Groove socket pipeline butt joint device and construction method thereof

By designing a docking device for movable base, centering mechanism and thrust mechanism, the problems of low assembly efficiency and low quality in the construction of cement bearing and insertion pipes are solved, and the precise docking and construction efficiency of bearing and insertion pipes are achieved.

CN119267641APending Publication Date: 2025-01-07CHINA METALLURGICAL CONSTR ENG GRP
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411544246.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-31
Publication Date
2025-01-07

AI Technical Summary

Technical Problem

During the construction of cement bearing pipes, it is impossible to move manually due to weight reasons, resulting in low assembly efficiency, requiring multiple people to operate and relying on experience, which can easily lead to deviation and affect construction quality and efficiency.

Method used

A docking device including a movable base, a centering mechanism, a support assembly and a thrust mechanism is designed. Through the coordination of the centering disk and the support assembly, the precise docking of the bearing tube is achieved, and manpower operation is reduced through the thrust mechanism.

Benefits of technology

It improves the efficiency and quality of the docking construction of the insertion pipe, reduces human resources waste, ensures the accuracy of docking, and simplifies the excavation and backfilling process of trenches.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119267641A_ABST
    Figure CN119267641A_ABST
Patent Text Reader

Abstract

The invention discloses a butt joint device for groove socket pipelines. The butt joint device comprises a movable base; the centering mechanism comprises a base arranged on the movable base in a lifting mode and a centering disc which can be driven to be arranged on the base in the axis direction of the socket pipe in a sliding mode. The two supporting assemblies are oppositely arranged on the movable base, each supporting assembly comprises a supporting seat which can be driven to move transversely and can be arranged on the movable base in a locked mode, and a supporting face which is obliquely arranged relative to the horizontal plane and used for supporting the socket pipe is arranged on each supporting seat; the movable base is provided with a notch part which enables the socket pipe to fall on the ground and enables the movable base to be moved away after the supporting base is moved away. A base locking device; a thrust mechanism; the invention further discloses a construction method of the groove socket pipeline, the butt joint device and the construction method of the groove socket pipeline can be beneficial to improving the construction efficiency of butt joint construction of the cement socket pipeline, and meanwhile, the construction quality of the pipeline is beneficial to improving.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, and in particular to a grooved socket pipe docking device and a construction method thereof. Background Art

[0002] The socket and spigot pipes are made into sockets and spigots at both ends of the pipe respectively, and then the two adjacent sections of the socket and spigot pipes are sealed and spliced ​​to form a conveying pipe. Cement socket and spigot pipes have been widely used in urban road drainage systems because of their relatively low production cost. However, due to the relatively heavy weight of the cement socket and spigot pipes, it is impossible to manually move the pipe sections for assembly, and the efficiency of their docking and assembly has always been one of the key links affecting the overall progress of the construction. At present, in the construction process of cement socket and spigot pipes, generally, the trench for laying the cement socket and spigot pipes is first excavated by an excavator, and then the socket and spigot pipes are tied with slings, and then two to three operators go down to the trench to manually straighten the socket and spigot pipes for docking and assembly. This construction method first requires a large number of operators, which wastes human resources; at the same time, the width of the trench needs to reserve enough standing space for people, which makes the construction efficiency of the early excavation and later backfilling of the trench low; at the same time, the docking process depends entirely on the workers' experience to judge whether it is aligned, which is inefficient, and it is easy to force the splicing due to incomplete alignment, causing the installed pipe sections to be offset, affecting the overall docking quality of the pipeline.

[0003] Therefore, it is necessary to provide a docking device and a construction method for grooved and socket pipe construction, hoping to improve the construction efficiency of grooved and socket pipe docking construction and improve the quality of pipeline construction. Summary of the invention

[0004] In view of this, an object of the present invention is to provide a grooved and socket pipe docking device and a construction method thereof, which can be beneficial to improving the construction efficiency of the grooved and socket pipe docking construction, and at the same time help to improve the quality of pipeline construction.

[0005] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: a grooved socket pipe docking device, comprising: a movable base; a centering mechanism, comprising a base that can be raised and lowered on the movable base and a centering plate that can be driven to slide along the axial direction of the socket pipe on the base; two groups of support assemblies arranged opposite to each other on the movable base, the support assembly comprising a support seat that is arranged on the movable base in a manner that can be driven to move laterally and can be locked, the support seat is provided with a support surface that is inclined relative to a horizontal plane and is used to support the socket pipe; the movable base is provided with a notch portion that can make the socket pipe fall to the ground and the movable base move away after the support seat is removed; a base locking device, which is arranged on the movable base to complete the position locking of the movable base; a thrust mechanism, which is arranged on the base to push the socket pipe to move.

[0006] Furthermore, the movable base includes a bottom plate, the support assembly also includes a slide seat fixed on the bottom plate, at least two groups of laterally arranged guide cylinders are fixed on the slide seat, the support seat includes a diagonal support plate and a sliding column fixed on the back of the diagonal support plate and slidably mounted with the guide cylinder, and the support surface is formed on the diagonal support plate.

[0007] Furthermore, a plurality of universal balls for supporting the bell-and-spigot pipe are evenly distributed on the diagonal support plate along the axial direction of the bell-and-spigot pipe; a first driving electric cylinder is fixed on the sliding seat, and a telescopic end of the first driving electric cylinder is fixedly connected to the diagonal support plate.

[0008] Furthermore, it also includes a base locking device, which includes at least two groups of second driving electric cylinders arranged on the bottom plate, and the telescopic ends of the two groups of second driving electric cylinders can be respectively abutted against the two side walls of the construction groove after moving.

[0009] Furthermore, it also includes a thrust mechanism, which includes a third driving electric cylinder and a thrust plate that can be driven to slide along the axis direction of the socket pipe and is arranged on the base. The telescopic end of the third driving electric cylinder is connected to the thrust plate to drive the thrust plate to move.

[0010] Furthermore, two groups of fixed cylinders are fixed on the base, a U-shaped slide is fixed on the back of the thrust plate, two side arms of the U-shaped slide are correspondingly slidably arranged in the two fixed cylinders, and the telescopic end of the third driving electric cylinder is fixedly connected to the U-shaped slide.

[0011] Furthermore, the centering disk and the thrust disk are both annular disk structures with a fractured portion at the bottom, and the thrust disk is coaxially arranged with the centering disk.

[0012] Furthermore, the notch is a U-shaped notch arranged on the bottom plate, the base is a door-shaped base, and a lifting cylinder is arranged at the bottom of the door-shaped base.

[0013] Furthermore, a U-shaped slide bar is fixedly arranged on the back of the centering plate, and the base is provided with two mounting holes which penetrate the base longitudinally, and two side arms of the U-shaped slide bar are correspondingly slidably arranged in the two mounting holes.

[0014] A method for constructing a grooved and socketed pipe is provided, wherein the construction is completed by using the grooved and socketed pipe docking device as described above, and comprises the following steps:

[0015] S1: Dig the trench and complete the hardening and leveling of the trench bottom;

[0016] S2: Hoist and complete the fixed installation of the first section of the bell and spigot pipe;

[0017] S3: Use the grooved socket pipe docking device to complete the socket pipe docking, including:

[0018] S301: Move the centering plate to make the centering plate slide into the first section of the bell-and-spigot pipe to align the movable base with the first section of the bell-and-spigot pipe, and lock the position of the movable base after alignment through the base locking device;

[0019] S302: Move out the centering plate, hoist the bell-and-spigot pipes to be connected onto the support assembly, and use the centering plate to coordinate with the position adjustment of the support seat to complete the position alignment of the bell-and-spigot pipes to be connected;

[0020] S303: Keep the centering plate in the bell-and-spigot pipe to be butted, and push the bell-and-spigot pipe to be butted through the thrust mechanism to complete the butt connection;

[0021] S304: Remove the centering plate, loosen the support seat, and then move the movable base to the installation position of the next section of the bell and spigot pipe until all the bell and spigot pipes are installed.

[0022] Compared with the prior art, the present invention has the following beneficial effects:

[0023] The grooved socket pipe docking device and the construction method thereof provided by the present invention can be beneficial to improving the construction efficiency of cement socket pipe docking construction, and at the same time, it is beneficial to improving the quality of pipe construction; specifically, the movable base can be quickly aligned with the upper section of the socket pipe through the provided centering mechanism, and then when the socket pipe to be docked is hoisted onto the supporting assembly, the centering mechanism and the supporting assembly can also be used to coordinate and adjust to quickly complete the centering and alignment, so that the socket pipe to be docked can be directly pushed to dock with the upper section of the socket pipe, and the centering plate can play a good guiding role in the docking process to ensure the accuracy of docking, thereby improving the construction efficiency and construction quality; at the same time, by adopting the device, there is no need for multiple people Just go down into the trench to operate, that is, there is no need for multiple people to straighten the socket and spigot for docking, which reduces the waste of human resources; at the same time, since the movable base is provided with a notch portion that can make the socket and spigot fall to the ground and the movable base move away after the support seat is removed, after the docking construction is completed, the support seat can be loosened to remove the movable base for docking installation at the next position, thereby ensuring the construction efficiency; at the same time, after the movable support seat is removed, a avoidance can be formed for the raised step at the socket of the socket and spigot, so that the movable base can be smoothly moved away; at the same time, by using the groove socket pipe docking device, the groove width does not need to be excavated too wide, which is beneficial to improving the trench excavation efficiency and backfilling efficiency, and can also improve the construction efficiency.

[0024] Other advantages, objectives and features of the present invention will be described in the following description to some extent, and to some extent, will be obvious to those skilled in the art based on the following examination and study, or can be taught from the practice of the present invention. The objectives and other advantages of the present invention can be realized and obtained through the following description. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 A schematic diagram of the axonometric structure of the present invention

[0026] Figure 2 Schematic diagram of the top view of the structure of the present invention

[0027] Figure 3 This is a structural diagram of the present invention in use

[0028] Figure markings: 1- movable base; 1a- notch; 101- bottom plate; 2- centering mechanism; 201- base; 201a- fixed cylinder; 202- centering plate; 203- lifting electric cylinder; 204- U-shaped slide bar; 3- support assembly; 301- support seat; 301a- support surface; 301b- diagonal support plate; 301c- slide column; 301d- universal ball; 302- slide seat; 303- first driving electric cylinder; 4- base locking device; 401- second driving electric cylinder; 5- thrust mechanism; 501- thrust plate; 502- third driving electric cylinder; 503- U-shaped slide; 6- socket pipe. DETAILED DESCRIPTION

[0029] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. It should be noted that the drawings are only for illustrative purposes, and only represent schematic diagrams, not physical drawings, and cannot be understood as limitations on the present invention; in order to better illustrate the embodiments of the present invention, some parts of the drawings may be omitted, enlarged or reduced, and do not represent the size of the actual product; for those skilled in the art, it is understandable that some well-known structures and their descriptions in the drawings may be omitted.

[0030] Here is a unified explanation. Unless otherwise specified, the "transverse" and "longitudinal" mentioned below refer to the width direction of the pipeline construction groove, and the "longitudinal" refers to the length direction of the pipeline construction groove; that is, the length direction of the bell-and-spigot pipe is the "longitudinal" direction, and the direction perpendicular to the length direction of the bell-and-spigot pipe in the horizontal plane is the "transverse" direction.

[0031] See also Figure 1-3In the present embodiment, a grooved socket pipe docking device is disclosed, comprising: a movable base 1, wherein the movable base 1 is used to ensure the movement of the device as a whole; a centering mechanism 2, comprising a base 201 which can be lifted and lowered on the movable base 1 and a centering plate 202 which can be driven to slide along the axial direction of the socket pipe 6 on the base 1. It can be understood that the height of the centering plate 202 can be adjusted by adjusting the height of the base 201 to ensure that the centering plate 202 can be smoothly inserted into the installed upper section of the socket pipe during centering, thereby completing the position confirmation of the centering plate 202. Two sets of support assemblies 3 are arranged on the movable base 1 in opposite directions, and the support assembly 3 includes a support seat 301 arranged on the movable base 1 in a manner that can be driven to move laterally and can be locked, and the support seat 301 is provided with a support surface 301a arranged obliquely relative to the horizontal plane and used to hold up the bell-and-spigot pipe 6. It can be understood that the support surfaces 301a on the two sets of support seats 301 can form an "inverted eight-shaped" support structure, and the bell-and-spigot pipe 6 can be placed on the two support seats 301; because the support seat 301 can be driven to move laterally and can be locked, the movable support By adjusting the position of the support seat 301, the height position of the bell-and-spigot 6 can be adjusted (the closer the two sets of support seats 301 are, the higher the position of the lifted bell-and-spigot 6 is). In this way, by controlling the position of the mobile support seat 301 and cooperating with the centering plate 202, the position of the bell-and-spigot to be connected can be quickly aligned, and then the bell-and-spigot to be connected can be pushed to complete the connection. The movable base 1 is provided with a notch 1a that can make the bell-and-spigot fall to the ground after the support seat 301 is removed and the movable base 1 can be removed. In this way, after the connection is completed, the movable base 1 can be removed to carry out the connection construction at the next position. It is understood that the distance between the bell and spigot 6 and the ground is very small. After the support seat 301 is removed, the bell and spigot 6 can be stably supported by the ground, which will not affect the docking quality; it is understandable that the centering plate 202 is usually slightly smaller than the inner diameter of the bell and spigot 6; the base locking device 4 is arranged on the movable base 1 to complete the position locking of the movable base 1. The base locking device 4 can complete the position locking of the movable base 1 to prevent displacement; the thrust mechanism 5 is arranged on the base 201 to push the bell and spigot to move. By setting the thrust mechanism 5, there is no need for manpower to push the bell and spigot to move, thereby reducing the waste of human resources;

[0032] The cement bell-and-spigot pipe docking auxiliary device in the above-mentioned structural design can help improve the construction efficiency of cement bell-and-spigot pipe docking construction, and at the same time help improve the quality of pipeline construction; specifically, the set centering mechanism 2 can quickly complete the centering and alignment of the movable base 1 and the previous section of the bell-and-spigot pipe, and then when the bell-and-spigot pipe to be docked is hoisted onto the support assembly 3, the position of the section of the bell-and-spigot pipe can also be quickly aligned through the coordinated adjustment of the centering mechanism 2 and the support assembly 3, so that the bell-and-spigot pipe to be docked can be directly pushed to dock with the previous section of the bell-and-spigot pipe. During the docking process, the centering plate can play a good guiding role to ensure the accuracy of the docking, thereby improving the construction efficiency and construction quality; at the same time, by adopting this device, there is no need for multiple people Just go down into the trench to operate, that is, there is no need for multiple people to straighten the socket and spigot for docking, which reduces the waste of human resources; at the same time, since the movable base 1 is provided with a notch portion that can make the socket and spigot fall to the ground and the movable base 1 move away after the support seat is removed, after the docking construction is completed, the support seat 301 can be loosened to remove the movable base 1 for docking installation at the next position, thereby ensuring the construction efficiency; at the same time, after the movable support seat 301 is removed, a avoidance for the raised step at the socket of the socket and spigot can be formed, so that the movable base 1 can be smoothly moved away; at the same time, by using the groove socket pipe docking device, the groove width does not need to be excavated too wide, which is beneficial to improving the trench excavation efficiency and backfilling efficiency, and can also improve the construction efficiency.

[0033] In this embodiment, the movable base 1 includes a base plate 101, and the support assembly 3 also includes a slide seat 302 fixed on the base plate 101, and at least two groups of laterally arranged guide cylinders 302a are fixed on the slide seat 302. The support seat 301 includes a slide column 301c and a slide column 301c fixed on the back of the inclined support plate 301b and slidably fitted with the guide cylinder 302a, and the support surface 301a is formed on the inclined support plate 301b; specifically, the slide seat 302 is welded and fixed on the base plate 101, and the guide cylinder 302a is arranged in two groups and adopts a square cylinder structure; the structural design has a simple structure, is easy to install, has good support stability, good structural strength, and good sliding reliability; the inclined support plate 301b can form a stable support for the socket pipe, and at the same time, the matching installation of the slide column 301c and the guide cylinder 302a can ensure sufficient bearing capacity.

[0034] In this embodiment, a plurality of universal balls 301d for supporting the bell-and-spigot pipe are evenly distributed on the diagonal support plate 301b along the axial direction of the bell-and-spigot pipe 6; by providing a plurality of universal balls 301d, the bell-and-spigot pipe contacts the universal balls 301d, which can effectively reduce friction, facilitate the sliding of the bell-and-spigot pipe to complete docking, and reduce the risk of jamming; at the same time, a plurality of universal balls 301d can form a stable support for the bell-and-spigot pipe, ensuring the position accuracy of the bell-and-spigot pipe, thereby further improving the construction efficiency.

[0035] In this embodiment, a first driving electric cylinder 303 is fixedly provided on the sliding seat 302, and the telescopic end of the first driving electric cylinder 303 is fixedly connected to the diagonal support plate 301b; it can be understood that the electric cylinder is a modular product that integrates the servo motor and the lead screw, converts the rotational motion of the servo motor into linear motion, and at the same time converts the best advantages of the servo motor - precise speed control, precise number of revolutions control, and precise torque control into - precise speed control, precise position control, and precise thrust control, thereby realizing a new revolutionary product in the high-precision linear motion series; of course, it can also be understood that the first driving electric cylinder 303 can be powered by batteries or the like, and can be remotely controlled, which will not be repeated here; by using an electric cylinder to drive the support seat 301 to move, it is beneficial to ensure the position accuracy and movement stability of the support seat 301, and the position locking of the support seat 301 can be completed, and the control is convenient, thereby further improving the convenience of adjustment and ensuring construction efficiency.

[0036] In this embodiment, the base locking device includes at least two groups of second driving electric cylinders 401 arranged on the base plate 101, and the telescopic ends of the two groups of second driving electric cylinders 401 can be respectively abutted against the two side walls of the construction groove after moving; specifically, the second driving electric cylinders 401 are four groups here, which are arranged at the four corners of the base plate 101, and the telescopic ends of the second driving electric cylinders 401 are fixedly connected with support plates to increase the support area and improve the support stability; by adopting the second driving electric cylinders 401, it is beneficial to ensure the convenience of locking. During use, the telescopic ends of the second driving electric cylinders 401 are controlled to move and abut against the two side walls of the construction groove to ensure the position locking of the movable base 1, and the locking effect is good, which is beneficial to ensuring the construction quality.

[0037] In this embodiment, the thrust mechanism includes a third driving electric cylinder 502 and a thrust plate 501 which can be driven to slide along the axial direction of the socket pipe 6 and is arranged on the base 201. The telescopic end of the third driving electric cylinder 502 is connected to the thrust plate 501 for driving the thrust plate 501 to move. Here, the third driving electric cylinder 502 is fixedly installed on the top of the base 201. By setting up the thrust mechanism 5, the pushing of the socket pipe to be spliced ​​can be completed without manual pushing, which is beneficial to reducing labor intensity. At the same time, the third driving electric cylinder 502 is used to complete the pushing, with good running stability and convenient operation, which is beneficial to further improve the construction efficiency.

[0038] In this embodiment, two groups of fixed cylinders 201a are fixedly provided on the base 201, a U-shaped slide 503 is fixedly provided on the back of the thrust plate 501, and the two side arms of the U-shaped slide 503 are correspondingly slidably arranged in the two fixed cylinders 201a, and the telescopic end of the third driving electric cylinder 502 is fixedly connected to the U-shaped slide 503; specifically, the fixed cylinder 201a here adopts a square cylinder; this structural design has good structural stability and good strength, which is conducive to ensuring that sufficient thrust is provided to the socket pipe and improves durability.

[0039] In this embodiment, the centering plate 202 and the thrust plate 501 are both annular plate structures with a broken portion at the bottom, and the thrust plate 501 is coaxially arranged with the centering plate 202; this structural design has good compactness, and the thrust plate 501 can fit onto the step at the socket of the bell-and-spigot pipe, so that the bell-and-spigot pipe is subjected to a more uniform thrust, thereby further improving the construction quality.

[0040] In this embodiment, the notch portion 1a is a U-shaped notch arranged on the bottom plate 101, and the base 201 is a gate-type seat. A lifting electric cylinder 203 is arranged at the bottom of the gate-type seat, and the telescopic end of the lifting electric cylinder 203 is fixedly connected to the base; the lifting electric cylinder 203 can ensure the accuracy and convenience of height adjustment of the base 201; the gate-type seat has a simple structure and good compactness.

[0041] In this embodiment, a U-shaped slide bar 204 is fixedly provided on the back side of the centering plate 202, and the base 201 is provided with two mounting holes that penetrate the base 201 longitudinally. The two side arms of the U-shaped slide bar 204 are correspondingly slidably arranged in the two mounting holes. By setting the U-shaped slide bar 204, the centering plate 202 can be manually pushed to slide stably, which has a simple structure and is easy to operate.

[0042] This embodiment also discloses a method for constructing a grooved and socketed pipe, which is completed by using the grooved and socketed pipe docking device as described above, and includes the following steps:

[0043] S1: excavating a trench, and completing the hardening and leveling of the trench bottom, which can facilitate the movement of the movable base 1 and prevent settlement;

[0044] S2: Lift and complete the fixed installation of the first section of the bell-and-spigot pipe. The lifting can be completed by lifting equipment such as electric hoists, balance cranes, etc.;

[0045] S3: Use the grooved socket pipe docking device to complete the socket pipe docking, including:

[0046] S301: Move the centering plate 202 so that the centering plate 202 slides into the first section of the bell-and-spigot pipe to align the movable base 1 with the first section of the bell-and-spigot pipe, and lock the position of the movable base 1 after alignment by the base locking device 4. It can be understood that the centering plate 202 can be moved into the first section of the bell-and-spigot pipe by adjusting the height of the base 201 and the position of the movable base 1;

[0047] S302: Remove the centering plate 202, hoist the bell-and-spigot pipes to be connected onto the support assembly 3, and use the centering plate 202 to coordinate with the position adjustment of the support seat 301 to complete the position alignment of the bell-and-spigot pipes to be connected;

[0048] S303: Keep the centering plate 202 in the socket pipe to be docked, and push the socket pipe to be docked through the thrust mechanism 4 to complete the docking. At this time, the centering plate 202 can provide a guide to ensure the position accuracy of the operation;

[0049] S304: Remove the centering plate 202, loosen the support seat 301, and then move the movable base 1 to the installation position of the next section of the bell and spigot pipe until all the bell and spigot pipes are installed;

[0050] Of course, after all the pipes are connected, the trench backfilling construction will be carried out.

[0051] The above-mentioned construction method of grooved socket pipe is conducive to ensuring construction quality and construction efficiency.

[0052] Although the present invention has been described in detail with reference to preferred embodiments, those skilled in the art should understand that the technical solutions of the present invention may be modified or replaced by equivalents without departing from the purpose and scope of the technical solutions of the present invention, which should be included in the scope of the claims of the present invention.

Claims

1. A grooved and socketed pipe docking device, characterized in that: include: A movable base (1); The centering mechanism (2) comprises a base (201) which can be lifted and lowered on the movable base (1) and a centering plate (202) which can be driven to slide along the axis direction of the bell pipe (6) and is arranged on the base (1); Two groups of supporting assemblies (3) are arranged opposite to each other on the movable base (1), the supporting assemblies (3) comprising a supporting seat (301) arranged on the movable base (1) in a manner that can be driven to move laterally and can be locked, the supporting seat (301) being provided with a supporting surface (301a) arranged obliquely relative to a horizontal plane and used to support the bell-and-spigot pipe (6); the movable base (1) is provided with a notch portion (1a) that can allow the bell-and-spigot pipe (6) to fall to the ground and the movable base (1) to be removed after the supporting seat (301) is removed; A base locking device (4), arranged on the movable base (1) and used to lock the position of the movable base (1); The thrust mechanism (5) is arranged on the base (201) and is used to push the bell-and-spigot pipe to move.

2. The grooved socket pipe docking device according to claim 1, characterized in that: The movable base (1) comprises a base plate (101), the support assembly (3) further comprises a slide seat (302) fixedly mounted on the base plate (101), at least two groups of transversely arranged guide cylinders (302a) are fixedly mounted on the slide seat (302), the support seat (301) comprises a diagonal support plate (301b) and a slide column (301c) fixedly mounted on the back of the diagonal support plate (301b) and slidably mounted with the guide cylinder (302a), and the support surface (301a) is formed on the diagonal support plate (301b).

3. The grooved socket pipe docking device according to claim 2, characterized in that: A plurality of universal balls (301d) for supporting the bell-and-spigot pipe are evenly arranged on the diagonal support plate (301b) along the axial direction of the bell-and-spigot pipe (6); a first driving electric cylinder (303) is fixedly arranged on the slide seat (302), and a telescopic end of the first driving electric cylinder (303) is fixedly connected to the diagonal support plate (301b).

4. The grooved socket pipe docking device according to any one of claims 2 or 3, characterized in that: The base locking device comprises at least two groups of second driving electric cylinders (401) arranged on the bottom plate (101), and the telescopic ends of the two groups of second driving electric cylinders (401) can respectively abut against two side walls of the construction groove after moving.

5. The grooved socket pipe docking device according to any one of claims 1 to 4, characterized in that: The thrust mechanism comprises a third driving electric cylinder (502) and a thrust plate (501) which is driven to slide along the axis direction of the socket pipe (6) and is arranged on the base (201); the telescopic end of the third driving electric cylinder (502) is connected to the thrust plate (501) to drive the thrust plate (501) to move.

6. The grooved and socket pipe docking device according to claim 5, characterized in that: Two groups of fixed cylinders (201a) are fixedly arranged on the base (201), a U-shaped slide (503) is fixedly arranged on the back of the thrust plate (501), two side arms of the U-shaped slide (503) are correspondingly slidably arranged in the two fixed cylinders (201a), and the telescopic end of the third driving electric cylinder (502) is fixedly connected to the U-shaped slide (503).

7. The grooved and socket pipe docking device according to claim 6, characterized in that: The centering disk (202) and the thrust disk (501) are both annular disk structures with a broken portion at the bottom, and the thrust disk (501) is coaxially arranged with the centering disk (202).

8. The grooved and socket pipe docking device according to claim 2, characterized in that: The notch portion (1a) is a U-shaped notch provided on the bottom plate (101); the base (201) is a gate-shaped base, and a lifting electric cylinder (203) is provided at the bottom of the gate-shaped base.

9. The grooved and socket pipe docking device according to claim 8, characterized in that: A U-shaped slide bar (204) is fixedly arranged on the back of the centering plate (202), and two mounting holes are longitudinally penetrated on the base (201), and two side arms of the U-shaped slide bar (204) are correspondingly slidably arranged in the two mounting holes.

10. A method for constructing a grooved and socketed pipe, using the grooved and socketed pipe docking device according to any one of claims 1 to 9, characterized in that: The steps include: S1: Dig the trench and complete the hardening and leveling of the trench bottom; S2: Hoist and complete the fixed installation of the first section of the bell and spigot pipe; S3: Use the grooved socket pipe docking device to complete the socket pipe docking, including: S301: Move the centering plate (202) so that the centering plate (202) slides into the first section of the bell-and-spigot pipe to align the movable base (1) with the first section of the bell-and-spigot pipe, and lock the position of the movable base (1) after alignment through the base locking device (4); S302: Remove the centering plate (202), hoist the bell-and-spigot pipes to be connected onto the support assembly (3), and use the centering plate (202) to coordinate with the position adjustment of the support seat (301) to complete the position alignment of the bell-and-spigot pipes to be connected; S303: Keep the centering plate (202) in the bell-and-spigot pipe to be connected, and push the bell-and-spigot pipe to be connected through the thrust mechanism (4) to complete the connection; S304: Remove the centering plate (202), then loosen the support seat (301), and then move the movable base (1) to the installation position of the next section of the bell and spigot pipe until all the bell and spigot pipes are installed.

Citation Information

Cited By

  • Pipeline butt joint device for water conservancy construction

    CN121025253A