Crab stick production whole process control method, system and equipment

By obtaining the production parameter information of crab willow and automatically controlling the crab willow production device, the inefficiency problem caused by manual operation in the traditional production process is solved, and a more efficient and accurate production process is achieved.

CN119087944AActive Publication Date: 2024-12-06RUIAN HUAZHONG AQUATIC PROD CO LTD

Patent Information

Application Number
CN202411265009.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-10
Publication Date
2024-12-06
Estimated Expiration
2044-09-10

AI Technical Summary

Technical Problem

The traditional crab willow production process relies on a large number of manual operations, which is prone to human errors and lead to low production efficiency.

Method used

By obtaining the production parameter information of the crab willow to be produced, the crab willow production device is automatically controlled, and manual operations are reduced to ensure that the production process is carried out according to the parameter information.

Benefits of technology

Improve production efficiency, reduce the occurrence of human errors, and ensure the automation and accuracy of the production process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119087944A_ABST
    Figure CN119087944A_ABST
Patent Text Reader

Abstract

The invention is suitable for the technical field of crab stick production whole-process control, and particularly relates to a crab stick production whole-process control method, system and equipment, and the method comprises the steps: obtaining the production parameter information of to-be-produced crab sticks; wherein the production parameter information is used for reflecting the type condition of the crab sticks to be produced; and controlling the crab stick production device to produce crab sticks based on the production parameter information. According to the whole-process control method for crab stick production, the problems that in the traditional crab stick production process, a large amount of manual operation is usually relied on, human errors are prone to occurring, and the production efficiency is low can be solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application belongs to the technical field of full-process control of crab stick production, and in particular, relates to a method, system and equipment for full-process control of crab stick production. Background Art

[0002] Crab sticks are imitation crab meat products made from fish meat and other ingredients as the main raw materials. For example, the main ingredients of crab sticks may include crab meat, fish meat, starch, seasonings and other additives. For example, the production process of crab sticks usually includes mixing crab meat and fish meat, adding starch and seasonings, extruding, steaming, cooling and packaging.

[0003] The traditional crab stick production process usually relies heavily on manual operation (for example, the adjustment and setting of crab stick production equipment often requires manual intervention), which is prone to human errors and leads to low production efficiency. Summary of the invention

[0004] The embodiments of the present application provide a method, system and equipment for controlling the entire process of crab stick production, which can solve the problem that in the traditional crab stick production process, a large amount of manual operation is usually relied on, which is prone to human errors and leads to low production efficiency.

[0005] In a first aspect, an embodiment of the present application provides a method for controlling the entire process of crab stick production, which is applied to a device for controlling the entire process of crab stick production, wherein the device for controlling the entire process of crab stick production is electrically connected to a crab stick production device, and the method comprises: Acquire production parameter information of the crab sticks to be produced; wherein the production parameter information is used to reflect the type of the crab sticks to be produced; Based on the production parameter information, the crab stick production device is controlled to produce crab sticks.

[0006] The whole process control method of crab stick production provided by the present application, firstly, by obtaining production parameter information including the type of crab sticks to be produced, data support can be provided for subsequent production, which helps to ensure that the parameter settings of the subsequent crab stick production device meet the specific requirements of the crab sticks to be produced, thereby reducing the occurrence of human errors and helping to improve production efficiency. Then, based on the production parameter information, the crab stick production device is controlled to produce crab sticks, which can ensure that the production process is automatically carried out according to the production parameter information, reducing the dependence on manual operation, reducing human errors, and thus helping to improve production efficiency.

[0007] In a possible implementation manner of the first aspect, before controlling the crab stick production device to produce crab sticks based on the production parameter information, the method further includes: In the case where the crab stick production device has not started the first production service, monitoring the adjustment service; wherein the first production service is the service of producing the first type of crab sticks; the adjustment service is used to instruct the crab stick production device to start the first production service in the case where production has not started, and to stop the first production service in the case where production has started; In the case of monitoring the adjustment service, starting the timing task, and not running the adjustment service before the timing task is completed; During the running of the timing task, if the first service is not monitored, the adjustment service is run after the timing task is completed; wherein the first service is a service in the same production period as the adjustment service, and the priority of the first service is higher than the priority of the adjustment service; the first service is used to indicate that the crab stick production device currently needs maintenance service; During the execution of the timing task, if the first service is monitored, the adjustment service is deleted after the timing task is completed.

[0008] In a possible implementation manner of the first aspect, if the first service is not monitored during the execution of the timing task, executing the adjustment service after the timing task is completed includes: During the execution of the timing task, if the first service is not monitored and the adjustment service is not monitored again, the adjustment service is executed after the timing task is completed.

[0009] In a possible implementation manner of the first aspect, the method further includes: During the running of the timing task, if the first service is not monitored and the adjustment service is monitored again, after the timing task is completed, it is determined whether the adjustment service monitored again is to instruct the crab stick production device to start the first production service; When it is determined that the adjustment service monitored again is to instruct the crab stick production device to start the first production service, the adjustment service monitored again is executed; When it is determined that the adjustment service monitored again is to instruct the crab stick production device to stop performing the first production service, the adjustment service and the adjustment service monitored again are deleted.

[0010] In a possible implementation manner of the first aspect, during the execution of the timing task, if the first service is not monitored, after the timing task is completed and the adjustment service is executed, the method further includes: When the crab stick production device starts to perform the first production business, a production control event corresponding to the first production business is run, and the crab stick production device corresponding to the production control event is set to a running mode; wherein the production control event is an event for controlling production parameters of the first production business; When the first instruction for the production control event corresponding to the first production business is monitored and it is obtained that the first production business has not been completely completed, the preset instruction is executed to set the device corresponding to the execution of the preset instruction to the stop mode, and the operation mode of the device corresponding to the preset instruction that has not been executed is continued to be maintained; wherein, the first instruction is used to suspend the control events in the entire production process, and the preset instruction is used to replace the response of the crab stick production device to the first instruction, and the preset instruction is an instruction to suspend one or more control events in the production control event.

[0011] In a possible implementation manner of the first aspect, when the crab stick production device starts to perform the first production business, after running a production control event corresponding to the first production business and setting the crab stick production device corresponding to the production control event to an operation mode, the method further includes: When a preset instruction for the production control event corresponding to the first production service is monitored and it is obtained that the first production service has been completely completed, the production control event corresponding to the first production service is stopped.

[0012] In a possible implementation manner of the first aspect, the method further includes: Obtaining the availability of raw materials; When it is obtained that the supply of raw materials has been completed, the preset instructions are automatically generated.

[0013] In a possible implementation manner of the first aspect, the method further includes: Detecting the volume value of the raw materials in the mixing device of the crab stick production device; When the volume value is greater than or equal to a preset value, and the residence time value of the raw material is greater than or equal to a threshold value, it is determined that the supply of the raw material has been completed.

[0014] In a possible implementation manner of the first aspect, the method further includes: When the crab stick production device starts the first production operation for the first time, the device that is not set to the operating mode is set to the operating mode and maintained for a first preset time; wherein the first preset time is set according to the production time required for the device set to the operating mode.

[0015] In a second aspect, an embodiment of the present application provides a crab stick production full process control system, which is applied to a crab stick production full process control device, wherein the crab stick production full process control device is electrically connected to a crab stick production device, and the crab stick production full process control system includes: An acquisition unit, used for acquiring production parameter information of the crab sticks to be produced; wherein the production parameter information is used for reflecting the type of the crab sticks to be produced; A control unit is used to control the crab stick production device to produce crab sticks based on the production parameter information.

[0016] In the third aspect, an embodiment of the present application provides a full-process control device for crab stick production, comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor implements the full-process control method for crab stick production described in any one of the first aspects above when executing the computer program.

[0017] It can be understood that the beneficial effects of the second to third aspects mentioned above can be found in the relevant description of the first aspect mentioned above, and will not be repeated here. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.

[0019] Figure 1 It is a flow chart of a method for controlling the entire process of crab stick production provided by an embodiment of the present application; Figure 2 This is a schematic diagram of the implementation process before step S200 in the crab stick production full process control method provided in one embodiment of the present application; Figure 3 It is a flow chart of a method for controlling the entire process of crab stick production provided by another embodiment of the present application; Figure 4 It is a schematic diagram of the implementation process after step S240 in the crab stick production full process control method provided in one embodiment of the present application; Figure 5 It is a flow chart of a method for controlling the entire process of crab stick production provided by another embodiment of the present application; Figure 6 It is a flow chart of a method for controlling the entire process of crab stick production provided by another embodiment of the present application; Figure 7 It is a structural schematic diagram of the whole process control system of crab stick production provided by the embodiment of the present application; Figure 8 It is a structural schematic diagram of the crab stick production full-process control equipment provided in the embodiment of the present application. DETAILED DESCRIPTION

[0020] In the following description, specific details such as specific system structures, technologies, etc. are provided for the purpose of illustration rather than limitation, so as to provide a thorough understanding of the embodiments of the present application. However, it should be clear to those skilled in the art that the present application may also be implemented in other embodiments without these specific details. In other cases, detailed descriptions of well-known systems, devices, circuits, and methods are omitted to prevent unnecessary details from obstructing the description of the present application.

[0021] It should be understood that when used in the present specification and the appended claims, the term "comprising" indicates the presence of described features, wholes, steps, operations, elements and / or components, but does not exclude the presence or addition of one or more other features, wholes, steps, operations, elements, components and / or combinations thereof.

[0022] It should also be understood that the term “and / or” used in the specification and appended claims refers to any and all possible combinations of one or more of the associated listed items, and includes these combinations.

[0023] As used in the specification of this application and the appended claims, the term "if" can be interpreted as "when" or "uponce" or "in response to determining" or "in response to detecting" depending on the context. Similarly, the phrase "if it is determined" or "if the described condition or event is detected" can be interpreted as meaning "uponce it is determined" or "in response to determining" or "uponce the described condition or event is detected" or "in response to detecting the described condition or event" depending on the context.

[0024] In addition, in the description of the present application specification and the appended claims, the terms "first", "second", "third", etc. are only used to distinguish the descriptions and cannot be understood as indicating or implying relative importance.

[0025] References to "one embodiment" or "some embodiments" etc. described in the specification of this application mean that one or more embodiments of the present application include specific features, structures or characteristics described in conjunction with the embodiment. Therefore, the statements "in one embodiment", "in some embodiments", "in some other embodiments", "in some other embodiments", etc. that appear in different places in this specification do not necessarily refer to the same embodiment, but mean "one or more but not all embodiments", unless otherwise specifically emphasized in other ways. The terms "including", "comprising", "having" and their variations all mean "including but not limited to", unless otherwise specifically emphasized in other ways.

[0026] In the related art, crab sticks are imitation crab meat products made from fish meat and other ingredients as main raw materials. For example, the main ingredients of crab sticks may include crab meat, fish meat, starch, seasonings and other additives. For example, the production process of crab sticks usually includes mixing crab meat and fish meat, adding starch and seasonings, extruding, steaming, cooling and packaging.

[0027] The traditional crab stick production process usually relies heavily on manual operation (for example, the adjustment and setting of crab stick production equipment often requires manual intervention), which is prone to human errors and leads to low production efficiency.

[0028] To solve the above problems, the embodiments of the present application provide a method, system and equipment for controlling the entire process of crab stick production.

[0029] In the method, first, by obtaining production parameter information including the type of crab sticks to be produced, data support can be provided for subsequent production, which helps to ensure that the parameter settings of the subsequent crab stick production device meet the specific requirements of the crab sticks to be produced, thereby reducing the occurrence of human errors and helping to improve production efficiency. Then, based on the production parameter information, the crab stick production device is controlled to produce crab sticks, which can ensure that the production process is automatically carried out according to the production parameter information, reducing dependence on manual operation, reducing human errors, and thus helping to improve production efficiency.

[0030] The full-process control method for crab stick production provided in the embodiment of the present application can be applied to the full-process control equipment for crab stick production. At this time, the full-process control equipment for crab stick production is the executor of the full-process control method for crab stick production provided in the embodiment of the present application. The embodiment of the present application does not impose any restrictions on the specific type of the full-process control equipment for crab stick production.

[0031] For example, the whole process control equipment of crab stick production can be a single chip microcomputer, a mobile phone, a tablet computer, a laptop computer, an ultra-mobile personal computer (UMPC), a netbook, a desktop computer, a computing device or a computer connected to a wireless modem, a laptop computer, a handheld communication device, a handheld computing device, etc.

[0032] For example, the crab stick production device is electrically connected to the crab stick production full-process control equipment, and the crab stick production device may include a mixing device, a forming device, a cooking device, and a packaging device. The mixing device is used to evenly mix the raw materials and seasonings to form a basic mixture of crab sticks, and convey the basic mixture of crab sticks to the forming device. The forming device is used to press the basic mixture into the shape and specifications required for the crab sticks, and convey the pressed product to the cooking device. The cooking device is used to steam and cook the pressed product to ensure that it is cooked, and convey the cooked product to the packaging device. The packaging device is used to package the cooked product to obtain the finished crab stick product. The crab stick production full-process control equipment can control the production process of the mixing device, the forming device, the cooking device, and the packaging device based on the production parameter information to produce the required crab stick finished product.

[0033] In order to better understand the whole-process control method of crab stick production provided in the embodiment of the present application, the specific implementation process of the whole-process control method of crab stick production provided in the embodiment of the present application is exemplarily introduced below.

[0034] Figure 1 A schematic flow chart of a method for controlling the entire process of crab stick production provided in an embodiment of the present application is shown. The method for controlling the entire process of crab stick production includes: S100, obtaining production parameter information of the crab sticks to be produced, wherein the production parameter information is used to reflect the type of the crab sticks to be produced.

[0035] For example, the production parameter information may be the recipe information of crab sticks, the taste information of crab sticks, the shape information of crab sticks, the parameter information required for the crab sticks to be produced (such as stirring speed, heating temperature), etc. The production parameter information can be obtained from the crab stick samples. For example, the recipe information of crab sticks can be obtained through experiments. The raw material ratios, additives and seasonings required for different types of crab sticks can also be obtained by checking the recipe files. Each type of crab stick has a specific recipe or process flow, and the parameter information corresponding to the type of crab stick can be obtained from the preset database.

[0036] Such a setting can provide data support for subsequent production by obtaining production parameter information of the crab sticks to be produced, which helps to ensure that the parameter settings of the subsequent crab stick production equipment meet the specific requirements of the crab sticks to be produced, thereby reducing the occurrence of human errors and helping to improve production efficiency.

[0037] S200, based on the production parameter information, controlling the crab stick production device to produce crab sticks.

[0038] It can be understood that, first, the key information in the production parameter information is extracted, such as the proportion of crab stick ingredients, the type and specification of raw materials, mixing time, molding pressure, cooking temperature and time, etc. Then, the key information is transmitted to the crab stick production device so that the crab stick production device automatically sets and adjusts parameters, such as setting the mixing time and speed of the mixing device according to the recipe requirements. Finally, the crab stick production device is started to produce crab sticks.

[0039] With such a setting, based on the production parameter information, the crab stick production device is controlled to produce crab sticks, which can ensure that the production process is automatically carried out according to the production parameter information, reduce dependence on manual operation, reduce human errors, and thus help improve production efficiency.

[0040] In one possible implementation, see Figure 2 In step S200, before controlling the crab stick production device to produce crab sticks based on the production parameter information, the crab stick production full process control method further includes: S210, when the crab stick production device has not started the first production service, monitor and adjust the service. The first production service is the service of producing the first type of crab sticks. The adjustment service is used to instruct the crab stick production device to start the first production service when production has not started, and to stop the first production service when production has started.

[0041] It is understandable that sensors can be used to monitor the operating status of the crab stick production device, such as whether the crab stick production device has started the first production business. In the case where the crab stick production device has not started the first production business, a monitoring mechanism can be suggested, for example, it can be implemented by programming logic or hardware sensors to continuously monitor whether there is an "adjustment business" sent to the crab stick production full process control device in the case where the crab stick production device has not started the first production business.

[0042] For example, when the adjustment service is monitored, if the first production service has not started at this time, the crab stick production process control device will control the crab stick production device to start the first production service. On the contrary, if the crab stick production device is already running the first production service when the adjustment service is monitored, the crab stick production process control device will control the crab stick production device to stop the first production service.

[0043] With such an arrangement, before the crab stick production device starts the first production operation, the operation can be monitored and adjusted to ensure that all aspects are ready before formal production, thereby avoiding waste of resources caused by starting production at an inappropriate time and helping to improve subsequent production efficiency.

[0044] S220: When an adjustment service is monitored, a timing task is started, and the adjustment service is not run before the timing task is completed.

[0045] It can be understood that when the crab stick production device monitors the adjustment business, a timing task is immediately started. The duration of this timing task can be set according to production requirements and equipment characteristics. For example, the timing time of the timing task can be 1 minute, 2 minutes, etc. When the timing task is started, the adjustment business will be locked, that is, before the timing task is completed, the adjustment business (such as starting or stopping production) will not be executed.

[0046] For example, when the crab stick production full process control device monitors the adjustment service, it is uncertain whether there are other services (such as maintenance services, overhaul services, parameter adjustment services, etc.) during the production period of the first production service. Therefore, the crab stick production full process control device locks the adjustment service, that is, controls the crab stick production device not to run the adjustment service. In addition, there may be no other services during the production period of the first production service. Therefore, the crab stick production full process control device can use the timing time of the timing task to determine whether there are other services during the production period of the first production service.

[0047] For example, operator A adds an adjustment service, and operator B may add other services after operator A adds the adjustment service. Therefore, in order to avoid production errors caused by the lack of information communication between operator A and operator B, a period of time (i.e., the timing time of the timing task) is required to determine what kind of service operator B adds other services, that is, to determine whether there are other services during the production period of the first production service. If so, the adjustment service will be arranged after the maintenance service; anyway, the adjustment service will be run after the timing task ends. In addition, operator A may continue to add other services (such as adding new production parameters) after adding the adjustment service. Therefore, the crab stick production full process control device can wait for operator A to add other services (such as adding new production parameters) during the timing time of the timing task to determine the final production parameter information. In addition, since operator A may continuously add other services (such as adding new production parameters) after adding the adjustment service, the timing time of the timing task can be the time required for the operator to add or supplement new production parameters.

[0048] This setting starts the timing task when the adjustment business is monitored, and does not run the adjustment business before the timing task is completed, which helps to better coordinate and allocate resources. For example, before production starts, it can ensure that the first production business does not conflict with other businesses, which helps to improve production efficiency.

[0049] S230, if the first service is not monitored during the execution of the timing task, the adjustment service is executed after the timing task is completed. The first service is a service in the same production period as the adjustment service, and the priority of the first service is higher than the priority of the adjustment service. The first service is used to indicate that the current crab stick production device needs maintenance service.

[0050] It can be understood that during the running of the timing task, an event monitoring mechanism or a query of the maintenance schedule can be used to monitor whether there are other businesses during the production period of the first production business. If there are other businesses during the production period when the first production business is not monitored (that is, the first business is not monitored), then after the timing task is completed, the adjustment business is run. If there are other businesses during the production period when the first production business is monitored (that is, the first business is not monitored), then after the timing task is completed, the adjustment business is not run, that is, the adjustment business is deleted. For example, a priority rule can be set so that the first business takes precedence over the adjustment business in scheduling. If the first business is completed, it can be re-evaluated whether to execute the adjustment business, or wait for new business. If the adjustment business is still valid and needs to be executed, the adjustment business will be restored and completed.

[0051] With this setting, if the first service is not monitored during the execution of the timing task, the adjustment service will be run after the timing task is completed. This can avoid conflicts between the adjustment service and the equipment maintenance service, and ensure that production can be carried out after the maintenance work is completed, which helps to better coordinate and allocate resources, thereby improving production efficiency.

[0052] In a possible implementation, S230, if the first service is not monitored during the execution of the timing task, then after the timing task is completed, the adjustment service is executed, including: During the execution of the timing task, if the first service is not monitored and the adjustment service is not monitored again, the adjustment service is executed after the timing task is completed.

[0053] For example, during the execution of the timing task, if the first business is not monitored, it means that there is no other business during the production period of the first production business. At the same time, during the execution of the timing task, operator A may have added an adjustment business (used to instruct the crab stick production full-process control equipment to control the crab stick production device to perform the first production business), and then, other operators did not add an adjustment business (used to instruct the crab stick production full-process control equipment to control the crab stick production device to perform the first production business), which means that there is no conflict with other businesses during the production period of the first production business. Therefore, after the timing task is completed, the adjustment business is run.

[0054] With such a configuration, if the first business is not monitored and the adjustment business is not monitored again during the execution of the timing task, the adjustment business will be run after the timing task is completed, so that the original first production business can be carried out according to the predetermined production plan, thereby preventing production delays due to delays or inaction, thereby improving production efficiency.

[0055] In one possible implementation, see Figure 3 The whole process control method of crab stick production also includes: S231, during the execution of the timing task, if the first service is not monitored and the adjustment service is monitored again, then after the timing task is completed, it is determined whether the adjustment service monitored again is to instruct the crab stick production device to start the first production service.

[0056] It can be understood that during the running of the timing task, if the first business is not monitored and the adjustment business is monitored again, there is a conflict with other businesses during the production of the first production business. For example, operator A may add an adjustment business (used to instruct the crab stick production full-process control equipment to control the crab stick production device to perform the first production business), and then operator B finds out that the quantity of raw materials is insufficient to support the crab stick production device to perform the first production business, or finds out that the energy required for production (such as electricity, steam, etc.) or other resources (such as cooling water, compressed air, etc.) cannot meet the production needs of the first production business. Therefore, operator B can add an adjustment business, so that the crab stick production full-process control equipment monitors the adjustment business again to instruct the crab stick production full-process control equipment to control the crab stick production device not to perform the first production business. For another example, operator A may have added an adjustment service (used to instruct the crab stick production process control equipment to control the crab stick production device to perform the first production service), and then operator B also added an adjustment service (used to instruct the crab stick production process control equipment to control the crab stick production device to perform the first production service). Therefore, in order to avoid multiple adjustment services occupying resources, at this time, when multiple adjustment services are instructing the crab stick production process control equipment to control the crab stick production device to perform the first production service, only the last added adjustment service, that is, the adjustment service monitored again, needs to be run. Therefore, after the timing task is completed, it is necessary to distinguish whether the adjustment service monitored again is to instruct the crab stick production device to start the first production service.

[0057] For example, if the adjustment service monitored again is used to instruct the crab stick production device to start the first production service, and the crab stick production device has not started the first production service, then the adjustment service monitored again can be run; if the adjustment service monitored again is used to instruct the crab stick production device to stop performing the first production service, and the crab stick production device has not started the first production service, then the adjustment service and the adjustment service monitored again are deleted, so that the crab stick production device will not be controlled to start the first production service.

[0058] With such a setting, during the running of the timing task, if the first business is not monitored and the adjustment business is monitored again, then after the timing task is completed, it is determined whether the adjustment business monitored again is to instruct the crab stick production device to start the first production business. Multiple businesses can be automatically processed to avoid confusion between businesses, which helps to better coordinate and allocate resources, thereby improving production efficiency.

[0059] S232: When it is determined that the adjustment service monitored again is to instruct the crab stick production device to start the first production service, the adjustment service monitored again is executed.

[0060] For example, when it is determined that the adjustment service monitored again is to instruct the crab stick production device to start the first production service, it means that the adjustment service monitored for the first time and the adjustment service monitored again are both instructing the crab stick production full-process control equipment to control the crab stick production device to perform the first production service. Therefore, only the adjustment service monitored again needs to be run.

[0061] With such a configuration, when it is determined that the adjustment service monitored again is instructing the crab stick production device to start the first production service, the adjustment service monitored again is run, which can ensure that the first production service starts production according to the predetermined plan, helps to meet production needs, and thus improves production efficiency.

[0062] S233, when it is identified that the adjustment service monitored again is to instruct the crab stick production device to stop performing the first production service, the adjustment service and the adjustment service monitored again are deleted.

[0063] It can be understood that when it is identified that the adjustment business monitored again is to instruct the crab stick production device to stop the first production business, it means that the current quantity of raw materials is insufficient to support the crab stick production device to carry out the first production business, or, it is found that the energy required for production (such as electricity, steam, etc.) or other resources (such as cooling water, compressed air, etc.) cannot meet the production needs of the first production business. Therefore, the adjustment business and the adjustment business monitored again can be deleted, so that the crab stick production device will not be controlled to start the first production business.

[0064] With such a setting, when it is identified that the adjustment business monitored again is to instruct the crab stick production device to stop the first production business, the adjustment business and the adjustment business monitored again are deleted, which can avoid continuing production when the current production conditions cannot meet the production requirements of the first production business, thereby helping to better coordinate and allocate resources and thus improve production efficiency.

[0065] S240: If the first service is monitored during the execution of the timing task, the adjustment service is deleted after the timing task is completed.

[0066] It is understood that during the execution of the timing task, the event monitoring mechanism or the query of the maintenance schedule can be used to monitor whether there are other services during the production period of the first production service. If there are other services during the production period of the first production service (i.e., the first service is not monitored), then after the timing task is completed, the adjustment service is not executed, i.e., the adjustment service is deleted.

[0067] With this setting, if the first business is monitored during the execution of the timing task, the adjustment business will be deleted after the timing task is completed, which can avoid conflicts between the adjustment business and the equipment maintenance business, ensuring that production can be carried out after the maintenance work is completed, which helps to better coordinate and allocate resources, thereby improving production efficiency.

[0068] In one possible implementation, see Figure 4 In step S230, if the first service is not monitored during the execution of the timing task, after the timing task is completed and the adjustment service is executed, the whole process control method of crab stick production further includes: S250, when the crab stick production device starts to perform the first production service, run the production control event corresponding to the first production service, and set the crab stick production device corresponding to the production control event to the operation mode. The production control event is an event for controlling the production parameters of the first production service.

[0069] It can be understood that, first, it is necessary to detect the current state of the crab stick production device to confirm whether the first production business has been started. For example, this can be achieved by monitoring specific system signals, production instructions or status identifiers. When it is confirmed that the crab stick production device has started the first production business, a production control event corresponding to the first production business can be triggered. The production control event can be to control and adjust the production parameters of the first production business, such as controlling temperature, pressure, speed, or controlling the start and stop of the device. When it is confirmed that the crab stick production device has started the first production business, it is necessary to start the crab stick production device, that is, to set the crab stick production device corresponding to the production control event to the operating mode, so that the crab stick production device automatically enters the operating state.

[0070] With such a setting, when the crab stick production device starts the first production business, the production control event corresponding to the first production business is run, and the crab stick production device corresponding to the production control event is set to the operation mode. The production parameters can be automatically adjusted without human intervention, thereby reducing human errors, ensuring smooth production process, and greatly improving production efficiency.

[0071] In a possible implementation, in step S250, when the crab stick production device starts to perform the first production business, the production control event corresponding to the first production business is run, and the crab stick production device corresponding to the production control event is set to the operation mode, the crab stick production full process control method further includes: When a preset instruction for a production control event corresponding to the first production service is monitored and it is obtained that the first production service has been completely terminated, the production control event corresponding to the first production service is stopped.

[0072] It can be understood that when the preset instructions for the production control event corresponding to the first production business are monitored and it is obtained that the first production business has been completely completed, it means that even if the operator accidentally touches the button of the control event to stop production, or the operator mistakenly thinks that the first production business has been completed and no longer needs to be controlled, and therefore enters the first instruction, it will not interfere with the production process of the first production business. Therefore, the first instruction can be responded to to stop the production control event corresponding to the first production business.

[0073] With such a setting, when the preset instructions for the production control event corresponding to the first production business are monitored and it is obtained that the first production business has been completely completed, the production control event corresponding to the first production business is stopped, which can prevent unnecessary resource consumption, such as waste of energy, raw materials and human resources, thereby improving the overall resource utilization efficiency.

[0074] S260, when a first instruction for a production control event corresponding to a first production service is monitored and it is obtained that the first production service has not been completely terminated, a preset instruction is executed to set the device corresponding to the preset instruction to a stop mode, and the operation mode of the device corresponding to the preset instruction not executed is continued. The first instruction is used to suspend the control event of the entire production process, the preset instruction is used to replace the response of the crab stick production device to the first instruction, and the preset instruction is an instruction to suspend one or more control events in the production control event.

[0075] For example, a listener can be set up to listen to a first instruction for a production control event corresponding to a first production business. The first instruction can be an instruction to stop the control events in the entire production process. For example, a crab stick production device can include a mixing device, a forming device, a steaming device, and a packaging device, etc. The first instruction can be an instruction to stop the control events of the mixing device, the forming device, the steaming device, and the packaging device. For example, the first instruction can be used to adjust the operating mode of the mixing device, the forming device, the steaming device, and the packaging device (such as a crab stick production mode) to a stop mode (such as a crab stick non-production mode).

[0076] It can be understood that the monitoring of the first instruction of the production control event corresponding to the first production business may be that the operator accidentally touched the button of the control event that stops the entire production process, or the operator mistakenly believes that the first production business has been completed and there is no need to control the first production business. Therefore, the first instruction is sent to the crab stick production full-process control equipment to make all crab stick production devices enter the non-crab stick production mode, that is, the stop mode. Therefore, when the first instruction for the production control event corresponding to the first production business is monitored and it is obtained that the first production business has not been completely completed, it means that the operator mistakenly touched the button of the control event to stop production, or the operator mistakenly thought that the first production business has been completed and there is no need to control the first production business, so the first instruction is input. At this time, in order to avoid production interruption and respond to the first instruction input by the operator, so as to send a response feedback to the operator, it is possible to determine which device has completed the production task and which device has not completed the production task, and control the device that has completed the production task to execute the preset instruction (that is, set the device corresponding to the preset instruction to the stop mode), control the device that has not completed the production task not to execute the preset instruction (that is, continue to maintain the control event of the device corresponding to the preset instruction that has not been executed), and send a notification of the execution of the pause instruction (that is, the preset instruction) to the operator. In this way, it can be avoided that the operator inputs the first instruction to the crab stick production full-process control device without any response, which causes the operator to mistakenly believe that the crab stick production full-process control device has a fault or the crab stick production device has a fault and causes no response.

[0077] For example, the crab stick production device may include a mixing device, a forming device, a cooking device, and a packaging device. During the production process, if the mixing device and the forming device have completed the production task, but the cooking device and the packaging device have not completed the production task, then the mixing device and the forming device are controlled to execute the preset instructions, and the cooking device and the packaging device are controlled not to execute the preset instructions. For example, when the mixing device and the forming device have completed the production task, the mixing device and the forming device can automatically generate a preset instruction to replace the response of the crab stick production device to the first instruction mistakenly input or touched by the operator at any time.

[0078] For example, the crab stick production device may need to suspend the entire production process due to production problems. When problems occur in the crab stick production device, the operator may input a first instruction. At this time, certain parameters in the production process can be obtained through sensors. When the parameter exceeds a preset safety range (for example, the heating temperature in the production process exceeds a threshold), the first instruction is responded to to suspend the entire production process.

[0079] With such a configuration, when the first instruction for the production control event corresponding to the first production business is monitored and it is obtained that the first production business has not yet been completely completed, the preset instruction is executed to set the device corresponding to the preset instruction to the stop mode, and continue to maintain the operation mode of the device corresponding to the preset instruction that has not been executed. This allows the operation of a certain device to be flexibly suspended without affecting the entire production process, which helps to avoid production interruptions and thereby improve production efficiency.

[0080] In one possible implementation, see Figure 5 The whole process control method of crab stick production also includes: S300, obtaining the supply status of raw materials.

[0081] It is understood that the supply of raw materials to the mixing device of the crab stick production device can be monitored in real time by sensors and cameras. For example, the supply status can include the situation of completed supply, the situation of uncompleted supply, etc.

[0082] With such a setting, by obtaining the supply situation of raw materials, it is possible to avoid inputting too much or too little raw materials into the mixing device of the crab stick production device, ensure that the input amount of raw materials in the mixing device meets the preset standards, avoid affecting the final product quality, and thus improve production efficiency.

[0083] S400, when it is obtained that the supply of raw materials has been completed, a preset instruction is automatically generated.

[0084] It can be understood that a workflow or script is set to stipulate that when the input amount of raw materials in the mixing device meets the preset amount, a preset instruction is automatically generated.

[0085] For example, a workflow or script is set to automatically generate a preset instruction when the molding device completes all molding tasks. Alternatively, a workflow or script is set to automatically generate a preset instruction when the steaming device completes all steaming tasks. Alternatively, a workflow or script is set to automatically generate a preset instruction when the packaging device completes all packaging tasks. These preset instructions are used to replace the response of the crab stick production device to the first instruction that is input or touched by mistake.

[0086] With such an arrangement, when it is obtained that the supply of raw materials has been completed, preset instructions are automatically generated. In the event of a first instruction being inputted in error due to human error, a response can be fed back to the operator without interrupting production, which helps to improve production efficiency.

[0087] In one possible implementation, see Figure 6 The whole process control method of crab stick production also includes: S500, detecting the volume value of the raw materials in the mixing device of the crab stick production device.

[0088] It is understood that a flow meter can be used to monitor the inflow of raw materials and calculate the volume value of the raw materials in the mixing device. A volume sensor (such as an ultrasonic or laser sensor) can also be installed in the mixing device to measure the volume value of the raw materials in real time.

[0089] With such a configuration, by detecting the volume value of the raw materials in the mixing device of the crab stick production device, it is possible to avoid inputting too much or too little raw materials into the mixing device of the crab stick production device, thereby ensuring that the input amount of raw materials in the mixing device meets the preset standards, avoiding affecting the final product quality, and thereby improving production efficiency.

[0090] S600: When the volume value is greater than or equal to a preset value and the residence time value of the raw material is greater than or equal to a threshold value, it is determined that the supply of the raw material has been completed.

[0091] It can be understood that when the volume value of the raw material reaches or exceeds the preset value, it means that there are enough raw materials in the mixing device. This preset value can be the minimum amount set according to production needs to ensure the effectiveness of the mixing process. After the volume value meets the conditions, checking the residence time value can ensure that the raw materials have stayed in the mixing device for a sufficient time. This time threshold is to ensure that the raw materials are fully mixed with other ingredients or other necessary processing steps are carried out. Only when the volume value of the raw material is sufficient and the residence time value meets the standard, it can be determined that the raw material has undergone a complete processing process in the mixing device, which means that the raw material has been fully mixed or processed to meet the standards required for production. Therefore, it can be confirmed that the supply process of the raw material has been completed, that is, the processing task in the mixing device has been successfully completed.

[0092] With this setting, when the volume value is greater than or equal to the preset value and the residence time value of the raw material is greater than or equal to the threshold, it is determined that the raw material has been supplied, which helps to ensure that the raw materials are fully mixed or processed, improve the quality of the final product, and thus improve production efficiency.

[0093] In a possible implementation, the whole process control method of crab stick production also includes: When the crab stick production device starts the first production business for the first time, the device that is not set to the operation mode is set to the operation mode and maintained for the first preset time. The first preset time is set according to the production time required for the device set to the operation mode.

[0094] It is understandable that when the crab stick production device starts the first production operation for the first time, some devices may be in the operation mode, while some devices are not in the operation mode. Therefore, in order to avoid production delays, the devices that are not set to the operation mode need to be set to the operation mode and maintained for the first preset time (for example, 20 minutes, 30 minutes, etc.). For example, if the mixing device needs to be processed for 30 minutes, the mixing device can be set to the operation mode and maintained for 30 minutes.

[0095] With such a setting, when the crab stick production device starts the first production operation for the first time, the device that is not set to the operating mode is set to the operating mode and maintained for the first preset time. This can ensure that the device can start normally and carry out production, avoiding production interruptions caused by the equipment not being ready, thereby improving production efficiency.

[0096] It should be understood that the size of the serial numbers of the steps in the above embodiments does not mean the order of execution. The execution order of each process should be determined by its function and internal logic, and should not constitute any limitation on the implementation process of the embodiments of the present application.

[0097] Corresponding to the whole-process control method of crab stick production described in the above embodiment, the embodiment of the present application also provides a whole-process control system for crab stick production, and each unit of the system can implement each step of the whole-process control method of crab stick production. Figure 7 The structural block diagram of the whole process control system of crab stick production provided by the embodiment of the present application is shown. For the convenience of explanation, only the part related to the embodiment of the present application is shown.

[0098] Reference Figure 7 The whole process control system of crab stick production includes: The acquisition unit is used to acquire production parameter information of the crab sticks to be produced, wherein the production parameter information is used to reflect the type of the crab sticks to be produced.

[0099] The control unit is used to control the crab stick production device to produce crab sticks based on production parameter information.

[0100] It should be noted that the information interaction, execution process, etc. between the above-mentioned systems / units are based on the same concept as the method embodiment of the present application. Their specific functions and technical effects can be found in the method embodiment part and will not be repeated here.

[0101] Those skilled in the art can clearly understand that, for the convenience and simplicity of description, only the division of the above-mentioned functional units is used as an example for illustration. In practical applications, the above-mentioned functions can be assigned to different functional units as needed, that is, the internal structure of the system can be divided into different functional units to complete all or part of the functions described above. The functional units in the embodiment can be integrated into a processing unit, or each unit can exist physically separately, or two or more units can be integrated into one unit. The above-mentioned integrated unit can be implemented in the form of hardware or in the form of software functional units. In addition, the specific names of the functional units are only for the convenience of distinguishing each other, and are not used to limit the scope of protection of this application. The specific working process of the units in the above-mentioned system can refer to the corresponding process in the aforementioned method embodiment, which will not be repeated here.

[0102] The present application also provides a crab stick production full process control device, Figure 8 This is a schematic diagram of the structure of the whole process control equipment for crab stick production provided by an embodiment of the present application. Figure 8 As shown, the crab stick production full process control device 6 of this embodiment includes: at least one processor 60 ( Figure 8 Only one is shown), at least one memory 61 ( Figure 8 Only one is shown in the figure) and a computer program 62 stored in the at least one memory 61 and executable on the at least one processor 60. When the processor 60 executes the computer program 62, the crab stick production full-process control device 6 implements the steps in any of the above-mentioned crab stick production full-process control method embodiments, or enables the crab stick production full-process control device 6 to implement the functions of each unit in the above-mentioned system embodiments.

[0103] Exemplarily, the computer program 62 may be divided into one or more units, which are stored in the memory 61 and executed by the processor 60 to complete the present application. The one or more units may be a series of computer program instruction segments capable of completing specific functions, which are used to describe the execution process of the computer program 62 in the crab stick production full-process control device 6.

[0104] The crab stick production process control device 6 can be a single chip microcomputer, a mobile phone, a tablet computer, a laptop computer, an ultra-mobile personal computer (UMPC), a netbook, a desktop computer, a computing device or a computer connected to a wireless modem, a laptop computer, a handheld communication device, a handheld computing device, etc. The crab stick production process control device 6 can include, but is not limited to, a processor 60 and a memory 61. Those skilled in the art can understand that Figure 8 It is only an example of the whole process control device 6 for crab stick production, and does not constitute a limitation of the whole process control device 6 for crab stick production. It may include more or fewer components than shown in the figure, or a combination of certain components, or different components, for example, it may also include input and output devices, network access devices, buses, etc.

[0105] The processor 60 may be a central processing unit (CPU), or other general-purpose processors, digital signal processors (DSP), application-specific integrated circuits (ASIC), field-programmable gate arrays (FPGA) or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, etc. A general-purpose processor may be a microprocessor or any conventional processor, etc.

[0106] In some embodiments, the memory 61 may be an internal storage unit of the crab stick production full process control device 6, such as a hard disk or memory of the crab stick production full process control device 6. In other embodiments, the memory 61 may also be an external storage device of the crab stick production full process control device 6, such as a plug-in hard disk, a smart media card (SMC), a secure digital (SD) card, a flash card, etc. equipped on the crab stick production full process control device 6. Further, the memory 61 may also include both an internal storage unit and an external storage device of the crab stick production full process control device 6. The memory 61 is used to store an operating system, an application program, a boot loader (BootLoader), data, and other programs, such as the program code of the computer program, etc. The memory 61 may also be used to temporarily store data that has been output or is to be output.

[0107] An embodiment of the present application further provides a computer-readable storage medium, wherein the computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the steps in any of the above method embodiments are implemented.

[0108] An embodiment of the present application provides a computer program product. When the computer program product is run on a crab stick production full-process control device, the crab stick production full-process control device implements the steps in any of the above-mentioned method embodiments.

[0109] If the integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the present application implements all or part of the processes in the above-mentioned embodiment method, which can be completed by instructing the relevant hardware through a computer program, and the computer program can be stored in a computer-readable storage medium. When the computer program is executed by the processor, the steps of the above-mentioned various method embodiments can be implemented. Among them, the computer program includes computer program code, and the computer program code can be in source code form, object code form, executable file or some intermediate form. The computer-readable medium may at least include: any entity or device that can carry the computer program code to the crab stick production full process control equipment, recording medium, computer memory, read-only memory (ROM, Read-Only Memory), random access memory (RAM, RandomAccess Memory), electric carrier signal, telecommunication signal and software distribution medium. For example, a USB flash drive, a mobile hard disk, a disk or an optical disk.

[0110] In the above embodiments, the description of each embodiment has its own emphasis. For parts that are not described or recorded in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.

[0111] Those of ordinary skill in the art will appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, or a combination of computer software and electronic hardware. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professional and technical personnel can use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of this application.

[0112] In the embodiments provided in the present application, it should be understood that the disclosed crab stick production full-process control system, crab stick production full-process control equipment and crab stick production full-process control method can be implemented in other ways. For example, the crab stick production full-process control system / crab stick production full-process control equipment embodiments described above are merely schematic. For example, the division of the units is only a logical function division. There may be other division methods in actual implementation, such as multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be an indirect coupling or communication connection through some interfaces, devices or units, which can be electrical, mechanical or other forms.

[0113] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.

[0114] The embodiments described above are only used to illustrate the technical solutions of the present application, rather than to limit them. Although the present application has been described in detail with reference to the aforementioned embodiments, a person skilled in the art should understand that the technical solutions described in the aforementioned embodiments may still be modified, or some of the technical features may be replaced by equivalents. Such modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present application, and should all be included in the protection scope of the present application.

Claims

1. A method for controlling the entire process of crab stick production, characterized in that: Applied to a whole-process control device for crab stick production, the whole-process control device for crab stick production is electrically connected to a crab stick production device, and the method comprises: Acquire production parameter information of the crab sticks to be produced; wherein the production parameter information is used to reflect the type of the crab sticks to be produced; Based on the production parameter information, the crab stick production device is controlled to produce crab sticks.

2. The whole process control method of crab stick production according to claim 1, characterized in that: Before controlling the crab stick production device to produce crab sticks based on the production parameter information, the method further includes: In the case where the crab stick production device has not started the first production service, monitoring the adjustment service; wherein the first production service is the service of producing the first type of crab sticks; the adjustment service is used to instruct the crab stick production device to start the first production service in the case where production has not started, and to stop the first production service in the case where production has started; In the case of monitoring the adjustment service, starting the timing task, and not running the adjustment service before the timing task is completed; During the running of the timing task, if the first service is not monitored, the adjustment service is run after the timing task is completed; wherein the first service is a service in the same production period as the adjustment service, and the priority of the first service is higher than the priority of the adjustment service; the first service is used to indicate that the crab stick production device currently needs maintenance service; During the execution of the timing task, if the first service is monitored, the adjustment service is deleted after the timing task is completed.

3. The whole process control method of crab stick production according to claim 2, characterized in that: If the first service is not monitored during the execution of the timing task, the adjustment service is executed after the timing task is completed, including: During the execution of the timing task, if the first service is not monitored and the adjustment service is not monitored again, the adjustment service is executed after the timing task is completed.

4. The whole process control method of crab stick production according to claim 2, characterized in that: The method further comprises: During the running of the timing task, if the first service is not monitored and the adjustment service is monitored again, after the timing task is completed, it is determined whether the adjustment service monitored again is to instruct the crab stick production device to start the first production service; When it is determined that the adjustment service monitored again is to instruct the crab stick production device to start the first production service, the adjustment service monitored again is executed; When it is determined that the adjustment service monitored again is to instruct the crab stick production device to stop performing the first production service, the adjustment service and the adjustment service monitored again are deleted.

5. The whole process control method of crab stick production according to claim 3, characterized in that: During the execution of the timing task, if the first service is not monitored, after the timing task is completed and the adjustment service is executed, the method further includes: When the crab stick production device starts to perform the first production business, a production control event corresponding to the first production business is run, and the crab stick production device corresponding to the production control event is set to a running mode; wherein the production control event is an event for controlling production parameters of the first production business; When the first instruction for the production control event corresponding to the first production business is monitored and it is obtained that the first production business has not been completely completed, the preset instruction is executed to set the device corresponding to the execution of the preset instruction to the stop mode, and the operation mode of the device corresponding to the preset instruction that has not been executed is continued to be maintained; wherein, the first instruction is used to suspend the control events in the entire production process, and the preset instruction is used to replace the response of the crab stick production device to the first instruction, and the preset instruction is an instruction to suspend one or more control events in the production control event.

6. The whole process control method of crab stick production according to claim 5, characterized in that: When the crab stick production device starts to perform the first production business, after running a production control event corresponding to the first production business and setting the crab stick production device corresponding to the production control event to a running mode, the method further includes: When a preset instruction for the production control event corresponding to the first production service is monitored and it is obtained that the first production service has been completely completed, the production control event corresponding to the first production service is stopped.

7. The whole process control method of crab stick production according to claim 5, characterized in that: The method further comprises: Obtaining the availability of raw materials; When it is obtained that the supply of raw materials has been completed, the preset instructions are automatically generated.

8. The whole process control method of crab stick production according to claim 7, characterized in that: The method further comprises: Detecting the volume value of the raw materials in the mixing device of the crab stick production device; When the volume value is greater than or equal to a preset value, and the residence time value of the raw material is greater than or equal to a threshold value, it is determined that the supply of the raw material has been completed.

9. A whole-process control system for crab stick production, characterized in that: Applied to the whole process control equipment of crab stick production, the whole process control equipment of crab stick production is electrically connected with the crab stick production device, and the whole process control system of crab stick production includes: An acquisition unit, used for acquiring production parameter information of the crab sticks to be produced; wherein the production parameter information is used for reflecting the type of the crab sticks to be produced; A control unit is used to control the crab stick production device to produce crab sticks based on the production parameter information.

10. A whole-process control device for crab stick production, characterized in that: The method comprises a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor implements the method according to any one of claims 1 to 8 when executing the computer program.

Citation Information

Patent Citations

  • Beverage production arrangement system

    CN107563678A

  • Method, device and equipment for adjusting production scheduling scheme and computer readable storage medium

    CN114548683A

  • Intelligent unmanned factory production method, system and equipment

    CN117784730A

  • Silver-plated copper alloy wire production control method and device

    CN118390145A

  • Preparation method and equipment of polypropylene composite material

    CN118534859A

Cited By

  • Production line management method and system for mixed production of konjak

    CN121329039A