Construction method for slope single-side formwork support

By using layered formwork support and pouring concrete in inclined construction, the problems of high construction difficulty and slow progress in the existing technology are solved, the construction efficiency and quality are improved, and safety is ensured.

CN119145415APending Publication Date: 2024-12-17GUANGZHOU ZHONG COAL JIANGNANJICHU ENG CO
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411568620.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-05
Publication Date
2024-12-17

AI Technical Summary

Technical Problem

The existing technology has problems such as difficult construction, slowing down construction progress, and inability to guarantee safety and quality in slope construction.

Method used

The anchor cables and bolts are constructed from top to bottom along the inclined surface, and the formwork installation and support are completed in layers along the inclined surface. After each layer of formwork is installed, concrete is poured in advance. After the concrete solidifies, the next layer is carried out. Pour until completely solidified and remove the formwork.

Benefits of technology

Through layered branching and pouring of the formwork, the problems of difficulty in one-time pouring, safety and quality cannot be guaranteed, the construction efficiency and quality are improved, and the problem of slow progress is solved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119145415A_ABST
    Figure CN119145415A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of concrete engineering construction, and particularly discloses a slope single-face formwork supporting construction method which comprises the following steps that anchor cables and bolt anchor rods are constructed from top to bottom along a slope; formwork mounting and erecting are completed in a layered mode from bottom to top along the inclined face, concrete pouring is conducted in advance after each layer of formwork is mounted and erected, and concrete pouring is conducted on the next layer after concrete is solidified; and after the solidification strength of the concrete reaches the preset strength, the surface of the concrete is coated with a curing agent for curing, the formwork is removed until the concrete is completely solidified, and the construction joint is treated. According to the method, the anchor cables and the bolt anchor rods are constructed firstly, layered mounting and erecting of the formwork are facilitated, layered concrete pouring is conducted in a formwork erecting mode, the problems that one-time pouring is large in difficulty, and safety and quality cannot be guaranteed are solved, compared with one-time concrete pouring, layered concrete pouring through formwork erecting can accelerate the construction flow, and the construction efficiency is improved. The problem of slow progress is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of concrete engineering construction, in particular to a construction method for inclined single-sided formwork support. Background Art

[0002] At present, for slope construction, slope support is usually used to achieve one-time pouring. However, one-time pouring has the problems of great construction difficulty, slowed construction progress, and inability to ensure safety and quality, which cannot meet the current high-efficiency needs. Summary of the invention

[0003] The technical problem to be solved by the present invention is: how to solve the problems of great construction difficulty, slowed construction progress, and inability to ensure safety and quality in the prior art.

[0004] In order to solve the above technical problems, the present invention provides a method for installing an inclined single-sided formwork, comprising the following steps:

[0005] Construct anchor cables and bolt anchor rods from top to bottom along the slope;

[0006] The formwork is installed and supported layer by layer from bottom to top along the slope. After each layer of formwork is installed and supported, concrete is poured in advance. After the concrete solidifies, concrete is poured for the next layer.

[0007] After the concrete solidification strength reaches the preset strength, the surface is coated with curing agent for maintenance. When it is completely solidified, the formwork is removed and the construction joints are treated.

[0008] Further preferably, the construction of anchor cables and bolt anchor rods from top to bottom along the slope includes the following steps:

[0009] Construct the first row of bolt anchors 0.2m below the excavation line at the top of the slope;

[0010] Cut the slope to 1.5m below the first row of bolt anchors according to the designed slope ratio and construct the first row of anchor cables;

[0011] Continue excavating to 3m below the first row of bolts and anchors, and construct the second row of bolts and anchors;

[0012] The slope surface continues to be excavated to the position of the second row of anchor cables, and the second row of anchor cables are constructed. After the construction of the second row of anchor cables is completed, excavation is carried out to the bottom of the slope.

[0013] Further preferably, the specifications of the first row of bolt anchor rods and the second row of bolt anchor rods are C14@1500.

[0014] Further preferably, the buried depth of the first row of bolt anchor rods and the second row of bolt anchor rods are both 2 m, and the exposed lengths are both 0.5 m.

[0015] Further preferably, the steps of installing and supporting the formwork in layers from bottom to top along the slope, pouring concrete in advance after each layer of formwork is installed and supported, and pouring concrete for the next layer after the concrete solidifies include:

[0016] The first layer of formwork is installed and supported, and the first layer of concrete pouring is completed;

[0017] After the first layer of concrete solidifies, the second layer of formwork installation and support begins, and the second layer of concrete pouring is completed;

[0018] After the second layer of concrete solidifies, the third layer of formwork installation and support begins, and the third layer of concrete pouring is completed;

[0019] After the concrete reaches the age, the tensioning anchor cables are locked.

[0020] Further preferably, the steps of installing and supporting the first layer of formwork and completing the first layer of concrete pouring include:

[0021] The first diagonal brace is set on the inter-slope platform;

[0022] Place the first layer of formwork according to the designed slope ratio and fix it with the first diagonal brace;

[0023] Embedded bolts are arranged at a height of 1-1.2 m between the first layer of formwork and the inter-slope platform, and the first layer of concrete is poured.

[0024] Further preferably, after the first layer of concrete solidifies, the second layer of formwork is installed and supported, and the steps of completing the second layer of concrete pouring include:

[0025] Set up a second diagonal brace on the inter-slope platform;

[0026] The second layer of formwork is placed according to the designed slope ratio, and fixed by the embedded bolts and the second row of bolt anchor rods, and the second layer of formwork is reinforced by the second diagonal brace;

[0027] An embedded steel pipe is arranged, and the embedded steel pipe extends horizontally out of the outside of the second layer of formwork to pour the second layer of concrete.

[0028] Further preferably, after the second layer of concrete solidifies, the steps of starting to install and support the third layer of formwork and completing the pouring of the third layer of concrete include:

[0029] Set up the third diagonal brace on the inter-slope platform;

[0030] Connecting the third layer of formwork to the first row of bolt anchor rods and the second row of bolt anchor rods according to the designed slope ratio, and reinforcing them through the third diagonal brace;

[0031] Pour the third layer of concrete.

[0032] Further preferably, a first die-cast steel pipe is provided on the outer surface of the second layer of formwork, and the first die-cast steel pipe is connected to the embedded bolts and the second row of bolt anchor rods; and / or

[0033] The outer surface of the third layer of formwork is provided with a second die-cast steel pipe, and the second die-cast steel pipe is connected to the first row of bolt anchor rods and the second row of bolt anchor rods.

[0034] Further preferably, the embedded steel pipe and the third diagonal brace are overlapped to form a manual operation platform.

[0035] Compared with the prior art, the method for installing a sloped single-sided formwork provided by the present invention has the following beneficial effects:

[0036] The present invention first constructs anchor cables and bolt anchor rods, which is beneficial to the layered installation and support of the formwork. The concrete is poured in layers by means of the support of the formwork, which solves the problem that one-time pouring is difficult and the safety and quality cannot be guaranteed. Compared with one-time pouring of concrete, pouring concrete in layers by means of the support of the formwork can speed up the construction flow and solve the problem of slow progress. BRIEF DESCRIPTION OF THE DRAWINGS

[0037] Figure 1 It is a construction flow chart of the present invention.

[0038] Figure 2 It is a schematic diagram of the construction of anchor cables and bolt anchor rods of the present invention.

[0039] Figure 3 It is a schematic diagram of the first layer of template support of the present invention.

[0040] Figure 4 It is a schematic diagram of the second layer template support of the present invention.

[0041] Figure 5 It is a schematic diagram of the third layer of template support of the present invention.

[0042] Reference numerals:

[0043] 10. Slope platform; 11. Inclined surface; 12. First row of bolts and anchor rods; 13. Second row of bolts and anchor rods; 14. First row of anchor cables; 15. Second row of anchor cables; 16. Supporting steel pipes; 17. First diagonal brace; 18. First layer of formwork; 19. Embedded bolts; 20. First layer of poured concrete; 21. Second diagonal brace; 22. Second layer of formwork; 23. First die-cast steel pipe; 24. First manual operation platform; 25. Fastening bolts; 26. Third diagonal brace; 27. Second layer of poured concrete; 28. Second manual operation platform; 29. ​​Third layer of formwork; 30. Second die-cast steel pipe; 31. Embedded steel pipe. DETAILED DESCRIPTION

[0044] The specific implementation of the present invention is further described in detail below in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention.

[0045] In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise", "axial", "radial", "circumferential" and the like used in the present invention to indicate the orientation or position relationship is based on the orientation or position relationship shown in the accompanying drawings, and is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention.

[0046] The terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In the description of the present invention, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.

[0047] In addition, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0048] In the present invention, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may mean that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, a first feature being "above", "above" or "above" a second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. A first feature being "below", "below" or "below" a second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.

[0049] It should be noted that when an element is referred to as being "fixed to" or "disposed on" another element, it may be directly on the other element or there may be a central element. When an element is considered to be "connected to" another element, it may be directly connected to the other element or there may be a central element at the same time. The terms "vertical", "horizontal", "upper", "lower", "left", "right" and similar expressions used herein are for illustrative purposes only and are not intended to be the only implementation method.

[0050] like Figures 1 to 5 As shown, this embodiment provides a method for installing an inclined single-sided formwork, comprising the following steps:

[0051] S10: construct anchor cables and bolt anchor rods from top to bottom along the slope 11;

[0052] S20: Installing and supporting the formwork in layers from bottom to top along the inclined surface 11, pouring concrete in advance after each layer of formwork is installed and supported, and pouring concrete for the next layer after the concrete solidifies;

[0053] S30: After the concrete solidification strength reaches the preset strength, a curing agent is applied to the surface for curing. The formwork is removed after it is completely solidified, and the construction joints are treated.

[0054] In this embodiment, anchor cables and bolt anchor rods are constructed first, which is conducive to the layered installation and support of the formwork. Concrete is poured in layers by supporting the formwork, which solves the problems of difficulty in one-time pouring and the inability to ensure safety and quality. Compared with pouring concrete at one time, pouring concrete in layers by supporting the formwork can speed up the construction flow and solve the problem of slow progress.

[0055] It should be noted that in order to ensure the strength and quality of concrete after pouring, steel mesh is usually laid on the slope.

[0056] In some embodiments, Figure 1 As shown, in step S10, the construction of anchor cables and bolt anchor rods from top to bottom along the slope includes the following steps:

[0057] S11: construct the first row of bolt anchor rods 12 at 0.2m below the excavation line at the top of the slope;

[0058] S12: Cut the slope to 1.5m below the first row of bolt anchor rods 12 according to the designed slope ratio, and construct the first row of anchor cables 14;

[0059] S13: Continue excavating to 3 m below the first row of bolt anchor rods 12, and construct the second row of bolt anchor rods 13;

[0060] S14: The slope surface continues to be excavated to the position of the second row of anchor cables 15, and the second row of anchor cables 15 are constructed. After the construction of the second row of anchor cables 15 is completed, the slope surface is excavated to the bottom.

[0061] In some embodiments, the first row of bolt anchor rods 12 and the second row of bolt anchor rods 13 are respectively perpendicular to the inclined plane 11, and the acute angle formed by the first row of anchor cables 14 and the second row of anchor cables 15 relative to the inclined plane 11 is 80-90°.

[0062] In some embodiments, to ensure construction quality and efficiency, the specifications of the first row of bolt anchors and the second row of bolt anchors are preferably C14@1500, wherein C14 represents that the diameter of the anchor is 14 mm, and “@1500” represents that the horizontal spacing of the anchors is 1500 mm.

[0063] In some embodiments, in order to ensure the firmness of the first row of bolt anchors 12 and the second row of bolt anchors 13, the depth of the first row of bolt anchors 12 and the second row of bolt anchors 13 into the ground is 2m. Furthermore, in order to facilitate the connection of the first row of bolt anchors 12 and the second row of bolt anchors 13 with the formwork, it is preferred that the exposed lengths of the first row of bolt anchors 12 and the second row of bolt anchors 13 are both 0.5m.

[0064] In some embodiments, in step S20, the steps of installing and supporting the formwork in layers from bottom to top along the slope, pouring concrete in advance after each layer of formwork is installed and supported, and pouring concrete for the next layer after the concrete solidifies include:

[0065] S21: The first layer of formwork 18 is installed and supported, and the first layer of concrete pouring is completed;

[0066] S22: After the first layer of concrete solidifies, the second layer of formwork 22 is installed and supported, and the second layer of concrete pouring is completed;

[0067] S23: After the second layer of concrete solidifies, the third layer of formwork 29 is installed and supported, and the third layer of concrete pouring is completed;

[0068] S24: After the concrete reaches the age, the tensioning anchor cables are locked.

[0069] Specifically, after the concrete reaches the age, the first row of anchor cables 14 and the second row of anchor cables 15 are tensioned and locked.

[0070] In some embodiments, in step S21, the first layer of formwork is installed and supported, and the steps of completing the first layer of concrete pouring include:

[0071] S211: Arrange a first diagonal brace 17 on the inter-slope platform 10;

[0072] S212: placing the first layer of formwork 18 according to the designed slope ratio and fixing it with the first diagonal brace 17;

[0073] S213: Embedded bolts 19 are arranged at a height of 1-1.2 m from the first layer of formwork 18 to the inter-slope platform 10, and a first layer of concrete is poured.

[0074] In some embodiments, in order to facilitate the fixation of the first diagonal brace 17, at least two rows of supporting steel pipes 16 are driven into the inter-slope platform 10. The specifications of the first diagonal brace 17 and the supporting steel pipes 16 are both 48mm*3.5mm steel pipes. The depth of the supporting steel pipes 16 driven into the inter-slope platform 10 is not less than 1m. Figure 1 As shown, L1≥1m.

[0075] In some embodiments, in order to improve the slope protection effect, the first layer of poured concrete 20 needs to be at least 0.5m below the inter-slope platform 10. Figure 1 As shown, L2≥0.5m, preferably L2=0.5m.

[0076] In some embodiments, the height of the first layer of poured concrete 20 above the inter-slope platform 10 is L3, preferably L2+L3 is equal to 1.5 m, and when L2=0.5 m, L3=1 m.

[0077] In some embodiments, after the first layer of formwork 18 is set up and the first layer of concrete is poured, after the first layer of poured concrete 20 solidifies and reaches a preset strength, a curing agent is applied to the surface for curing, and the formwork is removed after complete solidification, and the construction joints are treated. After the treatment is completed, the second layer of formwork 22 is installed and set up and the second layer of concrete is poured.

[0078] In some embodiments, in step S22, after the first layer of concrete solidifies, the second layer of formwork installation and support begins, and the steps of completing the second layer of concrete pouring include:

[0079] S221: Arrange a second diagonal brace 21 on the inter-slope platform 10;

[0080] S222: placing the second layer of formwork 22 according to the designed slope ratio, fixing it with the embedded bolts 19 and the second row of bolt anchor rods 13, and reinforcing the second layer of formwork 22 with the second diagonal brace 21;

[0081] S223: Arrange a pre-buried steel pipe 31, wherein the pre-buried steel pipe 31 extends horizontally out of the outside of the second layer formwork 22, and pour a second layer of concrete.

[0082] In some embodiments, the fixing method of the second diagonal brace 21 is similar to the fixing method of the first diagonal brace 17, that is, at least two rows of supporting steel pipes 16 are also driven into the inter-slope platform 10, and the specifications of the second diagonal brace 21 and the supporting steel pipes 16 are both 48mm*3.6mm steel pipes, wherein the depth of the supporting steel pipes 16 driven into the inter-slope platform 10 is not less than 1m.

[0083] In some embodiments, in order to further strengthen the support of the second layer formwork 22, a first die-cast steel pipe 23 is provided on the outer surface of the second layer formwork 22, and the first die-cast steel pipe 23 is connected to the embedded bolts 19 and the second row of bolt anchor rods 13; further, the first die-cast steel pipe 23 is welded to the steel mesh by fastening bolts to further realize the support firmness of the second layer formwork 22.

[0084] In some embodiments, considering the convenience of pouring the third layer of concrete, a pre-buried steel pipe 31 is set 1m below the second layer of concrete, and a filter bag is set at the bottom of the pre-buried steel pipe 31, which can also be used as a later drainage pipe. Finally, the second layer of concrete is poured, and the second layer construction joint is treated after the formwork is removed and maintained. After the treatment is completed, the installation and support of the third layer of formwork 29 and the pouring of the third layer of concrete are started.

[0085] In some embodiments, in step S23, after the second layer of concrete solidifies, the third layer of formwork is installed and supported, and the steps of completing the pouring of the third layer of concrete include:

[0086] S231: a third diagonal brace 26 is provided on the inter-slope platform;

[0087] S232: Connecting the third layer formwork 29 to the first row of bolt anchor rods 12 and the second row of bolt anchor rods 13 according to the designed slope ratio, and reinforcing them through the third diagonal brace 26;

[0088] S233: Pour the third layer of concrete.

[0089] In some embodiments, the fixing method of the third diagonal brace 26 is similar to the fixing method of the second diagonal brace 21, that is, at least two rows of supporting steel pipes 16 are also driven into the inter-slope platform 10, and the specifications of the third diagonal brace 26 and the supporting steel pipes 16 are both 48mm*3.5mm steel pipes, wherein the depth of the supporting steel pipes 16 driven into the inter-slope platform 10 is not less than 1m.

[0090] In some embodiments, in order to further strengthen the support of the third layer formwork 29, a second die-cast steel pipe 30 is provided on the outer surface of the third layer formwork 29, and the second die-cast steel pipe 30 is connected to the first row of bolt anchors and the second row of bolt anchors; further, in order to improve the fastening of the third layer formwork 29, the middle of the third layer formwork 29 is also welded to the steel mesh by fastening bolts 25.

[0091] In some implementations, in this embodiment, the first layer of concrete pouring height is 1.5 m, the second layer of concrete pouring height is 2.5 m, and the third layer of concrete pouring height is 3 m.

[0092] In some embodiments, the first layer formwork 18, the second layer formwork 22 and the third layer formwork 29 are preferably all made of 18 mm thick plywood.

[0093] In some implementations, to facilitate construction, the embedded steel pipe 31 and the third diagonal brace 26 are overlapped to form a first manual operation platform 24 .

[0094] In some implementations, this embodiment can support the lateral pressure of concrete on the third layer of formwork 29 through three bolts, set up the first manual operation platform 24 through the embedded steel pipe 31 during the second layer of concrete pouring, and finally complete the pouring of the third layer of concrete. The embedded steel pipe 31 can be used as an operating frame connecting wall member for tensioning the first row of anchor cables 14 and the second row of anchor cables 15 after reaching the age.

[0095] In some embodiments, after the first row of anchor cables 14 and the second row of anchor cables 15 are tensioned, they can be cut according to the required extension length of the drainage pipe and used as the drainage pipe.

[0096] In other embodiments, a second manual operation platform 28 is further provided on the third diagonal brace 26 , and the second manual operation platform 28 is placed above the first manual operation platform 24 to further improve the construction efficiency and quality and reduce the difficulty of pouring.

[0097] In summary, the present invention provides a method for supporting a sloped single-sided formwork, which first constructs anchor cables and bolt anchor rods, which is conducive to the layered installation and support of the formwork. Concrete is poured in layers by supporting the formwork, which solves the problems of difficulty in one-time pouring, and the inability to ensure safety and quality. Compared with pouring concrete at one time, pouring concrete in layers by supporting the formwork can speed up the construction flow and solve the problem of slow progress.

[0098] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and substitutions can be made without departing from the technical principles of the present invention, and these improvements and substitutions should also be regarded as the protection scope of the present invention. The basic principles, main features and advantages of the present invention are shown and described above. For those skilled in the art, it is obvious that the present invention is not limited to the details of the above preferred embodiments. The embodiments should be regarded as exemplary and non-restrictive. The scope of the present invention is defined by the attached claims rather than the above description, so it is intended to include all changes within the meaning and scope of the equivalent elements of the claims in the present invention.

[0099] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This narrative method of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in the embodiments may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.

Claims

1. A method for installing a single-sided inclined formwork, characterized in that: The following steps are involved: Construct anchor cables and bolt anchor rods from top to bottom along the slope; The formwork is installed and supported layer by layer from bottom to top along the slope. After each layer of formwork is installed and supported, concrete is poured in advance. After the concrete solidifies, concrete is poured for the next layer. After the concrete solidification strength reaches the preset strength, the surface is coated with curing agent for maintenance. When it is completely solidified, the formwork is removed and the construction joints are treated.

2. A method for installing an inclined single-sided formwork according to claim 1, characterized in that: The construction of anchor cables and bolt anchor rods from top to bottom along the inclined surface comprises the following steps: Construct the first row of bolt anchors 0.2m below the excavation line at the top of the slope; Cut the slope to 1.5m below the first row of bolt anchors according to the designed slope ratio and construct the first row of anchor cables; Continue excavating to 3m below the first row of bolts and anchors, and construct the second row of bolts and anchors; The slope surface continues to be excavated to the position of the second row of anchor cables, and the second row of anchor cables are constructed. After the construction of the second row of anchor cables is completed, excavation is carried out to the bottom of the slope.

3. A method for installing an inclined single-sided formwork according to claim 2, characterized in that: The specifications of the first row of bolt anchor rods and the second row of bolt anchor rods are C14@1500.

4. A method for installing an inclined single-sided formwork according to claim 2, characterized in that: The buried depth of the first row of bolt anchor rods and the second row of bolt anchor rods are both 2m, and the exposed length is both 0.5m.

5. The method for installing an inclined single-sided formwork according to claim 2, characterized in that: The steps of installing and supporting the formwork in layers from bottom to top along the inclined surface, pouring concrete in advance after each layer of formwork is installed and supported, and pouring concrete for the next layer after the concrete solidifies include: The first layer of formwork is installed and supported, and the first layer of concrete pouring is completed; After the first layer of concrete solidifies, the second layer of formwork installation and support begins, and the second layer of concrete pouring is completed; After the second layer of concrete solidifies, the third layer of formwork installation and support begins, and the third layer of concrete pouring is completed; After the concrete reaches the age, the tensioning anchor cables are locked.

6. A method for installing an inclined single-sided formwork according to claim 5, characterized in that: The steps of installing and supporting the first layer of formwork and completing the first layer of concrete pouring include: The first diagonal brace is set on the inter-slope platform; Place the first layer of formwork according to the designed slope ratio and fix it with the first diagonal brace; Embedded bolts are arranged at a height of 1-1.2 m between the first layer of formwork and the inter-slope platform, and the first layer of concrete is poured.

7. A method for installing an inclined single-sided formwork according to claim 6, characterized in that: After the first layer of concrete solidifies, the second layer of formwork is installed and supported, and the steps of completing the second layer of concrete pouring include: Set up a second diagonal brace on the inter-slope platform; The second layer of formwork is placed according to the designed slope ratio, and fixed by the embedded bolts and the second row of bolt anchor rods, and the second layer of formwork is reinforced by the second diagonal brace; An embedded steel pipe is arranged, and the embedded steel pipe extends horizontally out of the outside of the second layer of formwork to pour the second layer of concrete.

8. A method for installing an inclined single-sided formwork according to claim 7, characterized in that: After the second layer of concrete solidifies, the third layer of formwork is installed and supported, and the steps of completing the third layer of concrete pouring include: Set up the third diagonal brace on the inter-slope platform; Connecting the third layer of formwork to the first row of bolt anchor rods and the second row of bolt anchor rods according to the designed slope ratio, and reinforcing them through the third diagonal brace; Pour the third layer of concrete.

9. A method for installing an inclined single-sided formwork according to claim 8, characterized in that: A first die-cast steel pipe is provided on the outer surface of the second layer of formwork, and the first die-cast steel pipe is connected to the embedded bolts and the second row of bolt anchor rods; and / or The outer surface of the third layer of formwork is provided with a second die-cast steel pipe, and the second die-cast steel pipe is connected to the first row of bolt anchor rods and the second row of bolt anchor rods.

10. The method for installing an inclined single-sided formwork according to claim 8, characterized in that: The embedded steel pipe and the third diagonal support are overlapped to form a manual operation platform.