Charging pile operation device and method
Through the charging pile operation device and method, the charging power can be transferred by using the power-off time provided by the user, the problem that the charging mechanism in the prior art cannot meet the emergency charging and power limits is solved, and faster charging and more efficient power consumption is achieved manage.
Patent Information
- Application Number
- CN202411294579.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-14
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2044-09-14
AI Technical Summary
The existing charging mechanism cannot meet users' emergency charging needs, resulting in a reduced user experience and wasted charging power limits and invalid charging time.
Through the charging pile operation device and method, we receive the user's urgent request, collect the power outage time of each charging pile, select the power supply of the charging pile in use, transfer the charging power to the target charging pile for emergency charging, and realize the addition of the charging pile. Emergency charging, use the invalid charging time to ensure that the total electricity load is overloaded.
It effectively shortens the charging time, improves the user experience, makes full use of the invalid charging time, and does not increase the burden of electricity, ensuring that the power supply of existing users is reliable and continuous.
Smart Images

Figure CN119078585A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the field of electric vehicle charging, and in particular relates to operation optimization of charging piles. Background Art
[0002] As a charging device that replenishes power for electric vehicles, charging piles can be fixed on the ground or wall and installed in public buildings (charging stations, shopping malls, public parking lots, etc.) and residential parking lots. They can charge various models of electric vehicles by adjusting the voltage and current.
[0003] Some users may need urgent charging due to urgent matters, but the existing charging mechanism cannot meet the needs of customers for emergency charging, which reduces the user experience. Summary of the invention
[0004] In view of the above problems, the present invention aims to propose a charging pile operation device and method to solve the problem that the existing charging mechanism cannot meet user needs.
[0005] A charging pile operation device, characterized by comprising:
[0006] A receiving module (1) is used to receive the expedited charging request information sent by the user, retrieve the relevant data of the user from the information storage module (6), and determine whether the expedited charging request is qualified according to preset conditions. If qualified, the determination module (2) is triggered; if unqualified, the expedited charging request is rejected and feedback is given to the user;
[0007] A collecting module (5) is used to collect the power-off duration of each charging pile, and is connected to the acquisition module (3) and the information storage module (6) via an interface, wherein the power-off duration is the duration allowed for the power-off of the charging pile provided by the online user of each charging pile;
[0008] The determining module (2), after being triggered by the receiving module (1), triggers the acquiring module (3) according to the target charging pile carried in the expedited charging request information and the expedited charging time required by the user;
[0009] The acquisition module (3), when triggered, acquires the power-off duration of other charging piles from the collection module (5), and then triggers the power supply module (4);
[0010] The power supply module (4), after being triggered, selects to cut off the power supply of at least one of the charging piles in use according to the power-off time and the expedited charging time; and within the power-off time, allocates the charging power of the charging pile that has been cut off to the target charging pile for expedited charging;
[0011] The information storage module (6) is used to store the available power supply time of the users and the remaining value of the available power supply time of each user; the information storage module (6) is connected to the receiving module (1) via an interface.
[0012] A charging pile operation method, characterized in that it uses the charging pile operation device according to any one of claims 1 to 4, comprising:
[0013] G1, the receiving module (1) receives the expedited request information sent by the user;
[0014] G2, the determination module (2) determines the target charging pile carried by the expedited charging request information and the expedited charging time of the target charging pile;
[0015] G3, the acquisition module (3) acquires the power-off duration of other charging piles;
[0016] G4, the power supply module (4) selects to cut off the power supply of at least one of the charging piles in use according to the expedited charging time and the power-off time; and
[0017] G5. The power supply module (4) allocates the charging power of the power-off charging pile to the target charging pile for fast charging within the power-off time.
[0018] Compared with the prior art, the present invention can achieve the following technical effects:
[0019] In real life, every user has the need to fully charge the car in a short period of time. Therefore, this application proposes a mechanism for contributing charging time in exchange for expedited charging in response to customer needs. That is, the user spontaneously proposes the length of time that the power can be cut off in exchange for the qualification of expedited charging. The purpose of expedited charging is to reduce the charging time, and reducing the time will inevitably lead to an increase in the power of the charging pile, which will increase the power supply load. To this end, this application stops the power supply of the corresponding charging pile within the length of time that the power can be cut off provided by the user, and transfers the power of the charging pile to the charging pile for expedited charging (target charging pile). In the above manner, while ensuring that the total power load is not overloaded, that is, under the premise that existing users (excluding users whose power is cut off due to expedited charging) have reliable power supply and uninterrupted power supply, emergency users are charged, thereby improving the user experience. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1 A schematic diagram of the structure of a charging pile operation device provided for one or more embodiments of this specification;
[0021] Figure 2 A flowchart of a charging pile operation method provided for one or more embodiments of this specification. DETAILED DESCRIPTION
[0022] Example 1: See attached Figure 1 , a charging pile operation device, characterized by comprising:
[0023] The receiving module 1 is used to receive the expedited charging request information sent by the user, retrieve the relevant data of the user from the information storage module 6, and determine whether the expedited charging request is qualified according to the preset conditions. If qualified, the determining module 2 is triggered; if not qualified, the expedited charging request is rejected and fed back to the user;
[0024] The collecting module 5 is used to collect the power-off duration of each charging pile, and is connected to the obtaining module 3 and the information storage module 6 through an interface. The power-off duration is the duration provided by the online users of each charging pile that the charging pile is allowed to be powered off;
[0025] The determining module 2, after being triggered by the receiving module 1, triggers the acquiring module 3 according to the target charging pile carried in the expedited charging request information and the expedited charging time required by the user;
[0026] The acquisition module 3, after being triggered, obtains the power-off duration of other charging piles from the collection module 5, and then triggers the power supply module 4;
[0027] The power supply module 4, after being triggered, selects to cut off the power supply of at least one of the charging piles in use according to the power-off duration and the expedited charging duration; within the power-off duration, the charging power of the charging pile that is cut off is allocated to the target charging pile for expedited charging;
[0028] The information storage module 6 is used to store the available power supply time of each user and the remaining value of the available power supply time of each user; the information storage module 6 is connected to the receiving module 1 via an interface.
[0029] In the embodiment of the present application, the power supply load of the community has been designed before the community is built, and there is a clear power limit for the electric vehicle charging part. For the sake of electricity safety, the charging pile power set by the community is usually low, so users usually choose to charge at night or during rest. The night and rest time is usually much longer than the electric vehicle time. For example, if an electric vehicle is expected to be fully charged in 4 to 5 hours, then the night charging time is at least 3 hours, and the user's rest time arranged for charging will usually reserve 1-2 hours to ensure full charging.
[0030] In this scenario, two problems arise: On the one hand, the charging power of the community limits users from charging quickly. For example, sometimes users need an emergency vehicle and need to fully charge it in 2 hours, but due to power restrictions, users can only fully charge it within 4-5 hours, and users can only find high-power charging piles outside the community. On the other hand, users have a lot of invalid charging time. For example, if you start charging at 7 o'clock at night when you get home, and drive off at 7 o'clock the next morning, the actual charging time for the user is 12 hours. If the charging power is 10kW, the vehicle only needs 4-5 hours to be fully charged, and the remaining 7-8 hours are invalid charging time.
[0031] In response to the above problems, the present application proposes a contribution charging time mechanism, which can not only effectively utilize the invalid charging time, but also solve the power limitation.
[0032] Specifically, users need to choose to transfer part of the charging time within a certain period of time according to their actual charging situation. For example, user A finds that his effective charging time is 4 hours a day, which means that as long as he charges for 5 hours in the 7 hours at night, he can be fully charged. In the remaining 2 hours, even if the power is cut off, it will not affect his charging, so user A can transfer these 2 hours as the power-off duration. That is, the user can transfer the power of these 2 hours to the target charging pile. In this way, the target charging pile can charge at twice the original power in these 2 hours, and its charging time can be shortened by 50%. At the same time, this method does not increase the burden of electricity consumption. For example, under normal circumstances, the charging power of charging piles A, B and C in the community is set to 10kw respectively. Now charging pile A is the target charging pile, and charging pile C transfers the power-off duration. During the power-off duration, the charging power of charging pile A is 20kw, the charging power of charging pile B is 10kw, and the charging power of charging pile C is 0kw. In this way, the total charging load does not change, but the charging time of charging pile A is shortened by 50%, and the invalid charging time of charging pile C is fully utilized.
[0033] In order to implement the above mechanism, the present application sets up a collection module 5 for collecting the power-off duration of each charging pile. At the same time, in order to ensure the fairness of the above mechanism, in addition to receiving the expedited request information sent by the user, the receiving module 1 is also used to determine whether the expedited charging request is qualified according to preset conditions. If unqualified, the user's expedited request is rejected. After determining that it is qualified, the determination module 2 determines the target charging pile and the expedited charging duration required by the user. The acquisition module 3 obtains the power-off duration of other charging piles. Finally, the power supply module 4, according to the power-off duration and the expedited charging duration, selects to cut off the power supply of at least one of the charging piles in use; within the power-off duration, the charging power of the power-off charging pile is allocated to the target charging pile for expedited charging.
[0034] It should be noted that the charging pile in this application is adjustable, for example, the maximum power of the charging pile is 4 times the charging power limited by the community. Then during normal charging, it is still charged according to the charging power limited by the community. Only when charging urgently, while ensuring the safety of electricity use, the charging power of the target charging pile is adjusted to an integer multiple of the original charging power to achieve emergency charging.
[0035] Embodiment 2, according to the charging pile operation device of embodiment 1, is characterized in that:
[0036] The receiving module 1 also includes a first judgment module for determining whether the user who sends the expedited request information has submitted a power-off duration in the past. If so, the determination module 2 is triggered; otherwise, a rejection message is returned to the user and the current process ends.
[0037] In an embodiment of the present application, in order to further balance the interests of expedited charging users and normal charging users, before expedited charging, it is determined whether the user has submitted the power-off duration, thereby preventing someone from always expediting charging but never contributing charging time.
[0038] Embodiment 3, according to the charging pile operation device of embodiment 1, is characterized in that:
[0039] The receiving module 1 also includes a second judgment module, which is used to determine whether the expedited charging time carried in the expedited request information exceeds the cumulative power supply time provided by the user. If not, the determination module 2 is triggered; otherwise, a rejection message is returned to the user and the current process is terminated.
[0040] In the embodiment of the present application, in order to further balance the interests of expedited charging users and normal charging users, before expedited charging, it is determined whether the expedited charging time carried in the expedited request information exceeds the cumulative power supply time provided by the user, so as to prevent someone from enjoying the right to expedited charging for a long time with only one or a few times of contribution. For example, user A has only contributed 1 hour of charging time, but can enjoy the right to expedited charging indefinitely.
[0041] Embodiment 4, according to the charging pile operation device of embodiment 1, is characterized in that the power supply module 4 is configured as:
[0042] The expedited charging duration is derived from at least one of the power-off durations;
[0043] Determining the charging pile that needs to be powered off and the power-off duration of the charging pile that needs to be powered off according to the expedited charging duration and the at least one power-off duration; and
[0044] According to the charging piles that need to be powered off and the power-off duration of the charging piles that need to be powered off, the power supply of the corresponding remaining charging piles is cut off and the target charging pile is powered on.
[0045] In the embodiment of the present application, there are multiple ways to select the disconnected charging pile and the power-off duration, specifically:
[0046] Method 1
[0047] Prioritize charging stations whose power-off time is longer than the expedited charging time and whose difference between the power-off time and the expedited charging time is the smallest.
[0048] Taking double charging power as an example, the expedited time is 2 hours. Currently, there are 2 charging piles that can be disconnected for 1 hour, 1 charging pile that can be disconnected for 2 hours, and 1 charging pile that can be disconnected for 3 hours. The charging pile that can be disconnected for 1 hour needs to be reselected halfway. Choosing a charging pile that can be disconnected for 3 hours will increase the probability of switching multiple charging piles. Therefore, the final choice is to disconnect the charging pile that can be disconnected for 2 hours for 2 hours.
[0049] Method 2
[0050] According to the duration of the rush, determine the charging power multiple corresponding to the rush time. Then according to the charging power multiple, choose to disconnect the corresponding charging pile. For example, a regular full charge takes 4 hours. If the rush time is 1 hour, then the charging power multiple corresponding to the rush time is 4. At this time, you need to select 3 charging piles that can be disconnected for more than 1 hour, disconnect the power of these 3 charging piles for one hour, and transfer the power of these 3 charging piles to the target charging pile.
[0051] Method 3
[0052] According to the expedite duration, determine the charging power multiple corresponding to the expedite duration. Then, according to the charging power multiple and the current power-off duration, choose to disconnect the corresponding charging pile. For example, a conventional full charge takes 5 hours. If the expedite duration is 2 hours, the charging power multiple corresponding to the expedite duration is 2.5. Since it is impossible to transfer 0.5 times the charging power, you can choose to charge for 1 hour at 3 times the charging power, and then charge for 1 hour at 2 times the charging power. At this time, you need to first select 2 charging piles with a power-off duration greater than 1 hour, power off these 2 charging piles, and transfer the power of these 2 charging piles to the target charging pile. It is then preferred to select one of the above two charging piles as the charging pile to be powered off in the next hour. If the power-off duration of the above two charging piles is less than one hour, select another charging pile as the charging pile to be powered off in the next hour.
[0053] Example 5, see attached Figure 2, a charging pile operation method, characterized in that it uses the charging pile operation device described in any one of embodiments 1-4, including:
[0054] G1, the receiving module 1 receives the expedited request information sent by the user;
[0055] G2, the determination module 2 determines the target charging pile carried by the expedited request information and the expedited charging duration of the target charging pile;
[0056] G3, the acquisition module 3 obtains the power-off duration of other charging piles;
[0057] G4, the power supply module 4 selects to cut off the power supply of at least one of the charging piles in use according to the expedited charging time and the power-off time; and
[0058] G5. The power supply module 4 allocates the charging power of the power-off charging pile to the target charging pile for fast charging within the power-off time.
[0059] Embodiment 6, according to the charging pile operation method of embodiment 5, is characterized in that it uses the charging pile operation device of embodiment 1, and the method further includes:
[0060] The collecting module 5 collects the power-off duration of each charging pile according to a preset period.
[0061] In the embodiment of the present application, taking into account the user's moving in and out, as well as the adjustment of the user's commuting time, it is necessary to collect the user's power-off duration at regular intervals to ensure that the contribution charging duration mechanism can continue to operate.
[0062] Embodiment 7, according to the charging pile operation method of embodiment 6, is characterized in that it uses the charging pile operation device of embodiment 2, and after G1, the method further includes:
[0063] The judgment module determines whether the user who sent the expedited request information has submitted a power-off duration within a preset period. If yes, continue to execute G2; otherwise, end the current process.
[0064] In an embodiment of the present application, in order to further balance the interests of expedited charging users and normal charging users, the user's contribution to charging time is examined once every cycle, so as to prevent users from occupying too many opportunities for expedited charging. For example, user A only contributed 2 hours of charging time once throughout the year, but user A did perform expedited charging once throughout the year. Although the expedited charging time of user A did not exceed the user's power-off time, if everyone follows suit, it is likely to lead to a situation where the power-off time is sufficient in the first half of the year, but insufficient in the second half of the year. However, if statistics are taken every six months, it can be guaranteed that the power-off time is sufficient throughout the year.
[0065] Embodiment 8, according to the charging pile operation method of embodiment 7, is characterized in that it uses the charging pile operation device of embodiment 4, and the G4 includes:
[0066] The expedited charging duration is derived from at least one of the power-off durations;
[0067] Determining the charging pile that needs to be powered off and the power-off duration of the charging pile that needs to be powered off according to the expedited charging duration and the at least one power-off duration; and
[0068] According to the charging piles that need to be powered off and the power-off duration of the charging piles that need to be powered off, the power supply of the corresponding remaining charging piles is cut off and the target charging pile is powered on.
[0069] Embodiment 9, according to the charging pile operation method of embodiment 8, is characterized in that the method further comprises:
[0070] If the power-off time is shorter than the expedited charging time, the user is prompted to purchase part of the expedited charging time using money or preset points.
[0071] In the embodiment of the present application, in the actual process, the situation may occur that the power-off time is less than the expedited charging time. At this time, the expedited user still wants to expedite charging and can use cash to purchase part of the expedited charging time, thereby further meeting the user's demand for expedited charging.
[0072] Embodiment 10, according to the charging pile operation method of embodiment 6, is characterized in that it uses the charging pile operation device of embodiment 3, and after G1, the method further includes:
[0073] The receiving module 1 is used to determine whether the expedited charging time carried in the expedited request information exceeds the cumulative power supply time provided by the user. If not, the determination module 2 is triggered; otherwise, a rejection message is returned to the user and the current process is terminated.
Claims
1. A charging pile operation device, Features include: A receiving module (1) is used to receive the expedited charging request information sent by the user, retrieve the relevant data of the user from the information storage module (6), and determine whether the expedited charging request is qualified according to preset conditions. If qualified, the determination module (2) is triggered; if unqualified, the expedited charging request is rejected and feedback is given to the user; A collecting module (5) is used to collect the power-off duration of each charging pile, and connect the obtaining module (3) and the information storage module (6) through an interface, wherein the power-off duration is the duration allowed for the power-off of the charging pile provided by the online user of each charging pile; The determining module (2), after being triggered by the receiving module (1), triggers the acquiring module (3) according to the target charging pile carried in the expedited charging request information and the expedited charging time required by the user; The acquisition module (3), when triggered, acquires the power-off duration of other charging piles from the collection module (5), and then triggers the power supply module (4); The power supply module (4), after being triggered, selects to cut off the power supply of at least one of the charging piles in use according to the power-off time and the expedited charging time; and within the power-off time, allocates the charging power of the charging pile that has been cut off to the target charging pile for expedited charging; The information storage module (6) is used to store the available power supply time of the users and the remaining value of the available power supply time of each user; the information storage module (6) is connected to the receiving module (1) via an interface.
2. The charging pile operation device according to claim 1, Features: The receiving module (1) also includes a first judgment module, which is used to determine whether the user who sent the expedited request information has submitted a power-off duration in the past, and if so, trigger the determination module (2); Otherwise, a rejection message is returned to the user and the current process ends.
3. The charging pile operation device according to claim 1, Features: The receiving module (1) also includes a second judgment module, which is used to determine whether the expedited charging time carried in the expedited request information exceeds the accumulated power supply time provided by the user, and if not, trigger the determination module (2); Otherwise, a rejection message is returned to the user and the current process ends.
4. The charging pile operation device according to claim 1, Features The power supply module (4) is configured as follows: The expedited charging duration is derived from at least one of the power-off durations; Determining the charging pile that needs to be powered off and the power-off duration of the charging pile that needs to be powered off according to the expedited charging duration and the at least one power-off duration; as well as According to the charging piles that need to be powered off and the power-off duration of the charging piles that need to be powered off, the power supply of the corresponding remaining charging piles is cut off and the target charging pile is powered on.
5. A charging pile operation method, It is characterized in that It uses the charging pile operation device according to any one of claims 1 to 4, including: G1, the receiving module (1) receives the expedited request information sent by the user; G2, the determination module (2) determines the target charging pile carried by the expedited charging request information and the expedited charging time of the target charging pile; G3, the acquisition module (3) acquires the power-off duration of other charging piles; G4, the power supply module (4) selects to cut off the power supply of at least one of the charging piles in use according to the expedited charging time and the power-off time; and G5. The power supply module (4) allocates the charging power of the power-off charging pile to the target charging pile for fast charging within the power-off time.
6. The charging pile operation method according to claim 5, It is characterized in that It uses the charging pile operation device according to claim 1, and the method further includes: The collection module (5) collects the power-off duration of each charging pile according to a preset cycle.
7. The charging pile operation method according to claim 6, It is characterized in that It uses the charging pile operation device described in claim 2, and the method after G1 also includes: The judgment module determines whether the user who sent the expedited request information has submitted a power-off duration within a preset period. If yes, continue to execute G2; otherwise, end the current process.
8. The charging pile operation method according to claim 7, It is characterized in that It uses the charging pile operation device according to claim 4, and the G4 includes: The expedited charging duration is derived from at least one of the power-off durations; Determining the charging pile that needs to be powered off and the power-off duration of the charging pile that needs to be powered off according to the expedited charging duration and the at least one power-off duration; and According to the charging piles that need to be powered off and the power-off duration of the charging piles that need to be powered off, the power supply of the corresponding remaining charging piles is cut off and the target charging pile is powered on.
9. The charging pile operation method according to claim 8, Features The method further comprises: If the power-off time is shorter than the expedited charging time, the user is prompted to purchase part of the expedited charging time using money or preset points.
10. The charging pile operation method according to claim 6, It is characterized in that It uses the charging pile operation device described in claim 3, and the method after G1 also includes: The receiving module (1) is used to determine whether the expedited charging time carried in the expedited charging request information exceeds the accumulated power supply time provided by the user. If not, the determining module (2) is triggered; otherwise, a rejection message is returned to the user and the current process is terminated.
Citation Information
Patent Citations
Electric automobile charging planning method and system with wind power as priority, terminal and medium
CN109591651A
Charging control method and system for charging pile
CN109878353A
Virtual charging gun management method and system for connecting charging pile power modules in parallel
CN112606729A
Energy distribution method for new energy charging station in residential area
CN118607849A
Charging system and method
US20200215927A1
Cited By
Charging pile power failure monitoring method, system and device and storage medium
CN120318953A