Mineralization control system, method and device and mineralization equipment

By monitoring the historical running time of power components in mineralization equipment and adaptively adjusting the extraction time of mineral water, the problem that mineralization modules in the existing technology cannot stably produce fixed concentration mineral water, and realize the mineralization equipment Stable concentration output and improved user experience.

CN119235167AInactive Publication Date: 2025-01-03GREE ELECTRIC APPLIANCE INC OF ZHUHAI
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202411326868.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-23
Publication Date
2025-01-03
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The mineralization modules in existing water dispenser equipment cannot stably produce fixed concentrations of mineral water, resulting in large fluctuations in the concentration of mineralized water.

Method used

Design a mineralization control system to adaptively adjust the extraction time of mineral water by monitoring the historical running time of power components in mineralization equipment, including control components, valve body components and power components, using liquid level detectors and heating components , realize monitoring of the life of mineral filter element and stable extraction of mineral water.

Benefits of technology

When mineralization equipment is used for a long time, the mineralization equipment produces a stable concentration of mineral water, which improves the user experience of mineralization equipment and the stability of mineral water.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119235167A_ABST
    Figure CN119235167A_ABST
Patent Text Reader

Abstract

The invention relates to a mineralization control system, method and device and mineralization equipment, the system comprises a control assembly, a valve body assembly and a power assembly, and the control assembly is connected with the valve body assembly and the power assembly; the control assembly is used for acquiring historical operation time of the power assembly; determining target extraction time of the water body in the mineralization bin according to the historical operation time; and controlling the valve body assembly and the power assembly to execute the mineral water extraction step according to the target extraction time. By monitoring the accumulated operation time of the power assembly in the mineralization control system and adaptively adjusting the extraction time of the mineral water according to the historical operation time of the power assembly, the mineral water with stable concentration can be produced by the mineralization equipment under the condition that the mineralization equipment is used for a long time, and the use experience of the mineralization equipment is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of water production equipment, and in particular to a mineralization control system, method, device and mineralization equipment. Background Art

[0002] As living standards continue to improve, drinking water health issues have attracted widespread attention. The mainstream market often uses reverse osmosis filtration devices on water dispensers to filter out various impurities in the water to obtain pure water, thereby ensuring drinking water safety. However, while filtering out harmful substances, reverse osmosis filtration devices also filter out beneficial minerals in the water.

[0003] The mineralization module in the existing water dispenser equipment obtains mineral water by soaking mineralized materials in water. However, since the concentration of minerals precipitated from the mineralized materials fluctuates greatly when they are left to stand for different periods of time, the mineralization module cannot stably produce mineral water with a fixed concentration. Summary of the invention

[0004] Based on this, it is necessary to provide a mineralization control system, method, device and mineralization equipment that can accurately and stably produce a certain concentration of mineral water according to the life of the filter element to address the above technical problems.

[0005] In a first aspect, the present application provides a mineralization control system, which is applied to a mineralization device, wherein the mineralization device includes a mineralization bin; the system includes: a control component, a valve body component, and a power component, wherein the control component is connected to the valve body component and the power component respectively;

[0006] The valve body assembly is respectively arranged at the water inlet of the mineralization bin and the water outlet of the mineralization bin, and the valve body assembly is used to control the flow state of the water body;

[0007] The power assembly is connected to the valve body assembly, and the power assembly is used to control the water to flow in a corresponding direction;

[0008] The control component is used to obtain the historical operating time of the power component; determine the target extraction time of the water body in the mineralization chamber according to the historical operating time; and control the valve body component and the power component to perform the mineral water extraction step according to the target extraction time.

[0009] In one of the embodiments, the control component is used to determine the target extraction time as a first extraction time if the historical operation time is less than a first time threshold;

[0010] If the historical running time is greater than or equal to the first time threshold and less than the second time threshold, determining the target extraction time to be the second extraction time;

[0011] If the historical running time is greater than or equal to a second time threshold, the target extraction time is determined to be a third extraction time, wherein the first extraction time is less than the second extraction time, and the second extraction time is less than the third extraction time.

[0012] In one embodiment, the control component is used to extend the target extraction time according to the correspondence between the increase in the historical operating time and the extension time if the historical operating time increases.

[0013] In one of the embodiments, the system further comprises: an alarm component;

[0014] The control component is used to control the alarm component to alarm when the historical operating time is greater than or equal to the alarm time threshold, so as to prompt the user to replace the filter element.

[0015] In one embodiment, the mineralization equipment further comprises a water tank, wherein a first liquid level detector and a second liquid level detector are disposed in the water tank, and the first liquid level detector and the second liquid level detector are both connected to the control component;

[0016] The control component is used to control the valve body component and the power component to perform the mineral water extraction step if a low liquid level signal is received from the first liquid level detector;

[0017] The control component is used to control the valve body component and the power component to stop executing the mineral water extraction step if a high liquid level signal is received from the second liquid level detector.

[0018] In one embodiment, the valve body assembly includes a first solenoid valve and a second solenoid valve, and the power assembly includes a first self-priming pump and a second self-priming pump;

[0019] One end of the first solenoid valve is connected to one end of the first self-priming pump, the other end of the first solenoid valve is connected to the water inlet of the mineralization bin, and the other end of the first self-priming pump is used to access a preset water body;

[0020] One end of the second solenoid valve is connected to one end of the second self-priming pump, the other end of the second solenoid valve is connected to the water outlet of the mineralization bin, and the other end of the second self-priming pump is connected to the water storage tank.

[0021] In one of the embodiments, the system further comprises: a heating component;

[0022] The heating component is arranged between the first solenoid valve and the first self-priming pump, the heating component is connected to the control component, and the heating component is used to heat the water body to a preset temperature according to a target heating instruction.

[0023] In one embodiment, the control component is used to control the first solenoid valve and the first self-priming pump to open, and the second solenoid valve and the second self-priming pump to close if a low liquid level signal is received from the first liquid level detector, so that the water enters the mineralization bin after being heated by the heating component;

[0024] When the water volume of the first self-priming pump is greater than or equal to a preset water volume threshold, the first solenoid valve and the first self-priming pump are controlled to be closed, so that the mineralization bin performs thermal extraction to obtain mineral water of a preset concentration;

[0025] When the thermal extraction time of the mineralization bin is greater than or equal to the target extraction time, the second solenoid valve and the second self-priming pump are controlled to open so that the mineral water in the mineralization bin is transferred to the water storage tank;

[0026] When the opening time of the second self-priming pump is greater than or equal to the preset time, the second solenoid valve and the second self-priming pump are controlled to be closed, and it is determined whether a high liquid level signal sent by the second liquid level detector is received;

[0027] If no high liquid level signal is received from the second liquid level detector, the execution is skipped to the step of controlling the first solenoid valve and the first self-priming pump to be turned on, and the second solenoid valve and the second self-priming pump to be turned off, so that the water enters the mineralization bin after being heated by the heating component;

[0028] If a high liquid level signal is received from the second liquid level detector, the mineral water extraction step is completed.

[0029] In one embodiment, the control component is used to determine a target extraction time of water in the mineralization chamber based on a historical operating time of the second self-priming pump, wherein the longer the historical operating time of the second self-priming pump is, the longer the target extraction time is.

[0030] In one of the embodiments, the mineralization chamber includes a mineralization filter element and a membrane shell, and the membrane shell is provided with an atmospheric through hole, and the atmospheric through hole is used to balance the pressure inside the mineralization chamber with the external air pressure.

[0031] In a second aspect, the present application further provides a mineralization control method, which is applied to the mineralization control system described in the first aspect, comprising:

[0032] Get the historical running time of the power component;

[0033] Determining a target extraction time of the water body in the mineralization chamber according to the historical operation time;

[0034] The valve body assembly and the power assembly are controlled according to the target extraction time to perform the mineral water extraction step.

[0035] In one embodiment, determining the target extraction time of the water body in the mineralization bin according to the historical operation time includes:

[0036] If the historical running time is less than the first time threshold, determining the target extraction time as the first extraction time;

[0037] If the historical running time is greater than or equal to the first time threshold and less than the second time threshold, determining the target extraction time to be the second extraction time;

[0038] If the historical running time is greater than or equal to a second time threshold, the target extraction time is determined to be a third extraction time, wherein the first extraction time is less than the second extraction time, and the second extraction time is less than the third extraction time.

[0039] In one embodiment, determining the target extraction time of the water body in the mineralization bin according to the historical operation time includes:

[0040] If the historical running time increases, the target extraction time is extended according to the corresponding relationship between the increase in the historical running time and the extended time.

[0041] In one embodiment, the step of controlling the valve body assembly and the power assembly to perform the mineral water extraction step according to the target extraction time includes:

[0042] If a low liquid level signal is received from the first liquid level detector, the first solenoid valve and the first self-priming pump are controlled to be opened, and the second solenoid valve and the second self-priming pump are controlled to be closed, so that the water body enters the mineralization bin after being heated by the heating component;

[0043] When the water volume of the first self-priming pump is greater than or equal to a preset water volume threshold, the first solenoid valve and the first self-priming pump are controlled to be closed, so that the mineralization bin performs thermal extraction to obtain mineral water of a preset concentration;

[0044] When the thermal extraction time of the mineralization bin is greater than or equal to the target extraction time, the second solenoid valve and the second self-priming pump are controlled to open so that the mineral water in the mineralization bin is transferred to the water storage tank;

[0045] When the opening time of the second self-priming pump is greater than or equal to the preset time, the second solenoid valve and the second self-priming pump are controlled to be closed, and it is determined whether a high liquid level signal sent by the second liquid level detector is received;

[0046] If no high liquid level signal is received from the second liquid level detector, the execution is skipped to the step of controlling the first solenoid valve and the first self-priming pump to be turned on, and the second solenoid valve and the second self-priming pump to be turned off, so that the water enters the mineralization bin after being heated by the heating component;

[0047] If a high liquid level signal is received from the second liquid level detector, the mineral water extraction step is completed.

[0048] In a third aspect, the present application further provides a mineralization control device, which is applied to the mineralization control system described in the first aspect, comprising:

[0049] An acquisition module, used for acquiring the historical running time of the power component;

[0050] A determination module, used to determine a target extraction time of the water body in the mineralization bin according to the historical operation time;

[0051] The extraction module is used to control the valve body component and the power component to perform the mineral water extraction step according to the target extraction time.

[0052] In a fourth aspect, the present application further provides a mineralization device, comprising the mineralization control system, mineralization bin and water storage tank described in the first aspect.

[0053] In one of the embodiments, the mineralization chamber includes a mineralization filter element and a membrane shell, and the membrane shell is provided with an atmospheric through hole, and the atmospheric through hole is used to balance the pressure inside the mineralization chamber with the external air pressure.

[0054] In a fifth aspect, the present application further provides a computer device, comprising a memory and a processor, wherein the memory stores a computer program, and the processor implements the steps of the mineralization control method described in the second aspect when executing the computer program.

[0055] In a sixth aspect, the present application further provides a computer-readable storage medium having a computer program stored thereon, and when the computer program is executed by a processor, the steps of the mineralization control method described in the second aspect are implemented.

[0056] In a seventh aspect, the present application further provides a computer program product, wherein the computer program product comprises a computer program, and when the computer program is executed by a processor, the steps of the mineralization control method described in the second aspect are implemented.

[0057] In summary, the present application proposes a mineralization control system, method, device and mineralization equipment, the system includes: a control component, a valve body component and a power component, wherein the control component is connected to the valve body component and the power component respectively; the control component is used to obtain the historical operating time of the power component; determine the target extraction time of the water body in the mineralization bin according to the historical operating time; and control the valve body component and the power component to perform the mineral water extraction step according to the target extraction time. The present application monitors the cumulative operating time of the power component in the mineralization control system, and adaptively adjusts the extraction time of the mineral water according to the historical operating time of the power component. When the mineralization equipment is used for a long time, the mineralization equipment can maintain the output of mineral water with a stable concentration, thereby improving the user experience of the mineralization equipment. BRIEF DESCRIPTION OF THE DRAWINGS

[0058] Figure 1 is a structural block diagram of a mineralization device in one embodiment;

[0059] Figure 2 It is a structural block diagram of a mineralization control system in one embodiment;

[0060] Figure 3 A schematic diagram of the structure of a mineralization control system in one embodiment;

[0061] Figure 4 A schematic diagram of a mineralization control method in one embodiment;

[0062] Figure 5 A schematic flow chart of the steps for determining a target extraction time in one embodiment;

[0063] Figure 6 A schematic diagram of a process flow for performing a mineral water extraction step in one embodiment;

[0064] Figure 7 is a structural block diagram of a mineralization control device in one embodiment;

[0065] Figure 8 FIG. 4 is a diagram showing the internal structure of a computer device in one embodiment.

[0066] Summary of reference numerals:

[0067] Mineralization control system-100; control component-110; valve body component-120; first solenoid valve-121; second solenoid valve-122; power component-130; first self-priming pump-131; second self-priming pump-132; heating component-140; alarm component-150;

[0068] Mineralization chamber-200; mineralization filter element-210; membrane shell-220; atmosphere through hole-230; insulation layer-240;

[0069] Water storage tank-300; first liquid level detector-310; second liquid level detector-320. DETAILED DESCRIPTION

[0070] In order to make the purpose, technical solution and advantages of the present application more clearly understood, the present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present application and are not used to limit the present application.

[0071] The mineralization equipment provided in the embodiments of the present application is as follows: Figure 1 As shown, the mineralization equipment includes a mineralization control system 100, a mineralization bin 200 and a water storage tank 300. The mineralization control system 100 is arranged between the water pipes of the mineralization equipment, connecting the mineralization bin 200 and the water storage tank 300, so as to guide the water into the mineralization bin 200, extract minerals of a certain concentration, generate corresponding mineral water, and store the mineral water in the water storage tank 300, so as to provide the user with mineral water of a preset concentration when the user takes water.

[0072] In a specific embodiment, the mineralization chamber 200 includes a mineralization filter element 210 and a membrane shell 220, and an atmospheric through hole 230 is provided on the membrane shell 220, and the atmospheric through hole 230 is used to balance the pressure inside the mineralization chamber 200 with the external air pressure. Among them, the mineralization filter element 210 can be in the form of a compressed form of a mineralized material and a carbon rod, or in the form of a mixture of a mineralized material and activated carbon, or in the form of a mineralized material and activated carbon ceramic balls. In a specific embodiment, the mineralized material can use a certain amount of natural selected ore material to release some mineral elements required by the human body into the water, such as metasilicic acid, strontium, calcium, magnesium, potassium, zinc and other elements that are the same as the components of natural mineral water.

[0073] The membrane shell 220 can be made of stainless steel or high temperature resistant plastic. In a specific embodiment, the membrane shell 220 can also be provided with an insulation layer 240, and the insulation layer 240 is made of insulation material. The mineralization filter element 210 is arranged inside the cavity formed by the membrane shell 220, and an atmospheric through hole 230 is arranged on the membrane shell 220 for connecting to the atmosphere, which can effectively balance the pressure inside the cavity of the mineralization bin 200 and the external atmospheric pressure, so that the pressure inside the cavity is consistent with the external atmospheric pressure. In actual application, the setting of the atmospheric through hole 230 can effectively avoid the generation of negative pressure in the internal cavity of the mineralization bin 200, so that the soaking liquid in the mineralization bin 200 can be more easily extracted to the water storage tank 300, effectively improving the effect of solid-liquid separation in the mineralization bin 200, and making the solid-liquid separation more thorough.

[0074] In this example, the water tank 300 is used to store the mineral water generated by the mineralization bin 200, and the water tank 300 can be made of stainless steel or high temperature resistant plastic. It should be noted that the specific constituent materials of the membrane shell 220 and the water tank 300 in this embodiment can be adaptively configured according to the needs of the actual application scenario. At least two liquid level detectors are arranged inside the water tank 300, wherein the liquid level detector includes a high liquid level detector and a low liquid level detector. The high liquid level detector is arranged at a position where the water tank 300 is closer to the water inlet, that is, at a position where the internal cavity of the water tank 300 is higher than the bottom plane. The low liquid level detector is arranged at a position where the water tank 300 is closer to the water outlet, that is, at a position where the internal cavity of the water tank 300 is lower than the bottom plane.

[0075] In a specific embodiment, the liquid level detector may also be referred to as a liquid level switch. When the high liquid level detector is triggered, it indicates that the water storage tank 300 is full of mineral water. When the low liquid level detector is triggered, it indicates that the mineral water content in the water storage tank 300 is insufficient and mineral water cannot be provided to the user immediately.

[0076] In order to solve the problem that the mineral water machine in the prior art cannot provide users with mineral water of stable concentration after long-term operation, the present embodiment provides a mineralization control system 100, which can monitor the status of the mineralization filter element 210 in the mineralization bin 200 in the mineralization equipment in real time, and adaptively change the extraction time of mineral water extraction according to the life of the mineralization filter element 210, thereby effectively improving the stability of the mineral water extraction concentration.

[0077] In one embodiment, reference Figure 2 , provides a mineralization control system 100, which is applied to Figure 1 In the mineralization equipment shown, the specific composition structure of the mineralization equipment can refer to the description in the aforementioned embodiment, which will not be repeated here.

[0078] like Figure 2 As shown, the mineralization control system 100 includes: a control component 110, a valve body component 120 and a power component 130, wherein the control component 110 is connected to the valve body component 120 and the power component 130 respectively.

[0079] The valve body assembly 120 is respectively arranged at the water inlet of the mineralization bin 200 and the water outlet of the mineralization bin 200 , and the valve body assembly 120 is used to control the flow state of the water body.

[0080] The power assembly 130 is connected to the valve body assembly 120 , and the power assembly 130 is used to control the water to flow in a corresponding direction.

[0081] The control component 110 is used to obtain the historical operating time of the power component 130; determine the target extraction time of the water body in the mineralization chamber 200 according to the historical operating time; and control the valve body component 120 and the power component 130 to perform the mineral water extraction step according to the target extraction time.

[0082] In this embodiment, the control component 110 includes a chip or circuit such as a controller, a processor or a microprocessor that can realize the generation and distribution of control instructions. This embodiment does not limit the specific type of the control component 110, and can be adaptively configured according to the needs of the actual application scenario. The control component 110 is used to obtain the historical running time of the power component 130 and send corresponding control instructions to the valve body component 120 or the power component 130 to realize the generation of mineral water.

[0083] The valve body assembly 120 includes a switch component such as a solenoid valve that can be used to control the switch state of the water body pipeline. In this embodiment, the valve body assembly 120 is at least arranged at the water inlet of the mineralization bin 200 and the water outlet of the mineralization bin 200, and is used to realize the water inlet control and water outlet control of the mineralization bin 200. In this embodiment, the flow state of the water body includes a conducting state and a shutoff state. When the valve body assembly 120 is opened, the water body pipeline is in a conducting state, and the water body can flow to the corresponding device through the water pipe. When the valve body assembly 120 is closed, the water body pipeline is in a shutoff state, and the water body can no longer pass through the water pipe.

[0084] The power assembly 130 includes a pump body such as a self-priming pump that can provide power for the water body. The power assembly 130 in this embodiment can control the preset water body to flow into the mineralization chamber 200 in sequence through the heating assembly 140 and the valve body assembly 120, and can also control the water body in the mineralization chamber 200 to flow into the water storage tank 300 in sequence through the valve body assembly 120 and the power assembly 130.

[0085] In the present embodiment, the historical operation time of the power assembly 130 refers to the cumulative operation time of the power assembly 130 when performing the mineral water extraction step. In a specific embodiment, when the power assembly 130 is running, a certain flow of water is driven to run in a specified direction. The operation time of the power assembly 130 corresponds to the amount of mineral water obtained by the mineralization extraction in the mineralization warehouse. For the convenience of statistics, the historical operation time of the power assembly 130 is generally the cumulative operation time of a self-priming pump. Preferably, the power assembly 130 in the present embodiment includes a first self-priming pump 131 and a second self-priming pump 132, and the historical operation time of the power assembly 130 corresponds to the historical operation time of the second self-priming pump 132.

[0086] When implementing the mineral water extraction step, the control component 110 in this embodiment can first control the corresponding valve body component 120 and the power component 130 to open, so that the water body is driven by the power component 130 to enter the mineralization bin 200, and complete the extraction of the preset time in the mineralization bin 200. Then control the corresponding valve body component 120 and the power component 130 so that the mineral water of a certain concentration generated in the mineralization bin 200 is transferred to the water storage tank 300. Repeat the above extraction control and mineral water transfer control until the mineral water level in the water storage tank 300 is greater than or equal to the preset liquid level threshold. It should be noted that the volume of the water storage tank 300 in this embodiment is greater than the volume of the mineralization bin 200, and the volume of the water storage tank 300 can be several times the volume of the mineralization bin 200, which can be specifically configured according to the needs of the actual application scenario.

[0087] Since the mineralization filter element 210 in the mineralization chamber 200 has a corresponding service life, when the mineralization equipment is used for a long time, the mineralization filter element 210 will be consumed, resulting in an unstable concentration of mineral water generated in the mineralization chamber 200.

[0088] In the process of executing each mineral water extraction step, the control component 110 in this embodiment obtains the estimated total amount of water flowing through the mineralization bin 200 by recording the historical operation time of the power component 130. It should be noted that the estimated total amount of water flowing through the mineralization bin 200 corresponds to the service life of the mineralization filter element 210 of the mineralization bin 200. The target extraction time for the water body to be extracted in the mineralization bin 200 is then determined based on the historical operation time. In this embodiment, the target extraction time is the time required for the water body to complete an extraction in the mineralization bin 200. There is a corresponding relationship between the target extraction time and the historical operation time. The greater the historical operation time, the greater the target extraction time. In the case of determining the target extraction time based on the historical operation time, the valve body component 120 and the power component 130 are controlled to implement the corresponding mineral water extraction step, which can effectively realize the association between the mineral water extraction step and the life of the mineralization filter element 210, so that the mineral water extraction step can generate mineral water with a more stable concentration.

[0089] In summary, this embodiment realizes the monitoring of the life of the mineralization filter element 210 in the mineralization bin 200 by configuring the power component 130 at the water inlet or outlet of the mineralization bin 200 and monitoring the historical operating time of the power component 130. It can also adjust the execution logic of the mineral water extraction step in real time according to the life of the mineralization filter element 210, thereby greatly improving the stability of the mineralization equipment in generating mineral water.

[0090] In one embodiment, the control component 110 is configured to determine the target extraction time as the first extraction time if the historical operation time is less than the first time threshold.

[0091] If the historical running time is greater than or equal to the first time threshold and less than the second time threshold, the target extraction time is determined to be the second extraction time.

[0092] If the historical running time is greater than or equal to the second time threshold, the target extraction time is determined to be a third extraction time, wherein the first extraction time is less than the second extraction time, and the second extraction time is less than the third extraction time.

[0093] In this embodiment, the first time threshold can be set to 1-2 hours (h), the second time threshold can be set to 2-3h, the first extraction time can be set to 1 minute (min), the second extraction time can be set to 2-5min, and the third extraction time can be set to 6-10min. It should be noted that the above specific values ​​are all examples, and the specific values ​​can be adaptively configured according to the needs of actual application scenarios.

[0094] In this embodiment, when the historical running time reaches a certain threshold node, the target extraction time can be updated to achieve the update of the mineral water extraction logic.

[0095] In one embodiment, the control component 110 is configured to extend the target extraction time according to a corresponding relationship between the increase in the historical operation time and the extension time if the historical operation time increases.

[0096] In this embodiment, the target extraction time can be set to 15s-30min, and the target extraction time will increase with the increase of the historical running time. It should be noted that the target extraction time update logic that increases with the increase of the historical running time in this embodiment can also be used together with the update logic of changing the target extraction time at the corresponding threshold node in the above embodiment, so as to more flexibly control the mineralization equipment to extract mineral water.

[0097] It should be noted that in one extraction step, the historical operation time of the power assembly 130 may increase by 10-60 seconds (s). In a specific embodiment, the increase in the historical operation time may be determined according to the setting of the self-priming pump in the actual application scenario.

[0098] In one embodiment, the mineralization control system 100 further includes an alarm component 150 , which is connected to the control component 110 .

[0099] The control component 110 is used to control the alarm component 150 to sound an alarm when the historical operating time is greater than or equal to the alarm time threshold, so as to prompt the user to replace the filter element.

[0100] In this embodiment, the alarm time threshold can be set to 10-100h, and the alarm time threshold can also be adaptively set according to the needs of the actual application scenario. The alarm component 150 in this embodiment can include devices such as a buzzer, a control panel or a faucet ring light, which can be configured according to the specific type of mineralization equipment in the actual application scenario.

[0101] The control component 110 can control the alarm component 150 to directly sound a buzzer alarm, prompting the user to replace the mineralized filter element 210 of the mineralization device. The alarm component 150 can also be controlled to display a prompt message on the display panel of the mineralization device that the filter element needs to be replaced. This embodiment can effectively monitor the life of the mineralized filter element 210 by cooperating with the alarm component 150 to sound an alarm, and promptly remind the user to replace the mineralized filter element 210 when the mineralized filter element 210 has been used for too long.

[0102] It should be noted that after the user completes the filter element replacement, the user can operate on the corresponding control panel to confirm that the filter element replacement process is completed. At this time, the control component 110 will reset the historical operating time of the power component 130, that is, the historical operating time is set to 0. It should be noted that the control component 110 can also confirm whether the filter element has been replaced through the filter element monitoring device set in the mineralization equipment.

[0103] In a feasible embodiment, the control component 110 not only monitors the historical running time of the power component 130 during the use of a mineralized filter element 210, but also monitors the total running time of the power component 130. When the total running time of the power component 130 exceeds a preset time threshold, the power component 130 is replaced. It should be noted that the historical running time of the power component 130 in this embodiment corresponds to the cumulative running time of a mineralized filter element 210 during use.

[0104] In one embodiment, Figure 3 As shown, the mineralization equipment further includes a water tank 300 , in which a first liquid level detector 310 and a second liquid level detector 320 are disposed. The first liquid level detector 310 and the second liquid level detector 320 are both connected to the control component 110 .

[0105] The control component 110 is used to control the valve body component 120 and the power component 130 to perform the mineral water extraction step if a low liquid level signal is received from the first liquid level detector 310 .

[0106] The control component 110 is used to control the valve body component 120 and the power component 130 to stop executing the mineral water extraction step if a high liquid level signal is received from the second liquid level detector 320 .

[0107] In this embodiment, the control component 110 can start and stop the mineral water extraction step according to the liquid level in the water tank 300. By configuring the first liquid level detector 310 and the second liquid level detector 320 in the water tank 300, it can also effectively ensure that the mineral water content in the water tank 300 is always greater than or equal to the preset liquid level threshold, so as to provide mineral water to the user at any time.

[0108] It should be noted that the first liquid level detector 310 is set at a certain distance from the bottom surface of the water tank 300 to ensure that a certain amount of mineral water is always stored in the water tank 300, and timely remind the control component 110 to extract mineral water to achieve automatic replenishment of mineral water. The second liquid level detector 320 is set at a certain distance from the top surface of the water tank 300 to ensure that the mineral water in the water tank 300 is not full, thereby preventing the mineral water from being retained in the mineralization bin 200, effectively protecting the mineralization filter element 210 in the mineralization bin 200, and extending the service life of the mineralization filter element 210.

[0109] In one embodiment, the mineralization chamber 200 includes a mineralization filter element 210 and a membrane shell 220 . The membrane shell 220 is provided with an atmospheric through hole 230 . The atmospheric through hole 230 is used to balance the pressure inside the mineralization chamber 200 with the external air pressure.

[0110] In this embodiment, the membrane shell 220 in which the mineralization filter element 210 is placed is provided with a corresponding atmospheric through hole 230, so that the extraction liquid in the cavity of the mineralization bin 200 can flow more thoroughly to the water storage tank 300, so as to achieve solid-liquid separation in the cavity of the mineralization bin 200, and effectively extend the service life of the mineralization filter element 210.

[0111] In one embodiment, Figure 3 As shown, the valve body assembly 120 includes a first solenoid valve 121 and a second solenoid valve 122 , and the power assembly 130 includes a first self-priming pump 131 and a second self-priming pump 132 .

[0112] One end of the first solenoid valve 121 is connected to one end of the first self-priming pump 131, the other end of the first solenoid valve 121 is connected to the water inlet of the mineralization bin 200, and the other end of the first self-priming pump 131 is used to access a preset water body;

[0113] One end of the second solenoid valve 122 is connected to one end of the second self-priming pump 132 , the other end of the second solenoid valve 122 is connected to the water outlet of the mineralization bin 200 , and the other end of the second self-priming pump 132 is connected to the water storage tank 300 .

[0114] In this embodiment, the preset water body can be raw water, or it can be treated distilled water or pure water. This embodiment does not limit the preset water body, and the connection position of the other end of the first self-priming pump 131 can be adaptively configured according to the needs of the actual application scenario.

[0115] When the first self-priming pump 131 and the first solenoid valve 121 are turned on, a certain amount of preset water can be connected to the water inlet of the mineralization bin 200. The opening time and power of the first self-priming pump 131 can effectively control the flow rate of the preset water. The control component 110 in this embodiment realizes automatic water inflow to the mineralization bin 200 by controlling the opening time of the first self-priming pump 131 and the first solenoid valve 121. It should be noted that the water absorption of the first self-priming pump 131 is equivalent to the water flow of the mineralization bin 200, and the water absorption of the first self-priming pump 131 for performing a mineralized water extraction can be 180-1000 milliliters (ml). It should be noted that the specific value of the water absorption needs to be determined according to the volume of the mineralization bin 200 in the actual application scenario, and is not limited here.

[0116] When the second self-priming pump 132 and the second solenoid valve 122 are turned on, the mineral water in the mineralization bin 200 can be transferred to the water storage tank 300 to store the mineral water. The working principle of the second self-priming pump 132 is the same as that of the first self-priming pump 131, which will not be described in detail here.

[0117] In one embodiment, if Figure 3 As shown, the mineralization control system 100 further includes a heating component 140 , and the heating component 140 is connected to the control component 110 .

[0118] The heating component 140 is disposed between the first solenoid valve 121 and the first self-priming pump 131 , and the heating component 140 is used to heat the water body to a preset temperature according to a target heating instruction.

[0119] In this embodiment, the control component 110 is used to send a target heating instruction to the heating component 140. The target heating instruction includes a preset temperature. The preset temperature can be 40°C-100°C. The specific setting of the preset temperature can be adaptively replaced.

[0120] In this embodiment, the heating component 140 is disposed between the first solenoid valve 121 and the first self-priming pump 131, and can effectively heat the water entering the mineralization bin 200. Since the dissolution rate of the mineralized material in water is mainly determined by the temperature and the dissolution time, in order to accelerate the dissolution rate of the mineralized material in water, such as the dissolution rate of metasilicic acid in water, this embodiment heats the water entering the mineralization bin 200 to a preset temperature, and can more accurately achieve the concentration control of the mineral water. The step of using the heated water to extract the mineral water in this embodiment can also be called thermal extraction.

[0121] In one embodiment, the complete implementation logic of the control component 110 for performing the mineral water extraction step is as follows:

[0122] The control component 110 is used to control the first solenoid valve 121 and the first self-priming pump 131 to open and the second solenoid valve 122 and the second self-priming pump 132 to close if a low liquid level signal is received from the first liquid level detector 310, so that the water body enters the mineralization bin 200 after being heated by the heating component 140;

[0123] When the water volume of the first self-priming pump 131 is greater than or equal to the preset water volume threshold, the first solenoid valve 121 and the first self-priming pump 131 are controlled to be closed, so that the mineralization chamber 200 performs thermal extraction to obtain mineral water of a preset concentration;

[0124] When the thermal extraction time of the mineralization chamber 200 is greater than or equal to the target extraction time, the second solenoid valve 122 and the second self-priming pump 132 are controlled to be opened so that the mineral water in the mineralization chamber 200 is transferred to the water storage tank 300;

[0125] When the opening time of the second self-priming pump 132 is greater than or equal to the preset time, the second solenoid valve 122 and the second self-priming pump 132 are controlled to be closed, and it is determined whether a high liquid level signal sent by the second liquid level detector 320 is received;

[0126] If the high liquid level signal from the second liquid level detector 320 is not received, the execution is skipped to the step of controlling the first solenoid valve 121 and the first self-priming pump 131 to be opened, and the second solenoid valve 122 and the second self-priming pump 132 to be closed, so that the water body enters the mineralization chamber 200 after being heated by the heating component 140;

[0127] If a high liquid level signal is received from the second liquid level detector 320 , the mineral water extraction step is completed.

[0128] In this embodiment, the mineral water extraction step is divided into two parts, namely an extraction part and a transfer part.

[0129] When performing the extraction part, the control component 110 controls the first solenoid valve 121 and the first self-priming pump 131 to open according to the low liquid level signal, and the second solenoid valve 122 and the second self-priming pump 132 are closed. The first self-priming pump 131 allows the preset water body to flow to the heating component, and the preset water body is heated by the heating component. After heating to the preset temperature (40°C-100°C), the hot water passes through the first solenoid valve 121 and the flow component 120 and enters the mineralization chamber 200. When the first self-priming pump 131 detects that the hot water injected into the mineralization chamber 200 reaches the set volume (180-1000ml), the control component 110 controls the first solenoid valve 121 and the first self-priming pump 131 to close. It should be noted that the water pumping flow of the first self-priming pump 131 at this time is the same as the cavity volume in the internal cavity of the mineralization chamber 200. The mineralization chamber 200 performs thermal extraction for a preset time (15s-30min) to obtain mineral water with a certain concentration.

[0130] When executing the transfer part, after the mineralization bin 200 performs the thermal extraction for a preset time, it is confirmed that the thermal extraction is completed. The control component 110 controls the first self-priming pump 131, the heating component and the first solenoid valve 121 to close, and controls the second solenoid valve 122 and the second self-priming pump 132 to open, and the second self-priming pump 132 transfers the mineral water extracted from the mineralization bin 200 to the water storage tank 300. After the second self-priming pump 132 runs for a preset time (10s-60s), the control component 110 controls the second solenoid valve 122 and the second self-priming pump 132 to close. It should be noted that the running time of the second self-priming pump 132 can be determined according to the cavity volume of the mineralization bin 200. At the same time, the running time of the second self-priming pump 132 should not be too long to avoid functional waste. When completing a transfer part, if the control component 110 does not receive a high liquid level signal, the extraction part and the transfer part are re-executed until a high liquid level signal is received.

[0131] In summary, this embodiment provides a mineralization control system 100, which can not only realize the thermal extraction of mineral water, but also timely adjust the extraction time in the thermal extraction logic according to the service life of the mineralization filter element 210, and can accurately control the concentration of mineral water generated by the mineralization equipment. At the same time, this embodiment also sets an atmospheric through hole 230 on the cavity of the mineralization bin 200, so that the mineralization bin 200 can more smoothly realize solid-liquid separation, greatly extending the service life of the mineralization filter element 210.

[0132] In one embodiment, Figure 4 As shown, a mineralization control method is provided, which is applied to Figure 2 The mineralization control system 100 in FIG. 1 is taken as an example to illustrate, and includes the following steps:

[0133] S401, obtaining the historical operating time of the power component;

[0134] S402, determining a target extraction time of the water body in the mineralization chamber according to the historical operation time;

[0135] S403, controlling the valve body assembly and the power assembly to perform the mineral water extraction step according to the target extraction time.

[0136] In one embodiment, if Figure 5 As shown in the figure, the target extraction time of water in the mineralization tank is determined based on the historical operation time, including:

[0137] S501, if the historical running time is less than the first time threshold, determining the target extraction time as the first extraction time;

[0138] S502, if the historical running time is greater than or equal to the first time threshold and less than the second time threshold, determining the target extraction time to be the second extraction time;

[0139] S503: If the historical running time is greater than or equal to the second time threshold, determine the target extraction time as a third extraction time, wherein the first extraction time is less than the second extraction time, and the second extraction time is less than the third extraction time.

[0140] In one embodiment, determining a target extraction time of water in a mineralization chamber based on historical operation time includes:

[0141] If the historical running time increases, the target extraction time is extended according to the corresponding relationship between the increase in the historical running time and the extended time.

[0142] In one embodiment, if Figure 6 As shown, the valve body assembly and the power assembly are controlled according to the target extraction time to perform the mineral water extraction step, including:

[0143] S601, if a low liquid level signal is received from the first liquid level detector, the first solenoid valve and the first self-priming pump are controlled to be turned on, and the second solenoid valve and the second self-priming pump are controlled to be turned off, so that the water body enters the mineralization bin after being heated by the heating component;

[0144] S602, when the water volume of the first self-priming pump is greater than or equal to a preset water volume threshold, the first solenoid valve and the first self-priming pump are controlled to be closed, so that the mineralization chamber performs thermal extraction to obtain mineral water of a preset concentration;

[0145] S603, when the time of thermal extraction in the mineralization bin is greater than or equal to the target extraction time, the second solenoid valve and the second self-priming pump are controlled to be turned on to transfer the mineral water in the mineralization bin to the water storage tank;

[0146] S604, when the opening time of the second self-priming pump is greater than or equal to the preset time, the second solenoid valve and the second self-priming pump are controlled to be closed, and it is determined whether a high liquid level signal from the second liquid level detector is received;

[0147] S605, if the high liquid level signal from the second liquid level detector is not received, jump to the step of controlling the first solenoid valve and the first self-priming pump to open, and the second solenoid valve and the second self-priming pump to close, so that the water body enters the mineralization bin after being heated by the heating component;

[0148] S606: If a high liquid level signal is received from the second liquid level detector, the mineral water extraction step is completed.

[0149] In this embodiment, the specific implementation of the mineralization control method can refer to the specific implementation in the aforementioned system embodiment, which will not be described in detail here.

[0150] In summary, this embodiment provides a mineralization control method, which can not only realize the thermal extraction of mineral water, but also timely adjust the extraction time in the thermal extraction logic according to the service life of the mineralization filter element, and can accurately control the concentration of mineral water generated by the mineralization equipment. At the same time, this embodiment also sets an atmospheric through hole on the cavity of the mineralization bin, so that the mineralization bin can more smoothly achieve solid-liquid separation, greatly extending the service life of the mineralization filter element.

[0151] It should be understood that, although the steps in the flowcharts involved in the above embodiments are displayed in sequence according to the indication of the arrows, these steps are not necessarily executed in sequence according to the order indicated by the arrows. Unless there is a clear explanation in this article, the execution of these steps is not strictly limited in order, and these steps can be executed in other orders. Moreover, at least a part of the steps in the flowcharts involved in the above embodiments may include multiple steps or multiple stages, and these steps or stages are not necessarily executed at the same time, but can be executed at different times, and the execution order of these steps or stages is not necessarily carried out in sequence, but can be executed in turn or alternately with other steps or at least a part of the steps or stages in other steps.

[0152] Based on the same inventive concept, the embodiment of the present application also provides a mineralization control device for implementing the mineralization control method involved above. The implementation scheme for solving the problem provided by the device is similar to the implementation scheme recorded in the above method, so the specific limitations in one or more embodiments of the mineralization control device provided below can refer to the limitations of the mineralization control method above, and will not be repeated here.

[0153] In one embodiment, Figure 7 As shown, a mineralization control device 700 is provided, which is applied to the mineralization control system in the above-mentioned embodiment. The mineralization control device 700 includes: an acquisition module 710, a determination module 720 and an extraction module 730, wherein:

[0154] An acquisition module 710 is used to acquire the historical operating time of the power component;

[0155] A determination module 720, for determining a target extraction time of the water body in the mineralization chamber according to the historical operation time;

[0156] The extraction module 730 is used to control the valve body assembly and the power assembly to perform the mineral water extraction step according to the target extraction time.

[0157] In one embodiment, the determination module 720 is specifically used to determine that the target extraction time is the first extraction time if the historical operation time is less than the first time threshold; if the historical operation time is greater than or equal to the first time threshold and less than the second time threshold, determine the target extraction time is the second extraction time; if the historical operation time is greater than or equal to the second time threshold, determine the target extraction time is the third extraction time, wherein the first extraction time is less than the second extraction time, and the second extraction time is less than the third extraction time.

[0158] In one embodiment, the determination module 720 is specifically configured to extend the target extraction time according to a correspondence between the increase in the historical operation time and the extension time if the historical operation time increases.

[0159] In one embodiment, the extraction module 730 is specifically used to control the first solenoid valve and the first self-priming pump to open, and the second solenoid valve and the second self-priming pump to close if a low liquid level signal is received from the first liquid level detector, so that the water body enters the mineralization bin after being heated by the heating component; when the water pumping volume of the first self-priming pump is greater than or equal to a preset water volume threshold, the first solenoid valve and the first self-priming pump are controlled to close, so that the mineralization bin performs thermal extraction to obtain mineral water of a preset concentration; when the time for thermal extraction in the mineralization bin is greater than or equal to the target extraction time, the second solenoid valve and the second self-priming pump are controlled to close. The pump is turned on to transfer the mineral water in the mineralization bin to the water storage tank; when the opening time of the second self-priming pump is greater than or equal to the preset time, the second solenoid valve and the second self-priming pump are controlled to be closed, and it is determined whether a high liquid level signal from the second liquid level detector is received; if the high liquid level signal from the second liquid level detector is not received, the execution is jumped to control the first solenoid valve and the first self-priming pump to be turned on, and the second solenoid valve and the second self-priming pump to be closed, so that the water body enters the mineralization bin after being heated by the heating component; if the high liquid level signal from the second liquid level detector is received, the mineral water extraction step is completed.

[0160] Each module in the above-mentioned mineralization control device can be implemented in whole or in part by software, hardware or a combination thereof. Each of the above-mentioned modules can be embedded in or independent of a processor in a computer device in the form of hardware, or can be stored in a memory in a computer device in the form of software, so that the processor can call and execute the operations corresponding to each of the above modules.

[0161] In one embodiment, a computer device is provided. The computer device may be a terminal, and its internal structure diagram may be as follows: Figure 8As shown. The computer device includes a processor, a memory, an input / output interface, a communication interface, a display unit and an input device. Among them, the processor, the memory and the input / output interface are connected through a system bus, and the communication interface, the display unit and the input device are connected to the system bus through the input / output interface. Among them, the processor of the computer device is used to provide computing and control capabilities. The memory of the computer device includes a non-volatile storage medium and an internal memory. The non-volatile storage medium stores an operating system and a computer program. The internal memory provides an environment for the operation of the operating system and the computer program in the non-volatile storage medium. The input / output interface of the computer device is used to exchange information between the processor and the external device. The communication interface of the computer device is used to communicate with an external terminal in a wired or wireless manner, and the wireless manner can be implemented through WIFI, a mobile cellular network, NFC (near field communication) or other technologies. When the computer program is executed by the processor, a mineralization control method is implemented. The display unit of the computer device is used to form a visually visible picture, which can be a display screen, a projection device or a virtual reality imaging device. The display screen can be a liquid crystal display screen or an electronic ink display screen, and the input device of the computer device can be a touch layer covering the display screen, or a button, trackball or touchpad set on the computer device shell, or an external keyboard, touchpad or mouse.

[0162] Those skilled in the art will understand that Figure 8 The structure shown in the figure is only a block diagram of a part of the structure related to the solution of the present application, and does not constitute a limitation on the computer device to which the solution of the present application is applied. The specific computer device may include more or fewer components than those shown in the figure, or combine certain components, or have a different arrangement of components.

[0163] In one embodiment, a computer device is provided, including a memory and a processor, wherein a computer program is stored in the memory, and when the processor executes the computer program, the following steps are implemented:

[0164] Get the historical running time of the power component;

[0165] Determine the target extraction time of water in the mineralization chamber based on historical operation time;

[0166] The valve body component and the power component are controlled according to the target extraction time to execute the mineral water extraction step.

[0167] In one embodiment, a computer readable storage medium is provided, on which a computer program is stored, and when the computer program is executed by a processor, the following steps are implemented:

[0168] Get the historical running time of the power component;

[0169] Determine the target extraction time of water in the mineralization chamber based on historical operation time;

[0170] The valve body component and the power component are controlled according to the target extraction time to execute the mineral water extraction step.

[0171] In one embodiment, a computer program product is provided, comprising a computer program, which, when executed by a processor, implements the following steps:

[0172] Get the historical running time of the power component;

[0173] Determine the target extraction time of water in the mineralization chamber based on historical operation time;

[0174] The valve body component and the power component are controlled according to the target extraction time to execute the mineral water extraction step.

[0175] Those skilled in the art can understand that all or part of the processes in the above-mentioned embodiment methods can be completed by instructing the relevant hardware through a computer program, and the computer program can be stored in a non-volatile computer-readable storage medium. When the computer program is executed, it can include the processes of the embodiments of the above-mentioned methods. Among them, any reference to the memory, database or other medium used in the embodiments provided in this application can include at least one of non-volatile and volatile memory. Non-volatile memory can include read-only memory (ROM), magnetic tape, floppy disk, flash memory, optical memory, high-density embedded non-volatile memory, resistive random access memory (ReRAM), magnetoresistive random access memory (MRAM), ferroelectric random access memory (FRAM), phase change memory (PCM), graphene memory, etc. Volatile memory can include random access memory (RAM) or external cache memory, etc. As an illustration and not limitation, RAM can be in various forms, such as static random access memory (SRAM) or dynamic random access memory (DRAM). The database involved in each embodiment provided in this application may include at least one of a relational database and a non-relational database. Non-relational databases may include distributed databases based on blockchains, etc., but are not limited to this. The processor involved in each embodiment provided in this application may be a general-purpose processor, a central processing unit, a graphics processor, a digital signal processor, a programmable logic device, a data processing logic device based on quantum computing, etc., but are not limited to this.

[0176] The technical features of the above embodiments may be combined arbitrarily. To make the description concise, not all possible combinations of the technical features in the above embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.

[0177] The above-described embodiments only express several implementation methods of the present application, and the descriptions thereof are relatively specific and detailed, but they cannot be understood as limiting the scope of the present application. It should be pointed out that, for a person of ordinary skill in the art, several variations and improvements can be made without departing from the concept of the present application, and these all belong to the protection scope of the present application. Therefore, the protection scope of the present application shall be subject to the attached claims.

Claims

1. A mineralization control system, characterized in that: Applied to a mineralization device, the mineralization device includes a mineralization bin; the system includes: a control component, a valve body component and a power component, wherein the control component is connected to the valve body component and the power component respectively; The valve body assembly is respectively arranged at the water inlet of the mineralization bin and the water outlet of the mineralization bin, and the valve body assembly is used to control the flow state of the water body; The power assembly is connected to the valve body assembly, and the power assembly is used to control the water to flow in a corresponding direction; The control component is used to obtain the historical operating time of the power component; determine the target extraction time of the water body in the mineralization chamber according to the historical operating time; and control the valve body component and the power component to perform the mineral water extraction step according to the target extraction time.

2. The system according to claim 1, characterized in that The control component is used to determine the target extraction time as a first extraction time if the historical running time is less than a first time threshold; If the historical running time is greater than or equal to the first time threshold and less than the second time threshold, determining the target extraction time to be the second extraction time; If the historical running time is greater than or equal to a second time threshold, the target extraction time is determined to be a third extraction time, wherein the first extraction time is less than the second extraction time, and the second extraction time is less than the third extraction time.

3. The system according to claim 1, characterized in that The control component is used for extending the target extraction time according to the correspondence between the increase amount of the historical operation time and the extension time if the historical operation time increases.

4. The system according to any one of claims 1 to 3, characterized in that: The system further comprises: an alarm component; The control component is used to control the alarm component to alarm when the historical operating time is greater than or equal to the alarm time threshold, so as to prompt the user to replace the filter element.

5. The system according to claim 1, characterized in that The mineralization equipment further comprises a water tank, wherein a first liquid level detector and a second liquid level detector are arranged in the water tank, and the first liquid level detector and the second liquid level detector are both connected to the control component; The control component is used to control the valve body component and the power component to perform the mineral water extraction step if a low liquid level signal is received from the first liquid level detector; The control component is used to control the valve body component and the power component to stop executing the mineral water extraction step if a high liquid level signal is received from the second liquid level detector.

6. The system according to claim 5, characterized in that The valve body assembly includes a first solenoid valve and a second solenoid valve, and the power assembly includes a first self-priming pump and a second self-priming pump; One end of the first solenoid valve is connected to one end of the first self-priming pump, the other end of the first solenoid valve is connected to the water inlet of the mineralization bin, and the other end of the first self-priming pump is used to access a preset water body; One end of the second solenoid valve is connected to one end of the second self-priming pump, the other end of the second solenoid valve is connected to the water outlet of the mineralization bin, and the other end of the second self-priming pump is connected to the water storage tank.

7. The system according to claim 6, characterized in that The system also includes: a heating component; The heating component is arranged between the first solenoid valve and the first self-priming pump, the heating component is connected to the control component, and the heating component is used to heat the water body to a preset temperature according to a target heating instruction.

8. The system according to claim 7, characterized in that The control component is used to control the first solenoid valve and the first self-priming pump to open, and the second solenoid valve and the second self-priming pump to close, if a low liquid level signal is received from the first liquid level detector, so that the water enters the mineralization bin after being heated by the heating component; When the water volume of the first self-priming pump is greater than or equal to a preset water volume threshold, the first solenoid valve and the first self-priming pump are controlled to be closed, so that the mineralization bin performs thermal extraction to obtain mineral water of a preset concentration; When the thermal extraction time of the mineralization bin is greater than or equal to the target extraction time, the second solenoid valve and the second self-priming pump are controlled to open so that the mineral water in the mineralization bin is transferred to the water storage tank; When the opening time of the second self-priming pump is greater than or equal to the preset time, the second solenoid valve and the second self-priming pump are controlled to be closed, and it is determined whether a high liquid level signal sent by the second liquid level detector is received; If no high liquid level signal is received from the second liquid level detector, the execution is skipped to the step of controlling the first solenoid valve and the first self-priming pump to be turned on, and the second solenoid valve and the second self-priming pump to be turned off, so that the water enters the mineralization bin after being heated by the heating component; If a high liquid level signal is received from the second liquid level detector, the mineral water extraction step is completed.

9. The system according to claim 5, characterized in that The control component is used to determine a target extraction time of water in the mineralization bin according to the historical operation time of the second self-priming pump, wherein the longer the historical operation time of the second self-priming pump is, the longer the target extraction time is.

10. The system according to claim 5, characterized in that The mineralization bin comprises a mineralization filter element and a membrane shell. The membrane shell is provided with an atmospheric through hole, and the atmospheric through hole is used to balance the pressure inside the mineralization bin with the external air pressure.

11. A mineralization control method, characterized in that: The mineralization control system applied to any one of claims 1 to 10 comprises: Get the historical running time of the power component; Determining a target extraction time of the water body in the mineralization chamber according to the historical operation time; The valve body assembly and the power assembly are controlled according to the target extraction time to perform the mineral water extraction step.

12. The method according to claim 11, characterized in that Determining the target extraction time of the water body in the mineralization bin according to the historical operation time includes: If the historical running time is less than the first time threshold, determining the target extraction time as the first extraction time; If the historical running time is greater than or equal to the first time threshold and less than the second time threshold, determining the target extraction time to be the second extraction time; If the historical running time is greater than or equal to a second time threshold, the target extraction time is determined to be a third extraction time, wherein the first extraction time is less than the second extraction time, and the second extraction time is less than the third extraction time.

13. The method according to claim 11, characterized in that Determining the target extraction time of the water body in the mineralization bin according to the historical operation time includes: If the historical running time increases, the target extraction time is extended according to the corresponding relationship between the increase in the historical running time and the extended time.

14. The method according to claim 11, characterized in that The step of controlling the valve body assembly and the power assembly to perform the mineral water extraction step according to the target extraction time includes: If a low liquid level signal is received from the first liquid level detector, the first solenoid valve and the first self-priming pump are controlled to be opened, and the second solenoid valve and the second self-priming pump are controlled to be closed, so that the water body enters the mineralization bin after being heated by the heating component; When the water volume of the first self-priming pump is greater than or equal to a preset water volume threshold, the first solenoid valve and the first self-priming pump are controlled to be closed, so that the mineralization bin performs thermal extraction to obtain mineral water of a preset concentration; When the thermal extraction time of the mineralization bin is greater than or equal to the target extraction time, the second solenoid valve and the second self-priming pump are controlled to open so that the mineral water in the mineralization bin is transferred to the water storage tank; When the opening time of the second self-priming pump is greater than or equal to the preset time, the second solenoid valve and the second self-priming pump are controlled to be closed, and it is determined whether a high liquid level signal sent by the second liquid level detector is received; If no high liquid level signal is received from the second liquid level detector, the execution is skipped to the step of controlling the first solenoid valve and the first self-priming pump to be turned on, and the second solenoid valve and the second self-priming pump to be turned off, so that the water enters the mineralization bin after being heated by the heating component; If a high liquid level signal is received from the second liquid level detector, the mineral water extraction step is completed.

15. A mineralization control device, characterized in that: The mineralization control system applied to any one of claims 1 to 10 comprises: An acquisition module, used for acquiring the historical running time of the power component; A determination module, used to determine a target extraction time of the water body in the mineralization bin according to the historical operation time; The extraction module is used to control the valve body component and the power component to perform the mineral water extraction step according to the target extraction time.

16. A mineralization device, characterized in that: It comprises the mineralization control system, mineralization bin and water storage tank as described in any one of claims 1 to 10.

17. The device according to claim 16, characterized in that The mineralization bin comprises a mineralization filter element and a membrane shell. The membrane shell is provided with an atmospheric through hole, and the atmospheric through hole is used to balance the pressure inside the mineralization bin with the external air pressure.

Citation Information

Patent Citations

  • Warning method and warning system for filter elements of water purifiers

    CN108264106A

  • Water supply equipment and control method thereof

    CN117383679A

  • Mineralization control system, method and device and mineralization equipment

    CN119235166A

  • Clearing machine with a unit in use for displaying use state of filter element

    CN1915841A