Cutting slope protection structure synchronous with slope excavation and construction method

Through the arrangement of anchor blocks and connecting beams and BIM model analysis, synchronous reinforcement during slope excavation is achieved, the problem of delayed slope reinforcement is solved, the protection effect and stability are improved, and it is suitable for areas with poor geological conditions.

CN119083460APending Publication Date: 2024-12-06CHINA FIRST METALLURGICAL GROUP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411278036.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-12
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

The existing slope reinforcement method cannot be carried out simultaneously with slope excavation, resulting in delayed protection, poor protection effect and difficult to apply to areas with poor geological conditions.

Method used

Multiple anchor blocks are arranged in plum blossoms to form a diamond area, and fixed piles and second connecting beams are set up in the area. Simulation and analysis are carried out in combination with the BIM model to obtain the best arrangement of prefabricated anchor cables, and timely excavation of slopes Install prestressed anchor cables and reinforced structures to achieve synchronization of slope construction and protection.

Benefits of technology

It improves the stability of the slope, reduces the risk of landslides and collapses, improves the protective effect, and provides timely support for the slope. It is suitable for areas with poor geological conditions.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119083460A_ABST
    Figure CN119083460A_ABST
Patent Text Reader

Abstract

The cutting slope reinforcing structure comprises at least one slope reinforcing unit, each slope reinforcing unit comprises anchoring blocks, first connecting beams, second connecting beams, fixing piles and detachable formworks, the anchoring blocks are arranged in a quincunx shape, the first connecting beams are arranged between the two adjacent anchoring blocks, the second connecting beams are arranged between the two adjacent anchoring blocks, and the fixing piles are arranged between the first connecting beams and the second connecting beams. The fixing piles are connected to form a polygon which is arranged in an area formed by the first connecting beams, and the second connecting beams are arranged on the fixing piles in a crossed mode. The fixing piles are arranged in the rhombic area formed by the anchoring blocks and the first connecting beams, the slope area is divided into the small areas, then the second connecting beams are arranged to connect the small areas into a whole, and the stability of the reinforcing structure is improved; the cutting slope reinforcing structure is installed once a flat surface for anchor cable construction is formed, so that synchronization of slope construction and protection is achieved, and the problem of protection lag caused by reinforcement after slope excavation is completed is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of slope protection, and more specifically, relates to a road cutting slope reinforcement structure and a construction method that are synchronized with slope excavation. Background Art

[0002] Cut slopes are slopes formed by excavating the ground to open up a road surface during road construction. Specifically, when a highway or railway needs to be built on higher terrain, engineers will lower the height of the area by excavating soil or rocks to form a relatively flat section of road. This excavation process will create slopes on both sides or one side of the road. These slopes are called "cut slopes."

[0003] The stability of the cutting slope is directly related to the safe operation of the road. In the current construction of cutting slopes, slope protection work is usually carried out after the slope is completely excavated. For those cutting slopes with poor geological structures, especially those areas where rock joints and fissures are well developed and widely distributed, this traditional method has obvious shortcomings. During the excavation process, the slopes excavated in advance will be exposed for a long time, which not only accelerates the weathering and erosion process, but also may cause water infiltration, thereby increasing the risk of landslides and collapses. If timely and effective reinforcement measures are not taken, these slopes are prone to instability during or after construction, causing serious safety accidents and environmental damage.

[0004] Patent number: 202110012157.6, named as an invention patent for a high-safety reinforcement device for geotechnical engineering slopes. Anchor pipes, positioning sleeves, limit plates, anchors, anchor blocks and other structures are arranged on the slope after excavation to cooperate with each other to achieve stable and convenient installation and locking and limiting of the reinforcement device. The sealing layer can ensure that the entire structure can be stably fixed in the slope, playing a stable reinforcement role. However, the entire reinforcement construction process is carried out after the slope is completely excavated, and the reinforcement device has a complex structure and is difficult to construct.

[0005] Patent number: 202311446420.8, title: An invention patent for a reinforcement structure and method for shallow sliding type soft rock slopes. Before slope construction, multiple micro-piles are set at intervals on the shallow sliding type soft rock slopes to solve the problem of instantaneous instability during slope excavation. It cannot achieve the effect of long-term reinforcement of the slope.

[0006] It can be seen from this that the current slope reinforcement methods often have a lag, that is, the reinforcement work cannot be carried out simultaneously with the excavation work, resulting in a long time for the implementation of protection measures, and it is impossible to provide the necessary support for the slope in time. The stability is insufficient, the protection effect is difficult to guarantee, and it cannot be applied to areas with poor geological conditions of the slope. Summary of the invention

[0007] In view of the fact that the existing slope reinforcement work cannot be carried out synchronously with the slope excavation work, resulting in delayed protection, poor protection effect and difficulty in application in areas with poor slope geological conditions, the present invention provides a cutting slope reinforcement structure and construction method synchronized with slope excavation. By arranging multiple anchor blocks in a plum blossom pattern and forming a diamond-shaped area with the first connecting beam, fixed piles are set in the diamond-shaped area to divide the slope area into stable small areas, and then the second connecting beam is set to connect the small areas into a whole, increasing the stability of the entire reinforcement structure, reducing the risks of landslides and collapses, and improving the protection effect. By collecting information such as the slope shape and geological conditions before excavation, establishing a BIM model for simulation analysis, obtaining the optimal layout method of precast anchor cables, and installing prestressed anchor cables and the cutting slope reinforcement structure immediately when a flat surface for anchor cable construction is formed during the cutting slope excavation, the synchronization of slope construction and protection is achieved, and the problem of delayed protection caused by reinforcement after the slope excavation is completed is solved.

[0008] To achieve the above object, according to the first aspect of the present invention, a cutting slope reinforcement structure is provided, which includes at least one slope reinforcement unit. The slope reinforcement unit includes anchor blocks, a first connecting beam, a second connecting beam, fixed piles and a detachable formwork; The anchor blocks are arranged in a plum blossom pattern. The first connecting beam is arranged between two adjacent anchor blocks. The first connecting beam and the anchor blocks are connected into one body through a detachable formwork. The fixed piles are arranged in the area formed by the first connecting beam and are connected in sequence to form a polygon. There are multiple second connecting beams, and two of them form a column, and two columns are arranged in a cross on the fixed piles. One end of the second connecting beam is connected into one body with the second connecting beam in the same column through a detachable formwork, and the other end is connected to the first connecting beam through a detachable formwork. The second connecting beam is used to increase the stability of the entire slope reinforcement unit.

[0009] Preferably, the fixed pile includes a fixing plate, a first loop buckle and a second loop buckle; The first loop buckle and the second loop buckle are oppositely arranged on both sides of the fixing plate, and the bottoms of both sides of the fixing plate are in a pointed structure.

[0010] Preferably, the fixed piles are connected in sequence to form a "field" shape and are arranged in the diamond-shaped area formed by the first connecting beam. The intersection center of the two columns of the second connecting beams coincides with the center of the "field" shape.

[0011] Preferably, the anchor block is a precast concrete block, and anchor cable holes are provided at the four corners of the anchor block for fixing the anchor block on the cutting slope.

[0012] Preferably, both the first connecting beam and the second connecting beam are precast concrete beams. Anchor holes are provided at the centers of the first connecting beam and the second connecting beam, and the anchor holes are used to fix the first connecting beam and the second connecting beam to the cutting slope.

[0013] Preferably, the detachable formwork is rectangular in shape and is made of steel or wood.

[0014] According to the second aspect of the present invention, a construction method for a cutting slope reinforcement structure synchronized with slope excavation is provided, which is realized by applying the cutting slope reinforcement structure, and specifically includes the following steps: S1. Slope construction design: Before the excavation of the cutting slope, use a three-dimensional laser scanner and an unmanned aerial vehicle (UAV) aerial photography technology to measure the actual condition of the slope. Combine the geological radar detection data and use the BIM technology for simulation analysis to determine the spacing of the prestressed anchor cables and the dimensions of each precast component, and manufacture the precast components; S2. Prestressed anchor cable construction: When the cutting slope is excavated, immediately install the prestressed anchor cables every time a flat surface for anchor cable construction is formed. S3. Installation of the anchorage block and the first connecting beam: Install the anchorage block by passing the prestressed anchor cable through the anchor hole. For every two installed anchorage blocks, place the first connecting beam between these two anchorage blocks and build a detachable formwork. Pour concrete into the detachable formwork to connect the first connecting beam and the anchorage block into one body; S4. Installation of the fixed piles: Drive a plurality of fixed piles in sequence within the area formed by the first connecting beams. The fixed piles are connected into a "field" shape through the first loop fasteners and the second loop fasteners in the positive and negative directions, dividing the rhombus area into each part; S5. Installation of the second connecting beam: Immediately hoist and fix the second connecting beam every time the construction of the fixed piles in one area is completed. S6. Slope maintenance: Arrange a plurality of slope reinforcement units in an array on the cutting slope according to the design requirements, and carry out soil cultivation and grass planting in each area.

[0015] Preferably, in the step S1, the following steps are specifically included: S1-1. Data collection: Use a three-dimensional laser scanner to scan the area to be constructed in all directions, control the UAV to carry a high-definition camera to take multi-angle photos of the slope, and use the geological radar technology to detect the internal structure of the slope to understand the rock layer distribution and crack information; S1-2. Establish a BIM model: Import the collected data into the BIM software to create a digital model, which includes the geometric shape of the slope and also includes information such as material properties and mechanical properties; S1-3. BIM simulation analysis: Use the BIM model to conduct simulation analysis under various working conditions, such as stability analysis after slope excavation and the optimal arrangement of prestressed anchor cables, to further determine the optimal spacing of prestressed anchor cables and the size of prefabricated components.

[0016] Preferably, in S1-3, the prefabricated component includes an anchor block, a first connecting beam and a second connecting beam.

[0017] Preferably, in S3 and S5, the first connecting beam and the second connecting beam are first embedded with fixed steel bars before installation, and prestressed anchor cables are inserted into the anchor rod holes, and then grouting is performed to fix them. After the prestressed anchor cables are constructed, a detachable formwork is set up to cast concrete to cast the first connecting beam and the anchor block, the first connecting beam and the second connecting beam, and the second connecting beam in the same column as a whole, and the detachable formwork is removed after the concrete reaches the designed strength value.

[0018] In general, the above technical solutions conceived by the present invention can achieve the following beneficial effects compared with the prior art: A road cutting slope reinforcement structure and construction method synchronized with slope excavation, aimed at the existing slope reinforcement work cannot be carried out synchronously with the slope excavation work, resulting in delayed protection, poor protection effect and difficulty in application in areas with poor slope geological conditions 1. The road cutting slope reinforcement structure of the present invention is arranged in a plum blossom shape by a plurality of anchor blocks, and forms a diamond area with a first connecting beam. Fixed piles are arranged in the diamond area to divide the slope area into stable small areas, and then a second connecting beam is arranged to connect the small areas as a whole, thereby increasing the stability of the entire reinforcement structure, reducing the risk of landslide and collapse, and improving the protection effect.

[0019] 2. The road cutting slope reinforcement structure of the present invention provides anchor holes in the anchor blocks, and anchor holes are provided at the centers of the first connecting beam and the second connecting beam to facilitate the insertion of prefabricated anchor cables. Combined with fixed piles, it can be used in areas with poor geological conditions of the slopes.

[0020] 3. The method for constructing a cutting slope reinforcement structure synchronized with slope excavation of the present invention collects information on the slope shape, geological conditions, etc. before excavation, establishes a BIM model for simulation analysis, and then obtains the optimal arrangement of prefabricated anchor cables. When the cutting slope is excavated, prestressed anchor cables and cutting slope reinforcement structures are immediately installed whenever a flat surface is formed for anchor cable construction, thereby achieving synchronization of slope construction and protection, and solving the problem of delayed protection caused by reinforcement after slope excavation is completed. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Figure 1 It is a schematic diagram of the connection of the road cutting slope reinforcement structure of the present invention.

[0022] Figure 2 It is a schematic diagram of the structure of the slope reinforcement unit of the present invention.

[0023] Figure 3 Schematic diagram of the connection between the first connecting beam and the anchor block.

[0024] Figure 4 Schematic diagram of the connection between two adjacent anchor blocks.

[0025] Figure 5 Schematic diagram of the installation of fixed piles in the diamond-shaped area.

[0026] Figure 6 It is a schematic diagram of the connection between the first connecting beam and the second connecting beam.

[0027] Figure 7 Schematic diagram of the anchor block structure.

[0028] Figure 8 Schematic diagram of the fixed pile structure.

[0029] Fig. 9 The present invention is a flow chart of a construction method of a cutting slope reinforcement structure synchronized with slope excavation.

[0030] In the figure: 1. anchor block; 2. first connecting beam; 3. second connecting beam; 4. fixed pile; 4-1. fixed plate; 4-2. first back-shaped buckle; 4-3. second back-shaped buckle; 5. detachable formwork; 6. anchor cable hole; 7. anchor rod hole. DETAILED DESCRIPTION

[0031] In order to make the purpose, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention. In addition, the technical features involved in the various embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other.

[0032] Depend on Figures 1 to 8 As shown, the present invention provides a road cutting slope reinforcement structure, including at least one slope reinforcement unit, the number of which can be determined according to the specific slope conditions, and multiple slope reinforcement units are arranged in an array on the slope, and the slope reinforcement unit includes an anchor block 1, a first connecting beam 2, a second connecting beam 3, a fixed pile 4 and a detachable template 5; There are four anchoring blocks 1 arranged in a plum blossom shape. The first connecting beam 2 is arranged between two adjacent anchoring blocks 1. The two ends of the first connecting beam 2 and the anchoring blocks 1 are connected as a whole through a detachable formwork 5. The first connecting beam 2 and the anchoring blocks 1 are connected to form a rhombus area. The fixed piles 4 are sequentially connected to form a "field" shape and are arranged in the rhombus area formed by the first connecting beam 2. There are four second connecting beams 2, and two of them form a column. The two columns are arranged in a cross on the fixed piles 4. One end of the second connecting beam 2 is connected to the second connecting beam 2 in the same column as a whole through a detachable formwork 5, and the other end is connected to the first connecting beam 2 as a whole through a detachable formwork 5. The intersection center of the two columns of the second connecting beam 3 coincides with the center of the "field" shape. The second connecting beam 2 is used to increase the stability of the entire slope reinforcement unit.

[0033] The anchoring block 1 is precast with concrete. The anchoring block 1 has a rectangular cross-section. Each anchoring block 1 has four corners, and a cable hole 6 is opened at each corner. The cable hole 6 is used to fix the anchoring block 1 on the cutting slope. The aperture of the cable hole 6 is determined according to the diameter of the prestressed cable. The main function of the anchoring block 1 is to firmly fix it on the cutting slope through the prestressed cable, playing a reinforcement role.

[0034] There are multiple first connecting beams 2 and second connecting beams 3, and they are all precast with concrete. Anchor holes 7 are opened at the centers of the first connecting beam 2 and the second connecting beam 3. The anchor holes 7 are used to fix the first connecting beam 2 and the second connecting beam 3 on the cutting slope. The aperture of the anchor hole 7 is determined according to the diameter of the prestressed cable.

[0035] The fixed pile 4 includes a fixed plate 4-1, a first loop buckle 4-2, and a second loop buckle 4-3. The first loop buckle 4-2 and the second loop buckle 4-3 are welded to the two sides of the fixed plate 4-1 relatively. The bottoms of the two sides of the fixed plate 4-1 are in a pointed structure, which is convenient for the fixed plate 4 to be inserted into the cutting slope. The fixed piles 4 are connected to each other through the first loop buckle 4-2 and the second loop buckle 4-3 to form an integral framework, and at the same time, the rhombus area is divided into small pieces to increase the rigidity of the slope reinforcement unit. The second connecting beam 3 is arranged on the fixed pile 4 to connect the small pieces inside the rhombus area into a whole, increasing the stability of the overall reinforcement unit.

[0036] The detachable formwork 5 is rectangular in shape, and the material includes but is not limited to steel or wood, and rubber formwork can also be used. The detachable formwork 5 enables the first connecting beam 2 and the second connecting beam 3 to be flexibly installed and disassembled, facilitating construction and maintenance.

[0037] As Fig. 9 shown, a construction method for a cutting slope reinforcement structure synchronized with slope excavation, using the above cutting slope reinforcement structure, specifically includes the following steps: S1. Slope construction design: Before excavating the cutting slope, use 3D laser scanners and drone aerial photography technology to measure the actual slope conditions. Combined with geological radar detection data, use BIM technology for simulation analysis to determine the spacing of prestressed anchor cables and the size of each prefabricated component, and make prefabricated components. The specific steps are as follows: S1-1. Data collection: Use a 3D laser scanner to perform a full-scale scan of the area to be constructed to ensure that all slope surfaces are covered. Multiple scans can be performed to ensure complete data is obtained, and the collected data is saved in a computer. Use point cloud processing software to denoise, filter and classify the scanned point cloud data to extract useful information.

[0038] Control the drone carrying a high-definition camera to take photos of the slope from multiple angles. The photos should have enough overlap to facilitate post-processing. All the photos taken should be saved and marked. Use image processing software to stitch the pictures taken by the drone to form a panorama, and correct the image to eliminate distortion.

[0039] Geological radar technology is used to scan along the slope surface or borehole, record the reflected signals at different depths underground, detect the internal structure of the slope, understand the distribution of rock layers and cracks, and record the detection results. The reflected signals detected by the radar are analyzed, and a map of the underground rock layer structure is drawn to identify potential unstable areas.

[0040] S1-2. Establish BIM model: Import the processed data in S1-1 into BIM software, such as Revit, ArchiCAD, etc. Import the previously processed point cloud data and images, and start to build the basic three-dimensional model of the slope. According to the results of geological radar detection, further refine the model, add information such as underground rock structure and cracks, and then add physical properties to each element in the model, such as material type, density, elastic modulus, etc.

[0041] S1-3, BIM simulation analysis: simulate different excavation schemes in the BIM model, analyze the stability of the slope under each scheme, and determine the optimal spacing of prestressed anchor cables and the size of prefabricated components by simulating prestressed anchor cable layout schemes in different positions and with different spacings. The prefabricated components include anchor blocks 1, first connecting beams 2 and second connecting beams 3.

[0042] S2. Construction of prestressed anchor cables: When the road cutting slope is excavated, the construction of prestressed anchor cables shall be carried out immediately once a flat surface is formed for anchor cable construction.

[0043] S3. Installation of the anchoring block 1 and the first connecting beam 2: The anchoring block 1 is installed by passing a prestressed anchor cable through the anchor cable hole 6. For every two installed anchoring blocks 1, the first connecting beam 2 is placed between these two anchoring blocks 1, and a removable formwork 5 is erected. Concrete is poured into the removable formwork to connect the first connecting beam 2 and the anchoring block 1 into an integral body. The specific operation is as follows: Before the installation of the first connecting beam 2, fixed steel bars are embedded. The first connecting beam 2 is hoisted and fixed. A prestressed anchor cable is inserted into the anchor rod hole 7 at the center of the first connecting beam 2, and then grouted for fixation. After the construction of the prestressed anchor cable is completed, the removable formwork 5 is erected, and concrete is poured into the formwork 5 to pour the first connecting beam 2 and the anchoring block 1 into a whole. After the cast-in-place concrete construction is completed, it is covered and watered for curing. The removable formwork 5 can be removed only after the concrete reaches the designed strength value.

[0044] S4. Installation of the fixed piles 4: A plurality of fixed piles 4 are successively driven into the diamond-shaped area formed by the first connecting beams 2. The fixed piles 4 are connected into a "field" shape through the first loop fasteners 4-2 and the second loop fasteners 4-3 in the positive and negative directions, dividing the diamond-shaped area into small pieces, so as to achieve the sub-regional stability of the slope.

[0045] S5. Installation of the second connecting beam 3: For every completed construction of the fixed piles 4 in a diamond-shaped area, the second connecting beam 3 is immediately hoisted and fixed. The specific operation is as follows: Before the installation of the second connecting beam 3, fixed steel bars are embedded. The second connecting beam 3 is hoisted and fixed. A prestressed anchor cable is inserted into the anchor rod hole 7 at the center of the second connecting beam 3, and then grouted for fixation. After the construction of the prestressed anchor cable is completed, the removable formwork 5 is erected, and concrete is poured into the formwork 5 to pour the second connecting beam 3 and the first connecting beam 2, and the second connecting beams 3 in the same column into a whole. After the cast-in-place concrete construction is completed, it is covered and watered for curing. The removable formwork 5 can be removed only after the concrete reaches the designed strength value.

[0046] S6. Slope maintenance: According to the design requirements, a plurality of slope reinforcement units are successively arrayed on the cutting slope. Soil is cultivated and grass is planted in each diamond-shaped area. Grass seeds suitable for the local climate and soil conditions of the construction are selected for sowing or turf laying, and maintenance work such as watering and fertilizing the vegetation is carried out regularly to ensure the healthy growth of the vegetation.

[0047] The present invention provides a cutting slope reinforcement structure and construction method that are synchronized with the slope excavation. A plurality of anchor blocks are arranged in a plum blossom shape and form a diamond area with a first connecting beam. Fixed piles are set in the diamond area to divide the slope area into stable small areas. A second connecting beam is set to connect the small areas as a whole, thereby increasing the stability of the entire reinforcement structure, reducing the risk of landslides and collapses, and improving the protection effect. Before excavation, the slope shape, geological conditions and other conditions are collected, a BIM model is established for simulation analysis, and the optimal arrangement of prefabricated anchor cables is obtained. When the cutting slope is excavated, prestressed anchor cables and the cutting slope reinforcement structure are immediately installed whenever a flat surface for anchor cable construction is formed, thereby achieving synchronization of slope construction and protection, and solving the problem of delayed protection caused by reinforcement after the slope excavation is completed.

[0048] It will be easily understood by those skilled in the art that the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A cutting slope reinforcement structure, characterized in that, it includes at least one slope reinforcement unit, and the slope reinforcement unit includes an anchor block (1), a first connecting beam (2), a second connecting beam (3), a fixing pile (4) and a detachable formwork (5); wherein, the anchor blocks (1) are arranged in a plum blossom shape, the first connecting beam (2) is arranged between two adjacent anchor blocks (1), and the first connecting beam (2) and the anchor block (1) are connected into one body through the detachable formwork (5); the fixing piles (4) are arranged in the area formed by the first connecting beams (2) and are connected in sequence to form a polygon. There are multiple second connecting beams (2), and two of them form a column. Two columns are arranged in a cross on the fixing piles (4). One end of the second connecting beam (2) is connected into one body with the second connecting beam (2) in the same column through the detachable formwork (5), and the other end is connected into one body with the first connecting beam (2) through the detachable formwork (5). The second connecting beam (2) is used to increase the stability of the entire slope reinforcement unit.

2. A cutting slope reinforcement structure according to claim 1, characterized in that, the fixing pile (4) includes a fixing plate (4-1), a first loop buckle (4-2) and a second loop buckle (4-3); the first loop buckle (4-2) and the second loop buckle (4-3) are oppositely arranged on both sides of the fixing plate (4-1), and the bottoms of both sides of the fixing plate (4-1) are in a pointed shape.

3. A cutting slope reinforcement structure according to claim 2, characterized in that, the fixing piles (4) are connected in sequence to form a "field" shape and are arranged in the diamond area formed by the first connecting beams (2). The intersection center of the two columns of the second connecting beams (3) coincides with the center of the "field" shape.

4. A cutting slope reinforcement structure according to any one of claims 1-3, characterized in that, the anchor block (1) is a precast concrete block, and anchor cable holes (6) are provided at the four corners of the anchor block (1) for fixing the anchor block (1) on the cutting slope.

5. A cutting slope reinforcement structure according to any one of claims 1-3, characterized in that, the first connecting beam (2) and the second connecting beam (3) are both precast concrete beams, and anchor rod holes (7) are provided at the centers of the first connecting beam (2) and the second connecting beam (3). The anchor rod holes (7) are used to fix the first connecting beam (2) and the second connecting beam (3) on the cutting slope.

6. A cutting slope reinforcement structure according to any one of claims 1-3, characterized in that, the detachable formwork (5) is rectangular in shape and is made of steel or wood.

7. A construction method for a cutting slope reinforcement structure synchronized with slope excavation, realized by using the cutting slope reinforcement structure according to any one of claims 1-6, characterized in that, specifically includes the following steps: S1. Slope construction design: Before the excavation of the cutting slope, use 3D laser scanners and UAV aerial photography technology to measure the actual condition of the slope. Combine the detection data of ground penetrating radar, and use BIM technology for simulation analysis to determine the spacing of prestressed anchor cables and the dimensions of each precast component, and then fabricate the precast components. S2. Prestressed anchor cable construction: During the excavation of the cutting slope, once a flat surface for anchor cable construction is formed, immediately install the prestressed anchor cables. S3. Installation of the anchorage block (1) and the first connecting beam (2): Install the anchorage block (1) by passing the prestressed anchor cable through the anchor cable hole (6). For every two installed anchorage blocks (1), place the first connecting beam (2) between these two anchorage blocks (1), and by erecting a detachable formwork (5), pour concrete into the detachable formwork to connect the first connecting beam (2) and the anchorage block (1) into one body. S4. Installation of the fixed piles (4): Drive a plurality of fixed piles (4) in sequence within the area formed by the first connecting beams (2). The fixed piles (4) are connected into a "field" shape through the first snap fasteners (4-2) and the second snap fasteners (4-3) in the positive and negative directions, dividing the area into various parts. S5. Installation of the second connecting beam (3): Immediately after the construction of the fixed piles (4) in each diamond-shaped area is completed, hoist and fix the second connecting beam (3). S6. Slope maintenance: Arrange a plurality of slope reinforcement units in an array on the cutting slope according to the design requirements, and carry out soil cultivation and grass planting in each area.

8. A cutting slope reinforcement structure according to claim 7, wherein, in the said S1, it specifically includes the following steps: S1-1. Data collection: Use a 3D laser scanner to conduct a full-range scan of the area to be constructed, control the UAV to carry a high-definition camera to take multi-angle photos of the slope, and use ground penetrating radar technology to detect the internal structure of the slope to understand the rock layer distribution and crack information. S1-2. Establish a BIM model: Import the collected data into BIM software to create a digital model, which includes the geometric shape of the slope, as well as information such as material properties and mechanical properties. S1-3. BIM simulation analysis: Use the BIM model to conduct simulation analysis under various working conditions, such as the stability analysis after slope excavation and the optimal layout method of prestressed anchor cables, and further determine the optimal spacing of prestressed anchor cables and the dimensions of precast components.

9. A cutting slope reinforcement structure according to claim 8, wherein, in the said S1-3, the precast components include the anchorage block (1), the first connecting beam (2) and the second connecting beam (3).

10. A cutting slope reinforcement structure according to any one of claims 7-9, wherein, In S3 and S5, the first connecting beam (2) and the second connecting beam (3) are first embedded with fixed steel bars before installation, and prestressed anchor cables are inserted into the anchor rod holes (7), followed by grouting to fix them. After the prestressed anchor cables are constructed, a detachable formwork (5) is set up to cast concrete to cast the first connecting beam (2) and the anchor block (1), the first connecting beam (2) and the second connecting beam (3), and the second connecting beam (3) in the same row as a whole. After the concrete reaches the designed strength value, the detachable formwork (5) is removed.