Soft stratum reinforcing method based on pile foundation

By lifting and spraying a mixed liquid of curing agent and water on the drill pipe, the soil in the drill hole is fluidized, and the prefabricated solidified soil piles are used for static pressure insertion, which solves the problems of collapse holes and shrinkage in pile foundation reinforcement, and realizes the problem of collapse holes and shrinkage. It has efficient and low-cost weak strata reinforcement effect.

CN119083415APending Publication Date: 2024-12-06SHANDONG HI SPEED CONSTRUCTION MANAGEMENT GROUP CO LTD +2
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411424556.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-12
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

The existing pile foundation reinforcement methods are prone to collapse and shrinkage during the construction process, and the construction is complex and costly, so it cannot effectively ensure the reinforcement effect of weak formations.

Method used

Use the drill pipe to lift the drill pipe and spray the mixed liquid of curing agent and water to turn the soil in the drill into a fluid state, avoiding collapse and necking, and use prefabricated solidified soil piles for static pressure insertion, simplifying the construction steps and reducing cost.

Benefits of technology

It effectively avoids hole collapse and neck shrinkage, simplifies the construction process, improves the friction resistance and bearing capacity of the pile foundation, ensures the reinforcement effect and bearing capacity of the weak formation, and reduces construction costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119083415A_ABST
    Figure CN119083415A_ABST
Patent Text Reader

Abstract

The invention relates to a soft stratum reinforcing method based on a pile foundation. The soft stratum reinforcing method comprises the following steps that drilling operation is conducted at a set point position; after drilling to the set depth, a drill rod of the drilling machine is lifted, and while the drill rod is lifted, a mixed liquid of a curing agent and water is sprayed out of the bottom of the drill rod in a rotary spraying mode so that the soil body reserved in the drill hole can be changed into a flow state, and a flow-state solidified soil liquid is formed; after the liquid level of the fluid-state solidified soil liquid and the bottom face of the drill hole reach a set distance, spraying of the mixed liquid of the curing agent and the water is stopped, and the drill rod continues to be lifted upwards till leaving the drill hole; and the multiple prefabricated piles are pressed into the drilled hole section by section till the top face of the uppermost prefabricated solidified soil pile is flush with the ground. By the adoption of the reinforcing method, the reinforcing effect is good.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of soft foundation reinforcement processing, and in particular to a soft stratum reinforcement method based on pile foundation. Background Art

[0002] The statements herein merely provide background information related to the present invention and do not necessarily constitute prior art.

[0003] In the field of engineering construction, when building (structure) construction is carried out on the upper part of a soft foundation with low strength and high compression, the soil layer needs to be treated to obtain a higher foundation bearing capacity and reduce post-construction settlement. Commonly used soft foundation treatment methods include: replacement method, strong tamping method, preloading method and pile foundation reinforcement method. Powder injection piles, lime soil compaction piles, cement mixing piles and CFG piles are often used as vertical reinforcements to improve the bearing capacity of the foundation during pile foundation reinforcement. However, the above-mentioned pile foundation reinforcement is all cast on the construction site, and the quality of the pile foundation cannot be guaranteed, and thus the reinforcement effect of the soft stratum cannot be guaranteed. In addition, the above-mentioned pile foundation reinforcement will have phenomena such as hole collapse and diameter shrinkage, which affects the reinforcement construction. The current precast piles can guarantee the reinforcement effect when used for soft stratum reinforcement, but the precast pile construction requires construction steps such as bottom cleaning, which is complicated to construct, and the precast piles are mostly reinforced concrete pipe piles, and the construction cost is high. Summary of the invention

[0004] In view of the shortcomings of the prior art, the purpose of the present invention is to provide a soft stratum reinforcement method based on pile foundation, which avoids phenomena such as hole collapse and diameter shrinkage, and does not require construction steps such as bottom cleaning. The construction cost is low and the reinforcement effect can be guaranteed.

[0005] In order to achieve the above object, the present invention is implemented through the following technical solutions:

[0006] An embodiment of the present invention provides a method for reinforcing a soft stratum based on a pile foundation, comprising the following steps:

[0007] Carry out drilling operations at set points;

[0008] After drilling to the set depth, the drill rod of the drilling rig is lifted up. At the same time, the bottom of the drill rod sprays out a mixed liquid of curing agent and water to make the soil remaining in the borehole fluid, forming a fluidized solidified soil liquid;

[0009] When the level of the fluidized solidifying soil liquid reaches the set distance from the bottom of the borehole, the spraying of the mixed liquid of the solidifying agent and water is stopped, and the drill rod continues to be lifted up until it leaves the borehole;

[0010] Press multiple prefabricated piles into the borehole section by section until the top surface of the uppermost prefabricated solidified soil pile is flush with the ground.

[0011] Optionally, set the distance to half the drilling depth.

[0012] Optionally, the prefabricated piles are prefabricated cured soil piles.

[0013] Optionally, the prefabricated solidified soil piles are made by mixing excavated soil with a soil solidifying agent and placing the mixture into a mold, and then extruding the mixture using solidified soil pile extrusion equipment.

[0014] Optionally, multiple prefabricated piles are pressed into the borehole section by section by static pressure.

[0015] Optionally, before the precast pile is pressed into the borehole, a guide mechanism is provided at the entrance of the borehole, and the precast pile passes through the guide mechanism and is pressed into the borehole.

[0016] Optionally, the guide mechanism includes a guide cylinder, which is used to be arranged at the entrance of the drill hole. A support plate is fixed to the outer cylinder surface of the guide cylinder, and the support plate is used to be placed on the ground to support the guide cylinder. The guide cylinder part below the support plate is used to be inserted into the drill hole.

[0017] Optionally, a plurality of lifting hooks are provided on the support plate.

[0018] Optionally, before the prefabricated pile is pressed into the drilled hole, a pilot block with a cone-shaped structure is placed inside the drilled hole, with the pointed structure of the pilot block facing downward.

[0019] Optionally, before the precast pile is pressed in, a solid block is arranged on the top surface of the precast pile, and the static pressure device presses the precast pile into the borehole through the solid block.

[0020] The beneficial effects of the present invention are as follows:

[0021] 1. The reinforcement method of the present invention comprises the following steps: a mixed liquid of water and a curing agent is jetted out by rotary jetting while the drill rod is lifted, that is, a fluidized slurry is injected into the borehole while the drill rod is lifted. The presence of the slurry supports and protects the borehole, thereby avoiding the occurrence of undesirable phenomena such as hole collapse and neck shrinkage. At the same time, the sprayed mixed liquid of water and a curing agent is used to convert the reserved soil in the borehole into fluidized soil, thereby avoiding bottom cleaning construction and simplifying the construction steps. At the same time, the precast pile and the fluidized soil are used together. After the precast pile is placed in the borehole, the fluidized solidified soil can fully fill the gap between the borehole wall and the precast pile, thereby improving the level of friction resistance of the pile foundation. Moreover, the bearing capacity of the precast pile relative to the cast-in-place pile can be guaranteed, thereby jointly ensuring the reinforcement effect and bearing capacity of the soft stratum.

[0022] 2. In the reinforcement method of the present invention, the prefabricated piles adopt prefabricated solidified soil piles, which have low production costs compared with traditional prefabricated piles, thereby reducing the cost of the entire reinforcement construction.

[0023] 3. In the reinforcement method of the present invention, after the drill rod is pulled out of the borehole, a guide mechanism is arranged at the entrance of the borehole, and the guide mechanism includes a guide cylinder and a support plate. The guide cylinder portion below the support plate is inserted into the borehole, which guides the precast pile to ensure the verticality of the precast pile and, together with the slurry, supports the borehole, thereby avoiding undesirable phenomena such as hole collapse and neck shrinkage. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] The accompanying drawings in the specification, which constitute a part of the present invention, are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute improper limitations on the present invention.

[0025] Figure 1 is a flow chart of the method of embodiment 1 of the present invention;

[0026] Figure 2 is a schematic diagram of a guide mechanism of Embodiment 1 of the present invention;

[0027] Figure 3 This is a schematic diagram of the pilot block structure of Example 1 of the present invention;

[0028] Figure 4 This is a schematic diagram of the solid block structure of Example 1 of the present invention;

[0029] Figure 5 This is a schematic diagram of a prefabricated solidified soil pile according to Embodiment 1 of the present invention;

[0030] Figure 6 Schematic diagram of different types of composite pile foundations formed in Example 1 of the present invention;

[0031] Among them, 1. Prefabricated solidified soil piles, 2. Guiding mechanism;

[0032] 201. guide cylinder, 202. support plate, 203. lifting hook, 204. solid block, 205. guide block;

[0033] 301. Auger drilling machine, 302. Drill rod, 303. Liquid storage tank, 304. Drilling hole, 305. Fluidized solidified soil, 306. Static pressure equipment. DETAILED DESCRIPTION

[0034] Example 1

[0035] This embodiment provides a soft stratum reinforcement method based on pile foundation, such as Figure 1 As shown, the following steps are included:

[0036] Step 1: Level the construction site to facilitate the construction machinery to enter the site for operation. The construction machinery can be a spiral drill, and the leveling method can be the existing technology, which will not be described in detail here.

[0037] Step 2: The spiral drilling machine 301 enters the site and performs drilling operations at the set points to loosen the soil layer at the pile foundation position and drill holes. After drilling to the set depth, the drill rod 302 begins to be lifted up. While being lifted up, a mixed liquid of curing agent and water is sprayed out from the bottom of the drill rod 302 to transform the loose soil remaining in the borehole into fluidized solidified soil 305, forming a fluidized solidified soil liquid.

[0038] As the drill rod 302 is lifted, a mixed liquid of water and curing agent is jetted out, that is, a fluid slurry is injected into the borehole as the drill rod is lifted. The presence of the slurry supports and protects the borehole, thereby avoiding the occurrence of undesirable phenomena such as hole collapse and neck shrinkage.

[0039] When the liquid level of the fluidized solidifying soil liquid reaches a set distance from the bottom hole surface of the borehole 304, the spraying of the mixed liquid of the solidifying agent and water is stopped.

[0040] Further, the distance is set to be half of the depth of the drill hole 304 .

[0041] In this embodiment, the spiral drilling machine 301 can adopt existing equipment. The bottom end of the drill rod is provided with a drill bit, and the bottom end of the drill rod is provided with an outlet for a mixed liquid of a curing agent and water. The top end of the drill rod 302 is connected to the power system and is connected to the liquid storage barrel 303 through a pipeline and a pump. The liquid storage barrel 303 stores a mixed liquid of a curing agent and water. The connection method between the pipeline and the top end of the drill rod 302 can adopt existing technology and will not be described in detail here.

[0042] Step 3: Continue to lift the drill rod 302 until it leaves the borehole, and then install the guide mechanism 2 at the entrance of the top of the borehole.

[0043] In this embodiment, Figure 2 As shown, the guide mechanism 2 includes a guide cylinder 201, which is made of a steel cylinder with a length of 4 m. A support plate 202 is fixed to the outer surface of the steel cylinder. The support plate 202 is perpendicular to the axis of the guide cylinder 201. The support plate 202 is made of a steel plate. The distance between the support plate 202 and the top of the guide cylinder 201 is 1.5 m, and the area of ​​the support plate 202 is 1.5 m. 2 The support plate 202 is used to be placed on the ground to maintain the stability and verticality of the guide cylinder 201.

[0044] The guide cylinder portion below the support plate 202 is used to be inserted into the borehole 304. While guiding the construction of the precast pile and ensuring the verticality of the precast pile, it also plays a supporting role for the borehole together with the slurry, avoiding undesirable phenomena such as hole collapse and neck shrinkage.

[0045] Furthermore, a plurality of lifting hooks 203 are provided on the upper surface of the support plate 202 at equal intervals in the circumferential direction, so as to facilitate lifting the guide mechanism using a lifting device.

[0046] Step 4: After the construction of the guide mechanism 2 is completed, the construction of pressing multiple precast piles into the drilled holes section by section begins until the top surface of the uppermost precast pile is flush with the ground.

[0047] In this embodiment, Figure 5 As shown, the prefabricated pile adopts a prefabricated cured soil pile 1. The preparation method of the prefabricated cured soil pile 1 can adopt the existing technology. The excavated soil and the soil curing agent are evenly mixed and placed into a mold, and then extruded by a cured soil pile extrusion device. The prefabricated cured soil pile 1 has a length of 2.0m-2.5m, a diameter of 40cm, a pile body mass of 450kg, and a pile body compressive strength of up to 8Mpa. Compared with the traditional cast-in-place pile foundation, it can ensure the reinforcement effect of soft strata.

[0048] Before the precast pile is pressed in, the pilot block 205 is first inserted into the borehole 304 through the guide cylinder 201. Figure 3 As shown, the pilot block 205 adopts a conical structure, with its pointed structure arranged downward to facilitate the penetration of the precast pile in the borehole.

[0049] After the pilot block 205 is placed, the existing static pressure equipment 306 is used to statically press the multiple prefabricated solidified soil piles 1 into the borehole 304 section by section. During the pressing process, the guide cylinder 201 is used to vertically correct the multiple sections of the prefabricated solidified soil piles 1 to achieve vertical pressing to ensure construction quality. The pilot block 205 is used to improve the penetration ability and facilitate the pressing of the prefabricated piles.

[0050] Before a precast pile is driven in, a solid block 204 is placed on the top surface of the precast pile. Figure 4 As shown, the solid block 204 is a cylindrical steel block, and the pressing mechanism of the static pressure device 306 applies pressure to the precast pile through the solid block 204 to press the precast pile into the borehole 304 .

[0051] In this embodiment, while the precast pile is pressed into the borehole 304, the fluidized solidified soil fully fills the gap between the precast pile and the borehole wall, thereby increasing the level of friction resistance of the pile foundation and further increasing the bearing capacity of the soft soil layer.

[0052] Step 5: After the construction of multiple precast piles is completed, the guide cylinder 201 is pulled out by a lifting device and transferred to a new construction site. Steps 2 to 4 are repeated until the construction of all the designed composite pile sites on the construction site is completed. After the curing of the fluidized solidified soil is completed, the next step of operation can be carried out.

[0053] In this embodiment, Figure 6As shown, the ratio between the diameter of the precast pile and the diameter of the drilled hole can be set according to actual needs. At the same time, the precast pile can also be pressed into a depth deeper than the depth of the drilled hole to form different types of composite pile foundations. Those skilled in the art can set it according to actual needs, which will not be described in detail here.

[0054] By adopting the construction method of this embodiment, fluid slurry is injected into the borehole while the drill rod is lifted. The presence of the slurry and the guide tube supports and protects the borehole, avoiding the occurrence of undesirable phenomena such as hole collapse and neck shrinkage. At the same time, the sprayed water and curing agent mixed liquid are used to convert the reserved soil in the borehole into fluid soil, avoiding bottom cleaning construction and simplifying the construction steps. At the same time, precast piles and fluid soil are used together. After the precast piles are placed in the borehole, the fluidized solidified soil can fully fill the gap between the borehole wall and the precast pile, thereby improving the level of friction resistance of the pile foundation. In addition, the precast piles have better bearing capacity than cast-in-place piles, which together ensure the reinforcement effect and bearing capacity of soft strata.

[0055] The above description is only the preferred embodiment of the present application and is not intended to limit the present application. For those skilled in the art, the present application may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.

Claims

1. A method for reinforcing soft strata based on pile foundation, characterized in that: The following steps are involved: Carry out drilling operations at set points; After drilling to the set depth, the drill rod of the drilling rig is lifted up. At the same time, the bottom of the drill rod sprays out a mixed liquid of curing agent and water to make the soil reserved in the borehole fluid, forming a fluidized solidified soil liquid; When the level of the fluidized solidifying soil liquid reaches the set distance from the bottom of the borehole, the spraying of the mixed liquid of the solidifying agent and water is stopped, and the drill rod continues to be lifted up until it leaves the borehole; Press multiple prefabricated piles into the borehole section by section until the top surface of the uppermost prefabricated solidified soil pile is flush with the ground.

2. A method for reinforcing soft strata based on pile foundation as claimed in claim 1, characterized in that: Set the distance to half the drilling depth.

3. A method for reinforcing soft strata based on pile foundation as claimed in claim 1, characterized in that: The prefabricated piles are prefabricated solidified soil piles.

4. A method for reinforcing soft strata based on pile foundation as claimed in claim 3, characterized in that: The prefabricated solidified soil pile is made by mixing excavated soil with a soil solidifying agent and placing the mixture into a mold, and then extruding the mixture using solidified soil pile extrusion equipment.

5. A method for reinforcing soft strata based on pile foundation as claimed in claim 1, characterized in that: The multiple precast piles are pressed into the borehole section by section by static pressure.

6. A method for reinforcing soft strata based on pile foundation as claimed in claim 1, characterized in that: Before the precast pile is pressed into the borehole, a guide mechanism is arranged at the entrance of the borehole, and the precast pile passes through the guide mechanism and is pressed into the borehole.

7. A method for reinforcing soft strata based on pile foundation as claimed in claim 6, characterized in that: The guide mechanism includes a guide cylinder, which is used to be arranged at the entrance of the drill hole. A support plate is fixed to the outer cylinder surface of the guide cylinder, and the support plate is used to be placed on the ground to support the guide cylinder. The guide cylinder part below the support plate is used to be inserted into the drill hole.

8. A method for reinforcing soft strata based on pile foundation as claimed in claim 7, characterized in that: A plurality of lifting hooks are arranged on the support plate.

9. A method for reinforcing soft strata based on pile foundation as claimed in claim 1, characterized in that: Before the precast pile is pressed into the borehole, a pilot block with a cone-shaped structure is placed inside the borehole, with the pointed structure of the pilot block facing downward.

10. A method for reinforcing soft strata based on pile foundation as claimed in claim 1, characterized in that: Before the precast pile is pressed in, a solid block is set on the top surface of the precast pile, and the static pressure equipment presses the precast pile into the drilled hole through the solid block.

Citation Information

Cited By

  • Offshore soft soil foundation solidified soil in-situ reinforcement system and implementation method

    CN120520215A