Automatic pile changing control method for double-trolley environment-friendly dredger

Through the automatic pile replacement control method of double-vehicle environmentally friendly dredgers, automatic controllers and sensors are used to realize the automatic operation of steel piles and bridges, solving the problem of low pile replacement efficiency of traditional dredgers and improving dredging efficiency and accuracy , ensuring equipment safety and economic benefits.

CN119083516AActive Publication Date: 2024-12-06CCCC TIANJIN DREDGING

Patent Information

Application Number
CN202411106473.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-13
Publication Date
2024-12-06
Estimated Expiration
2044-08-13

AI Technical Summary

Technical Problem

Traditional single-vehicle dredgers are inefficient during pile replacement and rely on manual operations, which affects construction output and accuracy.

Method used

The automatic pile replacement control method of double-vehicle environmentally friendly dredger is adopted. By setting control target parameters and real-time detection, automatic controllers and sensors are used to realize the automatic operation of steel piles and bridges, including lifting, decentralization and Stepping control ensures automation and refinement of pile replacement process.

Benefits of technology

It greatly improves the pile replacement efficiency of the dredger, saves pile replacement time, improves dredging efficiency and accuracy, realizes automated operations, ensures the safety and economic benefits of the equipment, and increases efficiency by 50% compared with traditional models.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119083516A_ABST
    Figure CN119083516A_ABST
Patent Text Reader

Abstract

The invention provides an automatic pile changing control method for a double-trolley environment-friendly dredger, which comprises the following steps of: when a bridge frame reaches a left line, lifting a bridge frame reamer according to a set bridge frame lifting height, descending a left steel pile, lifting a right steel pile, descending the bridge frame reamer to a set depth, and entering a right trolley according to a set distance; and when the bridge reaches a right line, lifting the bridge reamer, lowering the right steel pile, lifting the left steel pile and lowering the bridge reamer to a set depth according to the set lowering depth of the bridge, and then entering the left trolley according to a set distance. The automatic dredging device has the beneficial effects that the automatic dredging device is applied to an environment-friendly cutter suction ship with double steel piles and double trolleys, efficient automatic dredging is achieved, the labor amount of dredging operators can be greatly reduced, the operation difference between different operators is reduced, the dredging efficiency and the construction quality are improved, the equipment safety is guaranteed, and oil consumption is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of engineering ship automation control, and in particular relates to an automatic pile-changing control method for a double-trolley environmentally friendly dredger. Background Art

[0002] Dredging of rivers, lakes and reservoirs is slightly different from dredging of sea channels. Dredging of rivers, lakes and reservoirs usually targets uniform mud, low original soil density and easy excavation. With the development of computer and network technology, the "whole ship integrated monitoring system" of dredgers has been gradually applied, making the control of dredger construction equipment more automated and integrated. Construction personnel can control dredging equipment and monitor the dredging process through remote workstations, which significantly improves the construction efficiency of dredgers.

[0003] However, when the bridge reaches the edge line, the traditional single-trolley dredger needs to control the trolley to step forward according to the set distance first, and then lower the steel piles. The construction ship cannot dredge when the trolley is moving forward and resetting, and when the steel piles are being inserted and pulled out. In addition, the existing dredgers all have manual control for pile replacement, and the operating level and proficiency of the dredging workers will also greatly affect the construction output of the dredger. Summary of the invention

[0004] In order to solve the problems existing in the prior art, the present invention aims to propose an automatic pile changing control method for a double-trolley environmentally friendly dredger, which solves the problem of low efficiency of manual pile changing, realizes automatic control of pile changing, and improves dredging efficiency.

[0005] To achieve the above object, the technical solution of the present invention is achieved as follows:

[0006] A method for automatically changing piles for a dual-trolley environmentally friendly dredger, comprising:

[0007] S1. Set the control target parameters, including the steel pile lifting height, steel pile lowering height, left and right trolley stepping distance, left and right trolley stepping sequence, bridge lifting height, bridge lowering depth and sideline distance;

[0008] S2. In the initial state, the left and right trolleys are on the same horizontal line, and the automatic pile-changing control mode is started. The steel pile trolley automatic controller lowers the right steel pile according to the set steel pile lowering height. After completion, it sends a lowering completion instruction to the bridge frame automatic controller;

[0009] S3, after receiving the lowering completion instruction, the bridge frame automatic controller lowers the bridge frame according to the set bridge frame lowering depth, and the bridge frame reamer starts excavation work. At the same time, it sends the bridge frame lowering completion instruction to the steel pile trolley automatic controller, and the steel pile trolley automatic controller controls the left trolley to step according to the trolley stepping distance;

[0010] S4. During the excavation process, it is detected in real time whether the bridge auger reaches the left line. If not, the bridge auger continues to maintain the excavation depth; if so, the bridge automatic controller lifts the bridge according to the set bridge lifting height, and after completion, sends a bridge lifting completion instruction to the steel pile trolley automatic controller;

[0011] S5. After receiving the bridge frame lifting completion instruction, the steel pile trolley automatic controller lowers the left steel pile according to the set steel pile lowering height, then lifts the right steel pile according to the set steel pile lifting height, and sends a pile replacement completion instruction to the bridge frame automatic controller;

[0012] S6. After receiving the pile replacement completion instruction, the bridge frame automatic controller lowers the bridge frame according to the set bridge frame lowering depth, and the bridge frame reamer starts excavation. At the same time, it sends the bridge frame lowering completion instruction to the steel pile trolley automatic controller, and the steel pile trolley automatic controller controls the right trolley to step at twice the trolley stepping distance;

[0013] S7. When the bridge frame reamer reaches the right line position, follow steps S4-S6 in the same way, lower the right steel pile, lift the left steel pile, and step the left trolley at twice the trolley stepping distance.

[0014] Furthermore, in step S4, a real-time search is performed based on Beidou satellite positioning to determine whether the bridge reamer has reached the set edge distance.

[0015] Furthermore, in step S5, the lifting height of the steel pile is monitored in real time by the hydraulic cylinder stroke sensor and the laser radar; when the stroke of the steel pile lifting hydraulic cylinder reaches the set stroke value, and the laser radar monitors in real time that the lifting height of the steel pile cap reaches the set steel pile lifting height, the pile replacement is completed.

[0016] Furthermore, the laser radar is installed at the place where the trolley and the steel pile are in contact, and transmits vertically upward to the steel pile cap to monitor the lifting height of the steel pile cap in real time.

[0017] Furthermore, the main signals required in the control process are: bridge depth, trolley travel, steel pile height, water depth and distance between the bridge and the edge line. Each signal is collected by sensors at the corresponding installation position.

[0018] Furthermore, the bridge frame automatic controller and the steel pile trolley automatic controller are not independent of each other, and influence each other through the commonly involved control parameters.

[0019] Furthermore, in step S5, the bridge lowering depth is calculated according to the reamer depth deviation automatic control model, and the reamer depth deviation automatic control model calculates the bridge reamer lowering depth according to the bridge angle sensor, hull parameters and reamer parameters, and corrects the deviation in real time according to the automatic tide telemetry data.

[0020] Furthermore, the bridge frame automatic controller and the steel pile trolley automatic controller adopt emergency control with the highest priority, manual control with the second priority, and automatic control with the lowest priority, that is, whenever the system receives an emergency control command or a manual control command, it will automatically exit the automatic control mode.

[0021] Compared with the prior art, the automatic pile replacement control method for the dual-trolley environmentally friendly dredger of the present invention has the following advantages:

[0022] The automatic pile changing control method described in the present invention is applied to an environmentally friendly dredger with double steel piles and double trolleys, and realizes the automatic pile changing function of the double-trolley environmentally friendly dredger according to the set construction process. Compared with the traditional single-trolley dredger, the double-trolley environmentally friendly dredger greatly saves the time of the dredger in changing piles after reaching the edge line. During the swinging process of the bridge frame, another trolley is pre-stepped to the specified position, and the pile changing operation can be performed directly after reaching the edge line. There is no need to control the trolley during the pile changing process, which saves a lot of time and solves the problems of reduced efficiency and accuracy caused by different levels of operators. The dredging efficiency is greatly improved. Compared with the traditional pile changing mode, the efficiency is increased by 50%, and the pile changing operation is automated and refined. At the same time, it can effectively ensure the safety of the equipment and improve the economic benefits. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] The accompanying drawings constituting a part of the present invention are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. In the accompanying drawings:

[0024] Figure 1 This is a control block diagram of automatic pile replacement for a double-trolley environmentally friendly dredger provided in an embodiment of the present invention. DETAILED DESCRIPTION

[0025] It should be noted that, in the absence of conflict, the embodiments of the present invention and the features in the embodiments may be combined with each other.

[0026] In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", and the like are only used for descriptive purposes, and cannot be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, features defined as "first", "second", and the like may explicitly or implicitly include one or more of the features. In the description of the present invention, unless otherwise specified, "multiple" means two or more.

[0027] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood by specific circumstances.

[0028] The present invention will be described in detail below with reference to the accompanying drawings and in conjunction with embodiments.

[0029] like Figure 1 As shown, a method for automatically changing piles for a dual-trolley environmentally friendly dredger comprises:

[0030] S1. Set the control target parameters, including the steel pile lifting height, steel pile lowering height, left and right trolley stepping distance, left and right trolley stepping sequence, bridge lifting height, bridge lowering depth and sideline distance;

[0031] S2. In the initial state, the left and right trolleys are on the same horizontal line, and the automatic pile replacement control mode is started. The control system of the whole ship controls the automatic controller of the steel pile trolley to lower the right steel pile according to the set steel pile lowering height. After completion, the lowering completion instruction is sent to the bridge frame automatic controller;

[0032] S3, after receiving the lowering completion instruction, the bridge frame automatic controller lowers the bridge frame according to the set bridge frame lowering depth, and the bridge frame reamer starts excavation work. At the same time, it sends the bridge frame lowering completion instruction to the steel pile trolley automatic controller, and the steel pile trolley automatic controller controls the left trolley to step according to the trolley stepping distance;

[0033] S4. During the excavation process, it is detected in real time whether the bridge auger reaches the left line. If not, the bridge auger continues to maintain the excavation depth; if so, the bridge automatic controller lifts the bridge according to the set bridge lifting height, and after completion, sends a bridge lifting completion instruction to the steel pile trolley automatic controller;

[0034] S5. After receiving the bridge frame lifting completion instruction, the steel pile trolley automatic controller lowers the left steel pile according to the set steel pile lowering height, then lifts the right steel pile according to the set steel pile lifting height, and sends a pile replacement completion instruction to the bridge frame automatic controller;

[0035] S6. After receiving the pile replacement completion instruction, the bridge frame automatic controller lowers the bridge frame according to the set bridge frame lowering depth, and the bridge frame reamer starts excavation. At the same time, it sends the bridge frame lowering completion instruction to the steel pile trolley automatic controller, and the steel pile trolley automatic controller controls the right trolley to step at twice the trolley stepping distance;

[0036] S7, when the bridge reamer is detected to reach the right line position, similarly according to steps S4-S6, the bridge automatic controller lifts the bridge according to the set bridge lifting height, and after completion, sends a bridge lifting completion instruction to the steel pile trolley automatic controller;

[0037] After receiving the bridge frame lifting completion command, the steel pile trolley automatic controller lowers the right steel pile according to the set steel pile lowering height, then lifts the left steel pile according to the set steel pile lifting height, and sends the pile replacement completion command to the bridge frame automatic controller;

[0038] After the bridge frame automatic controller receives the pile replacement completion instruction, it lowers the bridge frame according to the set bridge frame lowering depth, and the bridge frame reamer starts working. At the same time, it sends the bridge frame lowering completion instruction to the steel pile trolley automatic controller, and the steel pile trolley automatic controller controls the left trolley to step at twice the trolley step distance.

[0039] In a preferred implementation of the present invention, in step S4, whether the bridge reamer has reached the set edge line distance is retrieved in real time based on Beidou satellite positioning.

[0040] In a preferred embodiment of the present invention, in step S5, the lifting height of the steel pile is calculated by the hydraulic cylinder stroke sensor and monitored in real time by the laser radar; when the stroke of the steel pile lifting hydraulic cylinder reaches the set stroke value, and the laser radar monitors in real time that the lifting height of the steel pile cap reaches the set steel pile lifting height, the pile replacement is completed.

[0041] The laser radar is installed at the place where the trolley and the steel pile are in contact, and transmits vertically upward to the steel pile cap to monitor the lifting height of the steel pile cap in real time.

[0042] In actual use, it is necessary to simultaneously meet the requirements that the stroke of the steel pile lifting hydraulic cylinder reaches the set stroke value, and the laser radar monitors in real time that the lifting height of the steel pile cap reaches the set steel pile lifting height, and the pile replacement is completed; the real-time monitoring of the lifting height of the steel pile cap by the laser radar can monitor the lifting status of the steel pile to prevent the steel wire rope controlling the lifting of the steel pile from breaking, resulting in the failure of the steel pile to be lifted.

[0043] In a preferred embodiment of the present invention, the main signals required in the control process are: bridge depth, trolley travel, steel pile height, water depth and distance between the bridge and the edge line, and each signal is collected by a sensor at the corresponding installation position.

[0044] In a preferred embodiment of the present invention, the control method establishes sub-controllers for the main dredging control objects, including: a bridge frame automatic controller and a steel pile trolley automatic controller; the sub-controllers are not independent of each other, and influence each other through the commonly involved control parameters.

[0045] In a preferred embodiment of the present invention, for the bridge automatic controller, its automatic control model is: according to the Beidou satellite positioning, it is real-time retrieved whether the bridge auger has reached the set edge line distance. If not, the excavation depth of the bridge auger continues to be maintained; if it reaches the edge line position, the bridge auger is lifted according to the bridge lifting height; after receiving the pile replacement completion instruction, the bridge is lowered to the set bridge lowering depth, and the bridge lowering completion instruction is sent to the steel pile trolley automatic controller.

[0046] The bridge lowering depth is calculated based on the auger lowering depth, the auger lowering depth is calculated based on the auger depth deviation automatic control model, the auger depth deviation is calculated based on the bridge angle sensor, hull parameters and auger parameters, and the deviation is corrected in real time based on the automatic tide telemetry data.

[0047] In a preferred embodiment of the present invention, for the steel pile trolley automatic controller, the trolley automatic controller is linked with the steel pile automatic controller for control, and its automatic control model is: when the bridge frame reamer reaches the left line, it receives the bridge frame lifting completion command, lowers the left steel pile to the set steel pile lowering height, and then lifts the right steel pile to the set steel pile lifting height, and then sends the pile replacement completion command to the bridge frame automatic controller; after receiving the bridge frame lowering completion command, it steps the right trolley to the set distance;

[0048] When the bridge reamer reaches the right line, it receives the bridge lifting completion command, lowers the right steel pile to the set steel pile lowering height, and then lifts the left steel pile to the set steel pile lifting height, and sends the pile replacement completion command to the bridge automatic controller; after receiving the bridge lowering completion command, it steps the left trolley to the set distance;

[0049] Except for the initial state, the two trolleys are set to have a step distance value that is twice the interval between them, and the two trolleys drive the steel piles to move forward alternately, thereby moving the dredger.

[0050] In a preferred embodiment of the present invention, each sub-controller adopts emergency control with the highest priority, manual control with the second priority, and automatic control with the lowest priority, that is, whenever the system receives an emergency control instruction or a manual control instruction, it automatically exits the automatic control mode.

[0051] The specific operation method of the automatic pile replacement control method of the double-trolley environmental protection dredger is as follows:

[0052] 1. Start the automatic pile-changing control mode;

[0053] 2. The swing position of the bridge is monitored in real time according to the Beidou positioning system. When the swing position reaches the set left line position, the bridge is lifted to the set bridge lifting height, and then the left steel pile is lowered to the set depth, the right steel pile is lifted to the set height, the bridge is lowered to the set depth, and the right trolley is retracted to the specified position according to the set distance;

[0054] 3. According to the Beidou positioning system, the swing position of the bridge is monitored in real time. When the swing position reaches the set right line position, the bridge is lifted to the set height, and then the right steel pile is lowered to the set depth, the left steel pile is lifted to the set height, the bridge is lowered to the set depth, and the left trolley is retracted to the specified position according to the set distance.

[0055] Example:

[0056] In a certain construction condition, the construction swing width of the cutter suction dredger is 60m and the excavation depth is 3m. In the initial state, the left and right trolleys are located on the same horizontal line, the automatic pile replacement control mode is started, the right steel pile is lowered to the set depth of 4.5m, the bridge is lowered to the 3m position, and construction continues. At the same time, the left trolley is retracted, that is, it steps forward 4.5m.

[0057] When the Beidou positioning system detects that it has reached the left line (swinging 30m to the left from the center line), the bridge frame rises 1.5m, then lowers the left steel pile to the set depth of 4.5m, lifts the right steel pile to the set height of 5m, and then lowers the bridge frame to the 3m position to continue construction. At the same time, the right trolley is retracted, that is, it steps forward 9m.

[0058] Similarly, when the Beidou positioning system detects that it has reached the right line (swinging 30m to the right from the center line), the bridge frame rises 1.5m, then lowers the right steel pile to the set depth of 4.5m, lifts the left steel pile to the set height of 5m, and then lowers the bridge frame to the 3m position to continue construction. At the same time, the left trolley is retracted and steps forward 9m.

[0059] Except for the initial state, the left trolley and the right trolley are always separated by 4.5m, so that the steel piles move forward in a staggered manner, thereby driving the dredger forward.

[0060] The automatic control method of the present invention comprehensively utilizes technologies such as computers, networks, sensors and automatic control to realize the automatic pile changing function of the double-trolley environmentally friendly dredger according to the set construction process. Compared with the traditional single-trolley dredger, the double-trolley environmentally friendly dredger greatly saves the time of the dredger in changing piles after reaching the edge line. During the swinging process of the bridge frame, another trolley can be pre-stepped to the specified position, and the pile changing operation can be directly performed after reaching the edge line. There is no need to control the trolley during the pile changing process, which saves a lot of time and solves the problems of reduced efficiency and accuracy caused by different levels of operators. It greatly improves the dredging efficiency. Compared with the traditional pile changing mode, the efficiency is increased by 50%, and the pile changing operation is automated and refined. At the same time, it can effectively ensure the safety of the equipment and improve the economic benefits.

[0061] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. A method for automatically changing piles for a double-trolley environmentally friendly dredger. Features: include: S1. Set the control target parameters, including the steel pile lifting height, steel pile lowering height, left and right trolley stepping distance, left and right trolley stepping sequence, bridge lifting height, bridge lowering depth and sideline distance; S2. In the initial state, the left and right trolleys are on the same horizontal line, and the automatic pile-changing control mode is started. The steel pile trolley automatic controller lowers the right steel pile according to the set steel pile lowering height. After completion, it sends a lowering completion instruction to the bridge frame automatic controller; S3, after receiving the lowering completion instruction, the bridge frame automatic controller lowers the bridge frame according to the set bridge frame lowering depth, and the bridge frame reamer starts excavation work. At the same time, it sends the bridge frame lowering completion instruction to the steel pile trolley automatic controller, and the steel pile trolley automatic controller controls the left trolley to step according to the trolley stepping distance; S4. During the excavation process, it is detected in real time whether the bridge auger reaches the left line. If not, the bridge auger continues to maintain the excavation depth; if so, the bridge automatic controller lifts the bridge according to the set bridge lifting height, and after completion, sends a bridge lifting completion instruction to the steel pile trolley automatic controller; S5. After receiving the bridge frame lifting completion instruction, the steel pile trolley automatic controller lowers the left steel pile according to the set steel pile lowering height, then lifts the right steel pile according to the set steel pile lifting height, and sends a pile replacement completion instruction to the bridge frame automatic controller; S6. After receiving the pile replacement completion instruction, the bridge frame automatic controller lowers the bridge frame according to the set bridge frame lowering depth, and the bridge frame reamer starts excavation. At the same time, it sends the bridge frame lowering completion instruction to the steel pile trolley automatic controller, and the steel pile trolley automatic controller controls the right trolley to step at twice the trolley stepping distance; S7. When the bridge frame reamer reaches the right line position, follow steps S4-S6 in the same way, lower the right steel pile, lift the left steel pile, and step the left trolley at twice the trolley stepping distance.

2. The automatic pile replacement control method for a double-trolley environmentally friendly dredger according to claim 1, Features: In step S4, the Beidou satellite positioning is used to retrieve in real time whether the bridge reamer has reached the set edge line distance.

3. The automatic pile replacement control method for a dual-trolley environmentally friendly dredger according to claim 1, Features: In step S5, the lifting height of the steel pile is monitored in real time by the hydraulic cylinder stroke sensor and the laser radar; when the stroke of the steel pile lifting hydraulic cylinder reaches the set stroke value, and the laser radar monitors in real time that the lifting height of the steel pile cap reaches the set steel pile lifting height, the pile replacement is completed.

4. The automatic pile replacement control method for a dual-trolley environmentally friendly dredger according to claim 1, Features: The laser radar is installed at the place where the trolley and the steel pile are in contact, and transmits vertically upward to the steel pile cap to monitor the lifting height of the steel pile cap in real time.

5. The automatic pile replacement control method for a dual-trolley environmentally friendly dredger according to claim 1, Features: The main signals required in the control process are: bridge depth, trolley travel, steel pile height, water depth and distance between the bridge and the edge line. Each signal is collected by sensors at the corresponding installation position.

6. The automatic pile replacement control method for a dual-trolley environmentally friendly dredger according to claim 1, Features: The bridge automatic controller and the steel pile trolley automatic controller are not independent of each other, and they influence each other through the commonly involved control parameters.

7. The automatic pile replacement control method for a dual-trolley environmentally friendly dredger according to claim 1, Features: In step S3, the bridge lowering depth is calculated according to the reamer depth deviation automatic control model. The reamer depth deviation automatic control model calculates the bridge reamer lowering depth according to the bridge angle sensor, hull parameters and reamer parameters, and corrects the deviation in real time according to the automatic tide telemetry data.

8. The automatic pile replacement control method for a dual-trolley environmentally friendly dredger according to claim 1, Features: The bridge automatic controller and the steel pile trolley automatic controller adopt emergency control with the highest priority, manual control with the second priority, and automatic control with the lowest priority. That is, whenever the system receives an emergency control command or a manual control command, it will automatically exit the automatic control mode.

Citation Information

Patent Citations

  • Automatic controller of steel pile trolley of cutter suction dredger

    CN109750713A

  • Positioning and traveling device with double steel piles and double trolleys for suction dredger

    CN201952829U

  • Swing trolley positioning pile device

    CN210395482U

  • Dredge construction management system and dredge construction management method