Rubber tube assembly mounting equipment and valve assembly production line
By designing hose assembly installation equipment, the hose section cutting, bending, installation and shrinking pipes are automatically completed, solving the problem of inefficiency caused by manual participation in the production process of existing gas pressure reducing valves, and achieving efficient and automated production.
Patent Information
- Application Number
- CN202411353649.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-26
- Publication Date
- 2024-12-17
AI Technical Summary
The production process of existing gas pressure reducing valves requires a lot of manual participation, resulting in low production efficiency.
A hose assembly installation equipment is designed, including fixed-length cutting mechanism, transfer mechanism, pipe cap mechanism, joint nut mechanism, valve body mechanism and pipe shrink mechanism, and the cutting, bending and pipe of the hose section are automatically completed through mechanized process. The installation of caps and joints, the connection of gas pressure reducing valves and the compression of pipes to reduce manual participation.
It improves the production efficiency of finished gas pressure reducing valves, realizes automated production processes, reduces manual operations, and improves production efficiency.
Smart Images

Figure CN119141897A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of gas pressure reducing valve manufacturing technology, and in particular to a hose assembly installation device and a valve assembly production line. Background Art
[0002] In existing production processes, some manufacturers connect pre-assembled gas pressure reducing valves to hose assemblies (which include hose sections, two caps, a pagoda nut, and a pagoda connector) to obtain finished gas pressure reducing valves for user use after shipment. (Refer to...) Figure 8 or Figure 9 The process of connecting a gas pressure reducing valve to a hose assembly to obtain a finished gas pressure reducing valve is as follows: 1. Manually cut a hose section to a preset length; 2. Manually attach two caps to the two ends of the hose section; 3. Manually insert a pagoda connector into a pagoda nut, and then insert it into one end of the hose section, so that the pagoda nut is sandwiched between the pagoda connector and the corresponding cap; 4. Manually insert the gas outlet pipe of the gas pressure reducing valve into the other end of the hose section; 5. Manually use a hose shrinking device to shrink and tighten the two caps on both ends of the hose section. As can be seen from the above, the production process of the finished gas pressure reducing valve requires manual intervention, resulting in low production efficiency. Therefore, in order to improve the production efficiency of the finished gas pressure reducing valve, the inventor aims to solve the problem of designing a hose assembly installation device that can reduce manual intervention and connect the gas pressure reducing valve to the hose assembly. Summary of the Invention
[0003] The present invention aims to at least solve one of the technical problems existing in the prior art. To this end, the present invention proposes a hose assembly installation device.
[0004] The present invention also proposes a valve assembly line having the hose assembly installation equipment.
[0005] According to a first aspect of the present invention, a hose assembly installation device includes a frame, a fixed-length hose cutting mechanism, a first transfer mechanism, a hose capping mechanism, an upper connector nut mechanism, an upper valve body mechanism, a second transfer mechanism, and a hose shrinking mechanism. The fixed-length hose cutting mechanism is disposed on the frame and has an outlet hole for the hose to pass through. The fixed-length hose cutting mechanism can transport the hose through the outlet hole and can cut a hose segment of a predetermined length passing through the outlet hole. The first transfer mechanism is disposed on the frame and can pick up the hose segment cut by the fixed-length hose cutting mechanism. It can also drive the hose segment to bend into a U-shape and sequentially transfer it to a first station, a second station, a third station, and a fourth station. The hose capping mechanism is disposed on the frame and can store hose caps and can respectively fit two hose caps onto the two ends of the hose segment at the first station. The upper connector nut mechanism is... The upper connector nut mechanism on the frame can store the pagoda connector and the pagoda nut, and can insert the pagoda connector after the pagoda nut, and then insert it into one end of the hose section of the second station, so that the pagoda nut is clamped between the pagoda connector and the corresponding cap. The upper valve body mechanism is located on the frame. The upper valve body mechanism can receive the gas pressure reducing valve, and can insert the gas outlet pipe of the received gas pressure reducing valve into the other end of the hose section of the third station. The second transfer mechanism is located on the frame. The second transfer mechanism can transfer the hose section with the cap, pagoda nut, pagoda connector and gas pressure reducing valve of the fourth station, and can sequentially transfer the hose section to the fifth station and the sixth station. The tube shrinking mechanism is located on the frame. The tube shrinking mechanism can shrink and tighten the cap of one end of the hose section of the fifth station, and can shrink and tighten the cap of the other end of the hose section of the sixth station.
[0006] A hose assembly installation device according to an embodiment of the present invention has at least one of the following beneficial effects:
[0007] Based on the above structure, the working process of the hose assembly installation equipment is as follows: 1. The fixed-length hose cutting mechanism conveys the hose through the outlet hole and cuts the hose to a preset length through the outlet hole to obtain a hose segment; 2. The first transfer mechanism picks up the hose segment cut by the fixed-length hose cutting mechanism, drives the hose segment to bend into a U-shape, and then transfers it to the first station; 3. The capping mechanism puts two caps on the two ends of the hose segment at the first station; 4. The first transfer mechanism drives the hose segment at the first station to the second station; 5. The connector nut mechanism inserts the pagoda connector into the pagoda nut, and then inserts it into one end of the hose segment at the second station, so that the pagoda nut is clamped between the pagoda connector and the corresponding cap; 6. The first transfer mechanism... 7. The upper valve body mechanism inserts the gas outlet pipe of the received gas pressure reducing valve into the other end of the hose section in the third station; 8. The first transfer mechanism drives the hose section in the third station to the fourth station; 9. The second transfer mechanism removes the hose section in the fourth station (which is equipped with a cap, a pagoda nut, a pagoda connector, and a gas pressure reducing valve) and transfers it to the fifth station; 10. The hose shrinking mechanism performs hose shrinking and tightening work on the cap at one end of the hose section in the fifth station; 11. The second transfer mechanism drives the hose section in the fifth station to the sixth station; 12. The hose shrinking mechanism performs hose shrinking and tightening work on the cap at the other end of the hose section in the sixth station.
[0008] With the above structure, the fixed-length pipe cutting mechanism, the first transfer mechanism, the upper pipe cap mechanism, the upper connector nut mechanism, the upper valve body mechanism, the second transfer mechanism, and the pipe shrinking mechanism on the frame of the hose assembly installation equipment of this application can cooperate with each other to realize the connection of the gas pressure reducing valve and the hose assembly into a finished gas pressure reducing valve. The above process requires less manual intervention, thus improving the production efficiency of the finished gas pressure reducing valve.
[0009] According to some embodiments of the present invention, the first transfer mechanism includes a tube-taking assembly, a first transfer assembly, and a first tube-transfer assembly. The tube-taking assembly is disposed on the frame and is capable of receiving a tube segment cut by the fixed-length tube-cutting mechanism, and can bend the received tube segment into a U-shape and transfer it to the eighth station. The first transfer assembly is disposed on the frame and is capable of picking up the tube segment bent into a U-shape by the tube-taking assembly at the eighth station, and can transfer the picked-up tube segment to the ninth station. The first tube-transfer assembly is disposed on the frame and is capable of picking up the U-shaped tube segment at the ninth station, and can sequentially transfer the tube segment to the first station, the second station, the third station, and the fourth station.
[0010] According to some embodiments of the present invention, the capping mechanism includes a first material storage and conveying assembly, a first material dispensing assembly, and a first material transfer assembly. The first material storage and conveying assembly is disposed on the frame and has a first channel. The first material storage and conveying assembly is capable of storing caps and driving caps to move through the first channel. The first material dispensing assembly is disposed on the first material storage and conveying assembly and is capable of removing caps removed from the outlet of the first channel and sealing the outlet of the first channel. The first material transfer assembly is disposed on the frame and is capable of fitting the caps removed by the first material dispensing assembly onto the end of the hose section at the first workstation.
[0011] According to some embodiments of the present invention, the upper connector nut mechanism includes a second material storage and conveying assembly, a second material dispensing assembly, a third material storage and conveying assembly, a third material dispensing assembly, a second material transfer assembly, and a third material transfer assembly. The second material storage and conveying assembly is disposed on the frame and has a second channel. The second material storage and conveying assembly is capable of storing pagoda nuts and driving pagoda nuts to move through the second channel. The second material dispensing assembly is disposed on the second material storage and conveying assembly and is capable of removing pagoda nuts removed from the outlet of the second channel and closing the outlet of the second channel. The third material storage and conveying assembly is disposed on the frame and has a third channel. The material storage and conveying assembly can store pagoda connectors and drive them to move through the third channel. The third material distribution assembly is located on the third material storage and conveying assembly. The third material distribution assembly can remove pagoda connectors that have been removed from the outlet of the third channel and can close the outlet of the third channel. The second material transfer assembly is located on the frame. The second material transfer assembly can insert the pagoda connectors removed by the third material distribution assembly into the pagoda nuts removed by the second material distribution assembly. The third material transfer assembly is located on the frame. The third material transfer assembly can remove the pagoda nuts with pagoda connectors inserted that have been removed by the second material distribution assembly and can insert the pagoda connectors on the pagoda nuts into one end of the hose section of the second station.
[0012] According to some embodiments of the present invention, the upper valve body mechanism includes a receiving and transferring assembly and a fourth transferring assembly. The receiving and transferring assembly is disposed on the frame and is capable of receiving a gas pressure reducing valve at the tenth station and transferring the received gas pressure reducing valve to the eleventh station. The fourth transferring assembly is disposed on the frame and is capable of removing the gas pressure reducing valve from the receiving and transferring assembly at the eleventh station and inserting the gas outlet pipe of the removed gas pressure reducing valve into the other end of the hose section at the third station.
[0013] According to some embodiments of the present invention, the second transfer mechanism includes a second transfer component and a second pipe transfer component. The second transfer component is disposed on the frame and is capable of picking up the hose segment equipped with a pipe cap, a pagoda nut, a pagoda connector, and a gas pressure reducing valve from the fourth station and transferring the hose segment to the twelfth station. The second pipe transfer component is disposed on the frame and is capable of picking up the hose segment from the twelfth station and sequentially transferring the hose segment to the fifth and sixth stations.
[0014] According to some embodiments of the present invention, the tube shrinking mechanism includes two tube shrinking devices both disposed on the frame. One tube shrinking device is capable of shrinking and tightening the cap at one end of the hose section at the fifth station, and the other tube shrinking device is capable of shrinking and tightening the cap at the other end of the hose section at the sixth station.
[0015] According to some embodiments of the present invention, the frame is provided with a tag hanging mechanism, which can store tags and can transfer tags to the tube insertion position for the rubber tube to be moved through the tube outlet hole, so that the rubber tube segment transferred by the first transfer mechanism has a tag.
[0016] According to some embodiments of the present invention, the second transfer mechanism can sequentially transfer the hose segment to the fifth station, the sixth station and the seventh station, and the frame is provided with a marking mechanism, which can perform marking work on the finished gas pressure reducing valve at the seventh station.
[0017] According to a second aspect of the present invention, a valve assembly production line includes a hose assembly installation device as described above.
[0018] The valve assembly line according to embodiments of the present invention has at least the following beneficial effects: the above structure can improve the production efficiency of finished gas pressure reducing valves.
[0019] Additional aspects and advantages of the invention will be set forth in part in the description which follows, and in part will be obvious from the description, or may be learned by practice of the invention. Attached Figure Description
[0020] The above and / or additional aspects and advantages of the present invention will become apparent and readily understood from the following description of the embodiments with reference to the accompanying drawings, in which:
[0021] Figure 1 This is a partial structural diagram of an embodiment of the hose assembly installation device of the present invention;
[0022] Figure 2 for Figure 1 The structural diagram of the fixed-length pipe cutting mechanism and pipe taking assembly shown in the figure;
[0023] Figure 3 for Figure 1 The structural diagram of the first transfer assembly and the first transfer tube assembly shown in the figure;
[0024] Figure 4 for Figure 1 The diagram shows the structure of the upper cap mechanism.
[0025] Figure 5 for Figure 1 The diagram shows the structure of the upper connector nut mechanism.
[0026] Figure 6 for Figure 1 The diagram shows the structure of the upper valve body mechanism.
[0027] Figure 7 This is another partial structural diagram of an embodiment of the hose assembly installation device of the present invention;
[0028] Figure 8 A structural diagram of an embodiment of a finished gas pressure reducing valve;
[0029] Figure 9 This is a structural diagram of another embodiment of a finished gas pressure reducing valve. DETAILED DESCRIPTION
[0030] This section will describe in detail specific embodiments of the present invention. Preferred embodiments of the present invention are shown in the accompanying drawings. The purpose of the drawings is to supplement the textual description with graphics, so that people can intuitively and vividly understand each technical feature and overall technical solution of the present invention, but they should not be construed as limiting the scope of protection of the present invention.
[0031] In the description of this invention, the use of terms such as first, second, third, fourth, fifth, etc., is only for the purpose of distinguishing technical features and should not be construed as indicating or implying relative importance, or implicitly indicating the number of technical features indicated, or implicitly indicating the order of the technical features indicated.
[0032] In the description of the present invention, it should be understood that descriptions involving orientations, such as up, down, front, back, left, right, etc., indicating orientations or positional relationships, are based on the orientations or positional relationships shown in the accompanying drawings. They are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation. Therefore, they cannot be understood as limitations on the present invention.
[0033] In the present invention, unless otherwise expressly defined, terms such as "disposed," "installed," and "connected" should be interpreted broadly. For example, they may refer to direct connection or indirect connection through an intermediate medium; fixed connection or detachable connection or integral molding; mechanical connection; and internal communication between two components or interaction between two components. Those skilled in the art can reasonably determine the specific meanings of these terms in the present invention based on the specific content of the technical solution.
[0034] Reference Figures 1 to 7 An embodiment of the present invention provides a hose assembly installation device, which includes a frame 100, a fixed-length pipe cutting mechanism 200, a first transfer mechanism 300, an upper pipe cap mechanism 400, an upper connector nut mechanism 500, an upper valve body mechanism 600, a second transfer mechanism 700, and a pipe shrinking mechanism 800.
[0035] A fixed-length tube cutting mechanism 200 is mounted on the frame 100. The fixed-length tube cutting mechanism 200 has an outlet hole for the hose to pass through. The fixed-length tube cutting mechanism 200 can transport the hose through the outlet hole and cut a preset length of hose through the outlet hole to obtain a hose segment 921. A first conveying mechanism 300 is mounted on the frame 100. The first conveying mechanism 300 can pick up the hose segment 921 cut by the fixed-length tube cutting mechanism 200 and drive the hose segment 921 to bend into a U-shape before sequentially conveying it to the first station S1 and the second station S2. 2. In the third station S3 and the fourth station S4, the capping mechanism 400 is located on the frame 100. The capping mechanism 400 can store caps 922 and can respectively fit two caps 922 onto the two ends of the hose section 921 in the first station S1. The connector nut mechanism 500 is located on the frame 100. The connector nut mechanism 500 can store pagoda connectors 924 and pagoda nuts 923. It can insert the pagoda connector 924 into the pagoda nut 923 and then insert it into one end of the hose section 921 in the second station S2. The pagoda nut 923 is clamped between the pagoda connector 924 and the corresponding pipe cap 922. The upper valve body mechanism 600 is located on the frame 100. The upper valve body mechanism 600 can receive the gas pressure reducing valve 910 and can insert the gas outlet pipe of the received gas pressure reducing valve 910 into the other end of the hose section 921 of the third station S3. The second transfer mechanism 700 is located on the frame 100. The second transfer mechanism 700 can transfer the gas pressure reducing valve 922, pagoda nut 923, pagoda connector 924 and gas pressure reducing valve 922 from the fourth station S4. The hose section 921 of the pressure valve 910 can be sequentially transferred to the fifth station S5 and the sixth station S6. The hose shrinking mechanism 800 is provided on the frame 100. The hose shrinking mechanism 800 includes two hose shrinking devices 810, both of which are provided on the frame 100. One hose shrinking device 810 can shrink and tighten the cap 922 at one end of the hose section 921 at the fifth station S5, and the other hose shrinking device 810 can shrink and tighten the cap 922 at the other end of the hose section 921 at the sixth station S6.
[0036] The working process of the hose assembly installation equipment is as follows: 1. The fixed-length hose cutting mechanism 200 conveys the hose through the outlet hole and cuts the hose to a preset length through the outlet hole to obtain hose segment 921; 2. The first transfer mechanism 300 picks up the hose segment 921 cut by the fixed-length hose cutting mechanism 200, and drives the hose segment 921 to bend into a U-shape before transferring it to the first station S1; 3. The capping mechanism 400 puts two caps 922 onto the hose at the first station S1. 4. The first transfer mechanism 300 drives the hose segment 921 at the first station S1 to be transferred to the second station S2; 5. The upper connector nut mechanism 500 inserts the pagoda connector 924 into the pagoda nut 923, and then inserts it into one end of the hose segment 921 at the second station S2, so that the pagoda nut 923 is clamped between the pagoda connector 924 and the corresponding cap 922; 6. The first transfer mechanism 300 drives the hose segment 921 at the second station S2 to be transferred to the two ends of the hose segment 921; 7. The upper valve body mechanism 600 inserts the gas outlet pipe of the received gas pressure reducing valve 910 into the other end of the hose section 921 at the third station S3; 8. The first transfer mechanism 300 drives the hose section 921 at the third station S3 to be transferred to the fourth station S4; 9. The second transfer mechanism 700 removes the hose section 921 at the fourth station S4 (this hose section 921 is equipped with a pipe cap 922, a pagoda nut 923, a pagoda connector 924, and gas...). 10. A pressure reducing valve 910 is used to transfer the hose section 921 to the fifth station S5; 11. A hose shrinking device 810 performs hose shrinking and tightening work on the cap 922 at one end of the hose section 921 at the fifth station S5; 12. A second transfer mechanism 700 drives the hose section 921 at the fifth station S5 to the sixth station S6; 13. Another hose shrinking device 810 performs hose shrinking and tightening work on the cap 922 at the other end of the hose section 921 at the sixth station S6.
[0037] With the above structure, the fixed-length pipe cutting mechanism 200, the first transfer mechanism 300, the upper pipe cap mechanism 400, the upper connector nut mechanism 500, the upper valve body mechanism 600, the second transfer mechanism 700, and the pipe shrinking mechanism 800 on the frame 100 of the hose assembly installation equipment of this application can cooperate with each other to realize the connection of the gas pressure reducing valve 910 and the hose assembly into a finished gas pressure reducing valve. The above process requires less manual intervention, thus improving the production efficiency of the finished gas pressure reducing valve.
[0038] In this embodiment, refer to Figure 1 The frame 100 is provided with a tag hanging mechanism 110, which can store tags and transfer tags to the tube insertion position for the rubber tube to be moved through the tube outlet hole, so that the rubber tube segment 921 transferred by the first transfer mechanism 300 has a tag.
[0039] In this embodiment, refer to Figure 7The second transfer mechanism 700 can sequentially transfer the hose section 921 to the fifth station S5, the sixth station S6, and the seventh station. The frame 100 is equipped with a marking mechanism 120, which can mark the finished gas pressure reducing valve at the seventh station. The marking mechanism 120 is a laser marking machine.
[0040] Through the above structure, the setup of the listing agency 110 and the marking agency 120 allows users to read and understand certain information by listing and marking.
[0041] The first transfer mechanism 300 includes a tube-taking assembly 310, a first transfer assembly 320, and a first tube-transfer assembly 330, as shown in the figure. Figure 2 and Figure 3 The tube-taking assembly 310 is located on the frame 100. The tube-taking assembly 310 can receive the tube segment 921 cut by the fixed-length tube-cutting mechanism 200, and can bend the received tube segment 921 into a U-shape and transfer it to the eighth station S8. The first transfer assembly 320 is located on the frame 100. The first transfer assembly 320 can pick up the tube segment 921 bent into a U-shape by the tube-taking assembly 310 at the eighth station S8, and can transfer the picked-up tube segment 921 to the ninth station S9. The first tube-transfer assembly 330 is located on the frame 100. The first tube-transfer assembly 330 can pick up the U-shaped tube segment 921 at the ninth station S9, and can sequentially transfer the tube segment 921 to the first station S1, the second station S2, the third station S3 and the fourth station S4.
[0042] The tube-taking assembly 310 includes a first drive member 311 and a clamping assembly 312. The first drive member 311 is disposed on the frame 100, and there are two first drive members 311. There are also two clamping assemblies 312, with the two clamping assemblies 312 respectively disposed on the two first drive members 311. The first drive member 311 is configured as a linear module.
[0043] The first transfer assembly 320 includes a second drive member 321, a third drive member 322, a fourth drive member 323, a first rotating frame 324, a first clamp 325, and a second clamp 326, as shown in the reference. Figure 3 The second drive component 321 is mounted on the frame 100, the third drive component 322 is mounted on the second drive component 321, the fourth drive component 323 is mounted on the third drive component 322, the first rotating frame 324 is mounted on the fourth drive component 323, and the first clamp 325 and the second clamp 326 are both mounted on the first rotating frame 324. The second drive component 321 and the third drive component 322 are both configured as linear modules, etc.; the fourth drive component 323 is a rotary cylinder, etc.; and the first clamp 325 and the second clamp 326 are both pneumatic grippers, etc.
[0044] The first tube transfer assembly 330 includes a sliding bar 331, a fifth driving member 332, a clamping assembly 333, and a tube clamping assembly 334. (Refer to...) Figure 3 The sliding bar 331 is slidably mounted on the frame 100. The fifth driving member 332 is mounted on the frame 100 and connected to the sliding bar 331. The clamping group 333 is mounted on the sliding bar 331. There are five clamping groups 333. The five clamping groups 333 are arranged sequentially along the length of the sliding bar 331 and are named as the first clamping group, the second clamping group, the third clamping group, the fourth clamping group, and the fifth clamping group. The clamping group 333 includes two third clamps 333A arranged side by side. The clamping tube group 334 is mounted on the frame 100. There are four clamping tube groups 334. The clamping tube group 334 includes two sixth driving members 334A arranged opposite each other. The sixth driving member 334A is provided with a clamping block. The four clamping tube groups 334 are respectively located at the thirteenth station S13, the first station S1, the second station S2, and the third station S3.
[0045] It is understood that the two third clamps 333A of the clamp assembly 333 can respectively clamp the two ends of the hose segment 921 so that the clamp assembly 333 clamps the hose segment 921; the two sixth drive members 334A of the clamp assembly 334 drive the two clamping blocks to move towards each other to clamp the two ends of the hose segment 921 so that the clamp assembly 334 clamps the hose segment 921.
[0046] Reference Figure 2 and Figure 3The working process of the first transfer mechanism 300 is as follows: 1. Two first driving members 311 respectively drive two clamping assemblies 312 to move laterally, and the two clamping assemblies 312 respectively clamp and flip the hose segment 921 to receive the hose segment 921 cut by the fixed-length tube cutting mechanism 200, and then bend the received hose segment 921 into a U-shape and transfer it to the eighth station S8; 2. The first clamp 325 and the second clamp 326 respectively clamp the hose segment 921 bent into a U-shape by the tube taking assembly 310 at the eighth station S8, and the two clamping assemblies 312 release the clamp on the hose segment 921; 3. The second driving member 321 drives the first rotating frame 324 to move laterally, and the second clamping member 321 drives the first rotating frame 324 to move laterally. The third drive unit 322 drives the first rotating frame 324 to move longitudinally, and the fourth drive unit 323 drives the first rotating frame 324 to rotate, transferring the U-shaped hose segment 921, which has been gripped by the first clamp 325 and the second clamp 326, to the ninth station S9; 4. At the ninth station S9, the two third clamps 333A of the first clamp group respectively clamp the two ends of the U-shaped hose segment 921, and the first clamp 325 and the second clamp 326 release the gripping of the U-shaped hose segment 921; 5. The fifth drive unit 332 drives the sliding bar 331 to slide, so that the first clamp group transfers the U-shaped hose segment 921 from the ninth station S9 to the thirteenth station S13. 6. The fifth driving member 332 drives the sliding bar 331 to slide, (the clamping group 334 at the thirteenth station S13 releases its grip on the U-shaped hose segment 921), causing the second clamping group to transfer the U-shaped hose segment 921 from the thirteenth station S13 to the first station S1, where it is clamped by the clamping group 334 at the first station S1; 7. The fifth driving member 332 drives the sliding bar 331 to slide, (the clamping group 334 at the first station S1 releases its grip on the U-shaped hose segment 921), causing the third clamping group to transfer the U-shaped hose segment 921 from the first station S1 to the second station. S2, and is clamped by the clamping group 334 located at the second station S2; 8, the fifth driving member 332 drives the sliding bar 331 to slide, (the clamping group 334 located at the second station S2 releases the clamp on the U-shaped hose segment 921) so that the fourth clamping group moves the U-shaped hose segment 921 from the second station S2 to the third station S3, and is clamped by the clamping group 334 located at the third station S3; 9, the fifth driving member 332 drives the sliding bar 331 to slide, (the clamping group 334 located at the third station S3 releases the clamp on the U-shaped hose segment 921) so that the fifth clamping group moves the U-shaped hose segment 921 from the third station S3 to the fourth station S4.
[0047] The capping mechanism 400 includes a first material storage and conveying assembly 410, a first material distribution assembly 420, and a first material transfer assembly 430, as shown in the figure. Figure 4The first material storage and conveying assembly 410 is provided on the frame 100. The first material storage and conveying assembly 410 is provided with a first channel 411A. The first material storage and conveying assembly 410 can store the cap 922 and can drive the cap 922 to move through the first channel 411A. The first material dispensing assembly 420 is provided on the first material storage and conveying assembly 410. The first material dispensing assembly 420 can remove the cap 922 removed from the outlet of the first channel 411A and can close the outlet of the first channel 411A. The first material transfer assembly 430 is provided on the frame 100. The first material transfer assembly 430 can put the cap 922 removed by the first material dispensing assembly 420 onto the end of the hose section 921 of the first station S1.
[0048] The first material storage and conveying assembly 410 includes a first direct-vibration feeder 411 and a first vibratory feeder 412. (Refer to...) Figure 4 The first vibrating feeder 411 and the first vibrating plate 412 are both located on the frame 100. The first vibrating feeder 411 is provided with the first channel 411A mentioned above. The first vibrating feeder 411 and the first vibrating plate 412 are connected. The first vibrating plate 412 can store the pipe cap 922.
[0049] The first material distribution assembly 420 includes a seventh drive component 421 and a first material distribution block 422, as shown in the reference. Figure 4 The seventh driving component 421 is located on the first direct-vibration feeder 411 and is connected to the first material distribution block 422. The first material distribution block 422 is provided with a first material distribution groove 422A. The seventh driving component 421 can drive the first material distribution block 422 to move to a first position or a second position. The seventh driving component 421 is configured as a cylinder or similar component.
[0050] The first transfer assembly 430 includes an eighth drive member 431, a ninth drive member 432, a tenth drive member 433, and a fourth clamp 434, as shown in the reference. Figure 4 The eighth drive unit 431 is mounted on the frame 100, the ninth drive unit 432 is mounted on the eighth drive unit 431, the tenth drive unit 433 is mounted on the ninth drive unit 432, and the fourth clamp 434 is mounted on the tenth drive unit 434. The fourth clamp 434 is capable of clamping the pipe cap 922 transferred by the first material distribution component 420. The eighth drive unit 431, the ninth drive unit 432, and the tenth drive unit 433 can respectively drive the fourth clamp 434 to move along the X-axis, Y-axis, and Z-axis. Among them, the eighth drive unit 431, the ninth drive unit 432, and the tenth drive unit 43 are all configured as linear modules, etc.; the fourth clamp 434 is configured as a pneumatic gripper, etc.
[0051] Reference Figure 4The working process of the capping mechanism 400 is as follows: 1. The first vibratory feeder 411 and the first vibratory plate 412 work together to drive the cap 922 on the first vibratory plate 412 to move through the first channel 411A; 2. The seventh drive member 421 drives the first distribution block 422 to move to the first position, so that the first distribution groove 422A is connected to the outlet of the first channel 411A to receive the cap 922 moved out of the outlet of the first channel 411A; 3. The seventh drive member 421 drives the first distribution block 422 to move to the second position, so that the first distribution groove 422A receiving the cap 922 moves to the second position, so that the first distribution block 422 closes the outlet of the first channel 411A; 4. The fourth clamp 4 34. Clamp the cap 922 on the first distribution groove 422A at the second position; 5. The eighth drive member 431, the ninth drive member 432 and the tenth drive member 433 respectively drive the fourth clamp 434 to move along the X-axis, Y-axis and Z-axis, so that the cap 922 clamped by the fourth clamp 434 is sleeved on one end of the hose segment 921 at the first station S1; 6. Repeat steps 1 to 3; 7. The eighth drive member 431, the ninth drive member 432 and the tenth drive member 433 respectively drive the fourth clamp 434 to move along the X-axis, Y-axis and Z-axis, so that the fourth clamp 434 moves the cap 922 on the first distribution groove 422A at the second position and sleeves it on the other end of the hose segment 921 at the first station S1.
[0052] The upper connector nut mechanism 500 includes a second material storage and conveying assembly 510, a second material dispensing assembly 520, a third material storage and conveying assembly 530, a third material dispensing assembly 540, a second material transfer assembly 550, and a third material transfer assembly 560, as shown in the reference. Figure 5A second material storage and conveying assembly 510 is mounted on the frame 100. The second material storage and conveying assembly 510 has a second channel 511A. The second material storage and conveying assembly 510 can store pagoda nuts 923 and can drive the pagoda nuts 923 to move through the second channel 511A. A second material distribution assembly 520 is mounted on the second material storage and conveying assembly 510. The second material distribution assembly 520 can remove pagoda nuts 923 that have moved out of the outlet of the second channel 511A and can close the outlet of the second channel 511A. A third material storage and conveying assembly 530 is mounted on the frame 100. The third material storage and conveying assembly 530 has a third channel 531A. The third material storage and conveying assembly 530 can store pagoda connectors 924 and can drive the pagoda connectors 924 to move through the third channel 531A. The third material distribution component 540 is located on the third material storage and conveying component 530. The third material distribution component 540 can remove the pagoda connector 924 that has been removed from the outlet of the third channel 531A and can also close the outlet of the third channel 531A. The second material transfer component 550 is located on the frame 100. The second material transfer component 550 can insert the pagoda connector 924 removed by the third material distribution component 540 into the pagoda nut 923 removed by the second material distribution component 520. The third material transfer component 560 is located on the frame 100. The third material transfer component 560 can remove the pagoda nut 923 with the pagoda connector 924 inserted that has been removed by the second material distribution component 520 and can insert the pagoda connector 924 on the pagoda nut 923 into one end of the hose section 921 of the second station S2.
[0053] It is understood that the second material conveying assembly 510 includes a second linear vibrating feeder 511 and a second vibrating plate 512, and the third material conveying assembly 530 includes a third linear vibrating feeder 531 and a third vibrating plate 532. The structure and connection method of the second material conveying assembly 510 and the third material conveying assembly 530 are the same as those of the first material conveying assembly 510, so they will not be described again here.
[0054] It is understood that the second material distribution component 520 includes an eleventh driving component 521 and a second material distribution block 522, and the third material distribution component 540 includes a twelfth driving component 541 and a third material distribution block 542. The structure and connection method of the second material distribution component 520 and the third material distribution component 540 are the same as those of the first material distribution component 420, so they will not be described again here.
[0055] The second transfer assembly 550 includes a thirteenth drive component 551, a fourteenth drive component 552, and a fifth clamp 553, as shown in the reference. Figure 5The thirteenth drive component 551 is located on the frame 100, the fourteenth drive component 552 is located on the thirteenth drive component 551, and the fifth clamp 553 is located on the fourteenth drive component 552. Among them, the thirteenth drive component 551 is configured as a linear module, etc., the fourteenth drive component 552 is configured as a cylinder, etc., and the fifth clamp 553 is configured as a pneumatic gripper, etc.
[0056] The third transfer assembly 560 includes a fifteenth drive member 561, a sixteenth drive member 562, a sixth clamp 563, and a seventeenth drive member 564, as shown in the reference. Figure 5 The fifteenth drive unit 561 is located on the frame 100, the sixteenth drive unit 562 is located on the fifteenth drive unit 561, and the sixth clamp 563 and the seventeenth drive unit 564 are all located on the sixteenth drive unit 562. Among them, the fifteenth drive unit 561 and the sixteenth drive unit 562 are both configured as linear modules, etc.; the sixth clamp 563 is configured as a pneumatic gripper, etc.; and the seventeenth drive unit 564 is configured as a cylinder, etc.
[0057] Reference Figure 5The working process of the upper connector nut mechanism 500 is as follows: 1. The third linear vibrating feeder 531 and the third vibrating plate 532 work together to drive the pagoda connector 524 stored in the third vibrating plate 532 to move through the third channel 531A on the third linear vibrating feeder 531; 2. The second linear vibrating feeder 511 and the second vibrating plate 512 work together to drive the pagoda nut 923 stored in the second vibrating plate 512 to move through the second channel 511A on the second linear vibrating feeder 511; 3. The eleventh driving member 521 drives the second material distribution block 522 to move to the third position, so that the second material distribution groove 522A and the second The outlet of channel 511A is connected to receive the pagoda nut 923 removed from the outlet of the second channel 511A; 4. The eleventh drive unit 521 drives the second distribution block 522 to move to the fourth position, so that the second distribution groove 522A receiving the pagoda nut 923 moves to the fourth position, so that the second distribution block 522 closes the outlet of the second channel 511A; 5. The twelfth drive unit 541 drives the third distribution block 542 to move to the fifth position, so that the third distribution groove 542A is connected to the outlet of the third channel 531A to receive the pagoda connector 924 removed from the outlet of the third channel 531A; 6. The twelfth drive unit 541 drives the third distribution block 542 to move to the fifth position, so that the third distribution groove 542A is connected to the outlet of the third channel 531A to receive the pagoda connector 924 removed from the outlet of the third channel 531A; The actuator 541 drives the third distribution block 542 to move to the sixth position, causing the third distribution trough 542A receiving the pagoda connector 924 to move to the sixth position, thus closing the outlet of the third channel 531A; 7. The fifth clamp 553 clamps the pagoda connector 924 on the third distribution trough 542A at the sixth position; 8. The thirteenth drive member 551 drives the fifth clamp 553 to move laterally, and the fourteenth drive member 552 drives the fifth clamp 553 to move longitudinally, causing the pagoda connector 924 clamped by the fifth clamp 553 to move the pagoda nut 923 inserted into the second distribution trough 522A at the fourth position; 9. The The sixth clamp 563 clamps the pagoda nut 923 with a pagoda connector 924 inserted on the second material distribution groove 522A at the fourth position. The seventeenth drive member 564 passes through the pagoda nut 923 and abuts against the pagoda connector 924. The fifteenth drive member 561 drives the sixth clamp 563 and the seventeenth drive member 564 to move laterally, and the sixteenth drive member 562 drives the sixth clamp 563 and the seventeenth drive member 564 to move longitudinally, so that the pagoda nut 923 held by the sixth clamp 563 and inserted by the seventeenth drive member 564 moves and inserts the pagoda connector 924 on it into one end of the hose section 921 at the second station S2.
[0058] The upper valve body mechanism 600 includes a receiving and transferring assembly 610 and a fourth transferring assembly 620, as shown in the figure. Figure 1 and Figure 6The receiving and transferring component 610 is located on the frame 100. The receiving and transferring component 610 can receive the gas pressure reducing valve 910 at the tenth station S10 and can transfer the received gas pressure reducing valve 910 to the eleventh station S11. The fourth transferring component 620 is located on the frame 100. The fourth transferring component 620 can remove the gas pressure reducing valve 910 on the receiving and transferring component 610 at the eleventh station S11 and can insert the gas outlet pipe of the removed gas pressure reducing valve 910 into the other end of the hose section 921 at the third station S3.
[0059] The receiving and transferring assembly 610 includes an eighteenth drive member 611, a jig base 612, a nineteenth drive member 613, and an eighth clamp 614, as shown in the reference. Figure 1 and Figure 6 The eighteenth drive unit 611 is mounted on the frame 100, the nineteenth drive unit 613 is mounted on the sliding table of the eighteenth drive unit 611, and the eighth clamp 614 and fixture seat 612 are mounted on the nineteenth drive unit 613. The eighteenth drive unit 611 is configured as a linear module, etc.; the nineteenth drive unit 613 is configured as a rotary cylinder, etc.; and the eighth clamp 614 is configured as a pneumatic gripper, etc.
[0060] The fourth transfer assembly 620 includes a twentieth drive member 621, a twenty-first drive member 622, a mounting bracket 623, a ninth clamp 624, a pressing member 625, and a spring member 626, as shown in the figure. Figure 6 The twentieth drive component 621 is mounted on the frame 100, the twenty-first drive component 622 is mounted on the twentieth drive component 621, the mounting bracket 623 is mounted on the twenty-first drive component 622, the ninth clamp 624 is slidably mounted on the mounting bracket 623, the spring component 626 is located between the ninth clamp 624 and the mounting bracket 623, and the pressing component 625 is mounted on the mounting bracket 623. The twentieth drive component 621 and the twenty-first drive component 622 are both configured as linear modules, etc.; the ninth clamp 624 is configured as a pneumatic gripper, etc.
[0061] Reference Figure 1 and Figure 6The working process of the upper valve body mechanism 600 is as follows: 1. The fixture seat 612 receives the horizontally placed gas pressure reducing valve 910 at the tenth position S10, and the eighth clamp 614 clamps the gas outlet pipe of the gas pressure reducing valve 910; 2. The eighteenth drive member 611 drives the gas pressure reducing valve 910 on the fixture seat 612 to move to the eleventh position S11, and the nineteenth drive member 613 drives the fixture seat 612 and the eighth clamp 614 to rotate, so that the gas pressure reducing valve 910 flips to a vertical state at the eleventh position S11 (i.e., its gas outlet pipe). (Set downwards); 3. The ninth clamp 624 clamps the gas pressure reducing valve 910 of the eleventh station S11 in a vertical state; 4. The twenty-first drive member 622 drives the mounting bracket 623 to move longitudinally, and the twentieth drive member 621 drives the mounting bracket 623 to move laterally, so that the gas outlet pipe of the gas pressure reducing valve 910 is inserted into the other end of the hose section 921 of the third station S3 (during this process, the ninth clamp 624 moves upward so that the gas pressure reducing valve 910 is pressed by the pressing member 625, and the spring member 626 is in a compressed state).
[0062] The second transfer mechanism 700 includes a second transfer assembly 710 and a second transfer tube assembly 720, as shown in the reference. Figure 7 The second transfer assembly 710 is located on the frame 100. The second transfer assembly 710 can pick up the hose section 921 with the cap 922, pagoda nut 923, pagoda connector 924 and gas pressure reducing valve 910 at the fourth station S4, and can transfer the hose section 921 to the twelfth station S12. The second pipe transfer assembly 720 is located on the frame 100. The second pipe transfer assembly 720 can pick up the hose section 921 at the twelfth station S12, and can sequentially transfer the hose section 921 to the fifth station S5, the sixth station S6 and the seventh station S7.
[0063] The second transfer assembly 710 includes a twenty-second drive member 711, a twenty-third drive member 712, a second rotating frame 713, a tenth clamp 714, and an eleventh clamp 715, as shown in the reference. Figure 7 The twenty-second drive unit 711 is mounted on the frame 100, the twenty-third drive unit 712 is mounted on the twenty-second drive unit 711, the second rotating frame 713 is mounted on the twenty-third drive unit 712, and the tenth clamp 714 and the eleventh clamp 715 are both mounted on the second rotating frame 713. The twenty-second drive unit 711 is configured as a linear module, etc.; the twenty-third drive unit 712 is configured as a motor, etc.; and the tenth clamp 714 and the eleventh clamp 715 are both configured as pneumatic grippers, etc.
[0064] The second tube transfer assembly 720 includes a clamping assembly 721, a tube taking assembly 722, a connecting frame 723, a connecting strip 724, a twenty-fourth driving member 725, and a twenty-fifth driving member 726, as shown in the reference. Figure 7Four clamping assemblies 721 are configured, located at the twelfth station S12, the fifth station S5, the sixth station S6, and the seventh station S7, respectively. Each clamping assembly 721 includes two twelfth clamps 721A, which clamp the two ends of the hose segment 921. A connecting frame 723 is slidably mounted on the frame 100. A twenty-fourth driving member 725 is mounted on the frame 100 and connected to the connecting frame 723. A connecting strip 724 is slidably mounted on the connecting frame. 723, the twenty-fifth driving component 726 is located on the connecting frame 723 and connected to the connecting strip 724. Four tube-taking groups 722 are provided, each located on the connecting strip 724. The four tube-taking groups 722 are arranged sequentially along the length of the connecting strip 724. The four tube-taking groups 722 are named the first tube-taking group, the second tube-taking group, the third tube-taking group, and the fourth tube-taking group, respectively. Each tube-taking group 722 includes two thirteenth clamps 722A, which clamp the two ends of the hose segment 921. The twenty-fourth driving component 725 and the twenty-fifth driving component 726 are both cylinder components, etc.; the twelfth clamp 721A and the thirteenth clamp 722A are both pneumatic grippers, etc.
[0065] Reference Figure 7 The working process of the second transfer mechanism 700 is as follows: 1. The tenth clamp 714 and the eleventh clamp 715 respectively clamp the two ends of the hose segment 921 at the fourth station S4 (the hose segment 921 is equipped with a hose cap 922, a pagoda nut 923, a pagoda connector 924, and a gas pressure reducing valve 910); 2. The twenty-second drive member 711 drives the hose segment 921 clamped by the tenth clamp 714 and the eleventh clamp 715 to move laterally, and the twenty-third drive member 712 drives the hose segment 921 clamped by the tenth clamp 714 and the eleventh clamp 715 to rotate, so that the clamped hose segment 921 moves to be clamped by the clamping assembly 721 located at the twelfth station S12; 3. The twenty-fourth drive member 725 drives the connecting frame 723 to slide, and the twenty-fifth drive member 72... 6. Drive the connecting bar 724 to slide, so that the first tube-taking group moves the hose segment 921 from the twelfth station S12 to the fifth station S5, where it is clamped by the clamping assembly 721 located at the fifth station S5; 4. Drive the connecting frame 723 to slide, and drive the connecting bar 724 to slide, so that the second tube-taking group moves the hose segment 921 from the fifth station S5 to the sixth station S6, where it is clamped by the clamping assembly 721 located at the sixth station S6; 5. Drive the connecting frame 723 to slide, and drive the connecting bar 724 to slide, so that the third tube-taking group moves the hose segment 921 from the sixth station S6 to the seventh station S7, where it is clamped by the clamping assembly 721 located at the seventh station S7.
[0066] Understandably, the hose section 921, located at the seventh station S7 and equipped with a pipe cap 922, a pagoda nut 923, a pagoda connector 924, and a gas pressure reducing valve 910, becomes a finished gas pressure reducing valve after being compressed by the tube shrinking mechanism 800.
[0067] This invention also proposes a valve assembly production line, which includes the aforementioned hose assembly installation equipment. This structure improves the production efficiency of finished gas pressure reducing valves.
[0068] Of course, the present invention is not limited to the above-mentioned embodiments. Those skilled in the art may make equivalent modifications or substitutions without violating the spirit of the present invention. These equivalent modifications and substitutions are all included in the scope defined by the claims of this application.
Claims
1. A hose assembly installation device, characterized in that: include Rack(100); A fixed-length pipe cutting mechanism (200) is arranged on the frame (100), the fixed-length pipe cutting mechanism (200) is provided with a pipe outlet hole for the rubber pipe to pass through, the fixed-length pipe cutting mechanism (200) can transport the rubber pipe to move through the pipe outlet hole, and can cut the rubber pipe of a preset length passing through the pipe outlet hole to obtain a rubber pipe section (921); A first transfer mechanism (300) is disposed on the frame (100), and the first transfer mechanism (300) is capable of transferring the hose section (921) cut by the fixed-length hose cutting mechanism (200), and is capable of driving the hose section (921) to bend into a U shape and then sequentially transfer the hose section (921) to a first station (S1), a second station (S2), a third station (S3), and a fourth station (S4); A pipe capping mechanism (400) is arranged on the frame (100), and the pipe capping mechanism (400) can store pipe caps (922) and can respectively sleeve two pipe caps (922) on two ends of the rubber hose section (921) of the first station (S1); An upper joint nut mechanism (500) is arranged on the frame (100), and the upper joint nut mechanism (500) can store pagoda joints (924) and pagoda nuts (923), and can insert the pagoda joint (924) into the pagoda nut (923), and then insert it into one end of the hose section (921) of the second work station (S2), so that the pagoda nut (923) is sandwiched between the pagoda joint (924) and the corresponding pipe cap (922); an upper valve body mechanism (600) disposed on the frame (100), the upper valve body mechanism (600) being capable of receiving a gas pressure reducing valve (910), and being capable of inserting the gas outlet pipe of the received gas pressure reducing valve (910) into the other end of the hose section (921) of the third station (S3); A second transfer mechanism (700) is arranged on the frame (100), and the second transfer mechanism (700) is capable of removing the hose section (921) equipped with a pipe cap (922), a pagoda nut (923), a pagoda joint (924) and a gas pressure reducing valve (910) from the fourth station (S4), and is capable of sequentially transferring the hose section (921) to the fifth station (S5) and the sixth station (S6); A tube shrinking mechanism (800) is arranged on the frame (100), and the tube shrinking mechanism (800) can shrink and press the tube cap (922) at one end of the hose section (921) of the fifth station (S5), and can shrink and press the tube cap (922) at the other end of the hose section (921) of the sixth station (S6).
2. A hose assembly installation device according to claim 1, characterized in that: The first transfer mechanism (300) comprises: a tube taking assembly (310) disposed on the frame (100), the tube taking assembly (310) being capable of receiving the hose section (921) cut by the fixed-length tube cutting mechanism (200), and being capable of bending the received hose section (921) into a U shape and then transferring it to an eighth workstation (S8); a first transfer assembly (320) disposed on the frame (100), the first transfer assembly (320) being capable of removing the hose section (921) bent into a U shape by the hose removal assembly (310) from the eighth station (S8), and being capable of transferring the removed hose section (921) to the ninth station (S9); The first pipe transfer assembly (330) is arranged on the frame (100), and the first pipe transfer assembly (330) can remove the U-shaped hose section (921) of the ninth station (S9), and can transfer the hose section (921) to the first station (S1), the second station (S2), the third station (S3) and the fourth station (S4) in sequence.
3. The hose assembly installation device according to claim 1, characterized in that: The upper tube cap mechanism (400) comprises: A first material storage and conveying assembly (410) is disposed on the frame (100), the first material storage and conveying assembly (410) being provided with a first passage (411A), the first material storage and conveying assembly (410) being capable of storing pipe caps (922) and being capable of driving the pipe caps (922) to move through the first passage (411A); A first material distributing component (420) is provided on the first material storage and conveying component (410), and the first material distributing component (420) is capable of removing a pipe cap (922) removed from the outlet of the first channel (411A) and is capable of closing the outlet of the first channel (411A); The first material moving component (430) is arranged on the frame (100), and the first material moving component (430) can sleeve the pipe cap (922) moved by the first material dividing component (420) onto the end of the hose section (921) of the first station (S1).
4. The hose assembly installation device according to claim 1, characterized in that: The upper joint nut mechanism (500) comprises: A second material storage and conveying assembly (510) is disposed on the frame (100), the second material storage and conveying assembly (510) being provided with a second passage (511A), the second material storage and conveying assembly (510) being capable of storing the pagoda nuts (923) and being capable of driving the pagoda nuts (923) to move through the second passage (511A); A second material distribution component (520) is provided on the second material storage and conveying component (510), and the second material distribution component (520) is capable of removing the pagoda nut (923) removed from the outlet of the second channel (511A) and is capable of closing the outlet of the second channel (511A); A third material storage and conveying assembly (530) is disposed on the frame (100), the third material storage and conveying assembly (530) being provided with a third passage (531A), the third material storage and conveying assembly (530) being capable of storing pagoda joints (924) and being capable of driving the pagoda joints (924) to move through the third passage (531A); A third material distribution component (540) is provided on the third material storage and conveying component (530), and the third material distribution component (540) is capable of removing the pagoda joint (924) removed from the outlet of the third channel (531A) and is capable of closing the outlet of the third channel (531A); A second material moving component (550) is disposed on the frame (100), and the second material moving component (550) is capable of inserting the pagoda joint (924) removed by the third material dividing component (540) into the pagoda nut (923) removed by the second material dividing component (520); A third material moving assembly (560) is arranged on the frame (100), and the third material moving assembly (560) is capable of removing the pagoda nut (923) with a pagoda joint (924) inserted therein that is removed by the second material dividing assembly (520), and is capable of inserting the pagoda joint (924) on the pagoda nut (923) into one end of the hose section (921) of the second workstation (S2).
5. The hose assembly installation device according to claim 1, characterized in that: The upper valve body mechanism (600) comprises: a material receiving and transferring assembly (610), which is arranged on the frame (100), and the material receiving and transferring assembly (610) can receive the gas pressure reducing valve (910) at the tenth station (S10), and can transfer the received gas pressure reducing valve (910) to the eleventh station (S11); A fourth material moving assembly (620) is arranged on the frame (100), and the fourth material moving assembly (620) is capable of removing the gas pressure reducing valve (910) on the material receiving and transferring assembly (610) of the eleventh station (S11), and is capable of inserting the outlet pipe of the removed gas pressure reducing valve (910) into the other end of the hose section (921) of the third station (S3).
6. The hose assembly installation device according to claim 1, characterized in that: The second transfer mechanism (700) comprises: a second transfer assembly (710) disposed on the frame (100), the second transfer assembly (710) being capable of removing a hose section (921) equipped with a pipe cap (922), a pagoda nut (923), a pagoda joint (924) and a gas pressure reducing valve (910) from the fourth station (S4), and being capable of transferring the hose section (921) to the twelfth station (S12); The second pipe transfer assembly (720) is arranged on the frame (100), and the second pipe transfer assembly (720) can remove the hose section (921) of the twelfth station (S12), and can transfer the hose section (921) to the fifth station (S5) and the sixth station (S6) in sequence.
7. The hose assembly installation device according to claim 1, characterized in that: The tube shrinking mechanism (800) includes two tube shrinking devices (810) both arranged on the frame (100), one of the tube shrinking devices (810) being capable of shrinking and pressing the tube cap (922) at one end of the hose section (921) of the fifth station (S5), and the other tube shrinking device (810) being capable of shrinking and pressing the tube cap (922) at the other end of the hose section (921) of the sixth station (S6).
8. The hose assembly installation device according to claim 1, characterized in that: The frame (100) is provided with a hanging tag mechanism (110), and the hanging tag mechanism (110) can store the hanging tag and can transfer the hanging tag to the pipe insertion position to wait for the rubber hose moved through the pipe outlet hole to be inserted, so that the rubber hose section (921) removed by the first transfer mechanism (300) has the hanging tag.
9. The hose assembly installation device according to claim 1, characterized in that: The second transfer mechanism (700) can transfer the hose section (921) to the fifth workstation (S5), the sixth workstation (S6) and the seventh workstation in sequence. The frame (100) is provided with a marking mechanism (120), and the marking mechanism (120) can perform marking work on the finished gas pressure reducing valve at the seventh workstation.
10. Valve assembly production line, characterized by: It comprises a hose assembly installation device as described in any one of claims 1-9.