Underwater open caisson segmental prefabrication synchronous sinking construction control method

Through the construction control method of synchronous sinking in sections, the problem of improper synchronization control during the sinking of the underwater sinking well is solved, and uniform stress and synchronous sinking of the well wall are achieved, thereby avoiding deformation and safety accidents.

CN119083474APending Publication Date: 2024-12-06HUNAN JOCHON BUILDING TECH
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411303562.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-19
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

Improper synchronization control during the sinking process of underwater sinking may lead to deformation of the well wall and excessive inclination, affecting subsequent use, and may cause major safety accidents.

Method used

The construction control method of prefabricated synchronous sinking is adopted in sections, including building a facility bracket and a platform, setting up a jack group, performing synchronous pressurization control, sinking one by one, and real-time monitoring of the boom stress to ensure the synchronous lifting and downing of each section of concrete. Sink.

Benefits of technology

The uniform stress and synchronous sinking of the well wall are achieved, avoiding the over-limit deviation during the well wall deformation and sinking process, and ensuring construction safety and quality.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119083474A_ABST
    Figure CN119083474A_ABST
Patent Text Reader

Abstract

The invention discloses an underwater open caisson segmental prefabrication synchronous sinking construction control method. The method comprises the steps that a construction support and a platform are erected, and a jack set is arranged on the construction support and the platform; synchronous pressurization control is conducted on the jack set; synchronous lifting control is conducted on the first section of concrete; synchronous sinking control is conducted on the first section of concrete; synchronously sinking the open caisson section by section and monitoring suspender stress in real time; and cleaning the construction site. According to the underwater open caisson segmental prefabrication synchronous sinking construction control method, synchronous accurate control is achieved, and the situations that the well wall is stressed unevenly, concrete cracks due to over-limit deformation, and safety and quality accidents are caused by over-limit deviation in the sinking process are avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of construction control, and in particular to a construction control method for the synchronous sinking of segmented prefabrication of an underwater caisson. Background Art

[0002] Caisson construction is widely used in the engineering field. It is not only used in the foundation construction of roads and railway bridges, but also in pump rooms for water supply and drainage in municipal engineering, underground power plants, mining shafts, underground water storage, underground oil storage facilities and other occasions.

[0003] Underwater caissons are generally large in size (mostly with a diameter of more than 20 meters) and heavy (their own weight is usually more than 10,000 tons). Therefore, the control of their sinking construction process is an extremely critical task, especially when the underwater sinking depth reaches 20 meters. Improper control of the synchronization of their sinking may directly lead to deformation and cracking of the caisson wall, and a large inclination, affecting subsequent use, and even causing major safety accidents such as collapse of construction supports and platforms due to asynchronous descent and uneven force. Summary of the invention

[0004] The purpose of the present invention is to overcome the defects of the prior art and provide a method for controlling the synchronous sinking construction of the sub-section prefabrication of an underwater caisson to solve the problems in the prior art.

[0005] The present invention is implemented as follows: a method for controlling the construction of underwater caisson segmented prefabrication and synchronous sinking, the method comprising the steps of:

[0006] Set up construction supports and platforms and install jack sets on them;

[0007] Performing synchronous pressurization control on the jack group;

[0008] Conduct synchronous lifting control on the first section of concrete;

[0009] Conduct synchronous sinking control on the first section of concrete;

[0010] Sink the caisson section by section synchronously and monitor the boom stress in real time;

[0011] Clean up the construction site.

[0012] Optionally, the step of setting up a construction support and a platform and arranging a jack group thereon comprises the following steps:

[0013] Set up construction scaffolding and platforms;

[0014] Install construction equipment and first section concrete formwork;

[0015] Establishment of settlement observation points:

[0016] Installing boom stress monitoring equipment;

[0017] pouring the first section of concrete on the first section of concrete formwork;

[0018] The integrated controller for controlling the start and stop of the jack and receiving feedback of its displacement pressure signal is in place.

[0019] Optionally, the installation of the construction equipment and the first section of concrete formwork comprises the steps of:

[0020] Setting up the boom on the construction platform;

[0021] Installing a jack on the boom;

[0022] Install the first section of concrete formwork at the bottom of the hanger and lift it up by the hanger;

[0023] installing a tool nut on the jack;

[0024] A support frame and a working nut are installed between the bottom of the jack and the construction platform.

[0025] Optionally, the establishment of the settlement observation point comprises the steps of:

[0026] Build a construction platform;

[0027] The settlement observation point is established at the sinking support point.

[0028] Optionally, installing the boom stress monitoring device comprises the steps of:

[0029] Installing a hanger rod above the first section of concrete formwork;

[0030] installing a steel bar strain gauge on the hanger rod;

[0031] Set up a comprehensive data collection instrument on the construction platform;

[0032] Introducing the steel bar strain gauge into the comprehensive acquisition instrument;

[0033] Zero the integrated acquisition instrument.

[0034] Optionally, pouring the first section of concrete on the first section of concrete formwork comprises the steps of:

[0035] pouring the first section of concrete into the first section of concrete formwork;

[0036] The first section of concrete formwork is removed after a preset age.

[0037] Optionally, the integrated control instrument for controlling the start and stop of the jack and receiving the displacement pressure signal feedback thereof is in place, comprising the steps of:

[0038] Electrically connect the jack displacement pressure sensor to the integrated controller;

[0039] The start and stop of the jack as well as the oil inlet and return are controlled by an integrated controller.

[0040] Optionally, the cleaning of the construction site comprises the steps of:

[0041] Perform underwater desilting operations at construction sites;

[0042] Performing back cover construction operations at the construction site;

[0043] Remove the jacks from the construction site.

[0044] The present application provides a method for controlling the synchronous sinking of prefabricated sections of an underwater caisson, which realizes precise control of synchronization and avoids the occurrence of uneven stress on the well wall, cracking of excessive deformation concrete, and excessive displacement during the sinking process. BRIEF DESCRIPTION OF THE DRAWINGS

[0045] Figure 1 A schematic top view of a method for controlling the synchronous sinking of a submerged caisson prefabrication according to an embodiment of the present invention;

[0046] Figure 2 A cross-sectional schematic diagram of a method for controlling the synchronous sinking of a submerged caisson prefabrication according to an embodiment of the present invention;

[0047] Figure 3 It is a schematic diagram of a partially enlarged view of a method for controlling the synchronous sinking construction of a submerged caisson prefabrication according to an embodiment of the present invention;

[0048] In the figure, 1. Concrete of the first section of caisson; 2. Concrete of caisson section; 3-1. No. 1 lifting rod; 3-2. No. 2 lifting rod; 4-1. No. 1 jack; 4-2. No. 2 jack; 5-1. No. 1 tool nut; 5-2. No. 2 tool nut; 6. Inner wall steel pipe pile; 7. Outer wall steel pipe pile; 8-1. No. 1 steel bar strain gauge; 8-2. No. 2 steel bar strain gauge; 9-2. No. 2 working nut; 10. Support platform; 11. Comprehensive data acquisition instrument; 12-2. No. 2 support frame; 13-2. No. 2 displacement sensor; 14. Comprehensive control instrument; 15. Settlement monitoring point. DETAILED DESCRIPTION

[0049] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention.

[0050] It should be noted that when an element is referred to as being "fixed to" or "disposed on" another element, it may be directly on the other element or there may be an intermediate element at the same time. When an element is referred to as being "connected to" another element, it may be directly connected to the other element or there may be an intermediate element at the same time.

[0051] See also Figure 1-3 The present application provides a method for controlling the construction of underwater caisson segmented prefabrication and synchronous sinking, the method comprising the steps of:

[0052] S1: Set up the construction support and platform and install the jack group on them;

[0053] In the embodiment of the present application, the steps of setting up the construction support and platform and arranging a jack group thereon include:

[0054] Set up construction scaffolding and platforms;

[0055] Install construction equipment and first section concrete formwork;

[0056] Establishment of settlement observation points:

[0057] Installing boom stress monitoring equipment;

[0058] pouring the first section of concrete on the first section of concrete formwork;

[0059] The integrated controller for controlling the start and stop of the jack and receiving feedback of its displacement pressure signal is in place.

[0060] In the embodiment of the present application, the short side dimension or diameter of the caisson is generally not less than 20m, and the deadweight of the caisson is usually 10,000 tons or more. The following is an illustration taking a circular caisson as an example.

[0061] The inner wall brackets 6 and outer wall brackets 7 of the circular caisson are provided with 16, 24 or 32 sets of sinking support points (hereinafter referred to as 16 sets) according to the diameter and tonnage of the caisson, and each set of inner wall brackets 6 and outer wall brackets 7 is composed of no less than 2 steel pipe piles, and each set of inner wall brackets 6 and outer wall brackets 7 is evenly distributed around the circumference of the caisson. The following description is based on the first set of sinking support points. A construction platform 10 is provided on the top of the inner wall bracket 6 and the outer wall bracket 7 of the caisson. The first section of concrete 1 of the caisson is between the inner wall bracket 6 and the outer wall bracket 7, and the No. 1 suspension rod 3-1 and the No. 2 suspension rod 3-2 are pre-buried therein for lifting the first section of concrete 1 waiting to be lowered. The upper ends of the No. 1 suspension rod 3-1 and the No. 2 suspension rod 3-2 are supported on the platform 10. The No. 1 jack 4-1 is at the upper end of the No. 1 suspension rod 3-1 and the lower part thereof is the No. 1 support frame. Under the No. 1 support is the No. 1 working nut. The No. 1 support frame, the No. 1 working nut, the No. 1 jack 4-1, and the No. 1 tool nut 5-1 all pass through the No. 1 suspension rod 3-1. The configuration on the No. 2 suspension rod 3-2 is the same as that on the No. 1 suspension rod 3-1. A No. 1 steel bar strain gauge 8-1 is provided on the No. 1 suspension rod 3-1, and a No. 2 steel bar strain gauge 8-2 is provided on the No. 2 suspension rod 3-2. The No. 1 steel bar strain gauge 8-1 and the No. 2 steel bar strain gauge 8-2 are connected as a group to the comprehensive data acquisition instrument 11. A settlement observation point 15 is set at each sinking support point, a No. 1 displacement pressure sensor is set on the jack 4-1, and a No. 2 displacement pressure sensor 13-2 is set on the jack 4-2. The No. 1 displacement pressure sensor and the No. 2 displacement pressure sensor 13-2 are both electrically connected to the comprehensive control instrument 14, and the comprehensive control instrument 14 controls the oil inlet and return of all jacks (such as the No. 1 jack 4-1 and the No. 2 jack 4-2) through electrical connection.

[0062] In the embodiment of the present application, the construction platform comprises the following steps:

[0063] Build the inner wall support;

[0064] Building an outer wall support outside the outer wall support;

[0065] A construction platform is built on the top of the inner wall support and the outer wall support.

[0066] In the embodiment of the present application, each group of inner wall brackets 6 and outer wall brackets 7 and the construction platform 10 are constructed according to the design.

[0067] In the embodiment of the present application, the installation of the construction equipment and the first section of the concrete formwork comprises the following steps:

[0068] Setting up the boom on the construction platform;

[0069] Installing a jack on the boom;

[0070] Install the first section of concrete formwork at the bottom of the hanger and lift it up by the hanger;

[0071] installing a tool nut on the jack;

[0072] A support frame and a working nut are installed between the bottom of the jack and the construction platform.

[0073] In the embodiment of the present application, the first section of concrete formwork is installed, and a No. 1 hoist rod 3-1 and a No. 2 hoist rod 3-2 are set to lift the first section of concrete bottom formwork, and a No. 1 jack 4-1 and a No. 2 jack 4-2 are respectively installed on the No. 1 hoist rod 3-1 and the No. 2 hoist rod 3-2, and a No. 1 working nut 5-1 and a No. 2 working nut 5-2 are respectively installed on the No. 1 jack 4-1 and the No. 2 jack 4-2, and a No. 1 support frame and a No. 1 tool nut, a No. 2 support frame 12-2 and a No. 2 tool nut 9-2 are installed below.

[0074] In the embodiment of the present application, the establishment of the settlement observation point comprises the steps of:

[0075] Build a construction platform;

[0076] The settlement observation point is established at the sinking support point.

[0077] In the embodiment of the present application, after the construction platform is built, a settlement observation point 15 is set up at each sinking support point.

[0078] In an embodiment of the present application, the installation of the suspension rod stress monitoring device comprises the steps of:

[0079] Installing a hanger rod above the first section of concrete formwork;

[0080] installing a steel bar strain gauge on the hanger rod;

[0081] Set up a comprehensive data collection instrument on the construction platform;

[0082] Introducing the steel bar strain gauge into the comprehensive acquisition instrument;

[0083] Zero the integrated acquisition instrument.

[0084] In the embodiment of the present application, a No. 1 steel bar strain gauge 8-1 is installed on the No. 1 hanger 3-1 above the first section concrete 1 formwork, and a No. 2 steel bar strain gauge 8-2 is installed on the No. 2 hanger 3-2, and both are fed into the comprehensive data acquisition instrument 11, and the comprehensive data acquisition instrument 11 is zeroed.

[0085] In an embodiment of the present application, pouring the first section of concrete on the first section of concrete formwork comprises the following steps:

[0086] pouring the first section of concrete into the first section of concrete formwork;

[0087] The first section of concrete formwork is removed after a preset age.

[0088] In the embodiment of the present application, the first section of concrete is poured 1, and the formwork is removed after 7 days.

[0089] The integrated controller for controlling the start and stop of the jack and receiving its displacement pressure signal feedback is in place.

[0090] In the embodiment of the present application, the integrated control instrument 14 is in place, and the No. 1 displacement pressure sensor and the No. 2 displacement pressure sensor 13-2 on the No. 1 jack 4-1 and the No. 2 jack 4-2 are connected to the integrated control instrument. The remaining 15 groups of jack displacement pressure sensors are all connected to the integrated control instrument 14. The No. 1 displacement pressure sensor and the No. 2 displacement pressure sensor 13-2 on the No. 1 jack 4-1 and the No. 2 jack 4-2 are connected to the integrated control instrument. The remaining 15 groups of jack displacement pressure sensors are all connected to the integrated control instrument 14.

[0091] In the embodiment of the present application, the integrated control instrument for controlling the start and stop of the jack and receiving the displacement pressure signal feedback thereof comprises the following steps:

[0092] Electrically connect the jack displacement pressure sensor to the integrated controller;

[0093] The start and stop of the jack as well as the oil inlet and return are controlled by an integrated controller.

[0094] In the embodiment of the present application, 15 groups of jack displacement pressure sensors are electrically connected to the integrated controller 14, and the integrated controller 14 is used to control the start and stop of the jack as well as the oil inlet and oil return.

[0095] S2: Performing synchronous pressurization control on the jack group;

[0096] In the embodiment of the present application, the specific steps of synchronous pressurization control are:

[0097] (1) The comprehensive data acquisition instrument 11 collects data from the steel bar strain gauges installed on all the hangers, such as the stress changes of the No. 1 steel bar strain gauge 8-1 and the No. 2 steel bar strain gauge 8-2, and calculates the tensile stress increase value σ=E×ε of the No. 1 hanger 3-1, the No. 2 hanger 3-2 and all other hangers.

[0098] (2) Loosen the tool nuts of all jacks, and the integrated control instrument 14 starts to instruct each group of jacks to supply oil (a total of 16 groups of jacks, each group consists of jack No. 1 and jack No. 2). Stop when the stroke of all jacks reaches 80% of the standard stroke (the standard stroke of general jacks is 20 cm), and install and tighten the tool nuts.

[0099] Then, the oil is evenly fed in and pressurized, and the speed is controlled at 1.5-2.5L / min. The integrated controller 14 collects the oil pressure value / force value of each group of jacks.

[0100] (3) The force values ​​of the first group of jacks are T11 and T12, and the force values ​​of the nth group of jacks are Tn1 and Tn2. The target force values ​​are all T (the force value of the first section of concrete in the caisson evenly distributed to each jack multiplied by the safety factor). During the oil injection and pressurization process, the force error between groups is controlled to be no more than 20%, and the force error within the same group is controlled to be no more than 10%.

[0101] The specific steps of synchronous pressurization are as follows:

[0102] The integrated control instrument 14 collects the force values ​​of each group of jacks T11, T12...Tn1, Tn2, and obtains the median T M , compare the force values ​​of each group with the median T M The deviation between n1 =T n1 -T M ; If the maximum deviation value is greater than 20%, the jack whose command force value exceeds the deviation will stop supplying oil. Compare the force values ​​of the same group ΔT n =T n1 -T n2 If the maximum deviation value is greater than 10%, the jack with a larger command force value will stop supplying oil.

[0103] After 1-2 minutes, collect the force values ​​of each group of jacks again and compare them with the median at this time to calculate the force deviation. If the force value exceeds 20%, stop oil supply. If the force value deviation of the same group exceeds 10%, stop oil supply for the larger force value. The remaining groups of jacks continue to supply oil or re-supply oil (especially those that stopped supplying oil in the previous step). This control principle is repeated until each group of jacks reaches the target force value T (+5%) and stops supplying oil and pressurizing.

[0104] (4) Check whether the working nuts under the No. 1 jack 4-1 and the No. 2 jack 4-2 of the first group are loose, and check the working nuts of the remaining groups of jacks one by one. If they are not loose, go to the corresponding jack and manually control the pressure on the integrated control instrument 14 to loosen the working nut, and then all the jacks enter the self-locking state.

[0105] (5) Re-test the stress σ of the steel bar strain gauges on the first group No. 1 hanger 3-1 and the second hanger 3-2 and all hangers, and compare the stress value σ of each hanger. If the stress value of an individual hanger is significantly higher than that of the other hangers (exceeding the average value by 15%), the cause must be identified before proceeding to the next step.

[0106] S3: synchronously lifting and controlling the first section of concrete;

[0107] In the embodiment of the present application, the specific steps of synchronous lifting control are:

[0108] (1) After the synchronous pressurization process of the jack group is completed, the working nuts of all the suspension rods have been loosened and it has been collected that the force on each suspension rod is uniform, with a deviation within 15%.

[0109] (2) Each group of jacks continues to add oil and pressurize. At this time, the weight lifted by the jack group remains unchanged, and the displacement of the jack group increases. In order to ensure the synchronous lifting of the caisson, the displacement synchronization of different groups of jacks is ±20mm, and the displacement synchronization of the same group of jacks is ±5mm as the control target. The lifting stroke is 20mm, and the working nut can be turned as a principle.

[0110] (3) The synchronous control process of the lifting process is as follows: the integrated control instrument 14 collects the initial displacement values ​​of each group of jacks through the displacement pressure sensors on each jack. The displacement of the first group of jacks is L11, L12, and the target force value of the nth group of jacks is Ln1, Ln2. The target displacement value is L. During the oil feeding process, the integrated control instrument 14 collects the displacement of each group of jacks L11, L12...Ln1, Ln2; and obtains the median L M , compare the displacement values ​​of each group with the median L M The deviation between n1 =L n1 -L M ; If the deviation value is greater than 20mm, the jack whose displacement exceeds the deviation is commanded to stop supplying oil. The displacements of the jacks in the same group are compared. For example, if the difference between the displacement values ​​L11 and L12 collected from jack No. 1 4-1 and jack No. 2 4-2 exceeds 5mm, the jack with the larger displacement is commanded to stop supplying oil. After 1 to 2 minutes, the displacements of each group of jacks are collected again and compared with the median at this time to calculate the displacement deviation. If it exceeds ±20mm, the oil supply is stopped. If the displacement difference in the same group exceeds 5mm, the one with the larger displacement is stopped from supplying oil. The remaining groups of jacks continue to supply oil or re-supply oil (especially those that were suspended in the previous step). After a round of oil supply, if the individual working nuts are not loose, the integrated controller 14 is used to complete the pressurization by electric pressurization to ensure that all nuts can be frozen, and then all jacks are self-locked.

[0111] S4: synchronously controlling the sinking of the first section of concrete;

[0112] In the embodiment of the present application, the specific steps of synchronous sinking control are:

[0113] (1) In this example, the sinking stroke is 18 cm, and each stage is designed to be 30 mm. Here, six stages are used for explanation.

[0114] (2) The inner cylinder of the jack is preset to extend by 16 cm before being stressed, and is lifted by 2 cm as a whole during the pressurization process. In total, the working nuts of each suspension rod are tightened upwards so that they are 3 cm away from the top surface of the platform.

[0115] (3) Each group of jacks returns oil, and the oil return rate is controlled between 1.0-2.0L / min. The inner cylinder of the jack retracts. The time for the inner cylinder to retract into place is preferably about 2 minutes, and the jack is immediately locked after it is in place. At this time, all the suspension rods are lowered, and the first section of the caisson concrete 1 sinks accordingly.

[0116] (4) Loosen all the jack working nuts again so that the distance between the jack and the top surface of the platform is 3 cm again. Repeat the above steps several times to allow the caisson to complete a sinking process of 18 cm.

[0117] S5: Sink the caisson section by section synchronously and monitor the stress of the boom in real time;

[0118] In the embodiment of the present application, the specific steps of sinking the caisson section by section are:

[0119] (1) Complete the precast sinking of the first section of the caisson concrete 1 according to steps 2 to 4, check the displacement change value of each settlement observation point 15, and then proceed to the precast sinking work of the next section of the caisson concrete 2.

[0120] (2) Repeat steps 2 to 4 to complete the sinking of a caisson section.

[0121] (3) After a section is sunk, the stress change value and cumulative stress value of each group of hangers are collected again through the comprehensive collection instrument 11. The cumulative stress value of the hanger (when the last section of concrete pouring is completed) shall not exceed 1 / 2 of the yield stress value of the hanger.

[0122] S6: Clean up the construction site.

[0123] In an embodiment of the present application, the cleaning of the construction site comprises the steps of:

[0124] Perform underwater desilting operations at construction sites;

[0125] Performing back cover construction operations at the construction site;

[0126] Dismantle the construction machinery and equipment at the construction site.

[0127] In the embodiment of the present application, after the underwater caisson sinks to the base, underwater dredging and bottom sealing construction are completed according to the construction plan; and the jack groups on each group of supporting points are removed one by one according to the principle of symmetry.

[0128] The present application provides a method for controlling the synchronous sinking of prefabricated sections of an underwater caisson, which realizes precise control of synchronization and avoids the occurrence of uneven stress on the well wall, cracking of excessive deformation concrete, and excessive displacement during the sinking process.

[0129] The above description is only a preferred embodiment of the present invention, and its structure is not limited to the shapes listed above. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A method for controlling the synchronous sinking of sub-section prefabrication of an underwater caisson, characterized in that: The method comprises the steps of: Set up construction supports and platforms and install jack sets on them; Performing synchronous pressurization control on the jack group; Conduct synchronous lifting control on the first section of concrete; Conduct synchronous sinking control on the first section of concrete; Sink the caisson section by section synchronously and monitor the boom stress in real time; Clean up the construction site.

2. The method for controlling the synchronous sinking of the sub-section prefabrication of an underwater caisson according to claim 1 is characterized in that: The steps of setting up the construction support and platform and arranging the jack group thereon include: Set up construction scaffolding and platforms; Install construction equipment and first section concrete formwork; Establishment of settlement observation points: Installing boom stress monitoring equipment; pouring the first section of concrete on the first section of concrete formwork; The integrated controller for controlling the start and stop of the jack and receiving feedback of its displacement pressure signal is in place.

3. The method for controlling the synchronous sinking of the sub-section prefabrication of an underwater caisson according to claim 2 is characterized in that: The installation of the construction equipment and the first section of concrete formwork comprises the following steps: Setting up the boom on the construction platform; Installing a jack on the boom; Install the first section of concrete formwork at the bottom of the hanger and lift it up by the hanger; installing a tool nut on the jack; A support frame and a working nut are installed between the bottom of the jack and the construction platform.

4. The method for controlling the synchronous sinking of the sub-section prefabrication of an underwater caisson according to claim 2 is characterized in that: The setting up of the settlement observation point comprises the steps of: Build a construction platform; The settlement observation point is established at the sinking support point.

5. The method for controlling the synchronous sinking of the sub-section prefabrication of an underwater caisson according to claim 2 is characterized in that: The installation of the boom stress monitoring device comprises the steps of: Installing a hanger rod above the first section of concrete formwork; installing a steel bar strain gauge on the hanger rod; Set up a comprehensive data collection instrument on the construction platform; Introducing the steel bar strain gauge into the comprehensive acquisition instrument; Zero the integrated acquisition instrument.

6. The method for controlling the synchronous sinking of the sub-section prefabrication of an underwater caisson according to claim 2 is characterized in that: The pouring of the first section of concrete on the first section of concrete formwork comprises the following steps: pouring the first section of concrete into the first section of concrete formwork; The first section of concrete formwork is removed after a preset age.

7. The method for controlling the synchronous sinking of the sub-section prefabrication of an underwater caisson according to claim 2 is characterized in that: The integrated control device for controlling the start and stop of the jack and receiving the displacement pressure signal feedback thereof comprises the following steps: Electrically connect the jack displacement pressure sensor to the integrated controller; The start and stop of the jack as well as the oil inlet and return are controlled by an integrated controller.

8. The method for controlling the synchronous sinking of the sub-section prefabrication of an underwater caisson according to claim 1 is characterized in that: The cleaning of the construction site comprises the following steps: Perform underwater desilting operations at construction sites; Performing back cover construction operations at the construction site; Remove the jacks from the construction site.