Engineering drilling mud treatment device
Through the negative pressure suction and the splicing device of multiple square steel, the problems of insufficient pollution and stability in traditional drilling mud treatment methods are solved, and efficient and environmentally friendly mud collection and treatment are achieved, adapting to drilling projects of different scales and shapes.
Patent Information
- Application Number
- CN202411075991.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-07
- Publication Date
- 2024-12-10
AI Technical Summary
Traditional drilling mud treatment methods have problems such as serious pollution, slow construction speed, unstable structure and inability to completely collect mud, resulting in environmental pollution and waste of resources.
A device including a mud tank, a collection tank, a constant pressure tank and an air pump was designed to collect mud and water through the principle of negative pressure suction, and a stable mud tank structure was formed by splicing multiple square steels, which was realized by using a suction bowl and a connecting pipe system. Efficient collection and storage of mud and water.
It effectively reduces environmental pollution, improves the stability and construction efficiency of mud tanks, and can flexibly adjust the size and shape, which meets the environmental protection requirements of modern projects.
Smart Images

Figure CN119102531A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of engineering geological survey and drilling, and in particular relates to an engineering drilling mud processing device. Background Art
[0002] When drilling on the road of a nuclear power project, the exploration point is generally arranged on the side of the main road in the city. The ground is generally completely solidified, and mud pools are not allowed to be dug on the ground. During the survey and construction, mud discharge will seriously pollute the urban ground environment and even block the municipal drainage pipes. Traditionally, mud treatment is generally to cover the sandbags with plastic film, and then discharge the mud into the sandbags. After the sandbags are full, they are sealed and then transported out for treatment. This method has a slow construction speed, and the plastic film is easy to break, causing leakage and polluting the environment. There are also some mud troughs made by drilling workers, such as four square steels fixed by bolts, geotextiles or sponges are laid on the bottom, and a square trough structure with an outlet is formed to block mud and water turbulence. However, this homemade mud trough has a simple structure, lacks stability, and is prone to deformation or collapse during the drilling process, resulting in leakage, and it is also impossible to completely collect all the mud, resulting in some mud still leaking into the environment after being filled, which is less practical. Summary of the invention
[0003] In view of the defects and problems existing in the above-mentioned existing mud tank designs, the present invention provides an engineering drilling mud processing device.
[0004] The solution adopted by the present invention to solve its technical problems is: an engineering drilling mud processing device, including a mud tank, a collection tank, a constant pressure tank and an air pump, wherein the mud tank includes a plurality of square steels, each of which has the same appearance structure, a plug extending from one end, and a socket matching the plug opened inside the other end, and each square steel is fixedly inserted together head and tail in sequence, so that the interior is surrounded by a slurry chamber; each square steel has an upper chamber and a lower chamber opened inside along its length extension direction, the upper chamber is matched with a bronchus, the bottom of the lower chamber is an open structure, and a suction cup is fixedly installed inside, and the bronchus in the upper chamber and the suction cup in the lower chamber are connected by a connecting pipe; the inner side of the square steel A water suction pipe is provided, and a valve is provided on the water suction pipe. A water level sensor is fixedly installed on the square steel on one side of the valve, and a connecting pipe is provided on the outer side of the square steel, and the water suction pipe and the bronchial pipe are both connected with the connecting pipe; the output end of the connecting pipe is connected to the inlet of the collecting tank through the main pipe; the air suction port of the collecting tank is connected to the constant pressure tank through the air suction pipe, and the constant pressure tank is controlled by an air pump; the valve is closed in the natural state, and the interior of the constant pressure tank of the collecting tank maintains a constant negative pressure state, so that the bronchial pipe in each square steel is sucked by the negative pressure, so that the square steel is buckled and adsorbed on the ground through each suction bowl; when the valve is opened, the muddy water in the slurry chamber is sucked into the collecting tank through the main pipe.
[0005] Furthermore, each square steel is sequentially fixed and inserted together at the head and tail ends by through screws to be assembled into a mud trough structure capable of containing mud and water.
[0006] Furthermore, the collecting tank is a horizontal structure with a support at the bottom, an inlet and an exhaust port at the top of the tank body, the exhaust port is connected to the constant pressure tank through an exhaust pipe to maintain a constant negative pressure state inside the collecting tank; a slurry discharge port is installed at the bottom of the tank body.
[0007] Furthermore, the constant pressure tank and the air pump are placed on a base, the constant pressure tank is connected to the collection tank through an exhaust pipe, the constant pressure tank is controlled by the air pump, and the air pressure in the constant pressure tank is controlled by the air pump.
[0008] Furthermore, through grooves are evenly opened between the upper cavity and the lower cavity, and a connecting pipe is installed inside the through groove. One end of the connecting pipe is connected to the bronchus in the upper cavity, and the other end is fixedly connected to the suction bowl.
[0009] Furthermore, the end of the bronchial pipe in one of the square steels is also connected to a three-way pipe, the inner side of the three-way pipe is connected to the water pumping pipe, and the outer side is connected to the connecting pipe.
[0010] Furthermore, a filter screen is fixedly installed at the end of the water extraction pipe by bolts to prevent the pipe from being blocked.
[0011] Compared with the prior art, the present invention has the following beneficial effects: The engineering drilling mud processing device provided by the present invention can efficiently collect muddy water ejected during the drilling process into a mud tank through negative pressure suction, thereby reducing environmental pollution and waste of resources; the mud tank is formed by splicing a plurality of square steels, and the size and shape can be flexibly adjusted as needed to adapt to drilling projects of different scales and shapes; a suction cup is used to be adsorbed on the ground through the negative pressure principle, thereby enhancing the stability of the mud tank, and maintaining stability even in complex and changeable construction sites; through the coordinated use of a constant pressure tank and an air pump, a constant negative pressure state inside the collection tank can be maintained, ensuring that muddy water can be stably stored and sucked; the device of the present invention can effectively collect and process mud, reduces pollution to the environment, and meets the environmental protection requirements of modern engineering. BRIEF DESCRIPTION OF THE DRAWINGS
[0012] Figure 1 It is a schematic diagram of the three-dimensional structure of the present invention; Figure 2 for Figure 1 The enlarged cross-sectional structure diagram at A in the middle; Figure 3 This is a schematic diagram of the suction cup installation structure in the mud tank; Figure 4 Schematic diagram of the top view of the mud tank; Figure 5 for Figure 4The enlarged cross-sectional structure diagram at C in the middle; Figure 6 It is a front view structural schematic diagram of the collection tank; Figure 7 It is a schematic diagram of the connection structure between the constant pressure tank and the air pump; Figure 8 It is a schematic cross-sectional view of the plug-in structure of Example 2; Fig. 9 It is a schematic diagram of the structure of different insertion states of Example 2.
[0013] In the figure: 1-mud tank, 2-collection tank, 3-constant pressure tank, 4-air pump, 5-main pipe, 6-exhaust pipe, 7-exhaust port, 8-support, 9-discharge port, 10-inlet, 11-square steel, 12-water level sensor, 13-slurry chamber, 14-valve, 15-water pump, 17-suction bowl, 18-connecting pipe, 19-plug, 20-jack, 21-upper chamber, 22-bronchus, 23-lower Cavity, 24-connecting pipe, 25-tee pipe, 30-base, 101-plug-in body, 102-main air pipe, 103-plug connector, 104-connecting groove, 105-pin pipe, 106-side hole, 107-magnet, 201-plugged body, 202-auxiliary air pipe, 203-plug-in groove, 204-fixed block, 205-spring, 206-spring seat, 207-movable cavity, 208-blocking platform. DETAILED DESCRIPTION
[0014] The present invention is further described below in conjunction with the accompanying drawings and embodiments.
[0015] See also Figure 1-9 The present invention provides a technical solution for an engineering drilling mud treatment device: Example
[0016] The present embodiment provides an engineering drilling mud processing device, including a mud tank 1, a collecting tank 2, a constant pressure tank 3 and an air pump 4, etc. The inlet of the collecting tank is connected to the bronchial tube inside the square steel constituting the mud tank, and the air suction port 7 of the collecting tank is connected to the constant pressure tank 3 through the air suction pipe. The constant pressure tank 3 is controlled by the air pump 4, so that the inner cavity of the collecting tank and the constant pressure tank always maintains a horizontal negative pressure state, and at the same time, the square steel is fixed to the ground through the suction bowl at the bottom, so that the mud and water sprayed out from the borehole during engineering drilling can be collected in the mud tank 1, and the mud and water can be collected into the collection tank 2 through the main pipe 5 through the negative pressure suction effect.
[0017] Specifically, Figure 1 and Figure 3 As shown, the mud trough is made of multiple square steels. In this embodiment, four square steels are connected end to end to form a square slurry chamber 13. The mud trough structure is placed around the borehole to collect the splashed mud water. Figure 3As shown, each square steel has the same appearance structure, and the main body is a rectangular parallelepiped structure. A plug 19 extends from one end, and a socket 20 is opened inside the square steel at the other end. In this way, the plug of one square steel is vertically inserted into the socket of another square steel, and then the two square steels are fixed together by through screws. Four square steels can be fixedly assembled into a mud trough structure that can hold mud and water.
[0018] Furthermore, if Figure 4 As shown, the interior of each square steel is a double-layer structure, that is, the square steel body is provided with an upper cavity 21 and a lower cavity 23 along its extension direction, and the upper cavity is fixedly provided with a bronchus 22, and the bottom of the lower cavity 23 is an open structure, and a suction cup 17 is fixedly provided inside. The suction cup may be made of rubber material, and through grooves are evenly provided between the upper cavity and the lower cavity. A connecting pipe 24 is matched and provided inside the through groove, that is, the top of the connecting pipe is connected to the bronchus 22 in the upper cavity, and the bottom is connected to the inner cavity of the suction cup 17. In this way, when negative pressure suction is performed on each bronchus, negative pressure can be formed inside the suction cup through the connecting pipe 24, so that the suction cup is tightly adsorbed on the ground, so that a barrier is formed around the bottom of the mud trough to constitute a slurry chamber for collecting mud and water.
[0019] In the arrangement of the present invention, the bronchus in the upper cavity is used to connect to the collection system, and the suction cup in the lower cavity is connected to the upper cavity through a connecting tube, forming a negative pressure adsorption system, which combines the concepts of negative pressure suction and modular splicing, not only enhances the stability of the structure, but also cleverly utilizes the negative pressure principle to achieve adsorption on the ground, improves the efficiency of mud collection, and facilitates flexible deployment at complex and changeable drilling sites.
[0020] like Figure 5 As shown, a three-way pipe 25 is connected to the end of the bronchial pipe in one of the square steels to realize the suction of muddy water in the slurry chamber 13. Specifically, as Figure 2 and Figure 5 As shown, a pumping pipe 15 is provided inside the square steel, a valve 14 is provided on the pumping pipe, a water level sensor 12 is fixedly installed on the square steel near the valve, a connecting pipe 18 is provided outside the square steel, and the inside of the three-way pipe 25 is connected to the pumping pipe 15, and the outside is connected to the connecting pipe 18. In this way, when the valve 14 is closed, negative pressure suction is achieved only through each bronchus 22 and the suction bowl, so that the mud trough is tightly adsorbed on the ground, and when the depth of muddy water in the slurry chamber reaches the set height of the water level sensor 12, the water level sensor alarms, and the valve is automatically opened by the controller, so that the muddy water in the slurry chamber is sucked into the inner cavity of the collection tank 2 through the pumping pipe 15 and then through the three-way pipe 25 and the connecting pipe 18, which can prevent the muddy water in the slurry chamber from overflowing.
[0021] In addition, considering that the muddy water in the slurry chamber may contain some particulate impurities, which may cause blockage of pipelines at all levels, a filter screen can be installed at the end of the pumping pipe by bolts to prevent pipeline blockage and improve pumping efficiency; the filter screen is detachable for easy cleaning and replacement.
[0022] like Figure 1 and Figure 6 As shown, the output end of the connecting pipe 18 is connected to the inlet 10 of the collecting tank 2 through the main pipe 5. The collecting tank is a horizontal structure with a support 8 at the bottom. The top of the tank body is provided with an inlet 10 and an air suction port 7. The air suction port 7 is connected to the constant pressure tank 3 through the air suction pipe 6 to maintain a constant negative pressure state inside the collecting tank. A slurry discharge port 9 is installed at the bottom of the tank body. The slurry discharge port is in a normally closed state. The interior of the collecting tank maintains a constant negative pressure. When the valve 14 is opened, muddy water can flow into the interior of the collecting tank through the inlet 10. When the drilling work is completed, the muddy water in the tank body can be discharged by opening the slurry discharge port 9 at the bottom, thereby effectively realizing the collection, storage and discharge of mud. Figure 1 and Figure 7 As shown, the constant pressure tank 3 and the air pump 4 are placed on the base 30. The constant pressure tank is connected to the collection tank 2 through the air extraction pipe. The constant pressure tank is controlled by the air pump, and the air pressure in the constant pressure tank is controlled by the air pump to maintain a constant negative pressure state in the constant pressure tank and the collection tank. Furthermore, a pressure detection device, such as a pressure gauge, can be added to the collection tank and the negative pressure tank to adjust the negative pressure according to actual needs to avoid damage to the system caused by excessive or insufficient negative pressure.
[0023] The present invention provides an engineering drilling mud processing device. When it is actually used, the pipelines are connected accordingly, the valve 14 is kept closed, the collecting tank is assembled and fixed, and then placed around the borehole. The air pump 4 controls the constant pressure tank 3 to maintain a constant negative pressure state in the inner cavity of the collecting tank 2 and the constant pressure tank 3, and transmits the air to the suction cup 17 through the bronchus, so that the suction cup 17 is adsorbed on the ground under the action of negative pressure to keep the mud tank 1 stable. During the drilling process, the mud carries the rock cuttings into the slurry chamber 13 of the mud tank. When the depth of mud and water in the slurry chamber reaches the height set by the water level sensor 12, the water level sensor controls the water level sensor 12 to increase the pressure. The device sends a signal, and the controller automatically opens the valve after receiving the signal, allowing the muddy water to be sucked into the collection tank 2 through the pumping pipe 15, the three-way pipe 25, the connecting pipe 18 and the main pipe 5. Due to the effect of constant negative pressure, the muddy water can be stably stored in the tank; when the muddy water in the slurry chamber is completely sucked into the collection tank, the valve 14 is closed, and the slurry discharge port 9 at the bottom of the collection tank is opened to discharge the muddy water in the tank to the designated treatment area. After the discharge is completed, the slurry discharge port 9 is closed, and the collection tank is cleaned and maintained to prepare for the next use; at the same time, the residual mud sediment in the slurry chamber is cleaned.
[0024] The engineering drilling mud processing device provided by the present invention is easy to assemble and disassemble and has strong flexibility. It uses a suction cup to be adsorbed on the ground through the negative pressure principle, thereby enhancing the stability of the mud tank. It can remain stable even in complex and changeable construction sites and has strong stability. Through the coordinated use of a constant pressure tank and an air pump, a constant negative pressure state inside the collection tank can be maintained to ensure that mud and water can be stably stored and pumped. The present invention effectively collects and processes mud, reduces pollution to the environment, and meets the environmental protection requirements of modern engineering. Example
[0025] On the basis of Example 1, Figure 8 and Fig. 9 As shown, the similarities between this embodiment and embodiment 1 are not repeated here, except that the matching of the plug and the socket between each square steel can also be set to the structure described in this embodiment, such as Figure 8 As shown, one square steel structure is defined as a plug-in body 101, and the other is a plugged body 202. A plug connector 103 is provided at the end of each plug-in body 101, and a plug slot 203 is opened inside the other end, that is, one square steel structure can be used as both a plug-in body and a plugged body. Multiple plug-in bodies 101 are matched and fixedly inserted into the plugged body, and are connected end to end to form a mud tank.
[0026] Furthermore, a connecting groove 104 is provided on the upper side of one side of the plug connector 103, and the connecting groove is connected to the airflow channel I102 inside the plug body 101. A groove 108 perpendicular to the airflow channel I is provided on the side of the connecting groove away from the airflow channel I, and a pin tube 105 is matched and provided in the groove. The pin tube is hollow inside, and a side hole 106 is provided on the side close to the connecting groove 104. The bottom of the pin tube is a closed structure, and is fixed and adsorbed inside the groove 108 by a magnet 107.
[0027] like Figure 8 As shown, a fixed block 204 is installed inside the plug-in slot 203 of the plug-in body 201. The fixed block is a solid structure with an installation slot on the right side. A spring 205 is fixedly installed in the installation slot. The spring is fixedly connected to a spring seat 206 on the deep side wall of the plug-in slot 204 in the transverse direction. A moving cavity 207 connected to the plug-in slot is opened above the fixed block. A stopper 208 is provided on the top of the moving cavity, and the moving cavity is connected to the airflow channel II of the plug-in body 201. Under the action of the spring, the fixed block is naturally located in the middle of the plug-in slot and blocks the moving cavity, so that the airflow in the airflow channel II 202 cannot flow into the plug-in slot.
[0028] When the plug connector 103 of the plug body 101 is matched and inserted into the plug slot 203 on the plugged body 201, as shown in FIG. Fig. 9As shown, the pin tube 105 presses the fixed block 204 to move it inward, and at the same time the spring is compressed. When the plug connector 103 is completely inserted into the plug-in slot, due to the negative pressure inside the air flow channel II 202, the pin tube 105 is sucked upward, so that the magnetic adsorption effect of the magnet disappears, until the pin tube is adsorbed to the top and contacts the baffle in the movable chamber 207, and at the same time the side hole 106 on the pin tube is connected with the connecting slot 104. At this time, under the action of the pin tube, the air flow channel II and the pin tube 105, as well as the connecting slot 104 and the air flow channel I are connected with the air flow, and the upper part of the pin tube body is located in the movable chamber 207, and the lower part is located in the groove 108 of the plug connector, so that the plug connector 103 is fixedly inserted in the plug-in slot 203 under the action of negative pressure suction, thereby realizing the fixed plug-in connection between the four square steels, which together form a mud tank.
[0029] The arrangement of this embodiment utilizes the negative pressure system to form a self-sealing and self-locking matching relationship between each square steel. After each square steel structure is installed, it is only necessary to maintain the negative pressure state of the air flow channel inside the square steel through the air pump, so that the internal air flow channel forms a negative pressure environment. Under the continuous action of negative pressure, the plug connector is firmly fixed in the plug slot, and these square steels will automatically form a tight connection. This connection method does not require additional fasteners or manual operation, which greatly improves the installation efficiency and connection reliability. At the same time, due to the sealing effect of negative pressure, leakage is not easy to occur at the connection, and when the square steel needs to be disassembled or replaced, it is easy to do by simply turning off the air pump and releasing the negative pressure, which significantly improves the on-site construction efficiency and connection reliability, while also reducing maintenance costs and difficulty of use.
[0030] The above description is only a preferred embodiment of the present invention and does not limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. An engineering drilling mud treatment device, characterized in that: The invention comprises a mud tank (1), a collecting tank (2), a constant pressure tank (3) and an air pump (4), wherein the mud tank (1) comprises a plurality of square steels, each of which has the same appearance structure, a plug (19) extending from one end, and a socket (20) matching the plug opened inside the other end, and each square steel is fixedly inserted together head to tail in sequence, so that the interior forms a slurry chamber (13); each square steel has an upper chamber (21) and a lower chamber (23) opened inside along its length extension direction, the upper chamber is matched with a bronchial tube (22), the bottom of the lower chamber is an open structure, and a suction cup is fixedly installed inside, and the bronchial tube (22) in the upper chamber and the suction cup in the lower chamber are connected through a connecting pipe (24); a water suction pipe (15) is arranged on the inner side of the square steel, and a suction pipe (21) is arranged on the water suction pipe. A valve (14) is provided, a water level sensor (12) is fixedly mounted on a square steel on one side of the valve, a connecting pipe (18) is provided on the outside of the square steel, and the water pumping pipe and the bronchial pipe are both connected to the connecting pipe; the output end of the connecting pipe is connected to the inlet of the collection tank (2) through the main pipe; the air suction port (7) of the collection tank is connected to the constant pressure tank (3) through the air suction pipe (6), and the constant pressure tank is controlled by the air pump (4); in the natural state, the valve is closed, and the interior of the constant pressure tank of the collection tank maintains a constant negative pressure state, so that the bronchial pipe (22) in each square steel is sucked by the negative pressure, so that the square steel is buckled and adsorbed on the ground through each suction cup (17); when the valve is opened, the muddy water in the slurry chamber (13) is sucked into the collection tank through the main pipe (5).
2. The engineering drilling mud processing device according to claim 1, characterized in that: The ends of each square steel are fixed and inserted together in sequence by through screws to assemble into a mud trough structure capable of containing mud and water.
3. The engineering drilling mud processing device according to claim 1, characterized in that: The collecting tank is a horizontal structure, with a support (8) provided at the bottom, an inlet (10) and an air suction port (7) provided at the top of the tank body, the air suction port (7) being connected to the constant pressure tank (3) through an air suction pipe (6) to maintain a constant negative pressure state inside the collecting tank; a slurry discharge port (9) is provided at the bottom of the tank body.
4. The engineering drilling mud processing device according to claim 1, characterized in that: The constant pressure tank (3) and the air pump (4) are placed on a base (30); the constant pressure tank is connected to the collection tank (2) via an air extraction pipe; the constant pressure tank is controlled by the air pump, and the air pressure in the constant pressure tank is controlled by the air pump.
5. The engineering drilling mud processing device according to claim 1, characterized in that: Through grooves are evenly formed between the upper cavity and the lower cavity, and a connecting pipe (24) is installed inside the through groove. One end of the connecting pipe is connected to the bronchus (22) in the upper cavity, and the other end is fixedly connected to the suction bowl (17).
6. The engineering drilling mud processing device according to claim 1, characterized in that: The end of the bronchial tube in one of the square steels is also connected to a three-way pipe (25), the inner side of the three-way pipe (25) is connected to the water pumping pipe (15), and the outer side is connected to the connecting pipe (18).
7. The engineering drilling mud processing device according to claim 1, characterized in that: The end of the water pumping pipe is fixed with a filter screen by bolts to prevent the pipe from being blocked.