Calibration method and system for machine construction

By detecting and saving SFR values ​​during the machine construction process and regularly comparing to calibrate the environment, the problem of unstable machine construction environment in the existing technology is solved, ensuring that the product quality meets the standards.

CN119094731APending Publication Date: 2024-12-06TRULY OPTO ELECTRONICS
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202410955429.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-17
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

The existing camera module resolution detection method has high requirements for machine building environment, and the environment construction is unstable due to machine replacement, model differences and human interference, which may cause the outflow of products that do not meet production standards.

Method used

By building the machine for the first time and detecting the SFR value, saving the inspection module information and SFR value, setting work timing and inspection reminder, regularly comparing the current SFR value to determine whether the environment is abnormal, and calibrating the machine environment in time.

Benefits of technology

Ensure the stability of machine environment construction, prevent the outflow of products that do not meet production standards, and improve the accuracy and efficiency of testing.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119094731A_ABST
    Figure CN119094731A_ABST
Patent Text Reader

Abstract

The invention discloses a machine construction and calibration method, which comprises the following steps of: 1, constructing a machine for the first time, and constructing a machine environment to be normal; 2, a point inspection module is selected, and the SFR value of the selected point inspection module is detected and stored; step 3, setting point inspection time, timing the work of the machine, stopping detecting the to-be-detected module when the work timing of the machine reaches the point inspection time, and sending out a prompt that point inspection is needed at the same time; and 4, performing point inspection verification on the selected module again to obtain SFR values, and comparing the SFR values to judge whether the machine environment construction is normal or not. Therefore, the environment construction of the machine can be calibrated in time, and products which do not meet the production standard are prevented from flowing out. The invention further provides a machine construction calibration system.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of camera detection, and in particular to a machine platform construction and calibration method and system. Background Art

[0002] With the continuous development of smart phones and other mobile devices, people have higher and higher requirements for the pixels of camera modules. The resolution of the imaging system is one of the important indicators for judging the quality of a camera module. For example, users first determine whether the taken picture is clear. The clarity here refers to the resolution. The higher the resolution of the camera module, the clearer the taken picture.

[0003] The existing method for testing resolution usually adopts SFR test. SFR test has extremely high requirements for the machine setting environment, which needs to be kept stable. Since machines often need to be replaced, the test resolution distances of modules of different models are inconsistent, the differences between different machines are large, and the interference of human factors during the test will cause changes in the environment setting. If the correct environment setting cannot be adjusted in time, products that do not meet production standards will be discharged. Summary of the invention

[0004] The purpose of the present invention is to overcome the deficiencies in the prior art and provide a machine construction calibration method and system.

[0005] The object of the present invention is achieved through the following technical scheme: A machine construction calibration method, characterized in that it comprises the following steps:

[0006] Step 1: Set up the machine for the first time. The machine environment is set up normally.

[0007] Step 2: Select the inspection module, detect the SFR value of the selected inspection module and save it;

[0008] Step 3: Set the inspection time and count the machine work. When the machine work time reaches the inspection time, stop testing the module to be tested and issue a reminder that inspection testing is required;

[0009] Step 4: Check and verify the selected module again to obtain the SFR value, and compare the SFR value to determine whether the machine environment is set up normally.

[0010] In one embodiment, step 1 includes:

[0011] Step 1.1: The first installation of the machine is carried out by professional engineers according to the prescribed procedures;

[0012] Step 1.2: Test the machine environment that has been built for the first time. If the test parameters are within the standard error range, it means that the machine environment is built normally.

[0013] In one embodiment, step 2 includes:

[0014] Step 2.1: Place the selected qualified inspection module on the inspection area of ​​the machine that has been built for the first time, and the camera module on the machine takes a picture of the inspection module to obtain the SFR value;

[0015] Step 2.2: Save the information of the inspection module using the ID number and the obtained SFR value and set a password;

[0016] Furthermore, in step 2.1, the specific method for selecting a qualified spot inspection module is as follows: select a spot measurement module group, then use the machine that has been built for the first time to detect the SFR value of the selected spot measurement module group, and compare it with the qualified parameters provided by the customer. If the obtained parameters are within the error range, it means that the spot measurement module group is qualified.

[0017] Furthermore, in step 2: the number of selected inspection modules is at least one, and information of at most three inspection modules can be saved.

[0018] Furthermore, in step 2.2: the inspection module information and the SFR value can also be bound and saved by generating a QR code.

[0019] In one embodiment, step 4 includes:

[0020] Step 4.1: Select the ID number of the inspection module and enter the correct password;

[0021] Step 4.2: Place the inspection module on the machine inspection area, and the camera module on the machine takes a picture of the inspection module to obtain the SFR value;

[0022] Step 4.3: Compare the current SFR value with the saved SFR value.

[0023] Further, step 4.3 includes:

[0024] Step 4.3.1: Compare the results. If the SFR value is within the error range, it means that the machine environment is in a qualified state and the module to be tested can be tested again.

[0025] Step 4.3.2: If the SFR value is within the error range, it means that the machine environment setup is in an abnormal state and needs to be readjusted.

[0026] In one embodiment, a machine construction calibration system includes a database, wherein the database is used to store information of a spot inspection module and an SFR value of the spot inspection module.

[0027] Furthermore, it also includes software, which is mainly used to compare the current SFR value with the SFR value stored in the database to determine whether the environment setting of the machine is abnormal. The software also has the function of timing the work of the machine and reminding inspections.

[0028] Compared with the prior art, the present invention has at least the following advantages: a machine construction calibration method of the present invention saves the SFR value initially measured by the point measurement module, detects the current SFR value after the machine is replaced or works continuously for a period of time, and compares it with the saved SFR value to determine whether the machine environment construction is abnormal, and can timely calibrate the machine environment construction to prevent the outflow of products that do not meet production standards. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required for use in the embodiments are briefly introduced below.

[0030] Figure 1 A schematic diagram of a flow chart of a machine setting calibration method according to the present invention. DETAILED DESCRIPTION

[0031] To facilitate understanding of the present invention, the present invention will be described more fully below with reference to the relevant drawings.

[0032] See also Figure 1 , a machine construction and calibration method, comprising the following steps:

[0033] Step 1: The machine is built for the first time, and the machine environment is built normally. Step 1 specifically includes: the machine is built for the first time by a professional engineer according to the prescribed process, and the machine environment is tested after the first construction. If the parameters obtained by the test are within the standard error, it means that the machine environment is built normally.

[0034] It should be noted that the first construction of the machine is mainly to detect the distance between the camera and the detection area, whether the camera and the detection area are level, and the brightness and clarity of the camera's pictures. If the obtained parameters are outside the range of standard error, it means that the machine environment is abnormally constructed and needs to be rebuilt.

[0035] Step 2: Select the inspection module, detect the SFR value of the selected inspection module and save it. Step 2 specifically includes: placing the selected qualified inspection module on the inspection area of ​​the machine that has been built for the first time, the camera module on the machine takes a picture of the inspection module to obtain the SFR value, and the information of the inspection module is saved using the ID number and the obtained SFR value and a password is set.

[0036] It should be noted that the method for selecting the spot inspection module is: use the machine that has been built for the first time to detect the SFR value of the selected spot measurement module group, compare it with the qualified parameters provided by the customer, and if the obtained parameters are within the error range, it means that the spot measurement module is a qualified product. On the contrary, if the obtained parameters do not meet the error range, it means that the selected spot measurement module is an unqualified product, and it is necessary to reselect the spot measurement module group until the selected spot measurement module meets the error range; in this embodiment, the number of selected spot inspection modules is at least one, and the information of up to three spot inspection modules can be saved. In this way, multiple spot measurement modules are compared, so that the reliability of subsequent comparison results is further improved, and the environment construction accuracy of the machine is higher; the information of the spot inspection module is saved and a password is set using an ID number and the obtained SFR value. With this setting, the information and data of the spot measurement module can be scientifically managed, which is conducive to improving work efficiency and avoiding production accidents caused by data disorder between spot measurement modules; the spot inspection module information and the SFR value can also be bound and saved by generating a QR code. This setting can enrich the storage method of the spot measurement module information of the machine.

[0037] Step 3: Set the inspection time and count the machine work. When the machine work time reaches the inspection time, stop testing the module to be tested and issue a reminder that an inspection test is required.

[0038] It should be noted that in this embodiment, the inspection time is set to 8 hours as a cycle, and the inspection time can also be changed according to the work plan. An inspection test is required before the machine starts working to ensure that the environment setup of the machine is normal when it is working, to avoid the machine environment being set up and in standby state due to other factors changing the machine environment setup.

[0039] Step 4: Perform spot inspection and verification on the selected module again to obtain the SFR value, and compare the SFR value to determine whether the machine environment is set up normally. Step 4 specifically includes: selecting the ID number of the spot inspection module, entering the correct password, placing the spot inspection module on the machine detection area, the camera module on the machine takes a picture of the spot inspection module to obtain the SFR value, and compares the current SFR value with the saved SFR value to obtain the result. If the SFR value is within the error range, it means that the machine environment is in a qualified state, and the module to be tested can be retested. If the SFR value is not within the error range, it means that the machine environment is in an abnormal state and the machine environment needs to be readjusted.

[0040] It should be noted that the inspection and verification of the selected modules can be completed by ordinary operators. If it is detected that the machine's environment setup is in an abnormal state, it needs to be calibrated by professional engineers until the machine's environment setup is qualified.

[0041] A machine construction calibration system includes a database for storing information of a spot inspection module and the SFR value of the spot inspection module; and software for comparing a current SFR value with the SFR value stored in the database to determine whether the machine environment construction is abnormal. The software also has the function of timing the machine work and providing spot inspection reminders.

[0042] It should be noted that the software is mainly used to compare the current SFR value with the SFR value saved in the database. If the current SFR value is within the error range, the software will judge it as OK, indicating that the machine environment is set up normally. If the current SFR value is outside the error range, the software will judge it as NG, indicating that the machine environment is set up abnormally.

[0043] The above-mentioned embodiments only express several implementation methods of the present invention, and the description thereof is relatively specific and detailed, but it cannot be understood as limiting the scope of the invention patent. It should be pointed out that for ordinary technicians in this field, several modifications and improvements can be made without departing from the concept of the present invention, which all belong to the protection scope of the present invention. Therefore, the protection scope of the patent of the present invention shall be based on the attached claims.

Claims

1. A machine construction and calibration method, characterized in that: The following steps are involved: Step 1: Set up the machine for the first time. The machine environment is set up normally. Step 2: Select the inspection module, detect the SFR value of the selected inspection module and save it; Step 3: Set the inspection time and count the machine work. When the machine work time reaches the inspection time, stop testing the module to be tested and issue a reminder that inspection testing is required; Step 4: Check and verify the selected module again to obtain the SFR value, and compare the SFR value to determine whether the machine environment is set up normally.

2. A machine construction and calibration method according to claim 1, characterized in that: Step 1 includes: Step 1.1: The first installation of the machine is carried out by professional engineers according to the prescribed procedures; Step 1.2: Test the machine environment that has been built for the first time. If the test parameters are within the standard error range, it means that the machine environment is built normally.

3. A machine construction and calibration method according to claim 1, characterized in that: Step 2 includes: Step 2.1: Place the selected qualified inspection module on the inspection area of ​​the machine that has been built for the first time, and the camera module on the machine takes a picture of the inspection module to obtain the SFR value; Step 2.2: Save the information of the inspection module using the ID number and the obtained SFR value and set a password.

4. A machine construction and calibration method according to claim 3, characterized in that: In step 2.1, the specific method for selecting a qualified spot inspection module is as follows: select a spot measurement module group, then use the machine that has been built for the first time to detect the SFR value of the selected spot measurement module group, and compare it with the qualified parameters provided by the customer. If the obtained parameters are within the error range, it means that the spot measurement module group is qualified.

5. The machine construction and calibration method according to claim 3, characterized in that: In step 2: the number of selected inspection modules is at least one, and information of at most three inspection modules can be saved.

6. A machine construction and calibration method according to claim 3, characterized in that: In step 2.2: the inspection module information and SFR value can also be bound and saved by generating a QR code.

7. A machine construction and calibration method according to claim 3, characterized in that: Step 4 includes: Step 4.1: Select the ID number of the inspection module and enter the correct password; Step 4.2: Place the inspection module on the machine inspection area, and the camera module on the machine takes a picture of the inspection module to obtain the SFR value; Step 4.3: Compare the current SFR value with the saved SFR value.

8. A machine construction and calibration method according to claim 8, characterized in that: Step 4.3 includes: Step 4.3.1: Compare the results. If the SFR value is within the error range, it means that the machine environment is in a qualified state and the module to be tested can be tested again. Step 4.3.2: If the SFR value is within the error range, it means that the machine environment setup is in an abnormal state and needs to be readjusted.

9. A machine construction calibration system, characterized in that: A database is included, and the database is used to store the information of the inspection module and the SFR value of the inspection module.

10. A machine construction calibration system according to claim 9, characterized in that: It also includes software, which is mainly used to compare the current SFR value with the SFR value stored in the database to determine whether the environment setting of the machine is abnormal. The software also has the function of timing the work of the machine and reminding inspections.

Citation Information

Patent Citations

  • Monitoring method and monitoring device for detecting accuracy

    CN109186940A

  • Method and system for detecting anti-shake performance of optical anti-shake camera and storage medium

    CN112351274A

  • Test board

    CN207779666U

  • Correction device for camera module optical image stabilizer system and correction method therefor

    WO2017054689A1

  • Quality abnormity recording method and apparatus, and augmented reality device, system and medium

    WO2021164448A1