Novel specialized bulk cargo shipping wharf shipping process

By using a combination of two-tail truck and straight-climb single-tail truck in a mobile ship loader and raising the tail of the dock belt conveyor, the problem of remote operation location of the ship loader is solved and the maximum shoreline resources are achieved Reduced utilization and construction costs.

CN119079599APending Publication Date: 2024-12-06CHINA COMM CONSTR FIRST HARBOR CONSULTANTS
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202411298437.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-18
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

In the prior art, the stern arrangement of mobile bulk loading machines and the hill climbing demand of belt conveyors have caused the loader to be far away from the transfer station side of the transfer station, and it is impossible to maximize the use of coastline resources, and the construction cost is also carried out. high.

Method used

The mobile ship loader with a double-tail car is combined with a straight-climbing single-tail car. Through the fold-back arrangement and the rear of the dock belt conveyor, the distance between the ship loader and the transfer station is reduced, so that the double-tail car is located Operation on the berth side.

Benefits of technology

The distance between the loader's extreme operating position on the transfer station side and the transfer station is effectively reduced, saving shoreline resources and port engineering construction costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119079599A_ABST
    Figure CN119079599A_ABST
Patent Text Reader

Abstract

The invention relates to a novel specialized bulk cargo ship loading wharf ship loading process, which comprises belt conveyors, transfer stations, movable ship loaders, rails, berths and bulk cargo ships, and the belt conveyors comprise a first belt conveyor (6) and a second belt conveyor (5); the movable ship loader comprises a first movable ship loader body (1) and a second movable ship loader body (8), the first movable ship loader body (1) is provided with double tail cars and is arranged in a turn-back mode, and the double tail cars are the first tail car (4) of the first movable ship loader body and the second tail car (3) of the first movable ship loader body. The two tail cars of the first movable ship loader (1) are both located on the second berth side, the tail of a wharf belt conveyor is lifted at the same time, the first movable ship loader (1) can move to the position close to a transfer station, and therefore the distance between the limit operation position of the ship loader on the transfer station side and the transfer station is greatly reduced, shoreline resources are saved, and the port engineering construction cost is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of ship loaders, and in particular to a new type of specialized bulk material loading terminal loading process. Background Art

[0002] In the prior art, the loading processes of specialized bulk material loading terminals mainly include fixed loader loading process, linear swing loader loading process, arc swing loader loading process and mobile loader loading process, while efficient large-scale deep-water loading terminals basically adopt mobile loader loading process, and its loading process flow is as follows: bulk materials are transported from the dock belt conveyor to the mobile loader tail car, transferred to the loader arm belt conveyor through the loader tail car, and then loaded by the loader arm belt conveyor. The mobile loader tail car of this loading process is a straight climbing single tail car, located on the transfer station side, and the tail of the dock belt conveyor is arranged on the dock. The arrangement of the loader tail car and the climbing requirements of the belt conveyor result in the extreme operating position of the loader on the transfer station side being far away from the transfer station. This section of the coastline cannot be used for loading operations, and the shoreline resources cannot be used to the maximum extent. At the same time, the cost of building this section of the coastline is also high.

[0003] For example, the Chinese utility model patent application with authorization announcement number CN 210122395 U discloses a mobile bulk material ship loader with inner harbor crane, which includes a material conveyor belt conveyor, a discharge belt conveyor, an embedded scraper, a double-beam crane, and a track-walking dust-raising device. The ship loader can achieve a large range of bulk material distribution through the linkage of the double-beam crane and the track-walking dust-raising device. The whole process does not require moving the ship, which greatly improves labor efficiency, reduces labor intensity, reduces the number of operators, and is indoor operation, not affected by weather, and can operate 24 hours a day. However, the tail car layout of the mobile bulk material ship loader and the climbing requirements of the belt conveyor cause the extreme operating position of the ship loader on the transfer station side to be far away from the transfer station. This section of the coastline cannot be used for loading operations, and the coastline resources cannot be used to the maximum extent. At the same time, the cost of building this section of the coastline is also high. Summary of the invention

[0004] In order to solve the above-mentioned technical defects existing in the prior art, the purpose of the present invention is to provide a new type of specialized bulk material loading terminal loading process, which can minimize the distance between the loader's extreme operating position on the transfer station side and the transfer station, so as to save shoreline resources and reduce port engineering construction costs.

[0005] In order to solve the above technical problems, the solution adopted by the present invention is as follows:

[0006] The present invention provides a novel specialized bulk material loading terminal loading process, which comprises a belt conveyor, a transfer station, a mobile loader, a track, a berth and a bulk carrier, wherein the belt conveyor comprises a No. 1 belt conveyor and a No. 2 belt conveyor; the mobile loader comprises a No. 1 mobile loader and a No. 2 mobile loader, wherein the No. 1 mobile loader has a double tail car and is arranged in a return type, wherein the double tail car is a first tail car of the No. 1 mobile loader and a second tail car of the No. 1 mobile loader; the No. 2 mobile loader has a straight-climbing single tail car; and the two tail cars of the No. 1 mobile loader and the tail car of the No. 2 mobile loader are arranged back to back.

[0007] Preferably, the No. 1 mobile ship loader and the No. 2 mobile ship loader can operate simultaneously or individually.

[0008] In any of the above solutions, preferably, when berth No. 1 is loaded with a ship by mobile ship loader No. 1, the following steps are adopted:

[0009] In the first step, the materials are transported to the second tail car of the No. 1 mobile ship loader through the No. 1 belt conveyor;

[0010] In the second step, the materials are transferred from the second tail car of No. 1 mobile ship loader to the belt conveyor of the first tail car of No. 1 mobile ship loader;

[0011] In the third step, the materials are transferred to the arm belt conveyor of No. 1 mobile ship loader through the first tail car belt conveyor of No. 1 mobile ship loader;

[0012] In the fourth step, the materials are loaded onto the ship by the No. 1 mobile ship loader arm belt conveyor.

[0013] In any of the above solutions, preferably, when berth No. 2 is loaded with a ship by mobile ship loader No. 2, the following steps are adopted:

[0014] In the first step, the materials are transported to the tail car of the No. 2 mobile ship loader via the No. 2 belt conveyor;

[0015] In the second step, the materials are transferred to the arm-type belt conveyor of No. 2 mobile ship loader via the tail car of No. 2 mobile ship loader;

[0016] In the third step, the materials are loaded onto the ship by the No. 2 mobile ship loader arm belt conveyor.

[0017] In any of the above schemes, it is preferred that the double tail cars of the No. 1 mobile ship loader are both located on the side of berth No. 2, and at the same time, the tail of the dock belt conveyor is raised, so that the No. 1 mobile ship loader can be moved to a place closer to the transfer station, thereby greatly reducing the distance between the extreme operating position of the ship loader on the side of the transfer station and the transfer station, so as to save shoreline resources and reduce port engineering construction costs.

[0018] In any of the above schemes, it is preferred that the theoretical heights of the tail belt surfaces of the No. 2 belt conveyor and the No. 1 belt conveyor are respectively the same as or slightly lower than the theoretical heights of the middle belt surfaces of each, so that the distance between the loader and the transfer station is minimized.

[0019] In summary, the new specialized bulk material loading terminal loading process of the present invention has the following advantages: the double tail cars of mobile loader No. 1 are both located on the side of berth No. 2, and at the same time, the tail of the dock belt conveyor is raised, so that mobile loader No. 1 can be moved to a place closer to the transfer station, thereby greatly reducing the distance between the extreme operating position of the loader on the transfer station side and the transfer station, so as to save shoreline resources and reduce port engineering construction costs.

[0020] Description of Figure Numbers

[0021] Mobile ship loader No. 1, arm belt conveyor No. 1, second tail car of mobile ship loader No. 1, belt conveyor No. 1, first tail car of mobile ship loader No. 1, belt conveyor No. 2, belt conveyor No. 1, belt conveyor No. 6, tail car of mobile ship loader No. 2, mobile ship loader No. 2, arm belt conveyor No. 2, belt conveyor No. 2, tail car of mobile ship loader No. 2, mobile ship loader No. 2, and arm belt conveyor No. 2. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] Figure 1 The figure is a schematic diagram of the process layout of the new specialized bulk material loading terminal loading process according to the present invention.

[0023] Figure 2 According to the novel specialized bulk material loading terminal loading process of the present invention Figure 1 Flowchart of the preferred embodiment shown.

[0024] Figure 3 According to the novel specialized bulk material loading terminal loading process of the present invention Figure 1 A schematic cross-sectional view of the process of the preferred embodiment is shown. DETAILED DESCRIPTION

[0025] The following description is merely exemplary in nature and is not intended to limit the disclosure, application or use. The specific implementation of the novel specialized bulk material loading terminal loading process of the present invention is further described below in conjunction with the accompanying drawings.

[0026] like Figure 1-Figure 3As shown, a schematic diagram of a preferred embodiment of the new specialized bulk material loading terminal loading process of the present invention. The new specialized bulk material loading terminal loading process of the present invention includes a belt conveyor, a transfer station, a mobile loader, a track, a berth and a bulk carrier, wherein the belt conveyor includes a No. 1 belt conveyor 6 and a No. 2 belt conveyor 5; the mobile loader includes a No. 1 mobile loader 1 and a No. 2 mobile loader 8, wherein the No. 1 mobile loader 1 has a double tail car and is arranged in a return type, wherein the double tail car is the first tail car 4 of the No. 1 mobile loader and the second tail car 3 of the No. 1 mobile loader; the No. 2 mobile loader 8 has a straight climbing single tail car; the two tail cars of the No. 1 mobile loader 1 and the tail car of the No. 2 mobile loader 8 are arranged back to back.

[0027] In this embodiment, the No. 1 mobile ship loader 1 and the No. 2 mobile ship loader 8 can operate simultaneously or independently.

[0028] In this embodiment, when berth No. 1 is loaded with a ship by mobile ship loader No. 1, the following steps are adopted:

[0029] In the first step, the material is transported to the second tail car 3 of the No. 1 mobile ship loader through the No. 1 belt conveyor 6;

[0030] In the second step, the materials are transferred to the belt conveyor 4 of the first tail car of the No. 1 mobile ship loader via the second tail car 3 of the No. 1 mobile ship loader;

[0031] In the third step, the material is transferred to the arm belt conveyor 2 of the No. 1 mobile ship loader through the first tail car belt conveyor 4 of the No. 1 mobile ship loader;

[0032] In the fourth step, the materials are loaded onto the ship by the No. 1 mobile ship loader arm belt conveyor 2.

[0033] In this embodiment, when the No. 2 berth is loaded with a ship by the No. 2 mobile ship loader 8, the following steps are adopted:

[0034] In the first step, the material is transported to the No. 2 mobile ship loader tail car 7 via the No. 2 belt conveyor 5;

[0035] In the second step, the materials are transferred to the arm-frame belt conveyor 9 of the No. 2 mobile ship loader via the tail car 7 of the No. 2 mobile ship loader;

[0036] In the third step, the materials are loaded onto the ship by the No. 2 mobile ship loader arm belt conveyor 9.

[0037] In this embodiment, the double tail cars of the No. 1 mobile ship loader 1 are both located on the side of berth No. 2, and the tail of the dock belt conveyor is raised at the same time. The No. 1 mobile ship loader 1 can be moved to a place closer to the transfer station, thereby greatly reducing the distance between the loader's extreme operating position on the transfer station side and the transfer station, so as to save shoreline resources and reduce port engineering construction costs.

[0038] In this embodiment, the theoretical heights of the tail belt surfaces of the No. 2 belt conveyor 5 and the No. 1 belt conveyor 6 are respectively the same as or slightly lower than the theoretical heights of the middle belt surfaces of the belt conveyors, thereby minimizing the distance between the ship loader and the transfer station.

[0039] It is not difficult for those skilled in the art to understand that the novel specialized bulk material loading terminal loading process of the present invention includes any combination of the various parts in this specification. Due to space limitations and to make the specification concise, these combinations are not described in detail one by one here, but after reading this specification, the scope of the present invention consisting of any combination of the various parts constituting this specification is self-evident.

Claims

1. A new type of specialized bulk material loading terminal loading process, the process comprising a belt conveyor, a transfer station, a mobile ship loader, a track, a berth and a bulk carrier, the belt conveyor comprising a No. 1 belt conveyor (6) and a No. 2 belt conveyor (5); the mobile ship loader comprising a No. 1 mobile ship loader (1) and a No. 2 mobile ship loader (8), characterized in that: The No. 1 mobile ship loader (1) has two tail cars arranged in a return type, wherein the two tail cars are the first tail car (4) of the No. 1 mobile ship loader and the second tail car (3) of the No. 1 mobile ship loader; the No. 2 mobile ship loader (8) has a straight climbing single tail car; the two tail cars of the No. 1 mobile ship loader (1) and the tail car of the No. 2 mobile ship loader (8) are arranged back to back.

2. The novel specialized bulk material loading terminal loading process as claimed in claim 1 is characterized by: The No. 1 mobile ship loader (1) and the No. 2 mobile ship loader (8) can operate simultaneously or independently.

3. The novel specialized bulk material loading terminal loading process as claimed in claim 2 is characterized by: When berth No. 1 is loaded by mobile ship loader No. 1 (1), the following steps are adopted: In the first step, the material is transported to the second tail car (3) of the No. 1 mobile ship loader via the No. 1 belt conveyor (6); In the second step, the materials are transferred from the second tail car (3) of the No. 1 mobile ship loader to the belt conveyor (4) of the first tail car of the No. 1 mobile ship loader; In the third step, the material is transferred to the arm belt conveyor (2) of the No. 1 mobile ship loader through the first tail car belt conveyor (4) of the No. 1 mobile ship loader; In the fourth step, the materials are loaded onto the ship by the No. 1 mobile ship loader arm belt conveyor (2).

4. The novel specialized bulk material loading terminal loading process as claimed in claim 2 is characterized by: When loading a ship at berth No. 2 by mobile ship loader No. 2 (8), the following steps are adopted: In the first step, the material is transported to the tail car of the No. 2 mobile ship loader (7) via the No. 2 belt conveyor (5); In the second step, the materials are transferred to the arm-frame belt conveyor (9) of the No. 2 mobile ship loader via the tail car (7) of the No. 2 mobile ship loader; In the third step, the materials are loaded onto the ship by the No. 2 mobile ship loader arm belt conveyor (9).

5. The novel specialized bulk material loading terminal loading process as claimed in claim 1 or 2, characterized in that: The double tail cars of the No. 1 mobile ship loader (1) are both located on the side of the No. 2 berth, and the tail of the dock belt conveyor is raised at the same time, so that the No. 1 mobile ship loader (1) can be moved to a place closer to the transfer station.

6. The novel specialized bulk material loading terminal loading process as claimed in claim 1 is characterized by: The theoretical heights of the belt surfaces at the rear ends of the No. 2 belt conveyor (5) and the No. 1 belt conveyor (6) are respectively the same as or slightly lower than the theoretical heights of the belt surfaces at the middle ends thereof.

Citation Information

Patent Citations

  • Tail vehicle device, ship loader and stacker-reclaimer

    CN203269121U

  • Tripper car device and ship loader

    CN204038656U

  • Shipment unit

    CN205526799U

  • Tail-to-tail arrangement system for double bucket wheels of strip-shaped coal yard

    CN208994716U