat-conducting sheet 2031 is bolted to the top of the cooling mesh plate 2012, the heat-conducting fin 2032 is welded to the top of the heat-conducting sheet 2031, and the assembly slot 2033 is opened on the top of the heat-conducting fin 2032. By setting the heat-conducting component 203, the heat-conducting sheet 2031 can cooperate with the heat-conducting fin 2032 to dissipate the heat at the cooling mesh plate 2012 into the surrounding air, thereby cooling the cooling mesh plate 2012. The assembly slot 2033 can connect the heat-conducting fin 2032 with the heat transfer component 204 to form a preheating structure.

[0059] like Fig.11 As shown, the heat transfer component 204 includes a heat transfer sheet 2041, a heat transfer fin 2042 and an assembly plug plate 2043. The heat transfer sheet 2041 is bolted to the bottom of the guide plate 2022, the heat transfer fin 2042 is welded to the bottom of the heat transfer sheet 2041, and the assembly plug plate 2043 is bolted to the bottom of the heat transfer fin 2042. The surface of the assembly plug plate 2043 contacts the inner side of the assembly slot 2033. By setting the heat transfer component 204, the heat transfer sheet 2041 can cooperate with the heat transfer fin 2042 to bring out the heat at the transmission plate 2021, and the assembly plug plate 2043 can be connected to the assembly slot 2033 to form a preheating structure.

[0060] Brief description of the usage process: First, the cooling mechanism 2 is powered on and started. Then, when the upper mold 2011 needs to be preheated, the hydraulic rod 2013 is adjusted to drive the transmission plate 2021 to move downward, and then the heat-conducting fins 2032 are connected to the assembly plug plate 2043 at the heat transfer fins 2042 through the assembly slots 2033. Then, the external heating device is set on the surface of the heat-conducting fins 2032 and the heat transfer fins 2042. Then, the heat-conducting sheet 2031 will transfer heat to the upper mold 2011 for preheating. When cooling is required, the hydraulic rod 2013 is adjusted to lift the transmission plate 2021 upward, and then the exhaust fan 2023 will extract the hot air at the heat-conducting fins 2032 and the heat transfer fins 2042, thereby cooling the heat transfer fins 2042 and the heat-conducting fins 2032 until the upper mold 2011 is cooled.

[0061] This specific embodiment is merely an explanation of the present invention and is not a limitation of the present invention. After reading this specification, those skilled in the art may make non-creative modifications to the present embodiment as needed. However, as long as they are within the scope of the claims of the present invention, they are protected by the patent law.

Claims

1. A highly efficient cooling and temperature reduction structure for blister equipment used in the production of medical blister products, comprising a cooling mechanism (1) and a temperature reduction mechanism (2), characterized in that: The cooling mechanism (2) is bolted to the top of the cooling mechanism (1); the cooling mechanism (1) comprises a conveying component (101), a moving component (102), a liquid supply component (103), a cooling component (104) and a feeding component (105); the moving component (102) is bolted to the top of the conveying component (101); the liquid supply component (103) is bolted to both sides of the conveying component (101); the inner side of the liquid supply component (103) is connected to the moving component (102); the cooling component (104) is bolted to the top of the liquid supply component (103); the feeding component (105) ) is bolted to the top of the moving component (102), the top of the conveying component (101) is connected to the feeding component (105), the cooling mechanism (2) comprises a processing component (201), a heat dissipation component (202), a heat conduction component (203) and a heat transfer component (204), the processing component (201) is bolted to the top of the moving component (102), the heat dissipation component (202) is bolted to the top of the processing component (201), the heat conduction component (203) is bolted to the top of the processing component (201), and the heat transfer component (204) is bolted to the bottom of the heat dissipation component (202).

2. According to claim 1, a high-efficiency cooling structure for blister equipment used in the production of medical blister products is characterized by: The conveying assembly (101) comprises a material storage box (1011), a material extraction pump (1012) and a material feeding pipe (1013); the material extraction pump (1012) is connected to the top of the material storage box (1011), and the material feeding pipe (1013) is connected to the output end at the top of the material extraction pump (1012).

3. The efficient cooling structure for blister equipment used in the production of medical blister products according to claim 2, characterized in that: The moving assembly (102) includes a positioning plate (1021), a guide port (1022) and a moving hydraulic rod (1023); the positioning plate (1021) is bolted to the top of the material storage box (1011); the guide port (1022) is opened at the top of the positioning plate (1021); the moving hydraulic rod (1023) is bolted to both sides of the positioning plate (1021); and the inner side of the guide port (1022) contacts the surface of the feeding tube (1013).

4. The efficient cooling structure for blister equipment used in the production of medical blister products according to claim 3 is characterized in that: The liquid supply assembly (103) comprises a liquid storage box (1031), a liquid extraction pump (1032) and a liquid delivery pipe (1033); the liquid storage box (1031) is bolted to both sides of the material storage box (1011); the liquid extraction pump (1032) is connected to the top of the liquid storage box (1031); the liquid delivery pipe (1033) is connected to the top of the liquid extraction pump (1032); and the liquid delivery pipe (1033) is connected to the positioning plate (1021).

5. The efficient cooling structure for blister equipment used in the production of medical blister products according to claim 4, characterized in that: The cooling assembly (104) includes a connecting shell (1041), a heat conduction plate (1042) and a refrigerator (1043); the connecting shell (1041) is bolted to the top of the liquid storage box (1031); the heat conduction plate (1042) is bolted to the inner side of the connecting shell (1041); and the refrigerator (1043) is bolted to the top of the heat conduction plate (1042).

6. The efficient cooling structure for blister equipment used in the production of medical blister products according to claim 3, characterized in that: The feeding assembly (105) includes a material placement plate (1051), a heat transfer plate (1052) and a lower mold (1053); the material placement plate (1051) is bolted to the top of the positioning plate (1021); the heat transfer plate (1052) is bolted to the top of the material placement plate (1051); and the lower mold (1053) is clamped to the top of the material placement plate (1051).

7. The efficient cooling structure for blister equipment used in the production of medical blister products according to claim 3, characterized in that: The processing assembly (201) comprises an upper mold (2011), a cooling mesh plate (2012) and an adjusting hydraulic rod (2013); the upper mold (2011) is bolted to the top of a movable hydraulic rod (1023); the cooling mesh plate (2012) is bolted to the top of the upper mold (2011); and the adjusting hydraulic rod (2013) is bolted to both sides of the upper mold (2011).

8. The efficient cooling structure for blister equipment used in the production of medical blister products according to claim 7, characterized in that: The heat dissipation assembly (202) comprises a transmission plate (2021), a guide plate (2022) and an exhaust fan (2023); the transmission plate (2021) is bolted to the top of the adjustment hydraulic rod (2013); the guide plate (2022) is bolted to the top of the transmission plate (2021); and the exhaust fan (2023) is bolted to the top of the guide plate (2022).

9. The efficient cooling structure for blister equipment used in the production of medical blister products according to claim 8, characterized in that: The heat-conducting component (203) comprises a heat-conducting sheet (2031), a heat-conducting fin (2032) and an assembly slot (2033); the heat-conducting sheet (2031) is bolted to the top of the cooling mesh plate (2012); the heat-conducting fin (2032) is welded to the top of the heat-conducting sheet (2031); and the assembly slot (2033) is opened at the top of the heat-conducting fin (2032).

10. The efficient cooling structure for blister equipment used in the production of medical blister products according to claim 9, characterized in that: The heat transfer component (204) comprises a heat transfer sheet (2041), a heat transfer fin (2042) and an assembly plug plate (2043); the heat transfer sheet (2041) is bolted to the bottom of the guide plate (2022); the heat transfer fin (2042) is welded to the bottom of the heat transfer sheet (2041); the assembly plug plate (2043) is bolted to the bottom of the heat transfer fin (2042); and the surface of the assembly plug plate (2043) is in contact with the inner side of the assembly slot (2033).

Citation Information

Patent Citations

  • Continuous cooling plastic suction mold

    CN109955464A