Construction parameter processing method and device and nonvolatile storage medium
By obtaining and analyzing multiple time parameters during reservoir transformation construction, determining the fluid distribution and bottom-hole pressure in the wellbore at the target time, the problem of in-depth data analysis in the existing technology is solved, and the improvement of reservoir transformation construction is achieved Good guidance and optimization.
Patent Information
- Application Number
- CN202310834370.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2023-07-07
- Publication Date
- 2025-01-07
AI Technical Summary
The data analysis method for reservoir transformation construction parameters in the prior art is not in-depth enough to effectively guide construction optimization.
By obtaining the construction parameters of multiple moments during reservoir transformation construction, the fluid distribution and bottom-hole pressure in the target wellbore at the target time, including pressure losses caused by liquid mass, proppant mass, and flow friction resistance, and the bottom-hole pressure is calculated. To better guide the construction of reservoir renovation.
In-depth analysis of the construction parameters of reservoir renovation is achieved, and the bottom bottom pressure can be determined more accurately, thereby optimizing the construction process and improving the effect of reservoir renovation.
Smart Images

Figure CN119266806A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of reservoir transformation, and in particular to a method and device for processing construction parameters and a non-volatile storage medium. Background Art
[0002] Reservoir transformation is an important means to improve the production capacity of oil and gas wells. The effect of reservoir transformation construction needs to be analyzed and evaluated based on the construction data recorded during the construction process. The current technology uses oil pressure to judge and analyze whether there are defects in reservoir transformation construction. The analysis results are not in-depth enough and cannot effectively guide construction optimization.
[0003] To address the above-mentioned problems, no effective solution has been proposed yet. Summary of the invention
[0004] The embodiments of the present invention provide a method, device and non-volatile storage medium for processing construction parameters, so as to at least solve the technical problem that the data analysis method for reservoir transformation construction parameters in the prior art is not in-depth.
[0005] According to one aspect of an embodiment of the present invention, a method for processing construction parameters is provided, comprising: obtaining multiple construction parameters corresponding to multiple moments during reservoir transformation construction, wherein the multiple construction parameters are used to transform the reservoir; determining the distribution of fluid in a target wellbore at a target moment based on the multiple construction parameters, wherein the multiple moments include the target moment, and the target wellbore is used to transport the fluid used to transform the reservoir to the reservoir; determining the target bottom hole pressure at the target moment based on the distribution of the fluid in the target wellbore.
[0006] Optionally, determining the target bottom hole pressure at the target moment according to the distribution of the fluid in the target wellbore includes: separately determining the mass of the liquid included in the fluid in the target wellbore, and the mass of the proppant included in the fluid in the target wellbore; determining a first pressure and a second pressure according to the mass of the liquid and the mass of the proppant, wherein the first pressure is the pressure exerted on the bottom hole of the target wellbore by the gravity of the liquid, and the second pressure is the pressure exerted on the bottom hole of the target wellbore by the gravity of the proppant; determining the pressure loss caused by the frictional resistance exerted by the flow of the fluid in the target wellbore according to the distribution of the fluid in the target wellbore; and determining the target bottom hole pressure according to the first pressure, the second pressure and the pressure loss.
[0007] Optionally, the pressure loss caused by the frictional resistance generated by the fluid flow in the target wellbore is determined based on the distribution of the fluid in the target wellbore, including: obtaining the corresponding relationship between the pressure of the flow loss of the standard liquid in the experimental wellbore and the displacement of the standard liquid injected into the experimental wellbore, wherein the models of the experimental wellbore and the target wellbore match; determining the positions of multiple liquids included in the fluid in the target wellbore in the target wellbore based on the distribution of the fluid in the target wellbore; determining the liquid displacement injected into the target wellbore at the target time based on multiple construction parameters; obtaining the friction coefficients of multiple liquids; and determining the pressure loss caused by the frictional resistance generated by the fluid flow in the target wellbore based on the positions of the multiple liquids in the target wellbore, the liquid displacements, the friction coefficients of the multiple liquids and the corresponding relationships.
[0008] Optionally, determining the mass of the proppant included in the fluid in the target wellbore comprises: determining the volume of a first fluid in the fluid in the target wellbore based on a plurality of construction parameters, wherein the first fluid is a fluid mixed with the proppant and injected into the target wellbore from the ground; obtaining the concentration of the proppant in the first fluid; and determining the mass of the proppant included in the fluid in the target wellbore based on the volume of the first fluid and the concentration of the proppant in the first fluid.
[0009] Optionally, determining the target bottom hole pressure according to the first pressure, the second pressure and the pressure loss includes: determining the target bottom hole pressure as the difference between the sum of the first pressure and the second pressure and the pressure loss.
[0010] Optionally, the distribution of fluids in the target wellbore at the target time is determined based on multiple construction parameters, including: determining the order in which the multiple liquids are injected into the target wellbore and the volumes of the multiple liquids injected into the target wellbore at the target time based on the multiple construction parameters; obtaining the volume of the target wellbore; and determining the distribution of the multiple liquids in the target wellbore at the target time based on the order in which the multiple liquids are injected into the target wellbore, the volumes of the multiple liquids injected into the target wellbore at the target time, and the volume of the target wellbore.
[0011] Optionally, the method further includes: respectively determining a plurality of bottom hole pressures at other moments in the plurality of moments except the target moment; and visually displaying the plurality of bottom hole pressures and the target bottom hole pressure in a time sequence of the plurality of moments.
[0012] According to another aspect of an embodiment of the present invention, a construction parameter processing device is also provided, including: an acquisition module, used to acquire multiple construction parameters corresponding to multiple moments during reservoir transformation construction, wherein the multiple construction parameters are used to transform the reservoir; a first determination module, used to determine the distribution of fluid in a target wellbore at a target moment according to the multiple construction parameters, wherein the multiple moments include the target moment, and the target wellbore is used to transport the fluid used to transform the reservoir to the reservoir; a second determination module, used to determine the target bottom hole pressure at the target moment according to the distribution of the fluid in the target wellbore.
[0013] According to another aspect of an embodiment of the present invention, a non-volatile storage medium is provided, the non-volatile storage medium including a stored program, wherein when the program is running, the device where the non-volatile storage medium is located is controlled to execute any one of the above-mentioned construction parameter processing methods.
[0014] According to another aspect of the embodiments of the present invention, a computer device is provided. The computer device includes a processor, and the processor is used to run a program. When the program is run, any one of the above-mentioned methods for processing construction parameters is executed.
[0015] In an embodiment of the present invention, multiple construction parameters corresponding to multiple moments during reservoir transformation construction are obtained, wherein the multiple construction parameters are used to transform the reservoir; based on the multiple construction parameters, the distribution of the fluid in the target wellbore at the target moment is determined, wherein the multiple moments include the target moment, and the target wellbore is used to transport the fluid used to transform the reservoir to the reservoir; based on the distribution of the fluid in the target wellbore, the target bottom hole pressure at the target moment is determined, thereby achieving the purpose of analyzing the construction parameters to obtain the bottom hole pressure of the wellbore to better guide the reservoir transformation construction, thereby achieving the technical effect of deeply analyzing the reservoir transformation construction parameters to determine the bottom hole pressure, and further solving the technical problem that the data analysis method of the reservoir transformation construction parameters in the prior art is not in-depth. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] The drawings described herein are used to provide a further understanding of the present invention and constitute a part of this application. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. In the drawings:
[0017] Figure 1 A hardware structure block diagram of a computer terminal for implementing a construction parameter processing method is shown;
[0018] Figure 2 is a flow chart of a method for processing construction parameters provided in an embodiment of the present invention;
[0019] Figure 3is a schematic diagram of different fluid compositions in an oil pipe assembly and a wellbore according to an optional embodiment of the present invention;
[0020] Figure 4 4 is a structural block diagram of a construction parameter processing device provided according to an embodiment of the present invention. DETAILED DESCRIPTION
[0021] In order to enable those skilled in the art to better understand the scheme of the present invention, the technical scheme in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.
[0022] It should be noted that the terms "first", "second", etc. in the specification and claims of the present invention and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the data used in this way can be interchanged where appropriate, so that the embodiments of the present invention described herein can be implemented in an order other than those illustrated or described herein. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device that includes a series of steps or units is not necessarily limited to those steps or units that are clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.
[0023] According to an embodiment of the present invention, a method embodiment for processing construction parameters is provided. It should be noted that the steps shown in the flowchart of the accompanying drawings can be executed in a computer system such as a set of computer executable instructions, and although a logical order is shown in the flowchart, in some cases, the steps shown or described can be executed in an order different from that shown here.
[0024] The method embodiment provided in the first embodiment of the present application can be executed in a mobile terminal, a computer terminal or a similar computing device. Figure 1 FIG. 1 shows a hardware structure block diagram of a computer terminal for implementing a construction parameter processing method. Figure 1As shown, the computer terminal 10 may include one or more (102a, 102b, ..., 102n are used to illustrate) processors (the processor may include but is not limited to a processing device such as a microprocessor MCU or a programmable logic device FPGA), a memory 104 for storing data. In addition, it may also include: a display, an input / output interface (I / O interface), a universal serial bus (USB) port (which may be included as one of the ports of the BUS bus), a network interface, a power supply and / or a camera. It can be understood by those skilled in the art that Figure 1 The structure shown is only for illustration and does not limit the structure of the above electronic device. Figure 1 More or fewer components as shown, or with Figure 1 Different configurations shown.
[0025] It should be noted that the one or more processors and / or other data processing circuits described above may generally be referred to herein as "data processing circuits". The data processing circuits may be embodied in whole or in part as software, hardware, firmware, or any other combination thereof. In addition, the data processing circuit may be a single independent processing module, or may be incorporated in whole or in part into any of the other components in the computer terminal 10. As described in the embodiments of the present application, the data processing circuit acts as a processor control (e.g., selection of a variable resistor terminal path connected to an interface).
[0026] The memory 104 can be used to store software programs and modules of application software, such as program instructions / data storage devices corresponding to the method for processing construction parameters in the embodiment of the present invention. The processor executes various functional applications and data processing by running the software programs and modules stored in the memory 104, that is, realizing the method for processing construction parameters of the above-mentioned application program. The memory 104 may include a high-speed random access memory, and may also include a non-volatile memory, such as one or more magnetic storage devices, flash memory or other non-volatile solid-state memory. In some examples, the memory 104 may further include a memory remotely arranged relative to the processor, and these remote memories may be connected to the computer terminal 10 via a network. Examples of the above-mentioned network include, but are not limited to, the Internet, an intranet, a local area network, a mobile communication network and a combination thereof.
[0027] The display may be, for example, a touch screen liquid crystal display (LCD) that enables a user to interact with a user interface of the computer terminal 10 .
[0028] Figure 2 is a flow chart of a method for processing construction parameters according to an embodiment of the present invention, such as Figure 2 As shown, the method comprises the following steps:
[0029] Step S202, obtaining a plurality of construction parameters corresponding to a plurality of time points during the reservoir transformation construction, wherein the plurality of construction parameters are used for performing the reservoir transformation construction.
[0030] In this step, when exploiting oil and gas reservoirs, some reservoirs are relatively dense, and the reservoirs need to be transformed to allow the oil or gas in the formation to flow out. When transforming the reservoir, a wellbore is generally established to the reservoir that needs to be transformed, and then the fluid for transforming the reservoir is injected into the formation through the wellbore. Usually, liquid is first input to cause cracks in the reservoir, and then liquid carrying a support is injected to prevent the cracks from closing, and finally the oil or gas in the reservoir can be discharged smoothly. It should be noted that, in general, the wellbore is filled with liquid in the formation.
[0031] The multiple construction parameters include values of multiple parameters related to reservoir construction at multiple times. The multiple parameters may include the displacement of the input liquid, the density of the input liquid, whether the input liquid carries supports, the density of the supports, etc.
[0032] Step S204, determining the distribution of the fluid in the target wellbore at the target time according to the multiple construction parameters, wherein the multiple times include the target time, and the target wellbore is used to transport the fluid used to transform the reservoir to the reservoir.
[0033] In this step, since the reservoir reconstruction construction requires fluid to be injected into the target wellbore, the fluid in the target wellbore is flowing, so the fluid distribution in the target wellbore will change. Multiple construction parameters can be analyzed in depth to determine which fluids are included in the target wellbore at the target time and the locations of these fluids in the wellbore.
[0034] Step S206, determining a target bottom hole pressure at a target time according to the distribution of the fluid in the target wellbore.
[0035] Through the above steps, the purpose of analyzing the construction parameters to obtain the bottom hole pressure of the wellbore to better guide the reservoir transformation construction is achieved, thereby realizing the technical effect of in-depth analysis of the reservoir transformation construction parameters to determine the bottom hole pressure, and further solving the technical problem of the lack of in-depth data analysis methods for reservoir transformation construction parameters in the prior art.
[0036] As an optional embodiment, the target bottom hole pressure at the target moment is determined according to the distribution of the fluid in the target wellbore, including: respectively determining the mass of the liquid included in the fluid in the target wellbore and the mass of the proppant included in the fluid in the target wellbore; determining a first pressure and a second pressure according to the mass of the liquid and the mass of the proppant, wherein the first pressure is the pressure exerted on the bottom hole of the target wellbore by the gravity of the liquid, and the second pressure is the pressure exerted on the bottom hole of the target wellbore by the gravity of the proppant; determining the pressure loss caused by the frictional resistance exerted by the flow of the fluid in the target wellbore according to the distribution of the fluid in the target wellbore; and determining the target bottom hole pressure according to the first pressure, the second pressure and the pressure loss.
[0037] Optionally, the values of various construction parameters at the current moment can be recorded once at fixed intervals, for example, the values of various construction parameters can be recorded once every second. The pressure on the bottom of the well caused by the weight of the liquid and the proppant can be determined based on the mass of the liquid input into the target wellbore and the mass of the proppant input into the target wellbore. As the fluid flows in the target wellbore, the pressure of the fluid in the target wellbore on the bottom of the well will be partially lost due to the flow. The pressure loss caused by the frictional resistance generated by the fluid flow can also be determined by the distribution of the fluid in the target wellbore, and the target bottom hole pressure of the target wellbore is finally determined.
[0038] As an optional embodiment, the pressure loss caused by the frictional resistance generated by the fluid flow in the target wellbore is determined according to the distribution of the fluid in the target wellbore, including: obtaining the corresponding relationship between the pressure of the flow loss of the standard liquid in the experimental wellbore and the displacement of the standard liquid injected into the experimental wellbore, wherein the models of the experimental wellbore and the target wellbore match; determining the positions of multiple liquids included in the fluid in the target wellbore in the target wellbore according to the distribution of the fluid in the target wellbore; determining the liquid displacement injected into the target wellbore at the target time according to multiple construction parameters; obtaining the friction coefficients of multiple liquids; and determining the pressure loss caused by the frictional resistance generated by the fluid flow in the target wellbore according to the positions of the multiple liquids in the target wellbore, the liquid displacements, the friction coefficients of the multiple liquids and the corresponding relationships.
[0039] Optionally, Figure 3 It is a schematic diagram of different fluid compositions in an oil pipe combination and a wellbore provided according to an optional embodiment of the present invention. The diameter of the target wellbore is not the same everywhere, and the friction loss caused by different fluids flowing through wellbores with different diameters is different, so the distribution of the fluid in the target wellbore is required to confirm the positions of different fluids in the wellbore, and the fluids at different diameters in the wellbore are divided into blocks for calculation. In each block, there is only a fluid of a single density flowing through a wellbore of a single diameter, and the pressure loss caused by the frictional resistance generated by the fluid in the target wellbore in each block is calculated separately.
[0040] When calculating the pressure loss caused by the frictional resistance of the fluid in the target wellbore in each area, the calculation can be combined with the experimental data already available in the laboratory. In the laboratory, the pressure loss caused by the standard liquid flowing through the experimental wellbore of the same size can be calculated in advance, and the relationship between the displacement of the injected standard liquid and the pressure loss can be determined. If the wellbore includes three diameters, three related experiments can be performed to obtain three sets of relationships between displacement and pressure loss, and each set of relationships corresponds to the size of a diameter. In actual construction, the wellbore size of each area can be determined, the corresponding relationship between displacement and pressure loss can be found, and the pressure loss caused by the corresponding standard liquid in the relationship can be determined based on the liquid displacement at the current moment. Then, combined with the friction coefficient of the fluid in the target wellbore in this area and the pressure loss caused by the standard liquid, the pressure loss caused by the frictional resistance of the fluid in the target wellbore in this area can be determined.
[0041] As an optional embodiment, determining the mass of the proppant included in the fluid in the target wellbore includes: determining the volume of a first fluid in the fluid in the target wellbore based on multiple construction parameters, wherein the first fluid is a fluid mixed with the proppant and injected into the target wellbore from the ground; obtaining the concentration of the proppant in the first fluid; and determining the mass of the proppant included in the fluid in the target wellbore based on the volume of the first fluid and the concentration of the proppant in the first fluid.
[0042] Alternatively, the volume of the fluid mixed with the proppant can be determined based on the displacement of the injected liquid, and then the mass of the proppant included in the fluid can be determined based on the concentration of the proppant in the fluid. Subsequently, the bottom hole pressure caused by the gravity of the proppant on the target wellbore can be determined based on the mass of the proppant.
[0043] As an optional embodiment, determining the target bottom hole pressure according to the first pressure, the second pressure and the pressure loss includes: determining the target bottom hole pressure as the difference between the sum of the first pressure and the second pressure and the pressure loss. Optionally, after determining the pressure generated by the gravity of the liquid in the wellbore, the pressure generated by the gravity of the proppant and the pressure loss caused by the flow of the fluid in the target wellbore, the bottom hole pressure is the sum of the pressure generated by the gravity of the liquid and the pressure generated by the gravity of the proppant obtained by the above calculation, minus the pressure loss caused by the flow of the fluid in the target wellbore.
[0044] As an optional embodiment, the distribution of fluids in a target wellbore at a target time is determined based on multiple construction parameters, including: determining the order in which multiple liquids are injected into the target wellbore and the volumes of each of the multiple liquids injected into the target wellbore at the target time based on the multiple construction parameters; obtaining the volume of the target wellbore; and determining the distribution of the multiple liquids in the target wellbore at the target time based on the order in which the multiple liquids are injected into the target wellbore, the volumes of each of the multiple liquids injected into the target wellbore at the target time, and the volume of the target wellbore.
[0045] Optionally, the volume of the injected liquid can be determined based on the displacement of the liquid injected into the target wellbore at multiple moments recorded by multiple construction parameters. The positions of the multiple liquids in the wellbore after being injected can also be determined based on the moment when the multiple liquids are injected and the volume of the target wellbore, that is, the distribution of the multiple liquids in the target wellbore at a certain moment can be determined.
[0046] As an optional embodiment, it also includes: respectively determining multiple bottom hole pressures that the target wellbore is subjected to at other moments in the multiple moments except the target moment; and visually displaying the multiple bottom hole pressures and the target bottom hole pressure in the time sequence of the multiple moments.
[0047] Optionally, after determining the bottom hole pressure at a certain moment, the bottom hole pressures corresponding to multiple moments can be calculated, and the multiple bottom hole pressures can be plotted in time sequence for visual display. It should be noted that if the bottom hole pressure corresponding to the next moment of the target moment is calculated, the fluid distribution in the target wellbore can be updated based on the fluid distribution in the target wellbore corresponding to the target moment, and the updated fluid distribution in the target wellbore can be used for relevant calculations.
[0048] In reservoir transformation construction, bottom hole pressure refers to the pressure that the formation bears. Bottom hole pressure can be used to calculate the formation fracturing pressure, closing pressure, and evaluation and analysis after reservoir transformation, etc. It is the basis for optimizing construction and improving the process. However, due to technical and working conditions, many wells cannot directly install pressure gauges to measure bottom hole pressure, and can only indirectly guide construction through wellhead pressure (it is believed that the higher the wellhead pressure, the higher the bottom hole pressure). Guiding construction through wellhead pressure cannot take into account the composition, density differences, and friction differences of different liquids in the wellbore, and cannot consider the effect of proppants on bottom hole pressure (high wellhead pressure does not necessarily mean high bottom hole pressure). In summary, calculating the bottom hole pressure in reservoir transformation construction through construction data is of great significance to the analysis, optimization, and improvement of reservoir transformation construction.
[0049] It should be noted that, for the above-mentioned method embodiments, for the sake of simplicity, they are all described as a series of action combinations, but those skilled in the art should know that the present invention is not limited by the described action sequence, because according to the present invention, certain steps can be performed in other sequences or simultaneously. Secondly, those skilled in the art should also know that the embodiments described in the specification are all preferred embodiments, and the actions and modules involved are not necessarily required by the present invention.
[0050] Through the description of the above implementation methods, those skilled in the art can clearly understand that the processing method of the construction parameters according to the above embodiment can be implemented by means of software plus a necessary general hardware platform, and of course it can also be implemented by hardware, but in many cases the former is a better implementation method. Based on such an understanding, the technical solution of the present invention, in essence, or the part that contributes to the prior art, can be embodied in the form of a software product, which is stored in a storage medium (such as ROM / RAM, a magnetic disk, or an optical disk), and includes a number of instructions for enabling a terminal device (which can be a mobile phone, a computer, a server, or a network device, etc.) to execute the methods described in each embodiment of the present invention.
[0051] According to an embodiment of the present invention, a construction parameter processing device for implementing the above construction parameter processing method is also provided. Figure 4 is a structural block diagram of a construction parameter processing device provided according to an embodiment of the present invention, such as Figure 4 As shown, the construction parameter processing device includes: an acquisition module 42, a first determination module 44 and a second determination module 46. The construction parameter processing device is described below.
[0052] The acquisition module 42 is used to acquire a plurality of construction parameters corresponding to a plurality of time points during the reservoir transformation construction, wherein the plurality of construction parameters are used to perform the reservoir transformation construction.
[0053] The first determination module 44 is connected to the acquisition module 42 and is used to determine the distribution of the fluid in the target wellbore at the target time according to multiple construction parameters, wherein the multiple times include the target time, and the target wellbore is used to transport the fluid used to transform the reservoir to the reservoir.
[0054] The second determination module 46 is connected to the first determination module 44 and is used to determine the target bottom hole pressure at the target time according to the distribution of the fluid in the target wellbore.
[0055] It should be noted that the acquisition module 42, the first determination module 44 and the second determination module 46 correspond to steps S202 to S206 in the embodiment, and the examples and application scenarios implemented by the multiple modules and the corresponding steps are the same, but are not limited to the contents disclosed in the above embodiment. It should be noted that the above modules, as part of the device, can be run in the computer terminal 10 provided in the embodiment.
[0056] An embodiment of the present invention may provide a computer device. Optionally, in this embodiment, the computer device may be located in at least one network device among multiple network devices of a computer network. The computer device includes a memory and a processor.
[0057] Among them, the memory can be used to store software programs and modules, such as the program instructions / modules corresponding to the method and device for processing construction parameters in the embodiment of the present invention. The processor executes various functional applications and data processing by running the software programs and modules stored in the memory, that is, realizing the above-mentioned method for processing construction parameters. The memory may include a high-speed random access memory, and may also include a non-volatile memory, such as one or more magnetic storage devices, flash memory, or other non-volatile solid-state memory. In some examples, the memory may further include a memory remotely arranged relative to the processor, and these remote memories can be connected to the computer terminal via a network. Examples of the above-mentioned network include, but are not limited to, the Internet, an intranet, a local area network, a mobile communication network, and combinations thereof.
[0058] The processor can call the information and application programs stored in the memory through the transmission device to perform the following steps: obtaining multiple construction parameters corresponding to multiple moments during reservoir transformation construction, wherein the multiple construction parameters are used to transform the reservoir; determining the distribution of the fluid in the target wellbore at the target moment based on the multiple construction parameters, wherein the multiple moments include the target moment, and the target wellbore is used to transport the fluid used to transform the reservoir to the reservoir; determining the target bottom hole pressure at the target moment based on the distribution of the fluid in the target wellbore.
[0059] Optionally, the processor may also execute program code for the following steps: determining a target bottom hole pressure at a target moment based on the distribution of the fluid in the target wellbore, including: separately determining the mass of the liquid included in the fluid in the target wellbore, and the mass of the proppant included in the fluid in the target wellbore; determining a first pressure and a second pressure based on the mass of the liquid and the mass of the proppant, wherein the first pressure is the pressure exerted on the bottom hole of the target wellbore by the gravity of the liquid, and the second pressure is the pressure exerted on the bottom hole of the target wellbore by the gravity of the proppant; determining the pressure loss caused by the frictional resistance exerted by the flow of the fluid in the target wellbore based on the distribution of the fluid in the target wellbore; and determining the target bottom hole pressure based on the first pressure, the second pressure and the pressure loss.
[0060] Optionally, the processor may also execute program codes for the following steps: determining the pressure loss caused by the frictional resistance generated by the fluid flow in the target wellbore based on the distribution of the fluid in the target wellbore, including: obtaining the corresponding relationship between the pressure loss of the standard liquid flowing in the experimental wellbore and the displacement of the standard liquid injected into the experimental wellbore, wherein the models of the experimental wellbore and the target wellbore match; determining the positions of multiple liquids included in the fluid in the target wellbore in the target wellbore based on the distribution of the fluid in the target wellbore; determining the liquid displacement injected into the target wellbore at the target time based on multiple construction parameters; obtaining the friction coefficients of multiple liquids; determining the pressure loss caused by the frictional resistance generated by the fluid flow in the target wellbore based on the positions of the multiple liquids in the target wellbore, the liquid displacements, the friction coefficients of the multiple liquids and the corresponding relationships.
[0061] Optionally, the processor may also execute program code for the following steps: determining the mass of the proppant included in the fluid in the target wellbore, including: determining the volume of a first fluid in the fluid in the target wellbore based on a plurality of construction parameters, wherein the first fluid is a fluid mixed with proppant and injected into the target wellbore from the ground; obtaining the concentration of the proppant in the first fluid; and determining the mass of the proppant included in the fluid in the target wellbore based on the volume of the first fluid and the concentration of the proppant in the first fluid.
[0062] Optionally, the processor may also execute program code of the following steps: determining a target bottom hole pressure according to the first pressure, the second pressure and the pressure loss, including: determining the target bottom hole pressure as the difference between the sum of the first pressure and the second pressure and the pressure loss.
[0063] Optionally, the processor may also execute program code for the following steps: determining the distribution of fluids in the target wellbore at a target moment based on a plurality of construction parameters, including: determining the order in which the multiple liquids are injected into the target wellbore and the volumes of the multiple liquids injected into the target wellbore at the target moment based on the multiple construction parameters; obtaining the volume of the target wellbore; determining the distribution of the multiple liquids in the target wellbore at the target moment based on the order in which the multiple liquids are injected into the target wellbore, the volumes of the multiple liquids injected into the target wellbore at the target moment, and the volume of the target wellbore.
[0064] Optionally, the processor may also execute program code of the following steps: further comprising: respectively determining multiple bottom hole pressures at other moments in the multiple moments except the target moment; and visually displaying the multiple bottom hole pressures and the target bottom hole pressure in the time sequence of the multiple moments.
[0065] By adopting the embodiment of the present invention, a solution for processing construction parameters is provided. By obtaining multiple construction parameters corresponding to multiple moments during reservoir transformation construction, wherein the multiple construction parameters are used to transform the reservoir; according to the multiple construction parameters, the distribution of the fluid in the target wellbore at the target moment is determined, wherein the multiple moments include the target moment, and the target wellbore is used to transport the fluid used to transform the reservoir to the reservoir; according to the distribution of the fluid in the target wellbore, the target bottom hole pressure at the target moment is determined, and the purpose of analyzing the construction parameters to obtain the bottom hole pressure of the wellbore to better guide the reservoir transformation construction is achieved, thereby achieving the technical effect of deeply analyzing the reservoir transformation construction parameters to determine the bottom hole pressure, and further solving the technical problem that the data analysis method of the reservoir transformation construction parameters in the prior art is not in-depth.
[0066] A person of ordinary skill in the art can understand that all or part of the steps in the various methods of the above embodiments can be completed by instructing the hardware related to the terminal device through a program, and the program can be stored in a non-volatile storage medium, and the storage medium may include: a flash drive, a read-only memory (ROM), a random access memory (RAM), a magnetic disk or an optical disk, etc.
[0067] The embodiment of the present invention further provides a non-volatile storage medium. Optionally, in this embodiment, the non-volatile storage medium can be used to store the program code executed by the construction parameter processing method provided in the above embodiment.
[0068] Optionally, in this embodiment, the non-volatile storage medium may be located in any computer terminal in a computer terminal group in a computer network, or in any mobile terminal in a mobile terminal group.
[0069] Optionally, in this embodiment, the non-volatile storage medium is configured to store program codes for executing the following steps: obtaining multiple construction parameters corresponding to multiple moments during reservoir transformation construction, wherein the multiple construction parameters are used to transform the reservoir; determining the distribution of the fluid in the target wellbore at the target moment based on the multiple construction parameters, wherein the multiple moments include the target moment, and the target wellbore is used to transport the fluid used to transform the reservoir to the reservoir; determining the target bottom hole pressure at the target moment based on the distribution of the fluid in the target wellbore.
[0070] Optionally, in this embodiment, the non-volatile storage medium is configured to store program codes for executing the following steps: determining a target bottom hole pressure at a target moment based on the distribution of the fluid in the target wellbore, including: separately determining the mass of the liquid included in the fluid, and the mass of the proppant included in the fluid in the target wellbore; determining a first pressure and a second pressure based on the mass of the liquid and the mass of the proppant, wherein the first pressure is the pressure exerted on the bottom hole of the target wellbore by the gravity of the liquid, and the second pressure is the pressure exerted on the bottom hole of the target wellbore by the gravity of the proppant; determining the pressure loss caused by the frictional resistance exerted by the flow of the fluid in the target wellbore based on the distribution of the fluid in the target wellbore; and determining the target bottom hole pressure based on the first pressure, the second pressure and the pressure loss.
[0071] Optionally, in this embodiment, the non-volatile storage medium is configured to store program codes for executing the following steps: determining the pressure loss caused by the frictional resistance generated by the fluid flow in the target wellbore based on the distribution of the fluid in the target wellbore, including: obtaining the corresponding relationship between the pressure of the flow loss of the standard liquid in the experimental wellbore and the displacement of the standard liquid injected into the experimental wellbore, wherein the models of the experimental wellbore and the target wellbore match; determining the positions of multiple liquids included in the fluid in the target wellbore in the target wellbore based on the distribution of the fluid in the target wellbore; determining the liquid displacement injected into the target wellbore at the target time based on multiple construction parameters; obtaining the friction coefficients of multiple liquids; determining the pressure loss caused by the frictional resistance generated by the fluid flow in the target wellbore based on the positions of the multiple liquids in the target wellbore, the liquid displacements, the friction coefficients of the multiple liquids and the corresponding relationships.
[0072] Optionally, in this embodiment, the non-volatile storage medium is configured to store program code for executing the following steps: determining the mass of the proppant included in the fluid in the target wellbore, including: determining the volume of a first fluid in the fluid in the target wellbore based on multiple construction parameters, wherein the first fluid is a fluid mixed with proppant and injected into the target wellbore from the ground; obtaining the concentration of the proppant in the first fluid; and determining the mass of the proppant included in the fluid in the target wellbore based on the volume of the first fluid and the concentration of the proppant in the first fluid.
[0073] Optionally, in this embodiment, the non-volatile storage medium is configured to store program code for executing the following steps: determining the target bottom hole pressure based on the first pressure, the second pressure and the pressure loss, including: determining the target bottom hole pressure as the difference between the sum of the first pressure and the second pressure and the pressure loss.
[0074] Optionally, in this embodiment, the non-volatile storage medium is configured to store program code for executing the following steps: determining the distribution of fluid in the target wellbore at a target time based on multiple construction parameters, including: determining the order in which multiple liquids are injected into the target wellbore and the volumes of each of the multiple liquids injected into the target wellbore at the target time based on multiple construction parameters; obtaining the volume of the target wellbore; determining the distribution of the multiple liquids in the target wellbore at the target time based on the order in which the multiple liquids are injected into the target wellbore, the volumes of each of the multiple liquids injected into the target wellbore at the target time, and the volume of the target wellbore.
[0075] Optionally, in this embodiment, the non-volatile storage medium is configured to store program code for executing the following steps: also including: separately determining multiple bottom hole pressures at other moments in the multiple moments except the target moment; visually displaying the multiple bottom hole pressures and the target bottom hole pressure in time sequence of the multiple moments.
[0076] The serial numbers of the above embodiments of the present invention are only for description and do not represent the advantages or disadvantages of the embodiments.
[0077] In the above embodiments of the present invention, the description of each embodiment has its own emphasis. For parts that are not described in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.
[0078] In the several embodiments provided in this application, it should be understood that the disclosed technical content can be implemented in other ways. Among them, the device embodiments described above are only schematic. For example, the division of the units can be a logical function division. There may be other division methods in actual implementation. For example, multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some interfaces, indirect coupling or communication connection of units or modules, which can be electrical or other forms.
[0079] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple units. Some or all of the units may be selected according to actual needs to achieve the purpose of the present embodiment.
[0080] In addition, each functional unit in each embodiment of the present invention may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit. The above-mentioned integrated unit may be implemented in the form of hardware or in the form of software functional units.
[0081] If the integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a non-volatile storage medium. Based on this understanding, the technical solution of the present invention, or the part that contributes to the prior art, or all or part of the technical solution can be embodied in the form of a software product. The computer software product is stored in a storage medium, including a number of instructions to enable a computer device (which can be a personal computer, server or network device, etc.) to perform all or part of the steps of the method described in each embodiment of the present invention. The aforementioned storage medium includes: U disk, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), mobile hard disk, magnetic disk or optical disk and other media that can store program codes.
[0082] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principle of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.
Claims
1. A method for processing construction parameters, characterized in that: include: Acquire multiple construction parameters corresponding to multiple time points during reservoir transformation construction, wherein the multiple construction parameters are used to perform reservoir transformation construction; Determine the distribution of fluid in a target wellbore at a target time according to the multiple construction parameters, wherein the multiple time periods include the target time period, and the target wellbore is used to transport the fluid used to transform the reservoir to the reservoir; The target bottom hole pressure at the target time is determined according to the distribution of the fluid in the target wellbore.
2. The method according to claim 1, characterized in that The step of determining the target bottom hole pressure at the target time according to the distribution of the fluid in the target wellbore comprises: respectively determining the mass of the liquid included in the fluid in the target wellbore and the mass of the proppant included in the fluid in the target wellbore; Determine a first pressure and a second pressure according to the mass of the liquid and the mass of the proppant, wherein the first pressure is the pressure exerted on the bottom of the target wellbore by the gravity of the liquid, and the second pressure is the pressure exerted on the bottom of the target wellbore by the gravity of the proppant; Determining the pressure loss caused by the frictional resistance generated by the flow of the fluid in the target wellbore according to the distribution of the fluid in the target wellbore; The target bottom hole pressure is determined according to the first pressure, the second pressure and the pressure loss.
3. The method according to claim 2, characterized in that The step of determining the pressure loss caused by the frictional resistance generated by the flow of the fluid in the target wellbore according to the distribution of the fluid in the target wellbore comprises: Obtaining a corresponding relationship between the pressure of the flow loss of the standard liquid in the experimental wellbore and the displacement of the standard liquid injected into the experimental wellbore, wherein the model of the experimental wellbore matches that of the target wellbore; Determining positions of a plurality of liquids included in the fluid in the target wellbore in the target wellbore according to the distribution of the fluid in the target wellbore; Determining the liquid displacement injected into the target wellbore at the target time according to the multiple construction parameters; Obtaining friction coefficients of the plurality of liquids; The pressure loss caused by the frictional resistance generated by the fluid flow in the target wellbore is determined according to the positions of the multiple liquids in the target wellbore, the liquid displacement, the friction coefficients of the multiple liquids and the corresponding relationship.
4. The method according to claim 2, characterized in that: Determining a mass of the proppant included in the fluid within the target wellbore includes: According to the plurality of construction parameters, determining a volume of a first fluid in the fluid in the target wellbore, wherein the first fluid is a fluid mixed with the proppant and injected into the target wellbore from the ground; obtaining the concentration of the proppant in the first fluid; The mass of the proppant included in the fluid in the target wellbore is determined based on the volume of the first fluid and the concentration of the proppant in the first fluid.
5. The method according to claim 2, characterized in that: The step of determining the target bottom hole pressure according to the first pressure, the second pressure and the pressure loss comprises: The target bottom hole pressure is determined as a difference between a sum of the first pressure and the second pressure and the pressure loss.
6. The method according to claim 1, characterized in that The step of determining the distribution of the fluid in the target wellbore at the target time according to the plurality of construction parameters includes: Determining, according to the plurality of construction parameters, the order in which the plurality of liquids are injected into the target wellbore, and the volumes of the plurality of liquids injected into the target wellbore at the target time; Acquiring the volume of the target wellbore; The distribution of the multiple liquids in the target wellbore at the target moment is determined based on the order of injecting the multiple liquids into the target wellbore, the volumes of the multiple liquids injected into the target wellbore at the target moment, and the volume of the target wellbore.
7. The method according to any one of claims 1 to 6, characterized in that: Also includes: respectively determining a plurality of bottom hole pressures at other moments among the plurality of moments except the target moment; The multiple bottom hole pressures and the target bottom hole pressure are visually displayed according to the time sequence of the multiple moments.
8. A construction parameter processing device, characterized in that: include: An acquisition module, used for acquiring a plurality of construction parameters corresponding to a plurality of moments during the reservoir transformation construction, wherein the plurality of construction parameters are used for the reservoir transformation construction; A first determination module is used to determine the distribution of the fluid in the target wellbore at a target time according to the multiple construction parameters, wherein the multiple time points include the target time point, and the target wellbore is used to transport the fluid used to transform the reservoir to the reservoir; The second determination module is used to determine the target bottom hole pressure at the target moment according to the distribution of the fluid in the target wellbore.
9. A non-volatile storage medium, characterized in that: The non-volatile storage medium includes a stored program, wherein when the program is running, the device where the non-volatile storage medium is located is controlled to execute the construction parameter processing method described in any one of claims 1 to 7.
10. A computer device, characterized in that: include: Memory and processor, The memory stores a computer program; The processor is used to execute the computer program stored in the memory, and when the computer program is running, the processor executes the construction parameter processing method described in any one of claims 1 to 7.