Building information model drawing association and drawing-model consistency verification method
By establishing the matching relationship and consistency check between the building information model and two-dimensional drawings, the problem of inconsistency in the drawing model is solved, and the accuracy of intelligent review and the application effect of BIM technology are improved.
Patent Information
- Application Number
- CN202411197253.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-29
- Publication Date
- 2024-12-06
AI Technical Summary
There is a problem of inconsistency between the building information model and the two-dimensional drawings, which leads to poor design synchronization and insufficient information correspondence, which affects the accuracy of intelligent review and the application effect of BIM technology.
By establishing the matching relationship between the building information model and two-dimensional drawings, the view correlation is realized, and the consistency check of global information, geometric dimensions, and attribute information is carried out, and the inspection report is output to ensure the consistency of the drawing model.
It improves the efficiency and accuracy of graph model consistency inspection, solves the problem of graph model non-correlation generated by different software and personnel, provides a two- and three-dimensional linkage basis, and improves the efficiency of building information models.
Smart Images

Figure CN119089552A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the field of IT and software development, and in particular relates to a method for associating drawings of building information models and verifying the consistency of drawings and models. Background Art
[0002] As a pillar industry of the national economy, the construction industry has always been faced with a prominent problem of how to transform and upgrade under the background of high-quality development. In order to change the traditional construction industry operation mode, Building Information Modeling (BIM) technology has gradually been regarded as one of the important tools, and its application scope and depth have become more and more extensive in recent years.
[0003] BIM technology is a means of expressing information based on three-dimensional building information models, and is a collection of information on the entire life cycle of building engineering design, construction, and operation and maintenance. Under the current application model, due to the tight design cycle, difficulty in implementing modeling standards, and difficulty in checking the results of building information models, a common model is to first use two-dimensional CAD software to draw two-dimensional drawings and then use three-dimensional BIM software for modeling, namely "re-modeling design".
[0004] In the process of mold design, the two-dimensional design and the three-dimensional design are often not synchronized and completed by different designers, resulting in inconsistencies between the two-dimensional drawings and the building information model (referred to as "drawing-model inconsistency"), which also restricts the application of BIM technology in the subsequent construction guidance process.
[0005] Since the building information model is not associated with the two-dimensional drawings, misjudgments caused by the mismatch between the building information model and the two-dimensional drawing information often occur, which greatly reduces the accuracy of intelligent review.
[0006] In order to better solve the consistency problem between BIM results and two-dimensional drawings, an efficient method is urgently needed to realize the automatic and manual association between two-dimensional drawings and building information models, and to judge the consistency between the associated building information models and two-dimensional drawings.
[0007] The disadvantages of the prior art mainly include:
[0008] 1. The design standards of 2D drawings and building information models are not unified. The views in the building information model cannot correspond to the 2D drawings, and the 2D and 3D linkage cannot be achieved in the 3D scene, which is not conducive to consulting the building information model information;
[0009] 2. The 2D drawings and the building information model are created by different people, and the information expressed in the 2D drawings is missing or inconsistent in the building information model;
[0010] 3. The two-dimensional drawings and building information models are designed by different software, and it is impossible to perform two-dimensional and three-dimensional correlation verification and consistency verification when the results are submitted. Summary of the invention
[0011] Purpose of the invention: The technical problem to be solved by the present invention is to provide a method for associating building information model drawings and verifying the consistency of drawings and models in view of the shortcomings of the prior art. By establishing a matching relationship between building information model files and two-dimensional drawing files, and at the same time associating building information model file views with two-dimensional drawing files, the building information model views and two-dimensional drawings can be overlapped in space, providing a basis for verifying the consistency of drawings and models. Based on the associated views and two-dimensional drawings, the consistency check of the global information, geometric dimensions, and attribute information of the building information model and the two-dimensional drawings is carried out, and the review results are output.
[0012] The present invention provides a method for associating a building information model (BIM) with a two-dimensional drawing (CAD) and verifying the consistency of the drawing and the model, comprising the following steps:
[0013] Step 1, upload the building information model and the two-dimensional drawing respectively, check the consistency of the building information model view and the two-dimensional drawing catalog, and form a set of the building information model and the drawing;
[0014] Step 2: Check the names of the building information model file and the two-dimensional drawing file to establish a matching relationship; check the view name in the building information model and the two-dimensional drawing name, and automatically establish the association relationship between the building information model and the two-dimensional drawing; if it cannot be established automatically, manually select the building information model view and the two-dimensional drawing, and manually establish the association relationship in the two-dimensional and three-dimensional split-screen interactive view;
[0015] Step 3: Verify the consistency between the building information model and the two-dimensional drawing model, and check the consistency of the global information, geometric dimensions, and attribute information of the building information model and the two-dimensional drawing;
[0016] Step 4: Output the corresponding inspection report based on the inspection results.
[0017] In step 1, upload the 3D building information model containing the plan view, elevation view, section view, large view, and 2D drawing catalog corresponding to the 2D drawings, and upload the single-layer plan view, elevation view, section view, and Figure 2 2D drawings, build building information models and 2D drawing collections;
[0018] The building information model includes building information data formats such as RVT and NJM. The data needs to be able to save views such as plan views, elevation views and section views of each floor. A building information model contains more than two views such as plan views, elevation views, section views, etc. The naming of building information model files and views in the model needs to meet standardized naming requirements. The naming rule of a single-version single-professional single-unit building information model file is: professional_project abbreviation_building_date, example: "Building_Airport Third Road_Building A_20231111"; the naming rule of the building information model view name is: view name, example: "first floor plan";
[0019] The set of two or more single building information models is m. A single building information model refers to an independent building with a complete structure. The i-th single building information model is represented by m i , the number of individual building information models in the building information model set is N, then the building information model set is m = {m i |1≤i≤N};
[0020] Each single building information model contains different majors, namely, architecture, structure, water supply and drainage, HVAC, electrical, etc. p0, p1, p2, p3, p4 are used to represent architecture, structure, water supply and drainage, HVAC, electrical, respectively. Then each single building information model is formed by five major majors p0, p1, p2, p3, p4 to form a vector. At the same time, in order to ensure the consistency of mathematical expression in the present invention, two-dimensional subscripts are used to express different majors in the single building. The first dimension coordinate is the single building subscript, and the second dimension coordinate is the building information model design major. Then the jth major of the i-th single building model is recorded as p ij :
[0021]
[0022] Among them, p i4 represents the electrical engineering specialty of the i-th building, p 14 Indicates the electrical engineering of the first single building, p N4 Indicates the electrical specialty of the Nth single building, 1≤i≤N, 0≤j≤4;
[0023] The two-dimensional drawings include DWG and PDF two-dimensional data formats. Only a single view is saved in a single two-dimensional drawing. The naming of the two-dimensional drawing files must meet the standardized naming requirements. The naming rules of the two-dimensional drawing files are: major_project abbreviation_building_view name, for example: "Architecture_Airport 3rd Road_Building A_First Floor Plan_20231111";
[0024] The set of two or more single two-dimensional drawings is s d, a single two-dimensional drawing refers to an independent drawing with a complete structure. The i-th monomer two-dimensional drawing set is represented as The number of individual drawings in the two-dimensional drawing set is N, then N is a natural number, and the total number of floors in a single building is recorded as N L , the i-th floor in a single building is recorded as L i , then the drawing set is defined as a matrix according to the dimensions of the single building, with each floor as a vector. At the same time, the drawing set should be expanded into the form of a vector of the single building drawing matrix, then:
[0025]
[0026]
[0027] in, represents the set of all two-dimensional drawings of the i-th monomer, Indicates the Nth L Two-dimensional drawings of electrical engineering of the layer;
[0028] The building information model file name and building information model view name should be consistent with the naming rules of 2D drawings.
[0029] In step 2, the building information model and the 2D drawings are first matched according to the discipline, project abbreviation, and building, and a view-level association is established;
[0030] According to the discipline, project abbreviation, and building, a matching relationship between the building information model and the 2D drawing file is established. One building information model file corresponds to more than two 2D drawing files:
[0031] The building information model and the 2D drawing are matched using the file name, that is, the professional and building field information is obtained according to the file name of the building information model, and the model unique descriptor Hash of the single building building information model file in the same project is calculated m :
[0032] Hash m =f(p i ,m j )=i<<16|j<<8
[0033] Where f(p i ,m j ) represents the jth building information model m in the building information model j and the i-th major p i The unique descriptor between ;
[0034] And calculate the drawing unique descriptor Hash of each drawing file based on the uploaded 2D drawing file set d :
[0035] Hash d =f(p i ,m j ,L k )=i<<16|j<<8|k
[0036] Where f(p i ,m j ,L k ) represents the jth single building m in the two-dimensional drawing j and the i-th major calculates p i And calculate L on the kth floor k The unique descriptor between ;
[0037] By Hash m and Hash d The value of matches the association between the 2D drawing set and the building information model set, and the matching association function between the two is defined as Mapper:
[0038] Mapper=(Hash d >>8==Hash m )
[0039] Where Mapper represents the association relationship function between the 2D drawing set and the building information model set;
[0040] If the result of Mapper calculation is true, the model and the drawing are matched. Because the drawings are split according to individual views, the set of drawings associated with a single building information model, so the following matching relationship is obtained. i0 :
[0041] r i0 = <m i ,s d ,Similar i0 >,1≤i≤N
[0042] where r i0 Represents the matching relationship between the ith building information model and the 2D drawing set; Similar i0 Refers to the association similarity between the building information model and the matching 2D drawing set;
[0043] Further deduction is made to obtain the matching relationship between the building information model and the drawing set of the same project uploaded by the user. ij :
[0044]
[0045] where r ijRepresents the matching relationship between the jth floor of the i-th building information model and the j-th two-dimensional drawing;
[0046] Similar ij represents the similarity between the i-th building information model and the matching j-th floor 2D drawing;
[0047] The similarity between the single building model and the drawing is
[0048] In step 2, the establishment of a matching relationship is divided into two cases:
[0049] In the first case, the key features of the building information model file and the 2D drawing file are consistent, and a matching relationship is automatically established between the building information model file and the 2D drawing file;
[0050] In the second case, the key features in the building information model file and the two-dimensional drawing file are inconsistent. The corresponding building information model file and two-dimensional drawing file are manually selected, and the matching relationship is manually established.
[0051] In step 2, the automatically establishing the association relationship between the building information model and the two-dimensional drawing is to establish a correspondence between the view name in the building information model file and the view name in the two-dimensional drawing file name, and establish an association relationship between the building information model view and the two-dimensional drawing;
[0052] The automatic establishment of the association relationship between the building information model and the two-dimensional drawing is divided into two cases:
[0053] In the first case, key features can be extracted from the building information model view and the two-dimensional drawing file. The key features include 1A (the starting coordinate of the horizontal axis in the axis grid is 1, and the starting coordinate of the vertical axis is A) axis grid intersection and angle, and the two-dimensional drawing and the building information model view are automatically offset from the origin, and the offset is recorded as T0=(dx,dy,dz), where dx is the X-axis offset, dy is the Y-axis offset, and dz is the Z-axis offset. The rotation is recorded as R0=(0,0,θ), where θ is the rotation radian around the Z axis. Because the drawing is in a two-dimensional coordinate space and the model coordinates are in a three-dimensional coordinate space, the Z axis is selected to establish a unified coordinate system. Therefore, the rotation angle of the drawing relative to the reference point coordinate of the model is around the Z axis. At the same time, the scale of the two-dimensional drawing and the building information model is unified, and the scaling scale of the two-dimensional drawing is recorded as S0; the building information model view overlaps with the two-dimensional drawing position, and an association relationship r0 is established. The transformation matrix after the two-dimensional drawing and the two-dimensional drawing position overlap is recorded as The drawing Multiply the M0 transformation on the left to form a drawing that can match the similarity If there is no key feature, the transformation matrix M0 cannot be calculated, then
[0054]
[0055] In the second case, the building information model view and the two-dimensional drawing file failed to find the key features, and the feature points were manually selected. The feature points included the axis grid intersection (let the coordinates of the model origin after the top projection be (x0, y0, z0=0), and the corresponding two-dimensional drawing axis grid intersection is (x1, y1)), the first component intersection 1 (let the coordinates of the component origin after the top projection be (x′0, y′0, z′0,=0), and the corresponding two-dimensional drawing first component intersection is (x1′, y1′)), the second component intersection 2 (let the coordinates of the component origin after the top projection be (x″0, y″0, z″0=0), and the corresponding two-dimensional drawing second component intersection is (x″1, y″1)), and Establish the mapping relationship of key points and set the offset vector in matrix M0 to Assuming the rotation angle of the drawing around the Z axis is θ, the transformation equation is established:
[0056]
[0057] And solve the rotation angle θ and dx,dy around the Z axis to solve the transformation matrix M0.
[0058] After the building information model file is matched and associated with the two-dimensional drawing file, proceed to step 3; otherwise, the building information model file is modified again and adjusted according to the requirements of step 1.
[0059] In step 3, the checking of the consistency of the global information, geometric dimensions, and attribute information of the building information model and the two-dimensional drawings is divided into three cases:
[0060] In the first case, the consistency verification of the single floor of the building information model of a single building and the global information model of the two-dimensional drawing is carried out. The axis grid, elevation and coordinate information in the two-dimensional drawing with the established association relationship are compared to verify the consistency of the axis grid header number and axis grid position. Elevation header name, elevation height consistency The numerical consistency of the coordinate origin of the building information model and the coordinate origin of the 2D drawing The global information graph consistency is evaluated as:
[0061]
[0062] in represents the global information similarity between the i-th building information model and the matching j-th floor 2D drawing;
[0063] In the second case, the consistency verification of the geometric dimensions of the single floor of the building information model of a single building and the two-dimensional drawings is carried out. For the building information model and the two-dimensional drawings that have established an associated relationship, the spatial position and geometric dimensions of the components in the building information model and the two-dimensional drawings are checked according to the profession, and compared; for example, architectural professions such as walls, columns, floor slabs, stairs, doors, windows, furniture, etc.; structural professions such as walls, columns, floor slabs, beams, stairs, etc.; water supply and drainage professions such as pipes, pipe accessories, pipe fittings, sanitary fixtures, mechanical equipment, etc.; HVAC professions such as HVAC ducts, duct accessories, duct accessories, mechanical equipment, etc.; electrical professions such as cable trays, cable tray accessories, electrical equipment, etc., and the number of component types compared in each profession is recorded as
[0064] The specific process of spatial position comparison is as follows: First, the building information model is projected according to the view type of the two-dimensional drawing, and the spatial position after projection is calculated. If the view of the two-dimensional drawing is a top view, the building information model m is obtained. ij Vertex data of all components in Let the transformation matrix of the top view be M1, then the set of all vertices after the top view projection is Remember to use and the set of all vertices in the 2D graph Perform similarity matching to check whether the vertex coordinates in all building information models are located in the coordinate set of the 2D drawing, that is, verify Is it established? If so, record If not, verify percentage, and Located in The number of vertices in C V occupy The number of vertices The ratio is expressed as:
[0065]
[0066] in represents the spatial position similarity between the i-th building information model and the matching j-th floor 2D drawing;
[0067] The specific geometric dimension comparison process includes: firstly, the building information model is projected according to the view type of the two-dimensional drawing to form a two-dimensional view, the component dimension attribute value and unit are extracted according to the component type in the building information model, and the value is converted according to the set standard unit, such as the length unit is uniformly converted to millimeters, the angle unit is uniformly converted to radians, etc., and the geometric dimension attribute values after uniform conversion are compared to see whether they are equal. The number of geometric attributes of each component is recorded as The number of components is C e , then the similarity of geometric dimensions for:
[0068]
[0069] in represents the geometric similarity between the i-th building information model and the matching j-th floor 2D drawing;
[0070] In the third case, the consistency verification of the building information model and the two-dimensional drawing attribute information model is carried out. For the building information model and the two-dimensional drawing that have established an association relationship, the annotation information in the two-dimensional drawing is extracted and compared with the component attribute information in the building information model. The attribute number of each component is recorded as The number of the above components is C e , then the component attribute similarity Defined as:
[0071]
[0072] In step 4, based on the system-checked building information model view integrity, building information model and two-dimensional drawing name consistency, building information model and two-dimensional drawing matching relationship, building information model and two-dimensional drawing association relationship, building information model and two-dimensional drawing consistency results, a consistency check report is compiled to deduce the similarity between the model and the drawing of a single floor of a single building:
[0073]
[0074] Further derive the similarity between the single building information model and the drawings i0 for:
[0075]
[0076] Further derive the similarity between the project-level building information model and the drawings 00 for:
[0077]
[0078] The building information model view integrity refers to comparing the collected two-dimensional drawing catalog with the corresponding view in the building information model in step 1, and outputting the corresponding result if there is any inconsistency;
[0079] The consistency of the building information model two-dimensional drawing name refers to comparing the collected two-dimensional drawings with the building information model view names in step 1 to check their consistency, and outputting corresponding results if there is any inconsistency;
[0080] The building information model two-dimensional drawing matching relationship refers to that in step 2, firstly automatic matching is performed, and if automatic matching is not possible, then manual matching is performed and an unmatched result is output;
[0081] The building information model two-dimensional drawing association relationship means that in step 2, the building information model is first aligned in an automatic manner. If the axis grid intersection cannot be extracted and the two-dimensional drawing cannot be rotated, the corresponding result is output and changed to manual alignment;
[0082] The consistency between the building information model and the two-dimensional drawing refers to the automatic checking of the consistency of the global information, geometric dimensions, and component attribute information of the building information model in step 3, and the inconsistent results are recorded in the report.
[0083] In step 4, the building information model verification report header lists the project name, inspection time, design unit and inspection unit;
[0084] The building information model verification report lists the results by category according to the inspection type, including the matching relationship inspection results between the building information model and the two-dimensional drawing, the association relationship inspection results, and the consistency verification results between the building information model and the two-dimensional drawing model:
[0085] In the first case, the matching relationship check result between the building information model and the two-dimensional drawing lists the matching results between the building information model file and the two-dimensional drawing file;
[0086] In the second case, the association check result lists the association results between the building information model file view and the 2D drawing file;
[0087] In the third case, in the consistency verification results between the building information model and the 2D drawing model, the inspection results are listed according to the global information consistency, geometric information consistency, and attribute information consistency. The component-level inspection results should list the component's unique identification symbol, such as the component ID;
[0088] In order to solve the association between building information model and two-dimensional drawings and verify the consistency of drawings and models, necessary checks should be carried out on the building information model and two-dimensional drawings first. The check content includes the building information model file name, building information model view name, file name, etc., to ensure that the building information model file name, building information model view name, and two-dimensional drawing file name are unified rules for easy system identification. If any violation of the inspection rules is found, it needs to be adjusted to meet the requirements of the rules before association matching is carried out.
[0089] The present invention also provides an electronic device, comprising a processor and a memory, wherein the memory stores program code, and when the program code is executed by the processor, the processor executes the steps of the described method.
[0090] The present invention also provides a storage medium storing a computer program or instruction. When the computer program or instruction is run on a computer, the steps of the method described are executed.
[0091] The present invention has the following beneficial effects:
[0092] (1) The core inspection items for image-model association and consistency were analyzed and automatically checked through software to improve the efficiency and accuracy of image-model consistency checking.
[0093] (2) It solves the problem that the 2D drawings and the BIM are produced by different software and different personnel, which often leads to the situation that some information in the 2D drawings is not in the BIM, some information in the 2D drawings is inaccurate in the BIM, and other issues such as the disconnection and inconsistency between the drawings and the BIM.
[0094] (3) A building information model association method is provided to achieve the matching and association between the building information model and the two-dimensional drawings, providing basic conditions for drawing-model consistency checking and two- and three-dimensional linkage.
[0095] (4) A method for checking the consistency between a building information model and two-dimensional drawings is provided to avoid situations such as the inability to use the building information model on the construction site due to inconsistency between the drawings and the models, thereby improving the efficiency of using the building information model. BRIEF DESCRIPTION OF THE DRAWINGS
[0096] The present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments, and the above and / or other advantages of the present invention will become more clear.
[0097] Figure 1 It is a flow chart of the method of the present invention.
[0098] Figure 2 It is a schematic diagram of the element assembly of the present invention. DETAILED DESCRIPTION
[0099] like Figure 1 As shown, in one embodiment of the present invention, a method for associating drawings of a building information model and verifying the consistency of drawings and models is provided, comprising the following steps:
[0100] Step 1: Upload the building information model and 2D drawings respectively, check the consistency between the building information model view and the 2D drawing catalog, and form a set of building information models and drawings. The elements in the set are as follows: Figure 2 As shown;
[0101] Step 2: Check the names of the building information model file and the two-dimensional drawing file to establish a matching relationship; check the view name in the building information model and the two-dimensional drawing name, and automatically establish the association relationship between the building information model and the two-dimensional drawing; if it cannot be established automatically, manually select the building information model view and the two-dimensional drawing, and manually establish the association relationship in the two-dimensional and three-dimensional split-screen interactive view;
[0102] Step 3: Verify the consistency between the building information model and the two-dimensional drawing model, and check the consistency of the global information, geometric dimensions, and attribute information of the building information model and the two-dimensional drawing;
[0103] Step 4: Output the corresponding inspection report according to the inspection results. In step 1, upload the building information model and two-dimensional drawing data in the building information model consistency review system respectively;
[0104] The building information model is mainly based on .RVT data. The professional division of the building information model, the division of buildings, the name of the building information model, the name of the building information model view, the name of the building information model floor, the name of the component, and the component attribute information shall comply with the relevant national, provincial and municipal standards.
[0105] The building information model should include plan views, elevation views, section views, large-scale views, and a catalog of two-dimensional drawings corresponding to the two-dimensional drawings. If any of them are missing, a prompt should be given to supplement them.
[0106] The two-dimensional drawing data is mainly .DWG data. The two-dimensional drawings should upload floor plans, elevation views, section views, large-scale views, design instructions, two-dimensional drawing catalogs, etc. according to the profession and building. The naming rules of two-dimensional drawings should be consistent with the naming rules of building information model views.
[0107] In step 2, the building information model and the two-dimensional drawings are associated. First, the building information model and the two-dimensional drawings should be matched according to the profession, and the association relationship should be established manually or automatically.
[0108] The matching of the building information model with the two-dimensional drawings is to preliminarily match the building information model with the two-dimensional drawings in a database according to the discipline and the building.
[0109] Manually establishing an association relationship between the building information model and the two-dimensional drawings means providing a split-screen display of the building information model and the two-dimensional drawings in the system, and manually selecting a floor view in the building information model to keep it consistent with the two-dimensional drawings; at the same time, providing a building information model and two-dimensional drawing positioning tool, selecting a positioning point in the building information model, and selecting it in the two-dimensional drawings, so as to align the building information model with the two-dimensional drawings.
[0110] The automatic establishment of an association relationship between the building information model and the two-dimensional drawing refers to automatically extracting the building information model positioning points and the two-dimensional drawing positioning points through the system, and automatically aligning the positions.
[0111] The building information model and the two-dimensional drawings are associated with each other, and the floor plan, elevation view and section view of all floors should be associated with each other. The file formats of the building information model and the two-dimensional drawing should meet the system parsing requirements.
[0112] In step 3, the consistency verification between the building information model and the 2D drawing model is divided into three cases: global information, geometric dimensions, and component attribute information model consistency verification:
[0113] The global information model consistency verification refers to comparing the axis grid, elevation, and coordinate information in the two-dimensional drawing with the building information model that has established an association relationship through the system, and verifying the consistency of the axis grid header number and axis grid position; the consistency of the elevation header name and elevation height; the numerical consistency of the coordinate origin of the building information model and the coordinate origin of the two-dimensional drawing;
[0114] The geometric dimension drawing consistency verification refers to the system checking the components in the building information model and the two-dimensional drawings that have established an associated relationship, and comparing the spatial position and geometric dimensions of the components in the building information model with those in the two-dimensional drawings according to the profession;
[0115] The component attribute drawing consistency verification refers to extracting the annotation information in the two-dimensional drawing and comparing it with the component attribute information in the building information model through the system to establish an associated relationship between the building information model and the two-dimensional drawing.
[0116] In step 4, a consistency check report is compiled based on the system's checks on the integrity of the building information model views, the consistency of the building information model two-dimensional drawing names, the matching relationship of the building information model two-dimensional drawings, the association relationship of the building information model two-dimensional drawings, and the consistency results between the building information model and the two-dimensional drawings.
[0117] The building information model view integrity refers to comparing the collected two-dimensional drawing catalog with the corresponding view in the building information model in step 1, and outputting the corresponding result if there is any inconsistency;
[0118] The consistency of the building information model two-dimensional drawing name refers to comparing the collected two-dimensional drawings with the building information model view names in step 1 to check their consistency, and outputting corresponding results if there is any inconsistency;
[0119] The building information model two-dimensional drawing matching relationship means that in step 2, the system automatically matches first, and if the automatic matching fails, the matching is performed manually and the unmatched result is output;
[0120] The building information model two-dimensional drawing association relationship means that in step 2, the building information model is first aligned in an automatic manner. If the axis grid intersection cannot be extracted or the two-dimensional drawing cannot be rotated, the corresponding result is output and changed to manual alignment;
[0121] The consistency between the building information model and the two-dimensional drawing refers to the automatic checking of the consistency of the global information, geometric dimensions, and component attribute information of the building information model by the system in step 3, and the inconsistent results are recorded in the report.
[0122] The present invention provides a method for checking the consistency between the building information model and the two-dimensional drawings, which is effective in solving the problem of current mold remodeling. Through the system, the consistency result is automatically output, the modification of the building information model and the two-dimensional drawings is guided, and the application of BIM technology is ensured.
[0123] In another embodiment of the present invention, Figure 1 As shown, a method for associating two-dimensional drawings of a building information model and verifying the consistency of drawings and models is provided, comprising the following steps:
[0124] Step 1: Upload the building information model and 2D drawings in the system respectively, and check the consistency between the building information model view and the 2D drawing catalog;
[0125] Step 2: Create a matching relationship between the building information model and the 2D drawing, and automatically or manually associate the building information model view with the 2D drawing;
[0126] Step 3: Check the spatial position and information consistency of the global information, geometric dimensions, and component attribute information of the building information model and the two-dimensional drawings;
[0127] Step 4: According to the inspection results, classify and organize them into an inspection report.
[0128] Specifically, in Step 1, the uploaded building information model (.RVT) and 2D drawing (.CAD) files should be divided according to the profession and building. The professions are divided into five categories: architecture, structure, water supply and drainage, electrical, and HVAC. The buildings are marked according to the actual situation of the project, such as Building A and Building B.
[0129] The 2D drawings should be split according to the 2D drawing catalog and uploaded into two or more files, such as the first floor water supply and drainage and fire protection plan, the second floor water supply and drainage and fire protection plan, the third floor water supply and drainage and fire protection plan, and the roof water supply and drainage and fire protection plan. The corresponding building information model file should contain the corresponding first floor water supply and drainage and fire protection plan, the second floor water supply and drainage and fire protection plan, the third floor water supply and drainage and fire protection plan, and the roof water supply and drainage and fire protection plan.
[0130] The above building information model and view naming and division rules should comply with relevant national, provincial and municipal standards.
[0131] Optionally, if the number of views of the building information model is inconsistent with that of the 2D drawings, a prompt should be given to make changes and the user cannot proceed to the next stage.
[0132] In Step 2, the main purpose is to establish the matching relationship between the building information model and the two-dimensional drawing and align the positions.
[0133] Optionally, the system automatically matches the building information model with the 2D drawings. One building information model corresponds to multiple 2D drawings, which are matched by discipline, providing a basis for the association of building information models.
[0134] Optionally, the system can also perform manual matching, manually establishing a matching relationship between the building information model and the corresponding two-dimensional drawing in the system;
[0135] Optionally, after the matching relationship is established, the system automatically associates the building information model view with the two-dimensional drawing, automatically picks up the axis grid intersection points in the building information model and the axis grid intersection points in the two-dimensional drawing, and aligns their spatial positions and rotation angles;
[0136] Optionally, the system can also perform manual association, manually select the orthogonal intersection points in the building information model, select them in the 2D drawing, and align them manually.
[0137] In Step 3, for the building information model and two-dimensional drawings that have established an associated relationship, the consistency check of global information, geometric dimensions, and component attribute information is automatically performed.
[0138] Optional, the global information check mainly checks the consistency of the spatial position and header number of the axis grid in the building information model and the axis grid in the two-dimensional drawing. If there is no overlap in position or inconsistency in header number, an error will be reported;
[0139] Optional, the geometric dimension check mainly checks the consistency between the geometric projection lines of the components on different floors and the projection lines of the 2D drawings, and the positions and names of the block files in the family files and 2D drawings. If there is a projection position deviation, or the block files in the family files or 2D drawings are missing, an error will be reported.
[0140] Optionally, the component attribute information check mainly checks the consistency between the component information in the building information model and the component annotation information in the two-dimensional drawing at the corresponding position. If there is inconsistency, an error is reported.
[0141] In step 4, the system automatically generates a report on the association between the building information model and the two-dimensional drawings and a verification report on the consistency between the building information model and the two-dimensional drawings, records the corresponding results, and guides the modification of the building information model and the two-dimensional drawings.
[0142] In this embodiment, a method for associating a building information model with a two-dimensional drawing and verifying the consistency between the drawing and the model is described, which provides a basis for further clarifying the interface between the building information model and the two-dimensional drawing, implementing intelligent review, and ensuring the effectiveness of BIM technology application.
[0143] In the present invention, in order to facilitate the upload of building information models and two-dimensional drawings, the system should include five professional types: architecture, structure, electrical, water supply and drainage, and HVAC, and provide corresponding professional selection options. After the building information model and two-dimensional drawings are uploaded, the consistency check of the building information model view and the two-dimensional drawing catalog should be carried out first. If it fails, it will prompt for modification.
[0144] In the present invention, in order to facilitate the establishment of a matching relationship between the building information model and the two-dimensional drawings, the system lists the building information model and the two-dimensional drawings in a list form. Those that have established a matching relationship are indicated in green, and those that have not matched are indicated in red.
[0145] In the present invention, in order to facilitate the manual association of building information models with two-dimensional drawings, the system provides two-dimensional and three-dimensional split-screen lightweight viewing, view switching, and two-dimensional drawing switching functions. For building information model views and two-dimensional drawings that have established an associated relationship, space-level two-dimensional and three-dimensional linkage can be achieved.
[0146] In the present invention, in addition to automatic verification, the consistency verification of the building information model's global information, geometric dimensions, and attribute information can also be manually marked by the system, and the corresponding results are also reflected in the report.
[0147] The present invention provides a method for associating drawings of building information models and verifying the consistency of drawings and models. There are many methods and ways to implement the technical solution. The above is only a preferred implementation of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principle of the present invention. These improvements and modifications should also be regarded as the protection scope of the present invention. All components not specified in this embodiment can be implemented by existing technologies.
Claims
1. A method for verifying the consistency of drawings and models in building information models, characterized in that: The following steps are involved: Step 1, upload the building information model and the two-dimensional drawing respectively, check the consistency of the building information model view and the two-dimensional drawing catalog, and form a set of the building information model and the drawing; Step 2, check the names of the building information model file and the two-dimensional drawing file to establish a matching relationship; Check the view names and 2D drawing names in the building information model, and automatically establish the association between the building information model and the 2D drawing; if it cannot be established automatically, select the building information model view and 2D drawing, and establish the association in the 2D and 3D split-screen interactive view; Step 3: Verify the consistency between the building information model and the two-dimensional drawing model, and check the consistency of the global information, geometric dimensions, and attribute information of the building information model and the two-dimensional drawing; Step 4: Output the corresponding inspection report based on the inspection results.
2. The method according to claim 1, characterized in that In step 1, upload the 3D building information model including the plan view, elevation view, section view, large view, and 2D drawing catalog corresponding to the 2D drawings, upload the single-layer plan view, elevation view, and section view 2D drawings respectively, and establish a building information model and 2D drawing set; The building information model includes RVT and NJM building information data formats. A building information model includes more than two plan views, elevation views, and section views. The naming of the building information model file and the views in the model needs to meet the standardized naming requirements. The naming rule of a single version single professional single building information model file is: professional_project abbreviation_building_date; The set of two or more single building information models is m. A single building information model refers to an independent building with a complete structure. The i-th single building information model is represented by m i , the number of individual building information models in the building information model set is N, then the building information model set is m = {m i |1≤i≤N}; Each single building information model contains different majors. p0, p1, p2, p3, p4 are used to represent the architectural major, structural major, water supply and drainage major, HVAC major, and electrical major, respectively. Each single building information model is formed by the five major majors p0, p1, p2, p3, p4 to form a vector. Two-dimensional subscripts are used to express different majors in the single building. The first dimension coordinate is the single building subscript, and the second dimension coordinate is the building information model design major. The jth major of the i-th single building model is recorded as p ij : but Among them, p i4 represents the electrical engineering specialty of the i-th building, p 14 Indicates the electrical engineering of the first single building, p N4 Indicates the electrical specialty of the Nth single building, 1≤i≤N, 0≤j≤4; The two-dimensional drawings include DWG and PDF two-dimensional data formats. Only a single view is saved in a single two-dimensional drawing. The naming of the two-dimensional drawing files must meet the standardized naming requirements. The naming rules of the two-dimensional drawing files are: major_project abbreviation_building_view name; The set of two or more single two-dimensional drawings is s d , a single two-dimensional drawing refers to an independent drawing with a complete structure. The i-th monomer two-dimensional drawing set is represented as The number of individual drawings in the two-dimensional drawing set is N, then N is a natural number, and the total number of floors in a single building is recorded as N L , the i-th floor in a single building is recorded as L i , then the drawing set is defined as a matrix according to the dimensions of the single building, with each floor as a vector. At the same time, the drawing set should be expanded into the form of a vector of the single building drawing matrix, then: in, represents the set of all two-dimensional drawings of the i-th monomer, Indicates the Nth L Two-dimensional drawings of electrical engineering of the layer; The building information model file name and building information model view name should be consistent with the naming rules of 2D drawings.
3. The method according to claim 2, characterized in that In step 2, the building information model and the 2D drawings are first matched according to the discipline, project abbreviation, and building, and a view-level association is established; According to the discipline, project abbreviation, and building, a matching relationship between the building information model and the 2D drawing file is established. One building information model file corresponds to more than two 2D drawing files: The building information model and the 2D drawing are matched using the file name, that is, the professional and building field information is obtained according to the file name of the building information model, and the model unique descriptor Hash of the single building building information model file in the same project is calculated m : Hash m =f(p i ,m j )=i<<16|j<<8 Where f(p i ,m j ) represents the jth building information model m in the building information model j and the i-th major p i The unique descriptor between ; And calculate the drawing unique descriptor Hash of each drawing file based on the uploaded 2D drawing file set d : Hash d =f(p i ,m j ,L k )=i<<16|j<<8|k Where f(p i ,m j ,L k ) represents the jth single building m in the two-dimensional drawing j and the i-th major calculates p i And calculate L on the kth floor k The unique descriptor between ; By Hash m and Hash d The value of matches the association between the 2D drawing set and the building information model set, and the matching relationship association function between the two is defined as Mapper: Mapper=(Hash d >>8==Hash m ) Where Mapper represents the association relationship function between the 2D drawing set and the building information model set; If the calculation result of Mapper is true, the model and the drawing are matched, and the following matching relationship is obtained: i0 : r i1 =<m i ,s d ,Similar i0 >,1≤i≤N where r i0 Represents the matching relationship between the ith building information model and the 2D drawing set; Similar i0 Refers to the association similarity between the building information model and the matching 2D drawing set; Further deduction is made to obtain the matching relationship between the building information model and the drawing set of the same project uploaded by the user. ij : where r ij Represents the matching relationship between the jth floor of the i-th building information model and the j-th two-dimensional drawing; Similar ij represents the similarity between the i-th building information model and the matching j-th floor 2D drawing; The similarity between the single building model and the drawing is 4. The method according to claim 3, characterized in that In step 2, the establishment of a matching relationship is divided into two cases: In the first case, the key features of the building information model file and the 2D drawing file are consistent, and a matching relationship is automatically established between the building information model file and the 2D drawing file; In the second case, the key features in the building information model file and the two-dimensional drawing file are inconsistent. The corresponding building information model file and two-dimensional drawing file are manually selected, and the matching relationship is manually established.
5. The method according to claim 4, characterized in that In step 2, the automatically establishing the association relationship between the building information model and the two-dimensional drawing is to establish a correspondence between the view name in the building information model file and the view name in the two-dimensional drawing file name, and establish an association relationship between the building information model view and the two-dimensional drawing; The automatic establishment of the association relationship between the building information model and the two-dimensional drawing is divided into two cases: In the first case, key features can be extracted from the building information model view and the two-dimensional drawing file. The key features include the intersection and angle of the 1A axis grid. The starting coordinate of the horizontal axis in the axis grid is 1, and the starting coordinate of the vertical axis is A. The two-dimensional drawing and the building information model view are automatically offset from the origin, and the offset T0 = (dx, dy, dz), where dx is the X-axis offset, dy is the Y-axis offset, and dz is the Z-axis offset. The rotation amount is recorded as R0 = (0, 0, θ), where θ is the radian around the Z axis. The Z axis is selected to establish a unified coordinate system. Therefore, the rotation angle of the drawing relative to the reference point coordinate of the model is around the Z axis. At the same time, the scale of the two-dimensional drawing and the building information model are unified, and the scaling scale of the two-dimensional drawing is recorded as S0; the building information model view overlaps with the two-dimensional drawing position, and an association relationship r0 is established. The transformation matrix after the two-dimensional drawing and the two-dimensional drawing position overlap is recorded as The drawing Multiply the M0 transformation on the left to form a drawing that can match the similarity If there is no key feature, the transformation matrix M0 cannot be calculated, then In the second case, the building information model view and the two-dimensional drawing file fail to find the key features, and the feature points are manually selected, and the feature points include the intersection of the axis grid, the intersection of the first component, and the intersection of the second component; Let the coordinates of the model origin after the top projection be (x0, y0, z0=0), and the corresponding intersection of the axis grid on the two-dimensional drawing be (x1, y1). Let the coordinates of the component origin after the top projection be (x′0, y′0, z′0,=0), and the corresponding intersection of the first component on the two-dimensional drawing is (x′1, y′1). Let the coordinates of the component origin after the top projection be (x″0, y″0, z″0=0), and the corresponding intersection of the second component on the two-dimensional drawing is (x″1, y″1). and Establish the mapping relationship of key points and set the offset vector in matrix M0 to Assuming the rotation angle of the drawing around the Z axis is θ, the transformation equation is established: And solve the rotation angle θ and dx,dy around the Z axis to solve the transformation matrix M0; After the building information model file is matched and associated with the two-dimensional drawing file, proceed to step 3; otherwise, the building information model file is modified again and adjusted according to the requirements of step 1.
6. The method according to claim 5, characterized in that In step 3, the checking of the consistency of the global information, geometric dimensions, and attribute information of the building information model and the two-dimensional drawings is divided into three cases: In the first case, the consistency verification of the single floor of the building information model of a single building and the global information model of the two-dimensional drawing is carried out. The axis grid, elevation and coordinate information in the two-dimensional drawing with the established association relationship are compared to verify the consistency of the axis grid header number and axis grid position. Elevation header name, elevation height consistency The numerical consistency of the coordinate origin of the building information model and the coordinate origin of the 2D drawing The global information graph consistency is evaluated as: in represents the global information similarity between the i-th building information model and the matching j-th floor 2D drawing; In the second case, the consistency verification of the geometric dimensions of the single-story building information model of a single building and the two-dimensional drawings is carried out. For the building information model and the two-dimensional drawings that have established an associated relationship, the components in the building information model and the spatial position and geometric dimensions in the two-dimensional drawings are checked according to the profession, and the number of component types compared in each profession is recorded as The specific process of spatial position comparison is as follows: First, the building information model is projected according to the view type of the two-dimensional drawing, and the spatial position after projection is calculated. If the view of the two-dimensional drawing is a top view, the building information model m is obtained. ij Vertex data of all components in Let the transformation matrix of the top view be M1, then the set of all vertices after the top view projection is Remember to use and the set of all vertices in the 2D graph Perform similarity matching to check whether the vertex coordinates in all building information models are located in the coordinate set of the 2D drawing, that is, verify Is it established? If so, record If not, verify percentage, and Located in The number of vertices in C V occupy The number of vertices The ratio is expressed as: in represents the spatial position similarity between the i-th building information model and the matching j-th floor 2D drawing; The specific geometric dimension comparison process includes: firstly, the building information model is projected according to the view type of the two-dimensional drawing to form a two-dimensional view, the component dimension attribute value and unit are extracted according to the component type in the building information model, and the value is converted according to the set standard unit, and the geometric dimension attribute values after unified conversion are compared to see whether they are equal. The number of geometric attributes of each component is recorded as The number of components is C e , then the similarity of geometric dimensions for: in represents the geometric similarity between the i-th building information model and the matching j-th floor 2D drawing; In the third case, the consistency verification of the building information model and the two-dimensional drawing attribute information model is carried out. For the building information model and the two-dimensional drawing that have established an association relationship, the annotation information in the two-dimensional drawing is extracted and compared with the component attribute information in the building information model. The attribute number of each component is recorded as The number of the above components is C e , then the component attribute similarity Defined as:
7. The method according to claim 6, characterized in that In step 4, based on the system-checked building information model view integrity, building information model and two-dimensional drawing name consistency, building information model and two-dimensional drawing matching relationship, building information model and two-dimensional drawing association relationship, building information model and two-dimensional drawing consistency results, a consistency check report is compiled to deduce the similarity between the model and the drawing of a single floor of a single building: Further derive the similarity between the single building information model and the drawings i0 for: Further derive the similarity between the project-level building information model and the drawings 00 for: The building information model view integrity refers to comparing the collected two-dimensional drawing catalog with the corresponding view in the building information model in step 1, and outputting the corresponding result if there is any inconsistency; The consistency of the building information model two-dimensional drawing name refers to comparing the collected two-dimensional drawings with the building information model view names in step 1 to check their consistency, and outputting corresponding results if there is any inconsistency; The building information model two-dimensional drawing matching relationship refers to that in step 2, firstly automatic matching is performed, and if automatic matching is not possible, then manual matching is performed and an unmatched result is output; The building information model two-dimensional drawing association relationship means that in step 2, the building information model is first aligned in an automatic manner. If the axis grid intersection cannot be extracted and the two-dimensional drawing cannot be rotated, the corresponding result is output and changed to manual alignment; The consistency between the building information model and the two-dimensional drawing refers to the automatic checking of the consistency of the global information, geometric dimensions, and component attribute information of the building information model in step 3, and the inconsistent results are recorded in the report.
8. The method according to claim 7, characterized in that In step 4, the building information model verification report header lists the project name, inspection time, design unit and inspection unit; The building information model verification report lists the results by category according to the inspection type, including the matching relationship inspection results between the building information model and the two-dimensional drawing, the association relationship inspection results, and the consistency verification results between the building information model and the two-dimensional drawing model: In the first case, the matching relationship check result between the building information model and the two-dimensional drawing lists the matching results between the building information model file and the two-dimensional drawing file; In the second case, the association check result lists the association results between the building information model file view and the 2D drawing file; In the third case, in the consistency verification results between the building information model and the two-dimensional drawing model, the inspection results are listed according to the global information consistency, geometric information consistency, and attribute information consistency. The component-level inspection results should list the component's unique identification symbol.
9. An electronic device, characterized in that: The method comprises a processor and a memory, wherein the memory stores program codes, and when the program codes are executed by the processor, the processor executes the steps of the method according to any one of claims 1 to 8.
10. A storage medium, characterized in that: A computer program or instruction is stored, and when the computer program or instruction is run on a computer, the steps of the method according to any one of claims 1 to 8 are executed.
Citation Information
Cited By
Intelligent construction operation and maintenance management and control method based on BIM technology
CN120634474A
A smart construction operation, maintenance, management and control method based on BIM technology
CN120634474B
Architectural design system
JP7858849B1