Underground concrete aggregate screening and washing workshop and underground concrete aggregate screening and washing system
Through the support frame design combining the support foot assembly and the hanging beam mechanism, the installation and maintenance of cranes in small span underground workshops is simplified, and the complex and time-consuming construction of traditional rock anchor beams is solved, and the construction period is shorter and lower cost.
Patent Information
- Application Number
- CN202411402637.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-09
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2044-10-09
AI Technical Summary
The construction process of traditional rock anchor beams in small span underground workshops is complex and time-consuming, has high construction difficulty and high cost consumption, and is not suitable for use in underground concrete aggregate screening workshops.
The first and second support frames are designed with the support foot assembly and the hanging beam mechanism. One end of the support foot assembly is evenly distributed on the support foundation surface and the other end is connected to the hanging beam mechanism, so that the crane can be movably installed and realize the relative hanging beam mechanism. Movement in parallel directions simplifies the lifting and daily maintenance of cranes.
Compared with traditional rock anchor beams, the construction period is shorter, the construction difficulty is lower, and it effectively saves costs. It is suitable for the promotion and application of small-span underground workshops.
Smart Images

Figure CN119083491A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of concrete production, and in particular to an underground concrete aggregate screening and washing workshop and an underground concrete aggregate screening and washing system. Background Art
[0002] Large-scale hydropower projects at home and abroad, such as the high and low-line concrete production systems of Yangfanggou Power Station and the concrete system of the Yebatan Power Station dam project, are all ground-based concrete production systems. When the concrete production system needs to be arranged in an underground space, its screening and washing workshop also needs to be arranged underground, and it is necessary to consider arranging lifting and hoisting equipment in the underground space with limited space, and to use the lifting and hoisting equipment to hoist the screening and washing equipment and perform daily inspection and maintenance.
[0003] In the related art, a rock anchor beam is generally used as the installation foundation of the above-mentioned lifting and hoisting equipment.
[0004] However, the operation of rock anchor beams requires processes such as blasting, anchoring structure construction, and concrete pouring. The process is complex and time-consuming, the construction is difficult, and the cost is high, which is not conducive to application in small-span underground workshops. Summary of the invention
[0005] Based on this, it is necessary to provide an underground concrete aggregate screening and washing workshop and an underground concrete aggregate screening and washing system to address the problems in the relevant technology that the operation method of rock anchor beams has complex construction procedures, high construction difficulty and high cost, which is not conducive to application in small-span underground workshops.
[0006] On the one hand, the present application provides an underground concrete aggregate screening and washing workshop, the underground concrete aggregate screening and washing workshop comprising:
[0007] A first chamber, wherein the first chamber has a supporting base surface;
[0008] A first support frame, the first support frame comprises a support foot assembly and a suspension beam mechanism, one end of the support foot assembly is evenly distributed on the support base surface, the other end of the support foot assembly is connected to the suspension beam mechanism, the suspension beam mechanism is used to movably install a crane, and enables the crane to move relative to the suspension beam mechanism in a direction parallel to the support base surface;
[0009] A second support frame, the second support frame is arranged on the support base surface, the height of the second support frame in a direction perpendicular to the support base surface is lower than the height of the suspension beam mechanism, and the second support frame is used to install the screening and washing equipment;
[0010] The second chamber;
[0011] The third chamber, the first chamber has a first side wall and a second side wall opposite to each other, the second chamber and the third chamber are respectively arranged on two sides of the first chamber away from each other, the second chamber penetrates the first side wall to be connected with the first chamber, and the third chamber penetrates the second side wall to be connected with the first chamber.
[0012] In one embodiment, the first chamber has a first central axis extending along the first side wall toward the second side wall, and the second support frame has a second central axis, which deviates from and is parallel to the first central axis, so that the second support frame deviates from the first central axis.
[0013] In one embodiment, the second chamber and the third chamber have a coincident third central axis, the third central axis is parallel to the first central axis, the second central axis deviates from and is parallel to the first central axis, and the second chamber and the third chamber deviate from the first central axis in the same direction as the second support frame.
[0014] In one embodiment, the third chamber is gradually expanded along the third central axis and in a direction away from the first chamber.
[0015] In one embodiment, the first chamber further has a third side wall and a fourth side wall opposite to each other, and the underground concrete aggregate screening and washing workshop further includes a fourth chamber, which is arranged on one side of the first chamber and communicated with the third side wall.
[0016] In one of the embodiments, the underground concrete aggregate screening and washing workshop also includes a fifth chamber, which is arranged on the same side of the first chamber and the fourth chamber and is connected to the third side wall. The fifth chamber and the fourth chamber are spaced apart and extend parallel to each other.
[0017] In one embodiment, the fourth chamber and the fifth chamber are arranged on opposite sides of the second central axis that deviates from the first central axis.
[0018] In one embodiment, the second support frame includes a first support platform and a second support platform, the first support platform and the second support platform are arranged adjacent to each other along the extension direction of the second central axis and the first support platform is arranged on a side close to the second chamber, and the setting height of the first support platform in a direction perpendicular to the supporting base surface is higher than the setting height of the second support platform.
[0019] In one embodiment, the support leg assembly includes a plurality of support rods, and the plurality of support rods are evenly distributed along an extension direction of the side wall of the first chamber.
[0020] On the other hand, the present application also provides an underground concrete aggregate screening and washing system, including the above-mentioned underground concrete aggregate screening and washing workshop, the underground concrete production system also includes a crane loading mechanism, a screening and washing device and a discharging mechanism, the crane is movably installed on the suspension beam mechanism, the loading mechanism is arranged in the second chamber, the screening and washing device is installed on the second support frame, and the discharging mechanism is arranged in the third chamber.
[0021] In the above-mentioned underground concrete aggregate screening and washing workshop and underground concrete aggregate screening and washing system, one end of the support foot assembly is evenly distributed on the support base surface, and the other end of the support foot assembly is connected to the suspension beam mechanism, so that the crane can be movably installed on the suspension beam mechanism, and the crane can move relative to the suspension beam mechanism in a direction parallel to the support base surface, so that the crane can hoist the screening and washing equipment and perform daily operation inspection and maintenance. Specifically, the above-mentioned first support frame can be implemented as a steel frame or other structure, but is not limited to it. Compared with the traditional rock anchor beam method, it has a shorter construction period, lower construction difficulty, and can effectively save costs, which is conducive to promotion and application in small-span underground workshops. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] FIG1 is a front view schematic diagram of the structure of an underground concrete aggregate screening and washing system in one embodiment of the present application.
[0023] FIG. 2 is a schematic diagram of the structure of the underground concrete aggregate screening and washing system shown in FIG. 1 from above.
[0024] FIG. 3 is a left-side structural schematic diagram of the underground concrete aggregate screening and washing system shown in FIG. 1 .
[0025] Description of Figure Numbers
[0026] 100, first chamber; 100a, first central axis; 100b, inspection passage; 110, first side wall; 120, second side wall; 130, third side wall; 140, fourth side wall; 150, supporting base surface; 200, second chamber; 200a, third central axis; 300, third chamber; 400, fourth chamber; 500, fifth chamber; 600, first support frame; 610, support foot assembly; 611, support rod; 620, cantilever beam Mechanism; 700, second support frame; 700a, second central axis; 710, first support platform; 720, second support platform; 800, feed shaft; 10, crane; 20, loading mechanism; 30, screening and washing equipment; 31, first vibrating screen equipment; 32, second vibrating screen equipment; 33, spiral sand washing equipment; 40, discharging mechanism; 41, first discharging belt conveyor; 42, second discharging belt conveyor; 43, third discharging belt conveyor; 60, discarding belt conveyor. DETAILED DESCRIPTION
[0027] In order to make the above-mentioned purposes, features and advantages of the present application more obvious and easy to understand, the specific implementation methods of the present application are described in detail below in conjunction with the accompanying drawings. In the following description, many specific details are set forth to facilitate a full understanding of the present application. However, the present application can be implemented in many other ways different from those described herein, and those skilled in the art can make similar improvements without violating the connotation of the present application, so the present application is not limited by the specific embodiments disclosed below.
[0028] In the description of the present application, it should be understood that if the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise", "axial", "radial", "circumferential", etc. appear, the orientation or position relationship indicated by these terms is based on the orientation or position relationship shown in the accompanying drawings, which is only for the convenience of describing the present application and simplifying the description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present application.
[0029] In addition, if the terms "first" or "second" appear, these terms are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, a feature defined as "first" or "second" may explicitly or implicitly include at least one of the features. In the description of this application, if the term "plurality" appears, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.
[0030] In this application, unless otherwise clearly specified and limited, if the terms "installed", "connected", "connected", "fixed" and the like appear, these terms should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integrated connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to the specific circumstances.
[0031] In the present application, unless otherwise clearly specified and limited, if there is a description that a first feature is "above" or "below" a second feature, etc., or similar descriptions appear, it may mean that the first and second features are in direct contact, or that the first and second features are in indirect contact through an intermediate medium. Moreover, the first feature being "above", "above" and "above" the second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. The first feature being "below", "below" and "below" the second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.
[0032] It should be noted that if an element is referred to as being "fixed to" or "disposed on" another element, it may be directly on the other element or there may be a central element. If an element is considered to be "connected to" another element, it may be directly connected to the other element or there may be a central element at the same time. If any, the terms "vertical", "horizontal", "upper", "lower", "left", "right" and similar expressions used in this application are for illustrative purposes only and do not represent the only implementation method.
[0033] For large-span powerhouses in hydropower projects, the main function of rock anchor beams is to use long grouting anchors of a certain depth to firmly anchor the reinforced concrete beam body to the rock, and transmit the load to the rock mass through the friction between the long anchor and the rock wall. The design of the rock anchor beam does not set up columns, making full use of the bearing capacity of the surrounding rock. Compared with ordinary cast-in-place beams, this structure can narrow the span of the underground powerhouse, reduce the amount of work, reduce the cost of the project, and increase the stability of the cavern. However, since the application of rock anchor beams is mainly concentrated in the underground powerhouses of large-scale water conservancy projects, used for the installation and maintenance of electromechanical equipment, its construction is a comprehensive construction technology that integrates smooth (pre-cracking) blasting, anchoring technology, concrete technology, stress, strain and displacement measurement technology. It has high technical requirements, high construction difficulty and high construction cost, which is not conducive to its promotion and application in small-span underground workshops.
[0034] In view of the above problems, referring to FIG1 , the present application provides an underground concrete aggregate screening and washing system. FIG1 shows a front view structural schematic diagram of an underground concrete aggregate screening and washing system in one embodiment of the present application. The underground concrete aggregate screening and washing system in one embodiment of the present application includes a crane 10, a loading mechanism 20, a screening and washing device 30, a discharging mechanism 40, and an underground concrete aggregate screening and washing workshop. The present application also makes the following improvements to the underground concrete aggregate screening and washing workshop in the provided underground concrete aggregate screening and washing system.
[0035] Continuing to refer to FIG. 1, in one embodiment, the underground concrete aggregate screening and washing workshop includes a first chamber 100, a second chamber 200, a third chamber 300, a first support frame 600 and a second support frame 700. The first chamber 100 has a support base surface 150. The first support frame 600 includes a support foot assembly 610 and a suspension beam mechanism 620. As shown in FIG. 2, one end of the support foot assembly 610 is evenly distributed on the support base surface 150, and the other end of the support foot assembly 610 is connected to the suspension beam mechanism 620. The suspension beam mechanism 620 is used to flexibly install the crane 10, and enables the crane 10 to move relative to the suspension beam mechanism 620 in a direction parallel to the support base surface 150. The second support frame 700 is arranged on the support base surface 150, and the height of the second support frame 700 in a direction perpendicular to the support base surface 150 is lower than the height of the suspension beam mechanism 620, and the second support frame 700 is used to install the screening and washing equipment 30. The first chamber 100 has a first side wall 110 and a second side wall 120 opposite to each other. The second chamber 200 and the third chamber 300 are respectively arranged on two sides of the first chamber 100 that are away from each other. The second chamber 200 penetrates the first side wall 110 to be connected with the first chamber 100, and the third chamber 300 penetrates the second side wall 120 to be connected with the first chamber 110.
[0036] In one embodiment, the crane 10 of the underground concrete aggregate screening and washing system is movably installed on the suspension beam mechanism 620, the loading mechanism 20 is arranged in the second chamber 200, the screening and washing equipment 30 is installed on the second support frame 700, and the discharging mechanism 40 is arranged in the third chamber 300.
[0037] In the above-mentioned underground concrete aggregate screening and washing workshop and underground concrete aggregate screening and washing system, one end of the support leg assembly 610 is evenly distributed on the supporting base surface 150, and the other end of the support leg assembly 610 is connected to the suspension beam mechanism 620, so that the crane 10 can be movably installed on the suspension beam mechanism 620, and the crane 10 can move relative to the suspension beam mechanism 620 in a direction parallel to the supporting base surface 150, so that the crane 10 can hoist the screening and washing equipment 30 and perform daily operation inspection and maintenance. Specifically, the above-mentioned first support frame 600 can be implemented as a steel frame or other structure, but is not limited to it. Compared with the traditional rock anchor beam construction method, this solution uses the first support frame 600 as the installation base of the crane 10, and its construction period is shorter, the construction difficulty is lower, and it can effectively save costs, which is conducive to promotion and application in small-span underground workshops.
[0038] Specifically, when the underground concrete aggregate screening and washing system is in operation, the aggregate to be screened and washed is first transported by the loading mechanism 20 located in the first chamber 100 to be placed on the screening and washing device 30; then the aggregate is screened and washed by the screening and washing device 30, and finally the finished product is output from the third chamber 300 through the discharging mechanism 40. It can be understood that the height setting of the first chamber 100 can be adaptively set according to the height of the screening and washing device 30, or the height of the second supporting bracket can be adjusted to adapt to the height of the first chamber 100, which will not be repeated here.
[0039] Optionally, the feeding mechanism 20 may be implemented as a feeding belt conveyor but is not limited thereto. The screening and washing equipment 30 may be implemented as a first vibrating screen device 31, a second vibrating screen device 32 and a spiral sand washing device 33 but is not limited thereto. The first vibrating screen device 31 and the second vibrating screen device 32 are used for secondary screening of aggregates, and the spiral sand washing device 33 is used for washing, grading, removing impurities, and washing fine-grained and coarse-grained materials.
[0040] The first vibrating screen device 31 is connected to the feeding mechanism 20 and the first discharging belt conveyor 41. The first discharging belt conveyor 41 can directly output the finished product that meets the requirements after being screened by the first vibrating screen device 31 from the third chamber 300.
[0041] Optionally, the spiral sand washing device 33 is also connected to a waste material conveyor belt 60, and the waste material conveyor belt 60 is used to output waste materials.
[0042] Adaptively, the second support frame 700 may include, but is not limited to, a first support platform 710 and a second support platform 720. The first support platform 710 and the second support platform 720 are adjacently arranged along the extension direction of the second central axis 700a and the first support platform 710 is arranged on a side close to the second chamber 200. The setting height of the first support platform 710 in a direction perpendicular to the supporting base surface 150 is higher than the setting height of the second support platform 720, thereby satisfying the layout requirements of the above-mentioned first vibrating screen device 31 and the second vibrating screen device 32.
[0043] Adaptively, in combination with what is shown in FIG2 , the first chamber 100 may, but is not limited to, also have a third side wall 130 and a fourth side wall 140 that are opposite, and the underground concrete aggregate screening and washing workshop also includes a fourth chamber 400, which is disposed on one side of the first chamber 100 and is connected to the third side wall 130, and the fourth chamber 400 is used to set up the above-mentioned waste material conveyor 60 to meet the transportation requirements of waste materials.
[0044] In addition, the first vibrating screen device 31 also has a primary screening discharge port (not shown), which is connected to the feed port (not shown) of the second vibrating screen device 32. The discharge mechanism 40 can be implemented, but not limited to, as including the above-mentioned first discharge belt conveyor 41, and also including a second discharge belt conveyor 42 and a third discharge belt conveyor 43, the second discharge belt conveyor 42 and the third discharge belt conveyor 43 are respectively connected to the two secondary screening discharge ports of the second vibrating screen device 32, so that different finished products are output through the second discharge belt conveyor 42 and the third discharge belt conveyor 43.
[0045] Preferably, referring to 2, the second chamber 200 and the third chamber 300 have a coincident third central axis 200a, so that the second chamber 200 and the third chamber 300 can be arranged in a straight line to improve the efficiency of aggregate transportation and optimize the transportation route.
[0046] Optionally, the first chamber 100 has a first central axis 100a extending along the first side wall 110 toward the second side wall 120, and the second support frame 700 has a second central axis 700a, and the second central axis 700a deviates from and is parallel to the first central axis 100a, so that the second support frame 700 deviates from the first central axis 100a, thereby forming a maintenance channel 100b in the first chamber 100 to facilitate maintenance workers to perform maintenance work.
[0047] More preferably, the third central axis 200a is parallel to the first central axis 100a, the second central axis 700a deviates from and is parallel to the first central axis 100a, and the second chamber 200 and the third chamber 300 deviate from the first central axis 100a in the same direction as the second support frame 700. This makes it easier for the loading mechanism 20 and the discharging mechanism 40 to be arranged in a position that is compatible with the screening and washing equipment 30, which helps to optimize the aggregate conveying route and improve the screening and washing efficiency.
[0048] Preferably, the third chamber 300 is gradually expanded along the third central axis 200a and away from the first chamber 100, so that the first discharge belt conveyor 41, the second discharge belt conveyor 42 and the third discharge belt conveyor 43 are arranged in a staggered manner. On the one hand, it helps to meet the arrangement requirements of the first discharge belt conveyor 41, the second discharge belt conveyor 42 and the third discharge belt conveyor 43, and on the other hand, it helps to reduce the excavation material of the third chamber 300, thereby shortening the construction period, reducing construction costs and improving the safety of the chamber structure.
[0049] Optionally, in combination with Figures 1 and 3, the movement mode of the crane 10 can be but is not limited to being implemented as the suspension beam mechanism 620 being able to move along a first direction relative to the supporting leg assembly 610, thereby driving the crane 10 to move along the first direction X; in addition, referring to Figure 3, the crane 10 can move along a second direction Y relative to the suspension beam mechanism 620, thereby realizing the all-round movement of the crane 10 in a planar direction parallel to the supporting base surface 150, so as to ensure the preliminary lifting operation of the screening and washing equipment 30 and daily inspection and maintenance operations, such as the lifting and replacement of related screening and washing structures.
[0050] Optionally, referring to Figure 2, the support foot assembly 610 may include but is not limited to multiple support rods 611, and the multiple support rods 611 are evenly distributed along the extension direction of the side wall of the first chamber 100. This helps to make full use of the spatial characteristics of the first chamber 100 to arrange the support rods 611 at the edge of the first chamber 100, thereby reducing interference with the layout of the screening and washing equipment 30. It also helps to increase the layout range of the maintenance channel 100b in the first chamber 100, ensuring that maintenance workers have sufficient walking and maintenance space, thereby improving maintenance convenience.
[0051] Optionally, referring to FIG. 2 , the underground concrete aggregate screening and washing workshop may, but is not limited to, further include a fifth chamber 500, which is disposed on the same side of the first chamber 100 and the fourth chamber 400 and is connected to the third side wall 130, and the fifth chamber 500 is spaced apart from the fourth chamber 400 and extends parallel to each other. Specifically, the fifth chamber 500 is used to transport slag during the excavation stage of the underground concrete aggregate screening and washing workshop, and as an entrance channel for related equipment during the construction of the underground concrete aggregate screening and washing workshop, and also as a main access channel for maintenance workers to enter and exit the site, thereby solving the lower passage problem during the construction period of the underground concrete aggregate screening and washing workshop.
[0052] Preferably, the fourth chamber 400 and the fifth chamber 500 are arranged on the opposite side of the second central axis 700a deviating from the first central axis 100a, so as to adapt to the arrangement of the maintenance passage 100b, so that the fourth chamber 400 and the fifth chamber 500 are arranged on the side close to the maintenance passage 100b, thereby facilitating the maintenance personnel to enter and exit the fifth chamber 500 and perform maintenance work on the equipment in the fourth chamber 400.
[0053] Optionally, the underground concrete aggregate screening and washing workshop may include, but is not limited to, a feed shaft 800, and the feed shaft 800 is used to feed materials to the upper feeding mechanism 20 to meet the material feeding requirements during the screening and washing operation.
[0054] The technical features of the above-described embodiments may be arbitrarily combined. To make the description concise, not all possible combinations of the technical features in the above-described embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.
[0055] The above-described embodiments only express several implementation methods of the present application, and the descriptions thereof are relatively specific and detailed, but they cannot be construed as limiting the scope of the patent application. It should be pointed out that, for a person of ordinary skill in the art, several variations and improvements can be made without departing from the concept of the present application, and these all belong to the protection scope of the present application. Therefore, the protection scope of the patent application shall be subject to the attached claims.
Claims
1. An underground concrete aggregate screening and washing workshop, characterized in that: The underground concrete aggregate screening and washing workshop includes: A first chamber, wherein the first chamber has a supporting base surface; A first support frame, the first support frame comprises a support foot assembly and a suspension beam mechanism, one end of the support foot assembly is evenly distributed on the support base surface, the other end of the support foot assembly is connected to the suspension beam mechanism, the suspension beam mechanism is used to movably install a crane, and enables the crane to move relative to the suspension beam mechanism in a direction parallel to the support base surface; A second support frame, the second support frame is arranged on the support base surface, the height of the second support frame in a direction perpendicular to the support base surface is lower than the height of the suspension beam mechanism, and the second support frame is used to install the screening and washing equipment; The second chamber; The third chamber, the first chamber has a first side wall and a second side wall opposite to each other, the second chamber and the third chamber are respectively arranged on two sides of the first chamber away from each other, the second chamber penetrates the first side wall to be connected with the first chamber, and the third chamber penetrates the second side wall to be connected with the first chamber.
2. The underground concrete aggregate screening and washing workshop according to claim 1 is characterized in that: The first chamber has a first central axis extending along the first side wall toward the second side wall, and the second support frame has a second central axis, which deviates from and is parallel to the first central axis, so that the second support frame deviates from the first central axis.
3. The underground concrete aggregate screening and washing workshop according to claim 2 is characterized in that: The second chamber and the third chamber have a coincident third central axis, the third central axis is parallel to the first central axis, the second central axis deviates from and is parallel to the first central axis, and the second chamber and the third chamber deviate from the first central axis in the same direction as the second support frame.
4. The underground concrete aggregate screening and washing workshop according to claim 3 is characterized in that: The third chamber is arranged along the third central axis and gradually expands in a direction away from the first chamber.
5. The underground concrete aggregate screening and washing workshop according to claim 2 is characterized in that: The first chamber also has a third side wall and a fourth side wall opposite to each other. The underground concrete aggregate screening and washing workshop also includes a fourth chamber, which is arranged on one side of the first chamber and communicated with the third side wall.
6. The underground concrete aggregate screening and washing workshop according to claim 5 is characterized in that: The underground concrete aggregate screening and washing workshop also includes a fifth chamber, which is arranged on the same side of the first chamber and the fourth chamber and is connected to the third side wall. The fifth chamber and the fourth chamber are spaced apart and extend parallel to each other.
7. The underground concrete aggregate screening and washing workshop according to claim 6 is characterized in that: The fourth chamber and the fifth chamber are arranged on opposite sides of the second central axis that deviates from the first central axis.
8. The underground concrete aggregate screening and washing workshop according to claim 2 is characterized in that: The second support frame includes a first support platform and a second support platform. The first support platform and the second support platform are arranged adjacent to each other along the extension direction of the second central axis and the first support platform is arranged on a side close to the second chamber. The setting height of the first support platform in a direction perpendicular to the supporting base surface is higher than the setting height of the second support platform.
9. The underground concrete aggregate screening and washing workshop according to any one of claims 1 to 8, characterized in that: The support leg assembly includes a plurality of support rods, and the plurality of support rods are evenly distributed along the extension direction of the side wall of the first chamber.
10. An underground concrete aggregate screening and washing system, characterized in that: The underground concrete aggregate screening and washing workshop comprises the underground concrete aggregate screening and washing workshop as described in any one of claims 1 to 9, and the underground concrete production system further comprises a crane, a feeding mechanism, a screening and washing device and a discharging mechanism, the crane is movably mounted on the suspension beam mechanism, the feeding mechanism is arranged in the second chamber, the screening and washing device is installed on the second support frame, and the discharging mechanism is arranged in the third chamber.
Citation Information
Patent Citations
Gravel mixing system and method for underground cavern
CN107263730A
Chamber
CN107829754A
Ore drawing machine chamber structure
CN115822662A
Finished aggregate storage and transportation system of water-power engineering underground concrete system
CN118110174A
Production and supply system for underground green concrete materials
CN219993711U
Cited By
Underground concrete aggregate screening and washing workshop and underground concrete aggregate screening and washing system
WO2026076872A1