Horizontal hoisting method for reinforced concrete beam section

By setting up handles and counterweight devices on the reinforced concrete beam section, combined with lifting holes and ferrules, the problems of cumbersome and safety risks of beam section lifting in the existing technology are solved, and a simple, safe and flexible horizontal lifting of beam sections is achieved. process.

CN119240520APending Publication Date: 2025-01-03HUBEI UNIV OF TECH +2
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411343788.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-25
Publication Date
2025-01-03

AI Technical Summary

Technical Problem

The lifting process of the existing reinforced concrete beam sections is cumbersome and has safety risks, making it difficult to ensure that the beam sections remain in a horizontal state during the lifting process.

Method used

The horizontal lifting method of reinforced concrete beam section is adopted. By setting up handles and counterweight devices on the outside of the beam section, the horizontal or longitudinal lifting holes and ferrules are used for lifting, and the crane hook and load bag are adjusted to ensure horizontal lifting of the beam section, and Fluency is judged by transparent hose and fine-tune the balance of the counterweight device.

Benefits of technology

The lifting process is simplified, the safety is improved, and it is suitable for beam sections of different lengths, reducing costs and ensuring the smooth progress of horizontal lifting of beam sections.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119240520A_ABST
    Figure CN119240520A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of constructional engineering, and discloses a horizontal hoisting method of a reinforced concrete beam section, which comprises the reinforced concrete beam section, a lifting handle and a counterweight bag, during hoisting, a lifting handle ferrule is fixed on a reinforcing steel bar inserted into the beam section, and the lifting handle is hooked by a crane hook and hoisted; whether the two ends or the two sides of the beam section are horizontal or not is observed through the transparent water pipe, and if inclination exists, the counterweight bag is placed, and leveling is achieved by adjusting the position and the weight of the counterweight bag. The lifting device provided by the invention is simple in design, can be repeatedly used, can be suitable for lifting reinforced concrete beam sections with different lengths through different bending degrees of the lifting handle, and is flexible to use; the hoisting process is simplified, the problem of slight inclination caused by improper operation is solved through the fine adjustment of the counterweight device, smooth horizontal hoisting of the beam section is ensured, and the hoisting safety and accuracy are improved; used materials can be obtained locally, manufacturing is convenient, and the hoisting cost is low.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of construction engineering, in particular to a method for horizontally hoisting a reinforced concrete beam segment. Background Art

[0002] Reinforced concrete beams are beams made of reinforced concrete materials. Reinforced concrete beams can be made into independent beams, or they can be made into beam-slab floor slabs with reinforced concrete slabs, or they can be made into single-layer or multi-layer frames with reinforced concrete columns. Reinforced concrete beams come in various forms and are the most basic load-bearing components in engineering structures such as house construction and bridge construction, with a wide range of applications.

[0003] Prefabricated reinforced concrete buildings and bridge projects often involve beam segment lifting operations. Due to the needs of installation and docking, many occasions require the lifting of beam segments or column segments to remain horizontal. How to ensure the horizontal lifting posture of the beam segment while ensuring safety is an engineering problem that needs to be solved urgently. Therefore, a horizontal lifting method for reinforced concrete beam segments is proposed to solve the above problem. Summary of the invention

[0004] 1. Technical issues to be resolved In view of the deficiencies in the prior art, the present invention provides a method for horizontally lifting reinforced concrete beam sections, which has the advantages of convenient and safe lifting, and solves the problems of cumbersome and safety-risky lifting of existing beam sections.

[0005] (II) Technical solution To achieve the above-mentioned purpose, the present invention provides the following technical solutions: a method for horizontally hoisting a reinforced concrete beam segment, comprising a reinforced concrete beam segment and a handle disposed on the outside thereof, a counterweight device disposed on the outside of the reinforced concrete beam segment, transverse hoisting holes disposed on both ends of the side surfaces of the reinforced concrete beam segment, steel bars extending out of the holes disposed inside the transverse hoisting holes, and rings disposed on the four ends of the handle, wherein the steps for hoisting the reinforced concrete beam segment are as follows: Step 1: Put the ring of the handle on the steel bar outside the horizontal lifting hole, and tie the ring to the steel bar, and hook the crane hook on the middle intersection of the handle; Step 2: Slowly lift the reinforced concrete beam section and observe whether it is level; Step 3: If tilt occurs, place a counterweight device on the reinforced concrete beam section and level the reinforced concrete beam section by adjusting the counterweight device and its position.

[0006] Preferably, it comprises a reinforced concrete beam section and a handle arranged on the outside thereof, a counterweight device is arranged on the outside of the reinforced concrete beam section, longitudinal lifting holes are arranged on both end surfaces of the reinforced concrete beam section, and the longitudinal lifting holes are provided with steel bars extending out of the holes, and rings are arranged at the four ends of the handle. The steps of lifting the reinforced concrete beam section are as follows: Step 1: Put the ring of the handle on the steel bar outside the longitudinal lifting hole, and tie the ring to the steel bar, and hook the crane hook on the middle intersection of the handle; Step 2: Slowly lift the reinforced concrete beam section and observe whether it is level; Step 3: If tilt occurs, place a counterweight device on the reinforced concrete beam section and level the reinforced concrete beam section by adjusting the counterweight device and its position.

[0007] Preferably, the counterweight device consists of a sling and a carrying bag, and the number of the slings and the carrying bag are two. The two slings are placed on the top of the reinforced concrete beam section, and the carrying bags are fixedly installed at both ends of the sling. The carrying bags are located on both sides of the reinforced concrete beam section, and the two slings are parallel to each other and perpendicular to the longitudinal axis of the reinforced concrete beam section.

[0008] Preferably, the method for judging whether the reinforced concrete beam section is horizontal in the step 2 is: when the reinforced concrete beam section is slowly hoisted, a transparent hose whose length exceeds the length of the reinforced concrete beam section is selected, a sufficient amount of water is injected into the hose, and the water surface at one end of the hose is kept flush with the center of the upper edge of one end of the reinforced concrete beam section, and the water surface at the other end of the hose is checked to see whether it is flush with the center of the upper edge of the other end of the reinforced concrete beam section, thereby judging whether the two ends of the reinforced concrete beam section are flush; The method for judging whether the two sides of the reinforced concrete beam section are horizontal in the step 2 is as follows: when the reinforced concrete beam section is slowly lifted, a transparent hose whose length exceeds the width of the reinforced concrete beam section is selected, a sufficient amount of water is injected into the hose, and the water surface at one end of the hose is kept flush with the center of the upper edge of one side of the reinforced concrete beam section, and the water surface at the other end of the hose is checked to see whether it is flush with the center of the upper edge of the other side of the reinforced concrete beam section, thereby judging whether the two sides of the reinforced concrete beam section are flush.

[0009] Preferably, the ferrule is put on the steel bar, and the ferrule is fixedly connected to the steel bar by a cross-binding method.

[0010] Preferably, a U-shaped clamping ring is provided on the outside of the steel bar, a hand-tightened bolt is threadedly installed on the end of the U-shaped clamping ring, and the ring is located between the U-shaped clamping ring and the reinforced concrete beam section.

[0011] Preferably, the distances from all transverse lifting holes to the upper surface and end faces of the reinforced concrete beam section are equal, and the distances from all longitudinal lifting holes to the upper surface and side faces of the reinforced concrete beam section are equal.

[0012] Preferably, the distance from the transverse hoisting hole and the longitudinal hoisting hole to the upper surface of the reinforced concrete beam section is smaller than the distance to the lower surface of the reinforced concrete beam section, and the transverse hoisting hole and the longitudinal hoisting hole are through holes or blind holes.

[0013] Preferably, the handle is formed by binding two steel bars or steel wire ropes at the middle junction.

[0014] Preferably, the method for adjusting the counterweight device and its position to level the reinforced concrete beam section is as follows: When one end of the reinforced concrete beam section is tilted, the counterweight device needs to be moved to that end, and weights of the same weight need to be added to the bags on both sides to adjust the balance; When one side of the reinforced concrete beam section is tilted, place the counterweight device in the middle and add a counterweight to the carrier bag on that side to adjust the balance; When one end of a reinforced concrete beam section and any side of the end are warped, the counterweight device needs to be moved to the end, and counterweight material needs to be added to the carrier bag on the warped side to adjust the balance.

[0015] Beneficial Effects Compared with the prior art, the present invention provides a method for horizontally lifting reinforced concrete beam sections, which has the following beneficial effects: 1. The horizontal lifting method of reinforced concrete beam segments makes the lifting device design simple and reusable. Through the different bending degrees of the handle, it can be applied to the lifting of reinforced concrete beam segments of different lengths, and the flexibility of use is better; 2. This method of horizontal lifting of reinforced concrete beam sections not only simplifies the lifting process, but also solves the problem of slight tilt caused by improper operation by fine-tuning the counterweight device, ensuring the smooth horizontal lifting of the beam section and making the lifting safer; 3. The method for horizontally lifting reinforced concrete beam sections uses simple materials, which can be obtained locally and are easy to manufacture, making the lifting cost low. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 This is a schematic diagram of the transverse lifting connection between the handle and the reinforced concrete beam section of the present invention; Figure 2 This is a schematic diagram of the longitudinal lifting connection between the handle and the reinforced concrete beam section of the present invention; Figure 3 This is a schematic diagram of the connection between the handle of the present invention and the crane hook.

[0017] As shown in the figure: 1. Reinforced concrete beam section; 101. Horizontal lifting hole; 102. Longitudinal lifting hole; 2. Handle; 201. Ring; 3. Counterweight device; 301. Sling; 302. Carrying bag; 4. Rebar; 5. Crane hook. DETAILED DESCRIPTION

[0018] The following will be combined with the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0019] like Figure 1-3 As shown, the method for horizontally lifting a reinforced concrete beam segment includes a reinforced concrete beam segment 1 and a handle 2 arranged outside the reinforced concrete beam segment 1. A counterweight device 3 is arranged outside the reinforced concrete beam segment 1. Both end sides of the reinforced concrete beam segment 1 are provided with transverse lifting holes 101. The inside of the transverse lifting hole 101 is provided with a steel bar 4 extending out of the hole. The four ends of the handle 2 are provided with rings 201. The lifting steps of the reinforced concrete beam segment 1 are as follows: Step 1: Put the ring 201 of the handle 2 on the steel bar 4 outside the horizontal lifting hole 101, and tie the ring 201 and the steel bar 4 together, and hook the crane hook 5 on the middle intersection of the handle 2; Step 2: slowly lift the reinforced concrete beam section 1 and observe whether it is level; Step 3: If tilt occurs, place a counterweight device 3 on the reinforced concrete beam segment 1, and level the reinforced concrete beam segment 1 by adjusting the counterweight device 3 and its position.

[0020] In this embodiment, the counterweight device 3 is composed of a sling 301 and a carrying bag 302. The number of the slings 301 and the carrying bag 302 are both two. The two slings 301 are placed on the top of the reinforced concrete beam section 1. The carrying bags 302 are fixedly installed on the left and right ends of the bottom of the sling 301. The carrying bags 302 are located on the left and right sides of the reinforced concrete beam section 1. The two slings 301 are parallel to each other and perpendicular to the longitudinal axis of the reinforced concrete beam section 1.

[0021] Specifically, when one end of the reinforced concrete beam section 1 and any side of the end are warped, the counterweight device 3 needs to be moved to the end, and the counterweight material needs to be added to the carrier bag 3 on the warped side to adjust the balance.

[0022] The weight material filled in the carrying bag 3 can be made from local materials, such as bricks or stones; the handle 2 is formed by two steel bars or steel wire ropes tied together at the intersection in the middle.

[0023] In this embodiment, the ring 201 is put on the steel bar 4, and the ring 201 is fixedly connected to the steel bar 4 by a cross-binding method. A U-shaped clamping ring is arranged on the outside of the steel bar 4, and a hand-tightened bolt is threadedly installed on the end of the U-shaped clamping ring. The ring 201 is located between the U-shaped clamping ring and the reinforced concrete beam section 1.

[0024] It should be noted that after the ring 201 is tied to the steel bar 4, the U-shaped clamp can be fixed on the steel bar 4 and the ring 201 can be shielded by manually tightening the hand bolt, so as to avoid the ring 201 from shifting on the steel bar 4 during the lifting of the reinforced concrete beam section 1, thereby making the lifting of the reinforced concrete beam section 1 safer.

[0025] In this embodiment, the method for judging whether the reinforced concrete beam section 1 is horizontal in step 2 is as follows: when the reinforced concrete beam section 1 is slowly lifted, a transparent hose whose length exceeds the length of the reinforced concrete beam section 1 is selected, and a sufficient amount of water is injected into the hose, and the water surface at one end of the hose is kept flush with the center of the upper edge of one end of the reinforced concrete beam section 1, and the water surface at the other end of the hose is checked to see whether it is flush with the center of the upper edge of the other end of the reinforced concrete beam section 1, thereby judging whether the two ends of the reinforced concrete beam section 1 are flush; The method for judging whether both sides of the reinforced concrete beam segment 1 are horizontal in step 2 is as follows: when the reinforced concrete beam segment 1 is slowly lifted, a transparent hose whose length exceeds the width of the reinforced concrete beam segment 1 is selected, sufficient water is injected into the hose, and the water surface at one end of the hose is kept flush with the center of the upper edge of one side of the reinforced concrete beam segment 1, and the water surface at the other end of the hose is checked to see whether it is flush with the center of the upper edge of the other side of the reinforced concrete beam segment 1, thereby judging whether both sides of the reinforced concrete beam segment 1 are flush.

[0026] In this embodiment, on the basis of embodiment 1, the present invention provides a technical solution: a method for horizontally lifting a reinforced concrete beam segment, comprising a reinforced concrete beam segment 1 and a handle 2 arranged outside the reinforced concrete beam segment 1, a counterweight device 3 is arranged outside the reinforced concrete beam segment 1, longitudinal lifting holes 102 are arranged at both end surfaces of the reinforced concrete beam segment 1, and the longitudinal lifting holes 102 are provided with steel bars 4 extending out of the holes, and rings 201 are arranged at the four ends of the handle 2. The lifting steps of the reinforced concrete beam segment 1 are as follows: Step 1: Put the ring 201 of the handle 2 on the steel bar 4 outside the longitudinal lifting hole 102, and tie the ring 201 and the steel bar 4 together, and hook the crane hook 5 on the middle intersection of the handle 2; Step 2: slowly lift the reinforced concrete beam section 1 and observe whether it is level; Step 3: If tilt occurs, place a counterweight device 3 on the reinforced concrete beam segment 1, and level the reinforced concrete beam segment 1 by adjusting the counterweight device 3 and its position.

[0027] In this embodiment, the method for adjusting the counterweight device 3 and its position to level the reinforced concrete beam segment 1 is as follows: When one end of the reinforced concrete beam section 1 is tilted, the counterweight device 3 needs to be moved to that end, and weights of the same weight need to be added to the carrying bags 3 on both sides to adjust the balance; When one side of the reinforced concrete beam section 1 is tilted, the counterweight device 3 is placed in the middle, and a counterweight needs to be added to the carrier bag 302 on that side to adjust the balance; When one end of the reinforced concrete beam section 1 and any side of the end are warped, the counterweight device 3 needs to be moved to the end, and counterweight material needs to be added to the carrier bag 3 on the warped side to adjust the balance.

[0028] It should be noted that the handle 2 is made of steel wire rope or steel bar material, the ferrule 201 is formed by processing and welding the end of the handle 2 using a three-two splicing method, and the four ferrules 201 are of the same size.

[0029] The reinforced concrete beam section 1 can be prepared by prefabrication or on-site cutting. During prefabrication, embedded holes need to be set in the reinforced concrete beam section 1. During on-site cutting, drilling is required.

[0030] In addition, the distances from the transverse lifting hole 101 to the upper surface and end face of the reinforced concrete beam segment 1 are equal, the distances from the longitudinal lifting hole 102 to the upper surface and side face of the reinforced concrete beam segment 1 are equal, the distances from the transverse lifting hole 101 and the longitudinal lifting hole 102 to the upper surface of the reinforced concrete beam segment 1 are smaller than the distances to the lower surface of the reinforced concrete beam segment 1, and the transverse lifting hole 101 and the longitudinal lifting hole 102 can be through holes or blind holes.

[0031] Example 1 A city road bridge project aims to expand a main road bridge in the city to improve traffic flow and safety. The total length of the bridge is 100m and the width of the bridge deck is 15m. The entire project requires the hoisting of 20 prefabricated reinforced concrete beam segments 1. Each reinforced concrete beam segment 1 is 6m long, 1.5m wide, 0.5m high, and weighs about 3t.

[0032] 1) The reinforced concrete beam segment 1 is prefabricated in the factory, wherein two rows of 3 holes in each row, a total of 6 holes, with a diameter of 36 mm are set at the ends and sides of the two ends. The uppermost hole for inserting reinforcement is 0.2 m away from the top surface of the beam. HPB400 reinforcements are inserted into the holes for inserting reinforcements, and both sides of the reinforcements extend out of the holes by 0.3 m. 2) Select two steel wire ropes with a length of 7.4m and a diameter of 20mm, tie them with 4mm galvanized iron wire at the intersection in the middle, and reserve 120mm at both ends, and use the three-two splicing method to obtain a ring 201 with a diameter of about 38mm to form a handle 2; 3) Put the ring 201 at the end of the handle 2 onto the steel bar 4 outside the insertion hole, and tie the ring 201 and the steel bar 4 with a galvanized iron wire with a diameter of 4mm; 4) Use a crane hook 5 with a load-bearing capacity of 5 tons to hook the handle 2 and slowly lift it up, select a transparent hose with a length of 7 meters and a diameter of 15 mm, fill it with water, and place it at both ends of the reinforced concrete beam segment 1, and at the same time place a counterweight device 3 horizontally on the reinforced concrete beam segment 1; 5) Observe the water in the hose and the upper surface of the reinforced concrete beam segment 1 to determine whether it is horizontal. It is found that one end of the reinforced concrete beam segment 1 sinks and the center of gravity shifts to one end; 6) Place the counterweight device 3 at the raised end of the reinforced concrete beam section 1, and add the same counterweight to the two carrier bags 302 until the reinforced concrete beam section 1 is horizontal.

[0033] 7) Repeat steps 3), 4), 5) and 6) to complete the subsequent lifting.

[0034] Example 2 Due to the long service life of an old factory building, an assessment by a professional organization revealed that some of its structures had potential safety hazards, especially some load-bearing beams had aged to varying degrees. In order to ensure production safety, it was decided to reinforce and renovate the factory building. The main work included dismantling some old beam sections, drilling holes in the beam sections and inserting reinforcement bars at key locations. The beam sections were 5m long, 1.2m wide and 0.5m high.

[0035] 1) Complete the prefabrication of reinforced concrete beam segment 1 in the factory, punch holes at both ends or both sides of reinforced concrete beam segment 1, set two rows, 3 holes in each row, a total of 6, 36mm diameter transverse lifting holes 101 or longitudinal lifting holes 102 (i.e., reinforcement holes), the uppermost reinforcement hole is 0.2m away from the top surface of the beam, insert HPB400 reinforcement 4 into the reinforcement hole, and both sides of the reinforcement 4 extend out of the hole by 0.4m; 2) Select two steel wire ropes with a length of 6.4m and a diameter of 20mm, tie them with 4mm galvanized iron wire at the intersection in the middle, and reserve 120mm at both ends, and use the three-two splicing method to obtain a ring 201 with a diameter of about 38mm to form a handle 2; 3) Put the ring 201 at the end of the handle 2 onto the steel bar 4 outside the insertion hole, and tie the ring 201 and the steel bar 4 with a galvanized iron wire with a diameter of 4mm; 4) Use a crane hook 5 with a load-bearing capacity of 5 tons to hook the handle 2 and slowly lift it up, select a transparent hose with a length of 2m and a diameter of 15mm, fill it with water, and place it on both sides of the reinforced concrete beam segment 1, and at the same time place a counterweight device 3 horizontally on the reinforced concrete beam segment 1; 5) Observe the water in the hose and the upper surface of the reinforced concrete beam segment 1 to determine whether it is horizontal. It is found that one side of the reinforced concrete beam segment 1 sinks and the center of gravity shifts to one side; 6) Place a counterweight device 3 on the top of the reinforced concrete beam section 1, and add counterweight to the tilted side loading bag 302 until the reinforced concrete beam section 1 is level.

[0036] 7) Repeat steps 3), 4), 5) and 6) to complete the subsequent lifting.

[0037] Example 3 A foundation pit support beam section project involves the foundation pit support work of a high-rise building. The total depth of the foundation pit is 15m and the width is 20m. In order to ensure the safety and stability of the foundation pit, the project requires the hoisting of 15 prefabricated reinforced concrete support beam sections. Each beam section is 6m long, 1m wide, 0.5m high and weighs 2.5t.

[0038] 1) Complete the prefabrication of reinforced concrete beam segment 1 in the factory, punch holes at both ends or both sides of reinforced concrete beam segment 1, set two rows, 3 holes in each row, a total of 6, 36mm diameter transverse lifting holes 101 or longitudinal lifting holes 102 (i.e., reinforcement holes), the uppermost reinforcement hole is 0.2m away from the top surface of the beam, insert HPB400 reinforcement 4 into the reinforcement hole, and both sides of the reinforcement 4 extend out of the hole by 0.4m; 2) Select two steel wire ropes with a length of 7.2m and a diameter of 20mm, tie them with 4mm galvanized iron wire at the intersection in the middle, and reserve 120mm at both ends, and use the three-two splicing method to obtain a ring 201 with a diameter of about 38mm to form a handle 2; 3) Put the ring 201 at the end of the handle 2 onto the steel bar 4 outside the insertion hole, and tie the ring 201 and the steel bar 4 with a galvanized iron wire with a diameter of 4mm; 4) Use a crane hook 5 with a load-bearing capacity of 5 tons to hook the handle 2 and slowly lift it up. Select two transparent hoses, one with a length of 7 meters and a diameter of 15 mm, and the other with a length of 2 meters and a diameter of 15 mm. Fill them with water, place the 7-meter-long transparent hose at both ends of the reinforced concrete beam segment 1, and place the 2-meter-long transparent hose on both sides of the reinforced concrete beam segment 1. At the same time, place a counterweight device 3 horizontally on the reinforced concrete beam segment 1; 5) Observe the water in the hose and the upper surface of the reinforced concrete beam segment 1 to determine whether it is horizontal. It is found that one end of the reinforced concrete beam segment 1 sinks and one side sinks, causing the center of gravity to shift to one end. At the same time, the center of gravity shifts to one side. 6) Place the counterweight device 3 at the raised end of the reinforced concrete beam section 1, and add different counterweights to the two carrier bags 302 until the reinforced concrete beam section 1 is horizontal.

[0039] 7) Repeat steps 3), 4), 5) and 6) to complete the subsequent lifting.

[0040] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A method for horizontally lifting a reinforced concrete beam segment, comprising a reinforced concrete beam segment (1) and a handle (2) arranged outside the reinforced concrete beam segment, characterized in that: The reinforced concrete beam section (1) is provided with a counterweight device (3) on the outside, the handle (2) is provided with a crane hook (5) on the outside, the two end sides of the reinforced concrete beam section (1) are provided with transverse lifting holes (101), the inside of the transverse lifting holes (101) is provided with steel bars (4) extending out of the holes, and the four ends of the handle (2) are provided with rings (201). The steps of lifting the reinforced concrete beam section (1) are as follows: Step 1: Put the ring (201) of the handle (2) on the steel bar (4) outside the horizontal lifting hole (101), and tie the ring (201) and the steel bar (4) together, and hook the crane hook (5) on the middle intersection of the handle (2); Step 2: slowly lift the reinforced concrete beam section (1) and observe whether it is level; Step 3: If tilting occurs, a counterweight device (3) is placed on the reinforced concrete beam section (1), and the reinforced concrete beam section (1) is leveled by adjusting the counterweight device (3) and its position.

2. The method for horizontally lifting a reinforced concrete beam segment according to claim 1, comprising a reinforced concrete beam segment (1) and a handle (2) arranged outside the reinforced concrete beam segment, characterized in that: The reinforced concrete beam section (1) is provided with a counterweight device (3) on the outside, and longitudinal hoisting holes (102) are provided on both end surfaces of the reinforced concrete beam section (1). The longitudinal hoisting holes (102) are provided with steel bars (4) extending out of the holes, and the four ends of the handle (2) are provided with ferrules (201). The steps for hoisting the reinforced concrete beam section (1) are as follows: Step 1: Put the ring (201) of the handle (2) on the steel bar (4) outside the longitudinal lifting hole (102), and tie the ring (201) and the steel bar (4) together, and hook the crane hook (5) on the middle intersection of the handle (2); Step 2: slowly lift the reinforced concrete beam section (1) and observe whether it is level; Step 3: If tilting occurs, a counterweight device (3) is placed on the reinforced concrete beam section (1), and the reinforced concrete beam section (1) is leveled by adjusting the counterweight device (3) and its position.

3. The method for horizontally hoisting a reinforced concrete beam segment according to any one of claims 1 or 2, characterized in that: The counterweight device (3) is composed of a sling (301) and a carrying bag (302). The number of the sling (301) and the carrying bag (302) is two. The two slings (301) are placed on the top of the reinforced concrete beam section (1). The carrying bags (302) are fixedly installed at both ends of the sling (301). The carrying bags (302) are located on both sides of the reinforced concrete beam section (1). The two slings (301) are parallel to each other and perpendicular to the longitudinal axis of the reinforced concrete beam section (1).

4. The method for horizontally hoisting a reinforced concrete beam segment according to any one of claims 1 or 2, characterized in that: In step 2, the method for judging whether the two ends of the reinforced concrete beam section (1) are horizontal is as follows: when the reinforced concrete beam section (1) is slowly lifted, a transparent hose whose length exceeds the length of the reinforced concrete beam section (1) is selected, a sufficient amount of water is injected into the hose, and the water surface at one end of the hose is kept flush with the center of the upper edge of one end of the reinforced concrete beam section (1), and the water surface at the other end of the hose is checked to be flush with the center of the upper edge of the other end of the reinforced concrete beam section (1), thereby judging whether the two ends of the reinforced concrete beam section (1) are flush; In the step 2, the method for judging whether the two sides of the reinforced concrete beam section (1) are horizontal is as follows: when the reinforced concrete beam section (1) is slowly lifted, a transparent hose whose length exceeds the width of the reinforced concrete beam section (1) is selected, a sufficient amount of water is injected into the hose, and the water surface at one end of the hose is kept flush with the center of the upper edge of one side of the reinforced concrete beam section (1), and the water surface at the other end of the hose is checked to be flush with the center of the upper edge of the other side of the reinforced concrete beam section (1), thereby judging whether the two sides of the reinforced concrete beam section (1) are flush.

5. The method for horizontally hoisting a reinforced concrete beam segment according to any one of claims 1 or 2, characterized in that: A U-shaped clamping ring is arranged outside the steel bar (4), a hand-tightened bolt is threadedly mounted on the end of the U-shaped clamping ring, and the ferrule (201) is located between the U-shaped clamping ring and the reinforced concrete beam section (1).

6. The method for horizontally hoisting a reinforced concrete beam segment according to any one of claims 1 or 2, characterized in that: The ferrule (201) is sleeved on the steel bar (4), and the ferrule (201) is fixedly connected to the steel bar (4) by a cross-binding method.

7. The method for horizontally hoisting a reinforced concrete beam segment according to any one of claims 1 or 2, characterized in that: The distances from all transverse hoisting holes (101) to the upper surface and end surface of the reinforced concrete beam section (1) are equal, and the distances from all longitudinal hoisting holes (102) to the upper surface and side surfaces of the reinforced concrete beam section (1) are equal.

8. The method for horizontally hoisting a reinforced concrete beam segment according to any one of claims 1 or 2, characterized in that: The distance between the transverse hoisting hole (101) and the longitudinal hoisting hole (102) and the upper surface of the reinforced concrete beam section (1) is shorter than the distance between the transverse hoisting hole (101) and the longitudinal hoisting hole (102) and the lower surface of the reinforced concrete beam section (1), and the transverse hoisting hole (101) and the longitudinal hoisting hole (102) are through holes or blind holes.

9. The method for horizontally hoisting a reinforced concrete beam segment according to any one of claims 1 or 2, characterized in that: The handle (2) is formed by binding two steel bars or steel wire ropes at a middle junction.

10. The method for horizontally hoisting a reinforced concrete beam segment according to any one of claims 1 or 2, characterized in that: The method for adjusting the counterweight device (3) and its position to level the reinforced concrete beam section (1) is as follows: When one end of the reinforced concrete beam section (1) is tilted, the counterweight device (3) needs to be moved to that end, and weights of the same weight need to be added to the carrying bags (3) on both sides to adjust the balance; When one side of the reinforced concrete beam section (1) is tilted, the counterweight device (3) is placed in the middle thereof, and a counterweight is added to the carrier bag (302) on that side to adjust the balance; When one end of the reinforced concrete beam section (1) and any side of the end are warped, the counterweight device (3) needs to be moved to the end, and counterweight material is added to the carrier bag (3) on the warped side to adjust the balance.

Citation Information

Patent Citations

  • Crane weight testing device

    CN107758511A

  • Device for hoisting front beam and rear beam of large tonnage extruder

    CN108439198A

  • Lifting and mounting equipment for composite floor slabs

    CN220642250U

  • Level checker

    JP1993057611U

  • Cargo suspending jig

    JP1999228067A