Semi-automatic pavement crater rapid repairing device and repairing method
The semi-automatic rapid road crater repair device, which utilizes a tracked platform and electronic control panel to control cutting, cleaning, spraying, and water storage devices, combined with geopolymer concrete canvas and polyurethane foam materials, has solved the problem of rapid repair of airport pavement craters, achieving efficient repair and good load-bearing capacity.
Patent Information
- Application Number
- CN202411407922.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-10
- Publication Date
- 2025-01-07
AI Technical Summary
Existing technologies are insufficient to effectively repair bomb craters on airport pavements in a short period of time, and it is difficult to balance the load-bearing capacity of the repair device with the repair time.
A semi-automatic rapid road crater repair device is adopted, which includes a tracked platform, a cutting operation platform, a cleaning device, a spraying device, and a water storage device. The operation of each device is precisely positioned and controlled through an electronic control panel, and rapid repair is achieved by combining geopolymer concrete canvas and polyurethane foam materials.
It enables rapid repair of bomb craters on airport pavements in a short time, ensuring safe take-off and landing of aircraft. The repair device has good load-bearing capacity and impact resistance.
Smart Images

Figure CN119266072A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of road surface repair, and in particular to a semi-automatic road surface crater quick repair device and repair method. Background Art
[0002] Airport pavement is an important facility to ensure the safe takeoff and landing of aircraft. In a war environment, when the airport pavement is damaged by shells, multiple craters will be formed. It is necessary to fill the craters in a short time to complete the rapid repair of the damaged area to ensure the rapid and safe takeoff and landing of aircraft. Therefore, higher requirements are put forward for the rapid repair device and method of airport pavement craters. In order to meet the requirements of rapid recovery of aircraft takeoff and landing, the device for repairing airport pavement craters should not only have a load-bearing capacity that meets the standards, but also have the characteristics of short repair time. Summary of the invention
[0003] The present application aims to solve one of the technical problems in the related art at least to some extent.
[0004] To this end, the purpose of this application is to propose a semi-automatic road crater rapid repair device and repair method, which can fill airport pavement craters in a short period of time and complete the rapid repair of the damaged area.
[0005] To achieve the above-mentioned purpose, the first embodiment of the present application proposes a semi-automatic road crater rapid repair device, including a crawler platform, a cutting operation platform, an electronic control panel, a cleaning device, a spraying device and a water storage device, wherein:
[0006] The crawler platform is equipped with a crawler walking module, and is connected to the chassis frame and the cutting operation platform in an articulated manner through a support frame, and the crawler walking module includes a track shoe, a driving wheel, a driven wheel, a supporting wheel and a tensioning structure;
[0007] The cutting operation platform is composite with multiple types of operation equipment for cutting geopolymer concrete canvas;
[0008] The water storage device is provided with a valve at the pipe connection to control the opening and closing of the water flow;
[0009] The spray device is provided with a nozzle corresponding to the valve, a telescopic rod and a universal joint, and each nozzle can extend a water pipe to transport water to clean the debris at the bottom of the crater;
[0010] The cleaning device is equipped with a cleaning rotary arm, a high-pressure gas nozzle and a rotating brush, is connected to the dust removal device through four rotatable joints, and is provided with six telescopic rods for controlling the cleaning device.
[0011] The electronic control panel is fixed to the frame or supporting structure of the vehicle by screws or bolts, and is used to accurately locate the specific position of the crater and control the operation of the crawler platform, cutting operation platform, cleaning device, spray device and water storage device.
[0012] Optionally, the tracked platform has an adjustable suspension system to adapt to different terrains;
[0013] The bottom of the chassis of the crawler platform is equipped with a hydraulic stabilizing device to ensure stability during operation;
[0014] The articulated connection structure of the crawler platform and the cutting operation platform includes a rotating shaft, upper and lower hinge arms and a locking mechanism.
[0015] Optionally, a locking device and a universal joint are provided in the cleaning device, which can prevent the telescopic rod of the cleaning device from sliding and retracting at will and ensure that the telescopic rod can rotate freely for easy cleaning;
[0016] The dust removal device and the ventilation duct in the cleaning device are connected by flanges and fastened by bolts and nuts.
[0017] Optionally, the valve type installed at the connection between the spray device and the water storage device pipeline is at least one of a ball valve, a gate valve, and a stop valve, and the valve is controlled by the electronic control panel;
[0018] The nozzle of the spray device can be fine-tuned and rotated, and is controlled and adjusted by the electronic control panel;
[0019] The telescopic rod in the spraying device is connected to the water storage device and the dust removal device through a leveling device. The leveling device can maintain the connection between the telescopic rod and the water storage device and the dust removal device, thereby improving the efficiency of debris removal and watering.
[0020] Optionally, the telescopic rod in the spray device and the telescopic rod in the cleaning device are both high-strength telescopic rods.
[0021] Optionally, the water storage device contains a liquid level sensor and an electronic regulating valve, which can be jointly controlled through the electronic control panel.
[0022] Optionally, the cutting operation platform is equipped with a corresponding tool box, and the tool box has built-in electric cutting tools and laser measurement sensors;
[0023] The cutting operation platform is provided with a cutting control path and a changing system for replacing mechanical heads of different sizes and types;
[0024] The cutting operation platform is provided with a sensor control device for analyzing the input cutting shape and controlling the cutting head to cut the geopolymer concrete canvas.
[0025] To achieve the above-mentioned purpose, the second embodiment of the present application proposes a semi-automatic road crater rapid repair method, comprising the following steps:
[0026] The cleaning device is equipped with a high-pressure gas nozzle, a rotating brush and a dust removal device to clean up debris in the road craters, and the shape, size, bottom depth and volume of the road craters are obtained using drone imaging;
[0027] The geopolymer concrete canvas is cut by using a cutting operation platform to obtain a target geopolymer concrete canvas that meets the size of a preset road surface crater;
[0028] filling the crater with polyurethane foam material;
[0029] Using the cut target geopolymer concrete canvas to fill the location of the pavement crater, and fixing the target geopolymer concrete canvas with edge pressing strips and expansion bolts;
[0030] According to the water storage device and the spraying device, water is evenly sprayed from the edge to the middle of the target geopolymer concrete canvas until the color of the target geopolymer concrete canvas becomes darker;
[0031] The repair and hardening process of the target geopolymer concrete canvas is monitored, and adjustments are made when abnormalities occur to ensure that the specified repair effect can be achieved.
[0032] Optionally, when using the target geopolymer concrete canvas to fill craters, it also includes:
[0033] A waterproof layer is added at the bottom of the target geopolymer concrete canvas to prevent the spray water from leaking into the rock mass below, resulting in insufficient hydration reaction of the geopolymer concrete canvas, and a polyurea anti-explosion coating is added to improve the overall anti-explosion and anti-impact performance of the geopolymer concrete canvas.
[0034] Optionally, when water is evenly sprinkled from the edge to the middle of the target geopolymer concrete canvas, it is necessary to strictly follow the order of evenly sprinkling water from the edge to the middle, and the wetted geopolymer concrete canvas area needs to be kept warm and moisturized for at least 24 hours. If its shape needs to be adjusted, it needs to be completed within 2 hours of final setting time.
[0035] To achieve the above-mentioned purpose, the third aspect of the present application provides an electronic device, including: a processor, and a memory communicatively connected to the processor;
[0036] The memory stores computer-executable instructions;
[0037] The processor executes the computer-executable instructions stored in the memory to implement the method as described in any one of the second aspects.
[0038] To achieve the above-mentioned purpose, the fourth aspect embodiment of the present application proposes a computer-readable storage medium, in which computer-readable storage medium is stored computer execution instructions, and when the computer execution instructions are executed by a processor, they are used to implement the method as described in any one of the second aspects.
[0039] To achieve the above-mentioned purpose, the fifth aspect of the present application proposes a computer program product, which implements any method in the second aspect when executed by a processor.
[0040] The semi-automatic road surface rapid repair device and repair method provided in the present application can repair crater damage on the road surface in a short period of time and complete the rapid repair of the damaged area.
[0041] Additional aspects and advantages of the present application will be given in part in the description below, and in part will become apparent from the description below, or will be learned through the practice of the present application. BRIEF DESCRIPTION OF THE DRAWINGS
[0042] The above and / or additional aspects and advantages of the present application will become apparent and easily understood from the following description of the embodiments in conjunction with the accompanying drawings, in which:
[0043] Figure 1 is a schematic diagram of a semi-automatic road crater quick repair device according to an embodiment of the present application;
[0044] Figure 2 It is a flow chart of a semi-automatic road crater rapid repair method according to an embodiment of the present application.
[0045] Figure 1 Middle: 1-cleaning device; 2-spraying device; 3-water storage device; 4-cutting operation platform; 5-crawler platform; 6-electronic control panel. DETAILED DESCRIPTION
[0046] The embodiments of the present application are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are intended to be used to explain the present application, and should not be construed as limiting the present application.
[0047] A semi-automatic road crater quick repair device and repair method according to an embodiment of the present application will be described below with reference to the accompanying drawings.
[0048] Figure 1is a schematic diagram of a semi-automatic road crater quick repair device according to an embodiment of the present application, such as Figure 1 As shown, the semi-automatic road crater rapid repair device includes a crawler platform 5, a cutting operation platform 4, an electronic control panel 6, a cleaning device 1, a spraying device 2 and a water storage device 3.
[0049] The crawler platform 5 is equipped with a crawler walking module, and is connected to the chassis frame and the cutting operation platform 4 in an articulated manner through a support frame. The crawler walking module includes a track shoe, a driving wheel, a driven wheel, a supporting wheel and a tensioning structure.
[0050] The cutting operation platform 4 is composite with multiple types of operation equipment for cutting geopolymer concrete canvas;
[0051] The water storage device 3 is provided with a valve at the pipe connection to control the opening and closing of the water flow;
[0052] The spray device 2 is provided with a nozzle corresponding to the valve, a telescopic rod and a universal joint, and each nozzle can extend a water pipe to transport water to clean the debris at the bottom of the crater;
[0053] The cleaning device 1 is equipped with a cleaning rotary arm, a high-pressure gas nozzle and a rotating brush, is connected to the dust removal device through four rotatable joints, and is provided with six telescopic rods for controlling the cleaning equipment.
[0054] The electronic control panel 6 is fixed to the frame or supporting structure of the vehicle by screws or bolts, and is used to accurately locate the specific position of the crater and control the operation of the crawler platform 5, the cutting operation platform 4, the cleaning device 1, the spray device 2 and the water storage device 3.
[0055] Furthermore, in some embodiments of the present application, the crawler platform has an adjustable suspension system to adapt to different terrains; the bottom of the chassis of the crawler platform is equipped with a hydraulic stabilizer to ensure stability during operation; the articulated connection structure between the crawler platform and the cutting operation platform includes a rotating shaft, upper and lower hinge arms and a locking mechanism.
[0056] Furthermore, in some embodiments of the present application, a locking device and a universal joint are provided in the cleaning device, which can prevent the telescopic rod of the cleaning device from sliding and retracting at will and ensure that the telescopic rod can rotate freely for easy cleaning. The dust removal device and the ventilation duct in the cleaning device are connected by flanges and fastened with bolts and nuts.
[0057] Specifically, a flange is installed at the connecting end of the ventilation duct and the dust removal device. It is recommended that the material of the flange be carbon steel and the type be a threaded flange. This application does not make any specific restrictions on this.
[0058] Furthermore, in some embodiments of the present application, the valve type installed at the pipeline connection between the spray device and the water storage device is at least one of a ball valve, a gate valve, and a stop valve, and the valve is controlled by an electronic control panel to achieve automation; the nozzle of the spray device can achieve fine-tuning rotation, which is controlled and adjusted by the electronic control panel; the telescopic rod in the spray device is connected to the water storage device and the dust removal device through a leveling device, and supports adaptive fine-tuning of the angle, and the leveling device can maintain the connection between the telescopic rod and the water storage device and the dust removal device, which can further improve the efficiency of debris removal and watering.
[0059] In practical applications, the water storage device can make a preliminary estimate of the water demand based on the observed size of the crater. When the water storage capacity is insufficient, an additional mobile water supply vehicle can be set up.
[0060] Furthermore, in some embodiments of the present application, the telescopic rod in the spray device and the telescopic rod in the cleaning device are both high-strength telescopic rods, with the strength being sufficient to withstand the weight of transportation vehicles such as cars or airplanes.
[0061] Furthermore, in some embodiments of the present application, the water storage device contains a liquid level sensor and an electronic regulating valve, which can be jointly controlled through an electronic control panel.
[0062] Furthermore, in some embodiments of the present application, the cutting operation platform is equipped with a corresponding tool box, which has built-in electric cutting tools and laser measurement sensors. The damage notch data can be retrieved through the electronic control panel and corrected through the laser measurement sensor.
[0063] In addition, the cutting operation platform is equipped with a cutting control path and a changing system for replacing mechanical heads of different sizes and types; the cutting operation platform is equipped with a sensor control device for analyzing the input cutting shape and controlling the cutting head to cut the geopolymer concrete canvas.
[0064] It should be noted that in actual use, due to the use of automatic control and manual scanning and correction, the size of the automatically cut geopolymer concrete canvas may deviate from the actual size, so the cutting area during setting can be slightly enlarged, and manual correction and cutting can be performed when the geopolymer concrete canvas is fixed later.
[0065] In some embodiments, the fastener is an expansion bolt, which can make the fixed connection of the telescopic rod in the socket more secure. The fastener is not shown in the figure.
[0066] In the embodiment of the present application, by providing a cleaning device, debris and sundries can be cleaned from the crater and its surroundings in a short time; a spray device, a water storage device and a cutting operation platform are used to complete the cutting and spray fixing operations of the geopolymer concrete canvas for the filled crater, thereby completing the rapid repair of the panel in the damaged area. The operation is easy to implement, the structure is simple and reliable, the repair effect is good, and it is convenient and fast.
[0067] The present application also proposes a semi-automatic road surface crater rapid repair method, which is applied to the above-mentioned semi-automatic road surface rapid repair device, and comprises the following steps:
[0068] Step 101: clean the debris in the road crater using the high-pressure gas nozzle, rotating brush and dust removal device equipped in the cleaning device, and use drone imaging to obtain the shape, size, bottom depth and volume of the road crater.
[0069] In the embodiment of the present application, the electronic operation panel is operated according to the size of the pit to control the cleaning device to clean. In addition, the shape, size, bottom depth and volume of the road crater are obtained by drone imaging technology, making the information acquisition faster and replacing manual measurement to ensure personal safety.
[0070] Step 102: Use a cutting operation platform to cut the geopolymer concrete canvas to obtain a target geopolymer concrete canvas that meets the preset road surface crater size.
[0071] The present application adopts geopolymer concrete canvas to improve the shortcomings of conventional silicate cement itself, which is high in energy consumption and produces a large amount of carbon dioxide, and has the advantage of low economic cost compared with the "sulphoaluminate cement + gypsum" system.
[0072] The components of the geopolymer concrete canvas include a main three-dimensional spacer fabric, a cement matrix and a packaging material, wherein the main cement matrix is a oligomer material, the three-dimensional spacer fabric is a textile woven from polyethylene and polypropylene, and the packaging material is a basalt fiber plain cloth, which are mixed according to the proportions of the known technology.
[0073] It can be understood that the cutting operation platform is equipped with a sensor control device, which can analyze the input cutting shape and control the cutting head to cut the geopolymer concrete canvas. If the crater size is large, it is necessary to select segmented cutting when selecting the cutting part on the electronic operation panel, and continuously move the cut part outward until the entire geopolymer concrete canvas is cut.
[0074] It should be noted that in actual use, due to the use of automatic control and manual scanning and correction, the size of the automatically cut geopolymer concrete canvas may deviate from the actual size, so the cutting area during setting can be slightly enlarged, and manual correction and cutting can be performed when the geopolymer concrete canvas is fixed later.
[0075] Step 103, filling the crater with polyurethane foam material.
[0076] In the embodiment of the present application, the cavity of the crater is filled with polyurethane foam material, thereby improving the cushioning and shock-absorbing properties of the repair device.
[0077] The components of the polyurethane foam material include isocyanate, polyurethane rigid foam composite polyether, and foaming agent, which are mixed according to the proportions known in the art.
[0078] Step 104: Use the cut target geopolymer concrete canvas to fill the crater position on the pavement, and fix the target geopolymer concrete canvas with edge pressing strips and expansion bolts.
[0079] In the embodiment of the present application, when using geopolymer concrete canvas for crater filling, a waterproof layer is added to the bottom of the target geopolymer concrete canvas to prevent the spray water from leaking into the rock mass below, resulting in insufficient hydration reaction of the geopolymer concrete canvas, and a layer of polyurea anti-explosion coating is added to enhance the overall anti-explosion and anti-impact performance of the geopolymer concrete canvas.
[0080] Step 105: Sprinkle water evenly from the edge to the middle of the target geopolymer concrete canvas according to the water storage device and the spraying device until the color of the target geopolymer concrete canvas becomes darker.
[0081] In the embodiment of the present application, the target geopolymer concrete canvas is sprayed by a water storage device and a spraying device, and is cured and solidified. The hardening process is monitored based on the monitoring data and results. After hardening, the geopolymer concrete canvas has good impact resistance and friction resistance, and a short solidification time.
[0082] It should be noted that when evenly sprinkling water from the edge to the middle of the target geopolymer concrete canvas, it is necessary to strictly follow the order of evenly sprinkling water from the edge to the middle, and the wetted geopolymer concrete canvas area needs to be insulated and moisturized for at least 24 hours. If its shape needs to be adjusted, it needs to be completed within the 2-hour final setting time.
[0083] In addition, the amount of spraying water should not be too much. Spraying too much water will extend the hardening time of the geopolymer concrete canvas and significantly reduce the strength obtained by hardening.
[0084] Step 106: monitor the repair and hardening process of the target geopolymer concrete canvas, and make adjustments when abnormalities occur to ensure that the specified repair effect can be achieved.
[0085] In the embodiment of the present application, the repair and hardening process of the target geopolymer concrete canvas is monitored by a monitoring system. The monitoring system used includes a laser displacement sensor, an infrared thermal imager and a humidity sensor. The hardening process of the geopolymer concrete canvas is monitored, and the parameters measured by the sensor are analyzed to respond to and repair problems arising in the hardening process in a timely manner.
[0086] The present application also proposes a semi-automatic road surface crater quick repair device for use in airports, which can repair craters on airport pavements in a short time, restore takeoff and landing of various aircraft, and can perform repairs around the clock.
[0087] It should be noted that when the present application is applied to an airport scenario, the “road surface” mentioned in the above embodiments refers to the airport pavement.
[0088] The present invention is further described below through specific examples.
[0089] Example 1
[0090] Step 1: After the airport pavement is hit by an artillery shell, clean up the debris inside and around the crater on the airport pavement, and use drone imaging to obtain measurement data such as the shape, size, bottom diameter, depth and volume of the crater on the airport pavement.
[0091] Step 2: Conduct preliminary detection and cleanup of unexploded bombs and other dangerous objects near craters on the damaged road surface.
[0092] Step 3, driving the aforementioned semi-automatic road surface rapid repair device into the corresponding damaged area, and delivering the polyurethane foam material and geopolymer concrete canvas to the crater location.
[0093] Step 4: Use a semi-automatic road surface rapid repair device to clean the crater to remove damaged fragments, collect the specific information of the crater for a second time, and verify and correct the deficiencies in image recognition.
[0094] Step 5: Spray polyurethane foam to fill the crater.
[0095] Step 6, using the geopolymer concrete canvas cutting operation platform to cut the geopolymer concrete canvas, cutting to obtain a geopolymer concrete canvas that is slightly larger than the verified size of the road surface crater size.
[0096] Step 7, use the cut geopolymer concrete canvas to fill the crater on the road surface, and fix the geopolymer concrete canvas with edge strips and expansion bolts.
[0097] Step 8, use the spray system on the semi-automatic pavement rapid repair device to evenly sprinkle water from the edge to the middle until the color of the geopolymer concrete canvas becomes darker.
[0098] Step 9, use a monitoring system to monitor the repair and hardening process of the geopolymer concrete canvas, and make adjustments when necessary to ensure that the repair effect can be achieved.
[0099] In order to implement the above embodiments, the present application also proposes an electronic device, comprising: a processor, and a memory communicatively connected to the processor; the memory stores computer-executable instructions; the processor executes the computer-executable instructions stored in the memory to implement the method provided by the above embodiments.
[0100] In order to implement the above embodiments, the present application also proposes a computer-readable storage medium, in which computer-executable instructions are stored. When the computer-executable instructions are executed by a processor, they are used to implement the methods provided by the above embodiments.
[0101] In order to implement the above embodiments, the present application also proposes a computer program product, including a computer program, which implements the methods provided by the above embodiments when executed by a processor.
[0102] In the description of the aforementioned embodiments, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present application. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.
[0103] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In the description of this application, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.
[0104] Any process or method description in a flowchart or otherwise described herein may be understood to represent a module, fragment or portion of code comprising one or more executable instructions for implementing the steps of a custom logical function or process, and the scope of the preferred embodiments of the present application includes alternative implementations in which functions may not be performed in the order shown or discussed, including performing functions in a substantially simultaneous manner or in the reverse order depending on the functions involved, which should be understood by technicians in the technical field to which the embodiments of the present application belong.
[0105] The logic and / or steps represented in the flowchart or otherwise described herein, for example, can be considered as an ordered list of executable instructions for implementing logical functions, and can be embodied in any computer-readable medium for use by an instruction execution system, device or apparatus (such as a computer-based system, a system including a processor, or other system that can fetch instructions from an instruction execution system, device or apparatus and execute the instructions), or in combination with these instruction execution systems, devices or apparatuses. For the purpose of this specification, "computer-readable medium" can be any device that can contain, store, communicate, propagate or transmit a program for use by an instruction execution system, device or apparatus, or in combination with these instruction execution systems, devices or apparatuses. More specific examples of computer-readable media (a non-exhaustive list) include the following: an electrical connection with one or more wires (electronic device), a portable computer disk box (magnetic device), a random access memory (RAM), a read-only memory (ROM), an erasable and programmable read-only memory (EPROM or flash memory), a fiber optic device, and a portable compact disk read-only memory (CDROM). In addition, the computer-readable medium may even be paper or other suitable medium on which the program is printed, since the program may be obtained electronically, for example, by optically scanning the paper or other medium and then editing, interpreting or processing in other suitable ways if necessary, and then stored in a computer memory.
[0106] It should be understood that the various parts of the present application can be implemented by hardware, software, firmware or a combination thereof. In the above-mentioned embodiments, multiple steps or methods can be implemented by software or firmware stored in a memory and executed by a suitable instruction execution system. For example, if implemented by hardware, as in another embodiment, it can be implemented by any one of the following technologies known in the art or their combination: a discrete logic circuit having a logic gate circuit for implementing a logic function for a data signal, a dedicated integrated circuit having a suitable combination of logic gate circuits, a programmable gate array (PGA), a field programmable gate array (FPGA), etc.
[0107] A person skilled in the art may understand that all or part of the steps in the method for implementing the above-mentioned embodiment may be completed by instructing related hardware through a program, and the program may be stored in a computer-readable storage medium, which, when executed, includes one or a combination of the steps of the method embodiment.
[0108] In addition, each functional unit in each embodiment of the present application may be integrated into a processing module, or each unit may exist physically separately, or two or more units may be integrated into one module. The above-mentioned integrated module may be implemented in the form of hardware or in the form of a software functional module. If the integrated module is implemented in the form of a software functional module and sold or used as an independent product, it may also be stored in a computer-readable storage medium.
[0109] The storage medium mentioned above may be a read-only memory, a magnetic disk or an optical disk, etc. Although the embodiments of the present application have been shown and described above, it can be understood that the above embodiments are exemplary and cannot be understood as limiting the present application. A person of ordinary skill in the art may change, modify, replace and modify the above embodiments within the scope of the present application.
[0110] It should be understood that the various forms of processes shown above can be used to reorder, add or delete steps. For example, the steps recorded in this application can be executed in parallel, sequentially or in different orders, as long as the expected results of the technical solution of this application can be achieved, and this document is not limited here.
[0111] The above specific implementations do not constitute a limitation on the protection scope of this application. It should be understood by those skilled in the art that various modifications, combinations, sub-combinations and substitutions can be made according to design requirements and other factors. Any modifications, equivalent substitutions and improvements made within the spirit and principles of this application should be included in the protection scope of this application.
Claims
1. A semi-automatic road crater quick repair device, characterized in that: It includes a crawler platform, a cutting operation platform, an electronic control panel, a cleaning device, a spray device and a water storage device, among which: The crawler platform is equipped with a crawler walking module, and is connected to the chassis frame and the cutting operation platform in an articulated manner through a support frame, and the crawler walking module includes a track shoe, a driving wheel, a driven wheel, a supporting wheel and a tensioning structure; The cutting operation platform is composite with multiple types of operation equipment for cutting geopolymer concrete canvas; The water storage device is provided with a valve at the pipe connection to control the opening and closing of the water flow; The spray device is provided with a nozzle corresponding to the valve, a telescopic rod and a universal joint, and each nozzle can extend a water pipe to transport water to clean the debris at the bottom of the crater; The cleaning device is equipped with a cleaning rotary arm, a high-pressure gas nozzle and a rotating brush, is connected to the dust removal device through four rotatable joints, and is provided with six telescopic rods for controlling the cleaning device. The electronic control panel is fixed to the frame or supporting structure of the vehicle by screws or bolts, and is used to accurately locate the specific position of the crater and control the operation of the crawler platform, cutting operation platform, cleaning device, spray device and water storage device.
2. The semi-automatic road surface rapid repair device according to claim 1 is characterized in that: The crawler platform has an adjustable suspension system to adapt to different terrains; The bottom of the chassis of the crawler platform is equipped with a hydraulic stabilizing device to ensure stability during operation; The articulated connection structure of the crawler platform and the cutting operation platform includes a rotating shaft, upper and lower hinge arms and a locking mechanism.
3. The semi-automatic road surface rapid repair device according to claim 1 is characterized in that: The cleaning device is provided with a locking device and a universal joint, which can prevent the telescopic rod of the cleaning device from sliding and retracting at will and ensure that the telescopic rod can rotate freely for easy cleaning; The dust removal device and the ventilation duct in the cleaning device are connected by flanges and fastened by bolts and nuts.
4. The semi-automatic road surface rapid repair device according to claim 1 is characterized in that: The valve type installed at the connection between the spray device and the water storage device pipeline is at least one of a ball valve, a gate valve, and a stop valve, and the valve is controlled by the electronic control panel; The nozzle of the spray device can be fine-tuned and rotated, and is controlled and adjusted by the electronic control panel; The telescopic rod in the spraying device is connected to the water storage device and the dust removal device through a leveling device. The leveling device can maintain the connection between the telescopic rod and the water storage device and the dust removal device, thereby improving the efficiency of debris removal and watering.
5. The semi-automatic road surface rapid repair device according to claim 1 is characterized in that: The telescopic rod in the spray device and the telescopic rod in the cleaning device are both high-strength telescopic rods.
6. The semi-automatic road surface rapid repair device according to claim 1, characterized in that: The water storage device contains a liquid level sensor and an electronic regulating valve, which can be jointly controlled through the electronic control panel.
7. The semi-automatic road surface rapid repair device according to claim 1 is characterized in that: The cutting operation platform is equipped with a corresponding tool box, which has an electric cutting tool and a laser measurement sensor built in; The cutting operation platform is provided with a cutting control path and a changing system for replacing mechanical heads of different sizes and types; The cutting operation platform is provided with a sensor control device for analyzing the input cutting shape and controlling the cutting head to cut the geopolymer concrete canvas.
8. A semi-automatic road crater quick repair method, characterized in that: The semi-automatic road surface quick repair device applied to any one of claims 1 to 7 comprises the following steps: The cleaning device is equipped with a high-pressure gas nozzle, a rotating brush and a dust removal device to clean up debris in the road craters, and the shape, size, bottom depth and volume of the road craters are obtained using drone imaging; The geopolymer concrete canvas is cut by using a cutting operation platform to obtain a target geopolymer concrete canvas that meets the size of a preset road surface crater; filling the crater with polyurethane foam material; Using the cut target geopolymer concrete canvas to fill the location of the road surface crater, and fixing the target geopolymer concrete canvas with edge pressing strips and expansion bolts; According to the water storage device and the spraying device, water is evenly sprayed from the edge to the middle of the target geopolymer concrete canvas until the color of the target geopolymer concrete canvas becomes darker; The repair and hardening process of the target geopolymer concrete canvas is monitored, and adjustments are made when abnormalities occur to ensure that the specified repair effect can be achieved.
9. The method according to claim 8, characterized in that When using the target geopolymer concrete canvas for crater filling, it also includes: A waterproof layer is added at the bottom of the target geopolymer concrete canvas to prevent the spray water from leaking into the rock mass below, resulting in insufficient hydration reaction of the geopolymer concrete canvas, and a polyurea anti-explosion coating is added to improve the overall anti-explosion and anti-impact performance of the geopolymer concrete canvas.
10. The method according to claim 8, characterized in that When water is evenly sprinkled from the edge to the middle of the target geopolymer concrete canvas, it is necessary to strictly follow the order of evenly sprinkling water from the edge to the middle, and the wetted geopolymer concrete canvas area needs to be kept warm and moisturized for at least 24 hours. If its shape needs to be adjusted, it needs to be completed within 2 hours of final setting time.
Citation Information
Patent Citations
Device and construction method for quickly and efficiently repairing pavement
CN109024206A
Treatment structure and method for local sunken part in ecological restoration process of rock slope
CN113174971A
Road surface crater rapid repairing device and repairing method
CN117966540A
Road repairing device for highway site construction
CN213709095U
Road pothole repair equipment
CN221029534U