By designing a test device for roadbed filler for construction waste, the mixing plate and spiral blades are used to achieve uniform mixing of crushed materials, and the compaction is detected through rubber rings and air pressure sensors, the gap problem between bricks and concrete blocks is solved and the test is ensured. Accuracy of results and construction quality.
Patent Information
- Application Number
- CN202411745854.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-02
- Publication Date
- 2024-12-31
- Estimated Expiration
- 2044-12-02
AI Technical Summary
There is still a large gap between bricks and concrete blocks after crushing, which makes it impossible to determine whether the interior is completely solidified during the sampling and solidification test of construction waste, which affects the construction quality. Due to different materials, it is necessary to mix evenly to ensure the objective accuracy of the test results. .
A construction waste roadbed filler compaction test device is designed, including a base, hydraulic seat, compaction cylinder, material conveying assembly and air pressure sensor. The mixing plate and spiral blades are used to achieve uniform mixing of crushed materials, and the rubber ring and The flat plate detects the compaction of the crushed material to ensure the reliability of the test results.
Through uniform mixing and detection mechanism, the uneven size of the crushed material caused by friction during pouring is avoided, the reliability of the results of the impact test is ensured, the internal failure is not fully compacted, and the construction quality is improved.
Smart Images

Figure CN119223804A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of roadbed filler compaction, in particular to a construction waste roadbed filler compaction test device. Background Art
[0002] Roadbed filler is a material used to fill the roadbed. It requires easy digging, easy compaction, high strength, and good water stability. Construction waste has high strength and durability, and the recycling of resources reduces the exploitation of natural resources and damage to the environment. At the same time, it can reduce material costs, making the use of construction waste as roadbed filler more and more widespread.
[0003] Construction waste used as roadbed filler is mostly bricks and concrete blocks. After the bricks and concrete blocks are transported to the construction site, a roller with staggered crushing teeth on a steel wheel is generally used to crush and compact the construction waste. However, after the bricks and concrete blocks are crushed, there are still large gaps between them. In the compaction test of construction waste sampling, after the surface is compacted and leveled, it is impossible to determine whether the interior is completely compacted, which will cause deviations in the test results. If the construction compaction force is small according to the test data, it will affect the construction quality. In addition, the main bricks and concrete blocks in construction waste are two different materials. In order to ensure that the results of the compaction test are objective and accurate, it is necessary to evenly mix the two materials of bricks and concrete blocks and the size of the broken blocks. Therefore, a construction waste roadbed filler compaction test device is proposed. Summary of the invention
[0004] The purpose of the present invention is to solve the problem in the prior art that after bricks and concrete blocks are crushed, there are still large gaps between each other. After the surface is compacted and leveled in the compaction test of construction waste sampling, it is impossible to determine whether the interior is completely compacted, which will cause deviations in the test results. If the construction compaction force is small according to the test data, it will affect the construction quality. In addition, the main bricks and concrete blocks in construction waste are two different materials. In order to ensure that the results of the compaction test are objective and accurate, it is necessary to evenly mix the two materials of bricks and concrete blocks and the size of the broken blocks. A construction waste roadbed filler compaction test device is proposed.
[0005] In order to achieve the above object, the present invention adopts the following technical solutions: A compaction test device for construction waste roadbed filler comprises a base and a hydraulic seat, wherein a compaction cylinder is arranged on the base, the top of the base is connected to a fixed seat via two guide columns, the outer wall of the guide column is connected to a U-shaped plate via an electrically controlled guide ring, a feeding cylinder is arranged on the U-shaped plate, a feeding cylinder is arranged in the feeding cylinder, a feeding assembly for uniformly conveying the filler is arranged, a compaction seat is connected to the output end of the hydraulic seat, an annular groove is provided on the side wall of the compaction seat, a rubber ring for pressing and sealing the compaction cylinder is connected to the inner wall of the annular groove, a receiving groove is provided on the bottom end of the compaction seat, an air pressure sensor for detecting air pressure changes in the compaction cylinder is connected to the inner end face of the receiving groove, a plurality of one-way components are arranged on the periphery of the air pressure sensor, and a flattening plate is connected to the one-way component.
[0006] Preferably, a plurality of positioning columns are fixedly connected to the top end of the base, a bottom plate is fixedly connected to the bottom end of the compaction cylinder, and a plurality of collars are fixedly connected to the outer side wall of the bottom plate, and the collars correspond to the positioning columns one by one.
[0007] Preferably, the top end of the base is fixedly connected to the bottom end of the fixed seat through two guide columns, the top end of the fixed seat is fixedly connected to the end of the hydraulic seat, and the outer wall of the guide column is slidably connected to the inner wall of the electric control guide ring.
[0008] Preferably, the outer side wall of the electric-controlled guide ring is fixedly connected to the outward side wall of the U-shaped plate through an electric-controlled rod, the lower end of the U-shaped plate is fixedly connected to a lifting arc plate, the upper end of the U-shaped plate is fixedly connected to a semi-guide bucket, and an extension sleeve is provided at the top of the compaction cylinder, and the lifting arc plate and the semi-guide bucket are respectively arranged at the bottom and top of the extension sleeve.
[0009] Preferably, the feeding assembly consists of a feeding shaft and a spiral blade, the top of the semi-guide bucket is fixedly connected to the bottom of the feeding barrel, the upper wall of the U-shaped plate is fixedly connected to a feeding motor, and the feeding motor is fixedly connected to the inner wall of the spiral blade through the feeding shaft.
[0010] Preferably, a feeding hole is opened on the side wall of the bottom end of the feeding barrel, a feeding conduit is fixedly connected to the inner wall of the feeding hole, a feeding hopper is fixedly connected to the top end of the feeding barrel, and a plurality of mixing plates evenly arranged in an array are fixedly connected to the outer wall of the top end of the feeding shaft.
[0011] Preferably, the output end of the hydraulic seat is fixedly connected to the top of the compaction seat, and a micro air pump is fixedly connected to the top of the compaction seat. The output end of the micro air pump is interconnected with the annular groove on the outer wall of the compaction seat, and the inner wall of the annular groove of the compaction seat is fixedly connected to both ends of the rubber ring.
[0012] Preferably, the inner end surface of the receiving groove at the bottom end of the compaction seat is fixedly connected to the end of the air pressure sensor, the inner end surface of the receiving groove is fixedly connected to the top of the leveling plate through a plurality of electric push rods, and the side wall of the leveling plate is slidably connected to the inner side wall of the receiving groove.
[0013] Preferably, the one-way component consists of a sliding rod and two pillars, the outer walls at both ends of the sliding rod are slidably connected to the inner walls of the upper and lower pillars, a tension spring is sleeved on the outer wall of the sliding rod, the upper pillar end is fixedly connected to the inner end surface of the receiving groove at the bottom end of the compaction seat, and the lower pillar end is fixedly connected to the top of the leveling plate, and the connection height between the leveling plate and the two pillars is consistent with the depth of the receiving groove.
[0014] Compared with the prior art, the present invention has the following beneficial effects: 1. This scheme uses the setting of mixing plates and spiral blades to allow the crushed bricks and concrete blocks to be uniformly mixed and then transported into the compaction cylinder in sequence, avoiding the situation in which the crushed mixed materials fall into the cylinder one after another due to friction between them during the direct pouring process, thus affecting the results of the compaction test.
[0015] 2. This solution uses the rubber ring and the leveling plate to change the state of the rubber ring and the leveling plate on the compaction seat after the compaction of the crushed materials is completed, so as to detect whether the crushed materials are completely compacted, thereby avoiding the problem that the inside of the crushed materials is difficult to directly observe and ensuring the reliability of the compaction test results. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 A schematic diagram of the three-dimensional structure of a construction waste roadbed filler compaction test device proposed by the present invention Figure 1 ; Figure 2 A schematic diagram of the three-dimensional structure of a construction waste roadbed filler compaction test device proposed by the present invention Figure 2 ; Figure 3 It is a structural schematic diagram of two half guide buckets docking in a construction waste roadbed filler compaction test device proposed by the present invention; Figure 4 This is a structural schematic diagram of the position of the feeding motor in a construction waste roadbed filler compaction test device proposed by the present invention; Figure 5 This is a schematic structural diagram of a material feeding assembly in a construction waste roadbed filler compaction test device proposed by the present invention; Figure 6 This is a structural schematic diagram of the position of a rubber ring in a construction waste roadbed filler compaction test device proposed by the present invention; Figure 7This is a schematic diagram of the structure inside a receiving tank in a construction waste roadbed filler compaction test device proposed by the present invention; Figure 8 The present invention provides a schematic structural diagram of a tension spring in a construction waste roadbed filler compaction test device.
[0017] In the figure: 1. base; 2. hydraulic seat; 3. compaction cylinder; 4. bottom plate; 5. positioning column; 6. extension sleeve; 7. guide column; 8. fixed seat; 9. electric control guide ring; 10. electric control rod; 11. U-shaped plate; 12. lifting arc plate; 13. semi-guide bucket; 14. feed cylinder; 15. feed hopper; 16. feed duct; 17. feed motor; 18. feed shaft; 19. spiral blade; 20. mixing plate; 21. compaction seat; 22. micro air pump; 23. rubber ring; 24. air pressure sensor; 25. electric push rod; 26. leveling plate; 27. pillar; 28. slide rod; 29. tension spring. DETAILED DESCRIPTION
[0018] The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.
[0019] Embodiment 1, refer to Figure 1 - Figure 8 A construction waste roadbed filler compaction test device comprises a base 1 and a hydraulic base 2, a compaction cylinder 3 is arranged on the base 1, a fixing seat 8 is connected to the top of the base 1 through two guide columns 7, a U-shaped plate 11 is connected to the outer wall of the guide column 7 through an electric control guide ring 9, a feeding cylinder 14 is arranged on the U-shaped plate 11, and a feeding assembly for uniformly conveying the filler is arranged in the feeding cylinder 14; Furthermore, a plurality of positioning columns 5 are fixedly connected to the top of the base 1, a bottom plate 4 is fixedly connected to the bottom end of the compaction cylinder 3, a plurality of collars are fixedly connected to the outer wall of the bottom plate 4, and the collars correspond to the positioning columns 5 one by one. The top of the base 1 is fixedly connected to the bottom end of the fixed seat 8 through two guide columns 7, the top of the fixed seat 8 is fixedly connected to the end of the hydraulic seat 2, the outer wall of the guide column 7 is slidably connected to the inner wall of the electric control guide ring 9, the outer wall of the electric control guide ring 9 is fixedly connected to the outward side wall of the U-shaped plate 11 through the electric control rod 10, the lower end of the U-shaped plate 11 is fixedly connected to the lifting arc plate 12, the upper end of the U-shaped plate 11 is fixedly connected to the semi-guide bucket 13, and the top of the compaction cylinder 3 is provided with The extended sleeve 6, the lifting arc plate 12 and the semi-guide bucket 13 are respectively arranged at the bottom and top of the extended sleeve 6, the feeding assembly is composed of a feeding shaft 18 and a spiral blade 19, the top of the semi-guide bucket 13 is fixedly connected to the bottom of the feeding barrel 14, the upper side wall of the U-shaped plate 11 is fixedly connected to a feeding motor 17, and the feeding motor 17 is fixedly connected to the inner side wall of the spiral blade 19 through the feeding shaft 18. A feeding hole is opened on the side wall of the bottom end of the feeding barrel 14, and a feeding conduit 16 is fixedly connected to the inner side wall of the feeding hole. The top of the feeding barrel 14 is fixedly connected to a feeding hopper 15, and the outer side wall of the top of the feeding shaft 18 is fixedly connected to a plurality of mixing plates 20 evenly arranged in an array; It should be noted that: the bottom plate 4 of the compaction cylinder 3 is installed and docked with the multiple positioning columns 5 on the base 1, so that the axis of the compaction cylinder 3 and the compaction seat 21 are located on the same vertical line, and then the electric control guide ring 9 starts to slide on the outer wall of the guide column 7, and the electric control guide ring 9 moves the lifting arc plate 12 and the semi-guide bucket 13 to the bottom and top of the extension sleeve 6 respectively through the U-shaped plate 11, and uses the electric control rod 10 to push the two semi-guide buckets 13 to dock, and the feeding motor 17 is started to drive the feeding shaft 18 to rotate slowly. The rotation of the feeding shaft 18 will drive the spiral blade 19 to rotate in the feeding cylinder 14, and the feeding shaft 18 will also drive The plurality of mixing plates 20 are driven to rotate together, and then the crushed bricks and concrete blocks are respectively put into the feeding hoppers 15 on both sides, and the crushed stones are evenly mixed under the stirring of the rotating mixing plates 20, and the mixed crushed materials are introduced into the feeding cylinder 14 and rolled into the rotating spiral blades 19, and the mixed crushed materials are successively rolled into the spiral blades 19 and transported downward, so that the mixed crushed materials will not be layered up and down and the large and small particles will not roll and fall in sequence when being poured. After the crushed materials are transported to the bottom of the feeding cylinder 14, they will be discharged through the feeding conduit 16 and enter the two butted semi-guide buckets 13, and will be mixed with each other and enter the compaction cylinder 3; A further advantage of adopting the above method is that it allows the crushed bricks and concrete blocks to be uniformly mixed and then transported into the compaction cylinder 3 in sequence, thereby avoiding the situation in which the crushed mixed materials fall into the cylinder 3 one after another due to friction between the crushed materials during direct pouring, thus affecting the results of the compaction test.
[0020] Example 2, reference Figure 1 - Figure 8 The output end of the hydraulic seat 2 is connected to a compacting seat 21, a side wall of the compacting seat 21 is provided with an annular groove, the inner side wall of the annular groove is connected with a rubber ring 23 for pressing and sealing the compacting cylinder 3, a receiving groove is provided at the bottom end of the compacting seat 21, the inner end surface of the receiving groove is connected with an air pressure sensor 24 for detecting the air pressure change in the compacting cylinder 3, a plurality of one-way components are arranged on the periphery of the air pressure sensor 24, and the one-way components are connected with a flattening plate 26; Furthermore, the output end of the hydraulic seat 2 is fixedly connected to the top of the compacting seat 21, and the top of the compacting seat 21 is fixedly connected with a micro air pump 22. The output end of the micro air pump 22 is connected to the annular groove on the outer wall of the compacting seat 21. The inner wall of the annular groove of the compacting seat 21 is fixedly connected to both ends of the rubber ring 23. The inner end surface of the receiving groove at the bottom end of the compacting seat 21 is fixedly connected to the end of the air pressure sensor 24. The inner end surface of the receiving groove is fixedly connected to the top of the flattening plate 26 through a plurality of electric push rods 25. The flattening plate 2 6 side wall is slidably connected with the inner wall of the storage groove, the one-way component is composed of a slide bar 28 and two pillars 27, the outer walls at both ends of the slide bar 28 are slidably connected with the inner walls of the upper and lower pillars 27, and a tension spring 29 is sleeved on the outer wall of the slide bar 28. The end of the pillar 27 located at the top is fixedly connected with the inner end surface of the storage groove at the bottom end of the compaction seat 21, and the end of the pillar 27 located at the bottom is fixedly connected with the top of the flat plate 26. The connection height of the flat plate 26 and the two pillars 27 is consistent with the depth of the storage groove; It should be noted that after the crushed materials of construction waste are loaded into the compaction cylinder 3, the U-shaped plate 11 and the lifting arc plate 12 are used to move and impact, so that the crushed materials in the compaction cylinder 3 are vibrated and compacted, and then the hydraulic seat 2 is started to press the compaction seat 21 downward. The compaction seat 21 is pressed into the compaction cylinder 3 and will vibrate and press down, and the crushed materials in the compaction cylinder 3 are gradually compacted. After compaction once, a part of the crushed materials are refilled, and the compaction seat 21 is pressed down for compaction. After the compaction of the crushed materials in the compaction cylinder 3 is completed, the compaction seat 21 is slowly pressed down from top to bottom, and at the same time, the micro air pump 22 is started to pass gas into the rubber ring 23, so that the rubber ring 23 is compressed and expanded, and the rubber ring 23 will be pressed against the inner wall of the extension sleeve 6 and the compaction cylinder 3, so that the bottom of the compaction seat 21 is in a relatively sealed state during the downward pressing process, and the bottom of the compaction seat 21 The air pressure between the compacted crushed materials will gradually increase. Before pressing down, the electric push rod 25 is used to push out the leveling plate 26, so that the air pressure sensor 24 in the storage groove at the bottom of the compaction seat 21 can sense and detect the external air pressure. When the leveling plate 26 is pushed down, the two pillars 27 slide on the slide bar 28 and stretch and separate the tension spring 29. In the compaction process, the two pillars 27 are butted against each other to support the leveling plate 26 to ensure the flatness of the leveling plate 26 and the bottom of the compaction seat 21. If the crushed materials in the compaction cylinder 3 are not completely compacted, as the air pressure continues to increase, the high-pressure gas will enter the gap between the crushed materials along the gap, so that the air pressure below the compaction seat 21 and between the compacted crushed materials will suddenly decrease during the overall increase, which is sensed by the air pressure sensor 24 and the signal is transmitted; A further advantage of adopting the above method is that after the compaction of the crushed materials is completed, the state of the rubber ring 23 and the leveling plate 26 on the compaction seat 21 can be changed to detect whether the crushed materials are completely compacted, thereby avoiding the problem that the interior of the crushed materials is difficult to directly observe and ensuring the reliability of the compaction test results.
[0021] When the present invention is in use, the bottom plate 4 of the compacting cylinder 3 is installed and docked with the multiple positioning columns 5 on the base 1, so that the axis of the compacting cylinder 3 and the compacting seat 21 are located on the same vertical line, and then the electric control guide ring 9 starts to slide on the outer wall of the guide column 7, and the electric control guide ring 9 moves the lifting arc plate 12 and the semi-guide bucket 13 to the bottom and top of the extension sleeve 6 respectively through the U-shaped plate 11, and uses the electric control rod 10 to push the two semi-guide buckets 13 to dock, and the feeding motor 17 is started to drive the feeding shaft 18 to rotate slowly. The rotation of the feeding shaft 18 will drive the spiral blade 19 to rotate in the feeding cylinder 14, and the feeding shaft 18 will also drive the multiple mixing plates 20 to rotate together, and then the crushed bricks and concrete blocks are respectively put into the feeding hopper 1 on both sides. 5, the crushed stones are mixed evenly under the stirring of the rotating mixing plate 20, and the mixed crushed materials are introduced into the feeding tube 14 and rolled into the rotating spiral blades 19, so that the mixed crushed materials are rolled into the spiral blades 19 in turn and transported downward, which will not cause the mixed crushed materials to be layered up and down and the large and small particles to roll and fall in sequence when pouring. After the crushed materials are transported to the bottom of the feeding tube 14, they will be discharged through the feeding conduit 16 and enter the two docking semi-guide buckets 13, and mix with each other and enter the compaction tube 3. In this way, the crushed materials of bricks and concrete blocks can be uniformly mixed and transported into the compaction tube 3 in sequence, avoiding the situation that the crushed materials of different sizes fall in sequence due to the friction between each other during the direct pouring process, which affects the results of the compaction test; After the crushed materials of construction waste are loaded into the compaction cylinder 3, the U-shaped plate 11 and the lifting arc plate 12 are used to move and impact, so that the crushed materials in the compaction cylinder 3 are vibrated and compacted. Then, the hydraulic seat 2 is started to press the compaction seat 21 downward. The compaction seat 21 is pressed into the compaction cylinder 3 and vibrates and presses down to gradually compact the crushed materials in the compaction cylinder 3. After compaction once, a part of the crushed materials is refilled, and then the compaction seat 21 is pressed down to compact. After the crushed materials in the compaction cylinder 3 are compacted, the compaction seat 21 is moved downward. The compaction seat 21 is pressed down slowly from top to bottom, and at the same time, the micro air pump 22 is started to pass gas into the rubber ring 23, so that the rubber ring 23 is compressed and expanded. The rubber ring 23 will be pressed against the inner wall of the extension sleeve 6 and the compaction cylinder 3, so that the bottom of the compaction seat 21 is in a relatively sealed state during the downward pressing process. The air pressure below the compaction seat 21 and between the compacted crushed materials will gradually increase. Before pressing down, the electric push rod 25 is used to push the flat plate 26 out so that the bottom of the compaction seat 21 The air pressure sensor 24 in the storage groove can sense and detect the external air pressure. When the leveling plate 26 is pushed down, the two pillars 27 slide on the slide bar 28 and stretch and separate the tension spring 29. During the compaction process, the two pillars 27 dock with each other to support the leveling plate 26 to ensure the flatness of the leveling plate 26 and the bottom of the compaction seat 21. If the crushed materials in the compaction cylinder 3 are not completely compacted, as the air pressure continues to increase, the high-pressure gas will enter the gap between the crushed materials along the gap, causing the air pressure below the compaction seat 21 and between the compacted crushed materials to suddenly decrease during the overall increase, which is sensed by the air pressure sensor 24 and the signal is transmitted. In this way, after the compaction of the crushed materials is completed, the state of the rubber ring 23 and the leveling plate 26 on the compaction seat 21 can be changed to detect whether the compacted crushed materials are completely compacted, thereby avoiding the problem that the inside of the crushed materials is difficult to directly observe, and ensuring the reliability of the compaction test results.
[0022] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.
Claims
1. A construction waste roadbed filler compaction test device, comprising a base (1) and a hydraulic base (2), wherein a compaction cylinder (3) is arranged on the base (1), characterized in that: The top of the base (1) is connected to a fixed seat (8) via two guide columns (7); the outer wall of the guide column (7) is connected to a U-shaped plate (11) via an electric control guide ring (9); a feeding cylinder (14) is arranged on the U-shaped plate (11); a feeding assembly for uniformly conveying fillers is arranged inside the feeding cylinder (14); The output end of the hydraulic seat (2) is connected to a compaction seat (21), the side wall of the compaction seat (21) is provided with an annular groove, the inner side wall of the annular groove is connected to a rubber ring (23) for pressing and sealing the compaction cylinder (3), the bottom end of the compaction seat (21) is provided with a receiving groove, the inner end surface of the receiving groove is connected to an air pressure sensor (24) for detecting changes in air pressure in the compaction cylinder (3), a plurality of one-way components are arranged on the periphery of the air pressure sensor (24), and the one-way components are connected to a flattening plate (26).
2. A construction waste roadbed filler compaction test device according to claim 1, characterized in that: The top end of the base (1) is fixedly connected to a plurality of positioning columns (5), the bottom end of the compaction cylinder (3) is fixedly connected to a bottom plate (4), and the outer side wall of the bottom plate (4) is fixedly connected to a plurality of sleeve rings, the sleeve rings corresponding to the positioning columns (5) one by one.
3. A construction waste roadbed filler compaction test device according to claim 1, characterized in that: The top end of the base (1) is fixedly connected to the bottom end of the fixed seat (8) via two guide columns (7), the top end of the fixed seat (8) is fixedly connected to the end of the hydraulic seat (2), and the outer wall of the guide column (7) is slidably connected to the inner wall of the electric control guide ring (9).
4. A construction waste roadbed filler compaction test device according to claim 1, characterized in that: The outer side wall of the electrically controlled guide ring (9) is fixedly connected to the outward side wall of the U-shaped plate (11) via an electrically controlled rod (10); the lower end of the U-shaped plate (11) is fixedly connected to a lifting arc plate (12); the upper end of the U-shaped plate (11) is fixedly connected to a semi-guide bucket (13); an extended sleeve (6) is arranged at the top end of the compaction cylinder (3); the lifting arc plate (12) and the semi-guide bucket (13) are respectively arranged at the bottom and top ends of the extended sleeve (6).
5. A construction waste roadbed filler compaction test device according to claim 4, characterized in that: The feeding assembly is composed of a feeding shaft (18) and a spiral blade (19); the top end of the semi-guide bucket (13) is fixedly connected to the bottom end of the feeding cylinder (14); the upper side wall of the U-shaped plate (11) is fixedly connected to a feeding motor (17); and the feeding motor (17) is fixedly connected to the inner side wall of the spiral blade (19) via the feeding shaft (18).
6. A construction waste roadbed filler compaction test device according to claim 5, characterized in that: A feeding hole is formed on the side wall at the bottom end of the feeding cylinder (14), a feeding conduit (16) is fixedly connected to the inner wall of the feeding hole, a feeding hopper (15) is fixedly connected to the top end of the feeding cylinder (14), and a plurality of mixing plates (20) evenly arranged in an array are fixedly connected to the outer wall at the top end of the feeding shaft (18).
7. A construction waste roadbed filler compaction test device according to claim 1, characterized in that: The output end of the hydraulic seat (2) is fixedly connected to the top of the compaction seat (21), the top of the compaction seat (21) is fixedly connected to a micro air pump (22), the output end of the micro air pump (22) is in communication with the annular groove on the outer wall of the compaction seat (21), and the inner wall of the annular groove of the compaction seat (21) is fixedly connected to both ends of the rubber ring (23).
8. A construction waste roadbed filler compaction test device according to claim 1, characterized in that: The inner end surface of the receiving groove at the bottom end of the compaction seat (21) is fixedly connected to the end of the air pressure sensor (24), the inner end surface of the receiving groove is fixedly connected to the top of the leveling plate (26) via a plurality of electric push rods (25), and the side wall of the leveling plate (26) is slidably connected to the inner side wall of the receiving groove.
9. A construction waste roadbed filler compaction test device according to claim 1, characterized in that: The one-way component is composed of a slide bar (28) and two pillars (27). The outer walls at both ends of the slide bar (28) are slidably connected to the inner walls of the upper and lower pillars (27). A tension spring (29) is sleeved on the outer wall of the slide bar (28). The end of the upper pillar (27) is fixedly connected to the inner end surface of the receiving groove at the bottom end of the compaction seat (21). The end of the lower pillar (27) is fixedly connected to the top of the flattening plate (26). The connection height between the flattening plate (26) and the two pillars (27) is consistent with the depth of the receiving groove.
Citation Information
Patent Citations
Soil sample electric compaction device and testing method thereof
CN105115803A
Vibration compaction test device for road roller
CN118837249A
Expressway compactness test detection device
CN214143633U
Compaction equipment for building foundation construction
CN215252775U
Manual compaction apparatus auxiliary device and manual compaction apparatus capable of positioning compaction position
CN216791829U