Hidden arrangement structure and method for basement air pipe
By setting the passage cavity on the basement roof or bottom plate and installing prefabricated plates or finished pipes, the hidden arrangement of the air duct is achieved, solving the problem of air duct occupying a net high space, saving earth and building materials, improving air duct performance and basement space experience .
Patent Information
- Application Number
- CN202311274772.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2023-09-28
- Publication Date
- 2024-12-06
Smart Images

Figure CN119085058A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of construction, and in particular to a concealed arrangement structure and method of a basement air duct. Background Art
[0002] In the construction of engineering projects, the clear height is an important indicator of basement design, which is related to functional use and spatial perception. "Garage Building Design Code" JGJ 100-2015, Article 4.2.5, 4.3.6 stipulates: The minimum clear height of the parking area of the garage shall not be less than 2.2 meters.
[0003] In the control of clear height design, the plane projection area of the air ducts and other related pipelines arranged under the basement structural beams is the most unfavorable range of the clear height control link. This projection area accounts for about 8% of the projection area of the basement (this value fluctuates up and down according to different functions and other conditions).
[0004] In order to solve the 8% net height problem, the conventional method is to increase the height of the entire basement, which results in a large amount of earth excavation and a large investment in building materials. At the same time, the air ducts in the basement are hoisted finished air ducts, which have weak fire resistance and durability, and poor earthquake resistance. The excavation, transportation and backfilling of the basement earth also damages the ecological environment. The basement space also creates a messy and depressing spatial experience due to the huge volume of the air ducts. Summary of the invention
[0005] The present invention provides a hidden arrangement structure and method for basement air ducts, which separately process the height of the most unfavorable range of the net height of the arranged pipelines, thereby solving the problem that the existing basement pipelines are connected below the basement structure beams, which affects the height of the basement. The net height of the entire basement can be improved with a small amount of investment.
[0006] The present invention is achieved through the following technical solutions.
[0007] The present invention provides a hidden arrangement method for a basement air duct, comprising an air duct and an air outlet. The air duct is arranged above the elevation of a basement top plate structural beam, or is arranged below the elevation of a basement bottom plate floor building surface layer, or is arranged at the same time; the air outlet is formed by adding a ventilation component or a ventilation shaft to the air duct according to the designed position.
[0008] Furthermore, the air duct structure includes a structure of an S-type hidden arrangement method and a structure of an X-type hidden arrangement method.
[0009] Furthermore, the S-type implicit arrangement method includes:
[0010] Above the basement top plate structural beam elevation, a channel cavity with a bottom slotted toward the basement space is set in the building material, and a detachable prefabricated plate is installed as part of the bottom plate to seal the bottom of the slotted channel cavity to form an air duct;
[0011] Above the basement top slab structural beam elevation, a passage cavity opening to the basement space at the bottom slab is provided in the building material, and an air duct is formed by embedding finished pipes therein;
[0012] Above the basement top slab structural beam elevation, a closed channel cavity is set inside the building material to form an air duct;
[0013] Above the elevation of the basement top plate structural beam, a closed channel cavity is set in the building material and finished pipes are embedded in the channel cavity to form an air duct.
[0014] Furthermore, the X-type hidden arrangement method includes:
[0015] Below the elevation of the building surface layer of the basement floor, a channel cavity with a top slotted toward the basement space is set in the building material, and a detachable prefabricated plate is installed as a part of the top to block the slotted channel and form an air duct;
[0016] Below the building surface elevation of the basement floor, a closed channel cavity is provided in the building material to form an air duct;
[0017] Below the elevation of the building surface layer of the basement floor, a channel cavity with a top opening to the basement space is set in the building material, a finished pipe is embedded in the channel cavity, and a detachable plate is installed to block the channel cavity opening to form an air duct;
[0018] Below the building surface elevation of the basement floor, a closed channel cavity is set in the building material and finished pipes are embedded in the channel to form an air duct.
[0019] A method for concealed arrangement of basement air ducts is also disclosed, which is characterized by:
[0020] S01: According to the design requirements of the basement, design the diameter and path of the basement air duct;
[0021] S02: Determine the type of implicit layout method based on the basement site conditions and design requirements;
[0022] S03: Further determine the exact location and arrangement of the air duct and air outlet according to the arrangement;
[0023] S04: Determine the size and shape of the structural cavity of the air duct and the air outlet according to the design size required in practice;
[0024] S05: According to the actual design requirements, select the way to construct the structural cavity into an air duct;
[0025] S06: Complete the design of air ducts and air outlets.
[0026] Furthermore, in the above step S02, the implicit arrangement method includes an S-type implicit arrangement method and an X-type implicit arrangement method.
[0027] Furthermore, the upper S-shaped implicit arrangement method and the lower X-shaped implicit arrangement method can be used simultaneously, or one can be used selectively according to the situation.
[0028] Furthermore, in the above step S05, the methods of constructing the structural cavity are: a. directly using the structural cavity closed on four sides in the cross-section to form an air duct; b. using prefabricated panels to seal the structural cavity to form an air duct; c. installing the finished air duct in the structural cavity to form an air duct; d. the structural cavity can also be formed by combining two or three of the above methods "a", "b" and "c".
[0029] Beneficial effects of the present invention:
[0030] 1. Economic value: By processing the height of the projection area of equipment pipelines separately, the overall basement height can be saved by about 0.2-0.3 meters compared with conventional methods. The construction of every 10,000 square meters of basement can save 2,000-3,000 cubic meters of earthwork, and the investment in building materials is also relatively reduced;
[0031] 2. Social value: The hidden layout method makes it possible to replace the finished duct with the civil duct of the main part of the duct, further improving the seismic resistance, fire resistance and durability of the duct, and improving the safety factor of the basement; the amount of earth excavation, transportation and landfill is greatly reduced, which is beneficial to the protection of the ecological environment;
[0032] 3. Aesthetic value: Equipment pipelines such as air ducts seriously affect the appearance of the basement space. The hidden layout method will eliminate the huge air ducts and greatly improve the basement space experience. BRIEF DESCRIPTION OF THE DRAWINGS
[0033] In order to more clearly illustrate the embodiments of the invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.
[0034] Figure 1 It is a structural schematic diagram of the prior art basement air duct arrangement;
[0035] Figure 2 It is a structural schematic diagram of the basement air duct arrangement of the present invention;
[0036] Figure 3 Schematic diagram of the structure of the S-FG-A air duct according to an embodiment of the present invention;
[0037] Figure 4 This is a schematic diagram of another structure of the S-FG-A air duct and related pipeline arrangement in an embodiment of the present invention;
[0038] Figure 5 It is a schematic diagram of another structure of the S-FG-A air duct and another arrangement of related pipelines in an embodiment of the present invention;
[0039] Figure 6 Schematic diagram of the structure of the S-FG-B air duct according to an embodiment of the present invention;
[0040] Figure 7 Schematic diagram of the structure of the S-FG-C air duct according to an embodiment of the present invention;
[0041] Figure 8 Schematic diagram of the structure of the S-FG-D air duct according to an embodiment of the present invention;
[0042] Fig. 9 It is a schematic diagram of the structure of the X-FG-A air duct according to an embodiment of the present invention;
[0043] Fig.10 Schematic diagram of the structure of the X-FG-B air duct according to an embodiment of the present invention;
[0044] Fig.11 It is a schematic diagram of the structure of the X-FG-C air duct according to an embodiment of the present invention;
[0045] Fig.12 Schematic diagram of the structure of the X-FG-D air duct according to an embodiment of the present invention;
[0046] Fig.13 is a schematic structural diagram of the S-FK-A tuyere of an embodiment of the present invention;
[0047] Fig.14 is a schematic structural diagram of the S-FK-B tuyere of an embodiment of the present invention;
[0048] Fig.15 is a schematic structural diagram of the S-FK-C tuyere according to an embodiment of the present invention;
[0049] Fig.16 It is a schematic diagram of the structure of the X-FK-A tuyere of an embodiment of the present invention;
[0050] Fig.17 It is a schematic diagram of the structure of the X-FK-B tuyere of an embodiment of the present invention;
[0051] Fig.18 It is a schematic diagram of the structure of the X-FK-C tuyere of an embodiment of the present invention;
[0052] Fig.19 It is a schematic diagram of the structure of the X-FK-D tuyere of an embodiment of the present invention;
[0053] Fig. 20 This is a schematic diagram of the first structure of the X-shaped tuyere directly arranged in an embodiment of the present invention;
[0054] Fig.21 This is a schematic diagram of the second structure of the X-shaped tuyere directly arranged in an embodiment of the present invention;
[0055] Fig. 22 This is a schematic diagram of the third structure of the X-shaped tuyere directly arranged in an embodiment of the present invention;
[0056] Fig.23 It is a fourth structural schematic diagram of the direct arrangement of the X-shaped air outlets in an embodiment of the present invention. DETAILED DESCRIPTION
[0057] The present invention is described in detail below with reference to the drawings, wherein, for the convenience of description, the directions mentioned below are defined as follows: the up, down, left, right, front, and back directions mentioned below are Figure 1 The up-down, left-right, front-back directions of the projection relationship itself are consistent.
[0058] The air duct referred to in this article refers to the pipes used for ventilation, smoke exhaust, air supply and other purposes in basement construction for HVAC functions.
[0059] The floor height in this article refers to the vertical distance between the floor surfaces of two adjacent basement floors, or the vertical distance between the basement floor surface and the basement bottom slab surface.
[0060] The clear height in this article refers to the vertical distance between the floor surface or basement floor surface and the lowest point of the upper structure beams, equipment pipelines, and ceiling bottom surface.
[0061] Combined with Figure 1-23 The disclosed concealed arrangement structure of a basement air duct.
[0062] Including the arrangement structure formed by the S-type implicit arrangement method and the arrangement structure formed by the X-type implicit arrangement method:
[0063] The layout structure of the S-type implicit layout method is:
[0064] Above the basement top plate structural beam elevation, a channel cavity with a bottom slotted toward the basement space is set in the building material, and a detachable prefabricated plate is installed as part of the bottom plate to seal the bottom of the slotted channel cavity to form an air duct;
[0065] Above the basement top slab structural beam elevation, a passage cavity opening to the basement space at the bottom slab is provided in the building material, and an air duct is formed by embedding finished pipes therein;
[0066] Above the basement top slab structural beam elevation, a closed channel cavity is set inside the building material to form an air duct;
[0067] Above the elevation of the basement top plate structural beam, a closed channel cavity is set in the building material and finished pipes are embedded in the channel cavity to form an air duct.
[0068] The layout structure of the X-type implicit layout method is:
[0069] Below the elevation of the building surface layer of the basement floor, a channel cavity with a top slotted toward the basement space is set in the building material, and a removable plate is installed as part of the top to block the slotted channel to form an air duct;
[0070] Below the building surface elevation of the basement floor, a closed channel cavity is provided in the building material to form an air duct;
[0071] Below the elevation of the building surface layer of the basement floor, a channel cavity with a top opening to the basement space is set in the building material, a pipe is embedded in the channel cavity, and a detachable plate is installed to block the channel cavity opening to form an air duct;
[0072] Below the building surface elevation of the basement floor, a closed channel cavity is set in the building material and finished pipes are embedded in the channel to form an air duct.
[0073] Through the above technical solutions, the air duct no longer occupies the net height of the basement. The relevant water pipelines and cable trays are arranged as follows: 1. The air duct is arranged above the elevation of the basement top plate structural beam or below the elevation of the basement bottom plate building surface layer; 2. The pipeline is arranged through the perforation of the structural beam; 3. Select the area with lower beam height and arrange it under the structural beam; 4. Use some of the above 1, 2, 3 in combination.
[0074] The core of the implicit layout method is to accurately handle the height of the equipment pipeline area, so as to optimize the basement height. Setting the air duct above the basement top plate structural beam elevation, or setting it below the basement floor floor building surface elevation is part of its implementation method. There are many specific construction methods with the same topological relationship. The typical cases are as follows;
[0075] General Examples:
[0076] 1. S-shaped hidden layout method duct structure;
[0077] The S-type implicit layout method is to set the air duct above the elevation of the basement top plate structural beam.
[0078] 1.1S-FG-A type air duct structure;
[0079] like Figure 3-5The S-FG-A type duct is suitable for scenes where civil ducts can be used and the selected construction molds are difficult to remove. The construction method is as follows: above the basement top plate structural beam elevation, a structural cavity channel with three sides closed in the cross-sectional view is set. The direction and size of the cavity channel are determined by the HVAC design. The cavity channel is a structure with one or more parallel structures. A groove is reserved at the bottom of the cavity channel. Prefabricated panels are installed at the reserved grooves for blocking, so that the cavity channel has the function of an air duct;
[0080] The method of installing the plate at the reserved slot is: setting a structural head at the bottom of the cavity to facilitate the sealing of the prefabricated plate, or using a non-structural head, or directly sealing with a prefabricated plate.
[0081] The size and form of the reserved slots shall be designed in depth according to actual needs to facilitate the removal of construction formwork, installation of air vents and maintenance measures.
[0082] The slots are sealed with prefabricated panels, and the panels and connection methods must meet the relevant national standards for fire protection, earthquake resistance, air tightness, etc.
[0083] In subsequent implementations, in order to further optimize the net height of the basement, water pipelines and electromechanical bridges can be set in some cavities within the multiple cavity channels, or can be perforated through the structural beams, or placed under the structural beams.
[0084] 1.2S-FG-B type air duct structure;
[0085] like Figure 6 The S-FG-B type air duct is suitable for scenes where finished air ducts are required. The construction method is as follows: above the elevation of the basement top plate structural beam, a structural cavity channel that is closed on three sides in the cross-sectional view is set. The direction and size of the cavity channel are determined by the HVAC design. The cavity channel has one or more parallel structures. A groove is reserved at the bottom of the cavity channel. A finished air duct is set inside the cavity, and the finished air duct can be directly fixed inside the cavity.
[0086] The size and form of the reserved slots shall be designed in depth according to actual needs to facilitate the removal of construction formwork, installation of air ducts and air outlets, maintenance and repair, etc.
[0087] In subsequent implementations, in order to further optimize the net height of the basement, water pipelines and electromechanical bridges can be set in some cavities within the multiple cavity channels, or in the form of perforated structural beams, or placed under the structural beams.
[0088] 1.3S-FG-C type air duct structure;
[0089] like Figure 7The S-FG-C type air duct is suitable for scenes where civil engineering air ducts can be used and the selected construction molds are easy to remove. The construction method is as follows: above the elevation of the basement top plate structural beam, a structural cavity channel closed on all four sides in the cross-sectional view is set. The direction and size of the cavity channel are determined by the HVAC design. The cavity channel has one or more parallel structures, and the cavity can be used directly as an air duct.
[0090] In subsequent implementations, in order to further optimize the net height of the basement, water pipelines and electromechanical bridges can be set in cavities with partially open bottoms in multiple cavity channels, or in the form of perforated structural beams, or placed under structural beams.
[0091] 1.4S-FG-D type air duct structure;
[0092] like Figure 8 The S-FG-D type air duct is suitable for scenes where civil engineering air ducts can be used and the selected construction molds are easy to remove. The construction method is as follows: above the elevation of the basement top plate structural beam, a structural cavity channel closed on all four sides in the cross-sectional view is set. The direction and size of the cavity channel are determined by the HVAC design. The cavity channel has one or more parallel structures, and a finished air duct is set in the cavity.
[0093] In subsequent implementations, in order to further optimize the net height of the basement, water pipelines and electromechanical bridges can be set in cavities with partially open bottoms in multiple cavity channels, or in the form of perforated structural beams, or placed under structural beams.
[0094] 2. X-type hidden layout method duct structure;
[0095] The X-type hidden layout method is to set the air duct below the basement floor building surface elevation.
[0096] 2.1X-FG-A type air duct structure;
[0097] like Fig. 9 The X-FG-A type air duct is suitable for scenes where civil engineering air ducts can be used and the selected construction molds are difficult to remove. The construction method is as follows: below the basement floor building surface elevation, a structural cavity channel that is closed on three sides in the cross-sectional view is set. The direction and size of the cavity channel are determined by the HVAC design. The cavity channel is a structure with one or more parallel structures. Slots are reserved on the top of the cavity channel. Prefabricated panels are installed at the reserved slots for sealing, so that the cavity channel has the function of an air duct.
[0098] The method of installing the plate at the reserved slot is: setting a structural head through the top of the cavity to facilitate the sealing of the prefabricated plate or using a non-structural head and directly sealing with the prefabricated plate.
[0099] The size and form of the reserved slots shall be designed in depth according to actual needs to facilitate the removal of construction formwork, installation of air vents and maintenance measures.
[0100] The slots are sealed with prefabricated panels, and the panels and connection methods must meet the relevant national standards for fire protection, earthquake resistance, air tightness, etc.
[0101] In subsequent implementations, in order to further optimize the net height of the basement, water pipelines and electromechanical bridges can be set in some cavities within the multiple cavity channels, or in the form of perforated structural beams, or placed under the structural beams.
[0102] 2.2X-FG-B type air duct structure;
[0103] like Fig.10 The X-FG-B type air duct is constructed as follows: It is suitable for scenes where civil engineering air ducts can be used and the selected construction molds are easy to remove. The construction method is as follows: Below the basement floor building surface elevation, a structural cavity channel closed on all four sides in the cross-sectional view is set. The direction and size of the cavity channel are determined by the HVAC design. The cavity channel has one or more parallel structures, and the cavity can be used directly as an air duct.
[0104] In the subsequent implementation, in order to further optimize the net height of the basement, water pipelines, electromechanical bridges, etc. can be arranged in partial cavities within multiple cavity channels.
[0105] 2.3X-FG-C type air duct structure;
[0106] like Fig.11 The construction method of X-FG-C type air duct is as follows: below the basement floor building surface elevation, a structural cavity channel with three sides closed in the cross-sectional view is set. The cavity channel has one or more parallel structures. The finished air duct is embedded in the cavity channel. A groove is reserved on the top of the cavity channel, and prefabricated panels are installed at the reserved grooves for sealing.
[0107] The size and form of the openings are designed according to actual needs to facilitate the removal of construction templates, installation of vents, and maintenance measures. The openings are sealed with prefabricated panels, and the panels and connection methods must meet the requirements of relevant national standards such as fire protection, earthquake resistance, and air tightness.
[0108] In subsequent implementations, in order to further optimize the net height of the basement, water pipelines and electromechanical bridges can be set in multiple cavity channels with partially open top cavities (covered with prefabricated panels), or in the form of perforated structural beams, or placed under structural beams.
[0109] 2.1.4X-FG-D type air duct structure;
[0110] like Fig.12The X-FG-D type air duct is suitable for scenes where the selected construction mold is easy to remove. The construction method is as follows: below the basement floor building surface elevation, a structural cavity channel closed on all four sides in the cross-sectional view is set. The direction and size of the cavity channel are determined by the HVAC design. The cavity channel has one or more parallel structures, and the finished air duct is embedded in the cavity.
[0111] In subsequent implementations, in order to further optimize the net height of the basement, water pipelines and electromechanical bridges can be set in multiple cavity channels with partially open top cavities (covered with prefabricated panels), or in the form of perforated structural beams, or placed under structural beams.
[0112] 3. S-shaped hidden layout method of air outlet structure;
[0113] The air outlet of the S-shaped hidden arrangement method is used in conjunction with the air duct of the S-shaped hidden arrangement method.
[0114] 3.1S-FK-A type tuyere structure;
[0115] like Fig.13 The S-FK-A type air outlet is suitable for installation on the S-FG-A type and S-FG-C type air ducts. According to the HVAC design, holes are reserved at the appropriate position at the bottom of the S-FG-A type air duct, and plate air outlet plates are installed at the reserved openings for sealing. The air outlet can be in the form of ventilation louvers, grilles, etc.; or according to the air outlet height requirements, a finished downward air outlet can be selected.
[0116] The size and form of the opening are designed according to actual needs to facilitate the removal of construction templates, installation and maintenance of air outlets, etc. Prefabricated air outlets (ventilation shutters, etc.) are selected and installed at the opening position based on factors such as ventilation volume.
[0117] 3.2S-FK-B type tuyere structure;
[0118] like Fig.14 The S-FK-B type air outlet is suitable for setting on the S-FG-B type and S-FG-D type air ducts. According to the HVAC design, holes are reserved at the appropriate position at the bottom of the S-FG-B type air duct cavity, and the finished air duct and air outlet are connected through the reserved holes, or the air outlet is directly set on the finished wind and light. The air outlet can be in the form of ventilation shutters, grilles, etc. Or according to the height requirements of the air outlet, choose the finished downward air outlet.
[0119] The size and form of the opening are designed according to actual needs to facilitate the removal of construction templates, installation and maintenance of air outlets, etc. Prefabricated air outlets (ventilation shutters, etc.) are selected and installed at the opening position based on factors such as ventilation volume.
[0120] 3.3S-FK-C type tuyere structure;
[0121] like Fig.15The S-FK-C type tuyere is suitable for scenes where the tuyere needs to be lowered and a relatively complete duct image needs to be ensured. According to the HVAC design, holes are reserved at appropriate positions at the bottom of the S-FG-A, S-FG-B, S-FG-C, and S-FG-D duct cavities, and civil construction shafts are set below the reserved openings, and openings are set on the side walls of the shafts. Prefabricated tuyere (ventilation shutters, etc.) are selected based on factors such as ventilation volume and installed at the shaft opening.
[0122] The size and form of the opening are designed according to actual needs to facilitate the removal of construction templates, installation and maintenance of air outlets, etc. Prefabricated air outlets (ventilation shutters, etc.) are selected and installed at the opening position based on factors such as ventilation volume.
[0123] 4.X-type hidden layout method of air outlet structure.
[0124] The X-shaped concealed arrangement method of air outlets is used in conjunction with the X-shaped concealed arrangement method of air ducts.
[0125] 4.1X-FK-A type;
[0126] X-FK-A type air vent is suitable for use in scenarios where high demand for air vent maintenance is required.
[0127] like Fig.16 The X-FK-A type tuyere is constructed as follows: an expanded air chamber and a vertical shaft are set on one side of the cavity of the X-FG-A type, X-FG-B type, X-FG-C type, and X-FG-D type ducts, and tuyere openings are reserved on the side walls of the vertical shafts. The size and form of the openings are further designed according to actual needs to facilitate the removal of construction templates, tuyere installation and maintenance, etc.
[0128] Prefabricated air vents (ventilation shutters, etc.) are selected based on factors such as ventilation volume and installed at the opening of the shaft.
[0129] The size and form of the openings are designed according to actual needs to facilitate the removal of construction formwork, installation of vents and maintenance, etc.
[0130] 4.2X-FK-B type;
[0131] X-FK-B type air vent is suitable for use in scenarios where the air shaft area is relatively limited.
[0132] like Fig.17 The X-FK-B type air outlet is constructed as follows: a vertical shaft is set above the cavity of the X-FG-A type, X-FG-B type, X-FG-C type, and X-FG-D type air duct, and air outlet openings are reserved on the side walls of the vertical shaft. The opening size and form are further designed according to actual needs to facilitate the removal of construction templates, air outlet installation and maintenance measures. Prefabricated air outlets (ventilation shutters, etc.) are selected based on factors such as ventilation volume and installed at the opening position of the vertical shaft.
[0133] The size and form of the openings are designed according to actual needs to facilitate the removal of construction formwork, installation of vents and maintenance, etc.
[0134] 4.3X-FK-C type;
[0135] X-FK-C type air vents are suitable for scenarios where airflow needs to flow from the bottom.
[0136] like Fig.18 The X-FK-C type air outlet is constructed as follows: Openings and air outlets are directly set on the X-FG-A type, X-FG-B type, X-FG-C type, and X-FG-D type air duct cavity. The size and form of the opening are further designed according to actual needs to facilitate the removal of construction templates, air outlet installation and maintenance measures. Prefabricated air outlets (ventilation louvers, etc.) are selected based on factors such as ventilation volume and installed at the opening position of the cavity. If the cavity is equipped with a finished air duct, the connection between the air outlet and the finished air duct and the structural cavity must be handled properly.
[0137] The size and form of the openings are designed according to actual needs to facilitate the removal of construction formwork, installation of vents and maintenance, etc.
[0138] 4.4X-FK-D type;
[0139] The X-FK-D type air outlet is suitable for scenarios where airflow needs to flow from the bottom and the air duct cleaning requirements are high.
[0140] like Fig.19 The X-FK-D type air outlet is constructed as follows: holes are opened locally on the side of the cavity of the X-FG-A type, X-FG-B type, X-FG-C type, and X-FG-D type air ducts as required, and an expanded air chamber is set. When the cavity and the expanded air chamber are used as air ducts, air outlet openings are reserved on the top of the expanded air chamber. The size and form of the openings are further designed according to actual needs to facilitate the removal of construction templates, air outlet installation and maintenance measures. Prefabricated air outlets (ventilation louvers, etc.) are selected based on factors such as ventilation volume and installed at the opening position of the expanded air chamber. If a finished air duct is installed in the cavity and the expanded air chamber, the connection between the air outlet and the finished air duct and the structural cavity must be properly handled.
[0141] The size and form of the openings are designed according to actual needs to facilitate the removal of construction formwork, installation of vents and maintenance, etc.
[0142] The design of the air duct and the air outlet is not limited to the single structural form mentioned above, and a variety of structural forms can be used in combination. In addition, the structural head shapes of the air duct and the air outlet involved in the article can be changed according to actual conditions.
[0143] The tuyere structure of the X-shaped hidden arrangement method of the tuyere includes, in addition to the tuyere for the shaft travel mentioned above, the following:
[0144] like Figure 20-23 , a ventilation duct fence is directly set on the upper part of the air duct to form an air outlet. If the cavity has a prefabricated plate structure, a ventilation duct fence is set at the position of the prefabricated plate. If there is a finished air duct inside the cavity, a ventilation outlet needs to be set on the finished air duct, and then it is further used in conjunction with the ventilation duct fence on the prefabricated plate.
[0145] Meanwhile, in the above-mentioned embodiments of the air duct, there are two arrangements of the relevant pipelines, and the specific arrangements are the two arrangement structures disclosed in S-FG-A.
[0146] The basement air duct of the present application includes but is not limited to the above-mentioned specific structure.
[0147] The present application also discloses a hidden arrangement method of basement air ducts, the steps of which are:
[0148] S01: Design the path of the basement air duct according to the design requirements of the basement;
[0149] S02: Determine the model of the hidden layout method based on the basement site conditions and design requirements;
[0150] S03: Further determine the exact location and arrangement of the air duct and air outlet according to the arrangement;
[0151] S04: Determine the size and shape of the structural cavity of the air duct and the air outlet according to the design size required in practice;
[0152] S05: According to the actual design requirements, select the way to construct the structural cavity into an air duct;
[0153] S06: Complete the design of air ducts and air outlets.
[0154] In the above step S02, the implicit arrangement method includes an upper S-type implicit arrangement method and a lower X-type implicit arrangement method.
[0155] In the above step S05, the methods of constructing the structural cavity are: a. directly using the closed structural cavity as the air duct; b. using prefabricated panels to seal the structural cavity; c. installing the finished air duct in the structural cavity to form the air duct; d. the three methods of "a", "b" and "c" cooperate with each other to form the structural cavity.
[0156] The above embodiments are only for illustrating the technical concept and features of the present invention, and their purpose is to enable people familiar with the technology in this field to understand the content of the present invention and implement it, and they cannot be used to limit the protection scope of the present invention. Any equivalent changes or modifications made according to the spirit of the present invention should be included in the protection scope of the present invention.
Claims
1. A hidden arrangement structure of a basement air duct, comprising an air duct and an air outlet, characterized in that: The air duct is set above the elevation of the basement top plate structural beam, or below the elevation of the basement bottom plate building surface layer, or both; the air outlet is formed by adding ventilation components or ventilation shafts to the air duct according to the designed position.
2. The concealed arrangement structure of the basement air duct according to claim 1 is characterized in that: The air duct structure includes an S-type implicit layout method structure and an X-type implicit layout method structure.
3. The concealed arrangement structure of the basement air duct according to claim 2 is characterized in that: The S-type implicit arrangement method includes: Above the basement top plate structural beam elevation, a channel cavity with a bottom slotted toward the basement space is set in the building material, and a detachable prefabricated plate is installed as part of the bottom plate to seal the bottom of the slotted channel cavity to form an air duct; Above the basement top slab structural beam elevation, a passage cavity opening to the basement space at the bottom slab is provided in the building material, and an air duct is formed by embedding finished pipes therein; Above the basement top slab structural beam elevation, a closed channel cavity is set inside the building material to form an air duct; Above the elevation of the basement top plate structural beam, a closed channel cavity is set in the building material and finished pipes are embedded in the channel cavity to form an air duct.
4. The concealed arrangement structure of the basement air duct according to claim 2 is characterized in that: X-type hidden layout methods include: Below the elevation of the building surface layer of the basement floor, a channel cavity with a top slotted toward the basement space is set in the building material, and a detachable prefabricated plate is installed as a part of the top to block the slotted channel and form an air duct; Below the building surface elevation of the basement floor, a closed channel cavity is provided in the building material to form an air duct; Below the elevation of the building surface layer of the basement floor, a channel cavity with a top opening to the basement space is set in the building material, a finished pipe is embedded in the channel cavity, and a detachable plate is installed to block the channel cavity opening to form an air duct; Below the building surface elevation of the basement floor slab, a closed channel cavity is set in the building material and finished pipes are embedded in the channel to form an air duct.
5. A hidden arrangement method for basement air ducts, characterized in that: S01: According to the design requirements of the basement, design the diameter and path of the basement air duct; S02: Determine the type of implicit layout method based on the basement site conditions and design requirements; S03: Further determine the exact location and arrangement of the air duct and air outlet according to the arrangement; S04: Determine the size and shape of the structural cavity of the air duct and air outlet according to the design size of actual needs; S05: According to the actual design requirements, the structure of the structural cavity is selected to form the air duct; S06: Complete the design of air ducts and air outlets.
6. The method for concealed arrangement of basement air ducts according to claim 5, characterized in that: In the above step S02, the implicit arrangement method includes an S-type implicit arrangement method and an X-type implicit arrangement method.
7. The method for concealed arrangement of basement air ducts according to claim 6, characterized in that: The upper S-type implicit arrangement method and the lower X-type implicit arrangement method can be used simultaneously, or one can be used selectively according to the circumstances.
8. The method for concealed arrangement of basement air ducts according to claim 5, characterized in that: In the above step S05, the methods of constructing the structural cavity are: a. directly using the structural cavity closed on four sides in the cross-section to form an air duct; b. using prefabricated panels to seal the structural cavity to form an air duct; c. installing the finished air duct in the structural cavity to form an air duct; d. the structural cavity can also be formed by combining two or three of the above methods "a", "b" and "c".