Nuclear power plant overhaul planning system

By designing a nuclear power plant overhaul planning system, the problems of low data entry efficiency and unintuitive display are solved, automatic calculation and display are realized, planning efficiency and accuracy are improved, and the needs of nuclear power plant full-life overhaul planning are adapted.

CN119294649APending Publication Date: 2025-01-10CNNC NUCLEAR POWER OPERATION MANAGEMENT CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411239431.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-05
Publication Date
2025-01-10

AI Technical Summary

Technical Problem

The existing nuclear power plant overhaul planning methods have problems such as excessive data entry, low efficiency and error-prone, and the data display is not intuitive and comprehensive, so it cannot adapt to the requirements of the overhaul planning of the full life of nuclear power plant.

Method used

A nuclear power plant overhaul planning system was designed, including acquisition modules, calculation modules and display modules, which were used to automatically obtain, calculate and display nuclear power plant overhaul planning data, identify and identify overhauls during the Spring Festival, peak summer and peak winter Plan data, generate intuitive planning maps and statistics, and support data adjustment and release.

Benefits of technology

It improves the efficiency of the overhaul planning of nuclear power plants, avoids errors, realizes intuitive and comprehensive display of data, facilitates the adjustment and release of overhaul planning personnel, and meets the various needs of the overhaul planning of nuclear power plants.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119294649A_ABST
    Figure CN119294649A_ABST
Patent Text Reader

Abstract

The invention specifically relates to a nuclear power plant overhaul planning system comprising an acquisition module used for acquiring data required by nuclear power plant overhaul planning; the calculation module is used for generating nuclear power plant overhaul planning data; identifying the overhaul planning data falling into the Spring Festival, the peak-meeting summer period and the peak-meeting winter period and having overlapping, and calculating overlapping data of the overhaul planning data having overlapping; the display module is used for generating and displaying a nuclear power plant overhaul planning graph; generating and displaying nuclear power plant overhaul planning statistical data; marking the major repair planning data falling into the Spring Festival, the peak-meeting summer period and the peak-meeting winter period and having overlapping on the nuclear power plant major repair planning map, and displaying the overlapping data of the major repair planning data having overlapping on the nuclear power plant major repair planning map. According to the nuclear power plant overhaul planning system, nuclear power plant overhaul automatic planning is realized, nuclear power plant overhaul planning efficiency is improved, and nuclear power plant overhaul planning errors are avoided; and direct and comprehensive display of nuclear power plant overhaul planning data is realized.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of nuclear power plant overhaul planning, and in particular to a nuclear power plant overhaul planning system. Background Art

[0002] Nuclear power plant overhaul planning is an important reference for the formulation of nuclear power plant fuel planning, power generation planning and operating indicators. In addition to meeting the needs of the power grid, nuclear power plant overhaul planning must also consider the safety and economy of the nuclear power plant and is subject to the fuel cycle length of the unit.

[0003] At present, nuclear power plant overhaul planning is mainly calculated by using EXCEL tables, and the nuclear power plant overhaul planning map is drawn through the charts of EXCEL tables for display. This method has the following problems:

[0004] 1. All elements required for the nuclear power plant overhaul plan need to be entered one by one in the EXCEL table, resulting in low efficiency of the nuclear power plant overhaul plan. When the nuclear power plant overhaul plan is adjusted across years, the calculation formula needs to be adjusted, which is prone to errors.

[0005] 2. When using EXCEL table charts to draw nuclear power plant overhaul planning maps, it is necessary to copy data and a series of complex data references and formulas to generate charts and text information on the charts. The text information that can be displayed on the charts is also relatively limited. In order to obtain a better chart display effect, it is also necessary to constantly try and adjust the size, position and color of the charts.

[0006] 3. In order to obtain an overhaul plan that is more beneficial to the operating performance of the nuclear power plant and meets the requirements of the power grid, it is necessary to compare multiple overhaul planning schemes.

[0007] The existing nuclear power plant overhaul planning method has the above problems and cannot meet the requirements of nuclear power plant overhaul planning throughout its life cycle. At the same time, the display of nuclear power plant overhaul planning data is not intuitive and comprehensive, and non-overhaul planning personnel cannot easily obtain nuclear power plant overhaul planning data.

[0008] With the continuous improvement of the requirements for refined nuclear power plant overhaul management, it is necessary to take into account all factors that affect the overhaul planning of nuclear power plants and develop a new overhaul planning method for nuclear power plants to achieve convenient calculation and adjustment of nuclear power plant overhaul plans and intuitive and comprehensive display of nuclear power plant overhaul planning data. This will not only help overhaul planners to prepare nuclear power plant overhaul plans, but also better and more conveniently serve non-overhaul planners and provide a reference for fuel planning, power generation planning, and the formulation of operating indicators. Summary of the invention

[0009] One of the purposes of the present invention is to provide a nuclear power plant overhaul planning system to solve the problems of multiple data entry, low efficiency and easy errors in the existing nuclear power plant overhaul planning method, realize automatic planning of nuclear power plant overhaul, improve the efficiency of nuclear power plant overhaul planning, and avoid errors in nuclear power plant overhaul planning.

[0010] The second purpose of the present invention is to provide a nuclear power plant overhaul planning system to solve the problem that the existing nuclear power plant overhaul planning data display is not intuitive and comprehensive, and to achieve intuitive and comprehensive display of nuclear power plant overhaul planning data.

[0011] In order to solve the above problems, the present invention provides a nuclear power plant overhaul planning system, comprising:

[0012] The acquisition module is used to obtain the data required for the overhaul planning of nuclear power plants;

[0013] A calculation module is used to perform nuclear power plant overhaul planning according to the data required for nuclear power plant overhaul planning, and generate nuclear power plant overhaul planning data; identify overhaul planning data that falls into the Spring Festival, peak summer period and peak winter period in the nuclear power plant overhaul planning data, and calculate the overlapping data of the overhaul planning data that overlaps in the nuclear power plant overhaul planning data;

[0014] The display module is used to generate and display the nuclear power plant overhaul planning map according to the nuclear power plant overhaul planning data; generate and display the nuclear power plant overhaul planning statistical data according to the nuclear power plant overhaul planning data; mark the overhaul planning data that falls into the Spring Festival, the peak summer period and the peak winter period and overlaps in the nuclear power plant overhaul planning data on the nuclear power plant overhaul planning map, and display the overlapping overhaul planning data that overlaps in the nuclear power plant overhaul planning data on the nuclear power plant overhaul planning map;

[0015] The nuclear power plant overhaul planning map displays the nuclear power plant overhaul planning data.

[0016] As one of the achievable ways, the calculation module is further used to adjust the nuclear power plant overhaul plan according to the data required for the modified nuclear power plant overhaul plan, and generate adjusted nuclear power plant overhaul plan data; identify the overhaul plan data that falls into the Spring Festival, the peak summer period and the peak winter period in the adjusted nuclear power plant overhaul plan data, and the overhaul plan data that overlaps, and calculate the overlapping data of the overhaul plan data that overlaps in the adjusted nuclear power plant overhaul plan data;

[0017] The display module is also used to modify the data required for the nuclear power plant overhaul planning, generate the modified data required for the nuclear power plant overhaul planning; generate and display the adjusted nuclear power plant overhaul planning map according to the adjusted nuclear power plant overhaul planning data; generate and display the adjusted nuclear power plant overhaul planning statistical data according to the adjusted nuclear power plant overhaul planning data; mark the overhaul planning data that falls into the Spring Festival, the peak summer period and the peak winter period and overlaps in the adjusted nuclear power plant overhaul planning data on the adjusted nuclear power plant overhaul planning map, and display the overlapping data of the overhaul planning data that overlaps in the adjusted nuclear power plant overhaul planning data on the adjusted nuclear power plant overhaul planning map;

[0018] The adjusted overhaul planning map of the nuclear power plant shows the adjusted overhaul planning data of the nuclear power plant.

[0019] As one of the achievable ways, the data required for the overhaul planning of a nuclear power plant includes the data required for the overhaul planning of each unit of the nuclear power plant; the data required for the overhaul planning of each unit of the nuclear power plant includes the following field information of each overhaul planned for each unit of the nuclear power plant: power plant, unit, overhaul number, overhaul type, overhaul duration, target duration, power grid duration, non-standard items, end time of the last overhaul, fuel cycle number, standard fuel cycle length, other loss days in the unit cycle, fuel cycle days increased or decreased by adding or reducing fuel assemblies of the unit, unit adjustment and peak regulation days, and unit power reduction and extended operation days;

[0020] The overhaul planning data of a nuclear power plant includes the overhaul planning data of each unit of the nuclear power plant; the overhaul planning data of each unit of the nuclear power plant includes the following field information of each overhaul planned for each unit of the nuclear power plant: power plant, unit, overhaul number, overhaul type, overhaul duration, target duration, power grid duration, non-standard items, end time of the last overhaul, start time of overhaul, end time of overhaul, fuel cycle number, standard fuel cycle length, required fuel cycle length, other loss days in the unit cycle, fuel cycle days increased or decreased by adding or reducing fuel assemblies of the unit, unit adjustment and peak regulation days, and unit power reduction and extended operation days;

[0021] The overhaul start time of each planned overhaul for each unit of a nuclear power plant is the sum of the end time of the previous overhaul and the required fuel cycle length; the overhaul end time of each planned overhaul for each unit of a nuclear power plant is the sum of the overhaul start time and the overhaul duration; the required fuel cycle length of each planned overhaul for each unit of a nuclear power plant is the sum of the standard fuel cycle length of each planned overhaul for each unit of the nuclear power plant, other loss days within the unit cycle, fuel cycle days due to increase or decrease of fuel assemblies for the unit, unit adjustment and peak regulation days, and unit power reduction and extended operation days.

[0022] As one of the feasible ways, the statistical data of nuclear power plant overhaul planning includes the planned overhaul times of nuclear power plants, the planned overhaul times of each type of nuclear power plants, the annual planned overhaul times of nuclear power plants, the annual planned overhaul days of nuclear power plants, the annual planned equivalent million-kilowatt overhaul days of nuclear power plants, the annual planned capacity factors of nuclear power plants and the annual planned power generation of nuclear power plants.

[0023] As one of the achievable methods, the display module is provided with an edit version overhaul planning page and a release version overhaul planning page; both the edit version overhaul planning page and the release version overhaul planning page are provided with a "time interval" input box for inputting a time interval;

[0024] The display module generates overhaul planning statistical data within the time interval of the nuclear power plant according to the overhaul planning data within the time interval of the nuclear power plant and displays it on the corresponding overhaul planning page; generates an overhaul planning diagram within the time interval of the nuclear power plant according to the overhaul planning data within the time interval of the nuclear power plant and displays it on the corresponding overhaul planning page;

[0025] Both the editing version overhaul planning page and the release version overhaul planning page have a "full life cycle" query button;

[0026] Click the "Life Cycle" query button, and the display module will generate overhaul planning statistical data for the life cycle of the nuclear power plant based on the overhaul planning data for the life cycle of the nuclear power plant, and refresh and display it on the corresponding overhaul planning page; based on the overhaul planning data for the life cycle of the nuclear power plant, it will generate an overhaul planning diagram for the life cycle of the nuclear power plant and refresh and display it on the corresponding overhaul planning page.

[0027] As one of the possible ways to achieve this, the editing version of the overhaul planning page has a "Spring Festival, Peak Summer Period and Peak Winter Period" setting window, which is used to set the start and end time of the Spring Festival, Peak Summer Period and Peak Winter Period; both the editing version of the overhaul planning page and the release version of the overhaul planning page have "Spring Festival, Peak Summer Period and Peak Winter Period" display options;

[0028] After checking the "Spring Festival, Peak Summer and Peak Winter" display option, the calculation module identifies the overhaul planning data that falls within the Spring Festival, peak summer or peak winter periods in the overhaul planning data within the time interval or the entire life cycle of the nuclear power plant; the display module marks the overhaul planning data that falls within the Spring Festival, peak summer and peak winter periods in the overhaul planning data within the time interval or the entire life cycle on the overhaul planning diagram within the time interval or the entire life cycle of the nuclear power plant.

[0029] As one of the ways to achieve this, both the editorial overhaul planning page and the release overhaul planning page have an "overlapping overhaul" highlighting option;

[0030] After checking the "Overlapping Overhaul" highlight option, the calculation module identifies the overhaul planning data that overlaps in the overhaul planning data within the time interval or within the entire life cycle of the nuclear power plant, and calculates the overlapping data of the overhaul planning data that overlaps in the overhaul planning data within the time interval or within the entire life cycle of the nuclear power plant; the display module marks the overhaul planning data that overlaps in the overhaul planning data within the time interval or within the entire life cycle on the overhaul planning diagram within the time interval or within the entire life cycle of the nuclear power plant, and displays the overlapping data of the overhaul planning data that overlaps in the overhaul planning data within the time interval or within the entire life cycle on the overhaul planning diagram within the time interval or within the entire life cycle of the nuclear power plant.

[0031] As one of the possible ways to achieve this, both the editorial version overhaul planning page and the published version overhaul planning page have a "real-time data" display option;

[0032] After checking the "Real-time Data" display option, the acquisition module obtains the real-time data of nuclear power plant overhaul; the display module displays the real-time data of nuclear power plant overhaul on the overhaul planning diagram within the time interval or the entire life cycle of the nuclear power plant, and generates overhaul planning statistical data within the time interval or the entire life cycle of the nuclear power plant based on the real-time data of nuclear power plant overhaul and displays it on the corresponding overhaul planning page.

[0033] As one of the feasible ways, both the edited version of the overhaul planning page and the published version of the overhaul planning page are provided with a "data required for overhaul planning" modification window, which is used to display the data required for overhaul planning within the time range or the entire life cycle of the nuclear power plant and support modification.

[0034] As one of the feasible ways, the edited overhaul planning page is provided with a "Publish" button for publishing the nuclear power plant overhaul planning diagram and nuclear power plant overhaul planning statistical data displayed on the edited overhaul planning page; the published overhaul planning page saves the nuclear power plant overhaul planning diagram and nuclear power plant overhaul planning statistical data published on the edited overhaul planning page and displays the latest published nuclear power plant overhaul planning diagram and nuclear power plant overhaul planning statistical data.

[0035] As one of the feasible ways, the edited overhaul planning page is provided with a "Save" button for saving the nuclear power plant overhaul planning map and nuclear power plant overhaul planning statistical data displayed on the edited overhaul planning page; the edited overhaul planning page is provided with a "Save As" button for saving the nuclear power plant overhaul planning map and nuclear power plant overhaul planning statistical data displayed on the edited overhaul planning page.

[0036] Beneficial technical effects of the present invention:

[0037] The nuclear power plant overhaul planning system of the present invention automatically generates nuclear power plant overhaul planning data, improves the efficiency of nuclear power plant overhaul planning, and avoids errors in nuclear power plant overhaul planning; automatically generates and displays a nuclear power plant overhaul planning map, displays the nuclear power plant overhaul planning data on the nuclear power plant overhaul planning map, automatically generates and displays nuclear power plant overhaul planning statistical data, and realizes intuitive and comprehensive display of nuclear power plant overhaul planning data and nuclear power plant overhaul planning statistical data; automatically identifies overhaul planning data that falls into the Spring Festival, peak summer and peak winter periods, and overhaul planning data that overlaps in the nuclear power plant overhaul planning data, calculates overlapping data of overhaul planning data that overlaps in the nuclear power plant overhaul planning data, and performs overhaul planning on the overhaul planning data that falls into the Spring Festival, peak summer and peak winter periods, and overhaul planning data that overlaps in the nuclear power plant overhaul planning data. Overlapping overhaul planning data are marked on the nuclear power plant overhaul planning map, and overlapping overhaul planning data in the nuclear power plant overhaul planning data are displayed on the nuclear power plant overhaul planning map, so as to facilitate the overhaul planners to adjust the nuclear power plant overhaul plan; the display page is set with a release version overhaul planning page and an edit version overhaul planning page. The release version overhaul planning page is for ordinary users, which displays the latest released nuclear power plant overhaul planning map and nuclear power plant overhaul planning statistical data, and provides a modification without saving function to meet the ordinary users' experimental adjustment needs for the nuclear power plant overhaul plan; the edit version overhaul planning page is for overhaul planners, and is used by overhaul planners to carry out nuclear power plant overhaul planning, adjust nuclear power plant overhaul plans and publish nuclear power plant overhaul plans. BRIEF DESCRIPTION OF THE DRAWINGS

[0038] Figure 1 The figure is a schematic structural diagram of an embodiment of a nuclear power plant overhaul planning system of the present invention. DETAILED DESCRIPTION

[0039] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as commonly understood by technicians in the technical field to which this application belongs; the terms used in the specification of the application are only for the purpose of describing specific embodiments and are not intended to limit this application; the terms "including" and "having" and any variations thereof in the specification and claims of this application and the above-mentioned figure descriptions are intended to cover non-exclusive inclusions.

[0040] Reference to "embodiments" herein means that a particular feature, structure, or characteristic described in conjunction with the embodiments may be included in at least one embodiment of the present application. The appearance of the phrase in various locations in the specification does not necessarily refer to the same embodiment, nor is it an independent or alternative embodiment that is mutually exclusive with other embodiments. It is explicitly and implicitly understood by those skilled in the art that the embodiments described herein may be combined with other embodiments.

[0041] The technical solution of the present invention is clearly and completely described below in conjunction with the accompanying drawings and specific embodiments.

[0042] refer to Figure 1 , shows a schematic structural diagram of an embodiment of a nuclear power plant overhaul planning system, the nuclear power plant overhaul planning system comprising:

[0043] The acquisition module is used to obtain the data required for the overhaul planning of nuclear power plants;

[0044] A calculation module is used to perform nuclear power plant overhaul planning according to the data required for nuclear power plant overhaul planning, and generate nuclear power plant overhaul planning data; identify overhaul planning data that falls into the Spring Festival, peak summer period and peak winter period in the nuclear power plant overhaul planning data, and calculate the overlapping data of the overhaul planning data that overlaps in the nuclear power plant overhaul planning data;

[0045] The display module is used to generate and display the nuclear power plant overhaul planning map according to the nuclear power plant overhaul planning data; generate and display the nuclear power plant overhaul planning statistical data according to the nuclear power plant overhaul planning data; mark the overhaul planning data that falls into the Spring Festival, the peak summer period and the peak winter period and overlaps in the nuclear power plant overhaul planning data on the nuclear power plant overhaul planning map, and display the overlapping overhaul planning data that overlaps in the nuclear power plant overhaul planning data on the nuclear power plant overhaul planning map;

[0046] The nuclear power plant overhaul planning map displays the nuclear power plant overhaul planning data.

[0047] In this embodiment, as one of the achievable ways, the calculation module is further used to adjust the nuclear power plant overhaul plan according to the data required for the modified nuclear power plant overhaul plan, and generate adjusted nuclear power plant overhaul planning data; identify the overhaul planning data that falls into the Spring Festival, the peak summer period and the peak winter period in the adjusted nuclear power plant overhaul planning data, and the overhaul planning data that overlaps, and calculate the overlapping data of the overhaul planning data that overlaps in the adjusted nuclear power plant overhaul planning data;

[0048] The display module is also used to modify the data required for the nuclear power plant overhaul planning, generate the modified data required for the nuclear power plant overhaul planning; generate and display the adjusted nuclear power plant overhaul planning map according to the adjusted nuclear power plant overhaul planning data; generate and display the adjusted nuclear power plant overhaul planning statistical data according to the adjusted nuclear power plant overhaul planning data; mark the overhaul planning data that falls into the Spring Festival, the peak summer period and the peak winter period and overlaps in the adjusted nuclear power plant overhaul planning data on the adjusted nuclear power plant overhaul planning map, and display the overlapping data of the overhaul planning data that overlaps in the adjusted nuclear power plant overhaul planning data on the adjusted nuclear power plant overhaul planning map;

[0049] The adjusted overhaul planning map of the nuclear power plant shows the adjusted overhaul planning data of the nuclear power plant.

[0050] In this embodiment, as one of the achievable ways, the data required for the overhaul planning of the nuclear power plant includes the data required for the overhaul planning of each unit of the nuclear power plant; the data required for the overhaul planning of each unit of the nuclear power plant includes the following field information of each overhaul planned by each unit of the nuclear power plant: power plant, unit, overhaul number, overhaul type, overhaul duration, target duration, power grid duration, non-standard project, end time of the last overhaul, fuel cycle number, standard fuel cycle length, other loss days in the unit cycle, fuel cycle days increased or decreased by adding or reducing fuel assemblies in the unit, unit mediation peak regulation days and unit power reduction extended operation days, and other loss days in the unit cycle are the sum of test loss days and power increase and decrease loss days in the unit cycle;

[0051] Among them, the following field information of each planned overhaul of each unit of the nuclear power plant is obtained by the acquisition module from the nuclear power plant overhaul basic database and the nuclear power plant overhaul key project database: power plant, unit, overhaul number, overhaul type, overhaul duration, target duration, power grid duration, non-standard items, last overhaul end time and fuel cycle number;

[0052] The following field information of each planned overhaul of each unit in a nuclear power plant is obtained through setting: standard fuel cycle length, other loss days in the unit cycle, fuel cycle days increased or decreased by adding or reducing fuel assemblies in the unit, unit adjustment and peak regulation days, and unit power reduction and extended operation days.

[0053] In this embodiment, as one of the achievable ways, the overhaul planning data of the nuclear power plant includes the overhaul planning data of each unit of the nuclear power plant; the overhaul planning data of each unit of the nuclear power plant includes the following field information of each overhaul planned for each unit of the nuclear power plant: power plant, unit, overhaul number, overhaul type, overhaul duration, target duration, power grid duration, non-standard project, end time of the last overhaul, overhaul start time, overhaul end time, fuel cycle number, standard fuel cycle length, required fuel cycle length, other loss days in the unit cycle, fuel cycle days increased or decreased by adding or reducing fuel assemblies of the unit, unit adjustment and peak regulation days, and unit power reduction and extended operation days;

[0054] Among them, the overhaul start time of each overhaul planned for each unit of a nuclear power plant is the sum of the end time of the previous overhaul and the required fuel cycle length of each overhaul planned for each unit of the nuclear power plant; the overhaul end time of each overhaul planned for each unit of a nuclear power plant is the sum of the overhaul start time and the overhaul duration of each overhaul planned for each unit of the nuclear power plant; the required fuel cycle length of each overhaul planned for each unit of a nuclear power plant is the sum of the standard fuel cycle length of each overhaul planned for each unit of the nuclear power plant, other loss days within the unit cycle, fuel cycle days due to increase or decrease of fuel assemblies in the unit, unit adjustment and peak regulation days, and unit power reduction and extended operation days.

[0055] In this embodiment, as one of the achievable methods, the nuclear power plant overhaul planning statistical data includes the planned overhaul times of the nuclear power plant, the planned overhaul times of each type of the nuclear power plant, the annual planned overhaul times of the nuclear power plant, the annual planned overhaul days of the nuclear power plant, the annual planned equivalent million-kilowatt overhaul days of the nuclear power plant, the annual planned capacity factor of the nuclear power plant, and the annual planned power generation of the nuclear power plant;

[0056] The planned overhaul times of a nuclear power plant is the sum of the planned overhaul times of each unit in the nuclear power plant;

[0057] The types of overhaul include Type A, Type B and Type C; the number of overhauls of each type planned for a nuclear power plant includes the number of Type A overhauls, Type B overhauls and Type C overhauls planned for the nuclear power plant, and the number of overhauls of each type planned for a nuclear power plant is the sum of the number of overhauls of each type planned for each unit of the nuclear power plant;

[0058] The annual planned overhaul times of a nuclear power plant is the sum of the annual planned overhaul times of each unit in the nuclear power plant. The annual planned overhaul times of each unit in the nuclear power plant is the number of overhaul times of each unit in the nuclear power plant that are planned to start in the current year.

[0059] The annual planned overhaul days of a nuclear power plant are the sum of the annual planned overhaul days of each unit of the nuclear power plant, and the annual planned overhaul days of each unit of a nuclear power plant are the sum of the overhaul durations of each overhaul planned annually for each unit of the nuclear power plant; when the planned overhauls of each unit of a nuclear power plant span multiple years, the overhaul duration of the annual planned overhauls of each unit of the nuclear power plant shall be calculated separately according to the year in which they are located;

[0060] The annual planned equivalent million-kilowatt overhaul days of a nuclear power plant is the sum of the annual planned equivalent million-kilowatt overhaul days of each unit of the nuclear power plant. The annual planned equivalent million-kilowatt overhaul days of each unit of a nuclear power plant = the annual planned overhaul days of each unit of the nuclear power plant × the rated power of each unit of the nuclear power plant / the rated power of the million-kilowatt unit of the nuclear power plant;

[0061] The annual planned capacity factor of a nuclear power plant is the average of the annual planned capacity factors of each unit in the nuclear power plant;

[0062] When each unit of a nuclear power plant has a planned overhaul each year, the annual planned capacity factor of each unit of the nuclear power plant = ((annual calendar days - annual planned overhaul days of each unit of the nuclear power plant - annual planned overhaul start-up and shutdown loss days of each unit of the nuclear power plant - annual planned tuning test loss days of each unit of the nuclear power plant) / annual calendar days) × 100%;

[0063] When there is no planned overhaul for each unit of a nuclear power plant in the year, the annual planned capacity factor of each unit of the nuclear power plant = ((annual calendar days - annual planned loss days of valve test for each unit of the nuclear power plant) / annual calendar days) × 100%;

[0064] The annual planned power generation of a nuclear power plant is the sum of the annual planned power generation of each unit of the nuclear power plant;

[0065] When each unit of a nuclear power plant has a planned overhaul each year, the annual planned power generation of each unit of the nuclear power plant = ((annual calendar days - annual planned overhaul days of each unit of the nuclear power plant - annual planned overhaul start-up and shutdown loss days of each unit of the nuclear power plant - annual planned tuning test loss days of each unit of the nuclear power plant) × rated power of each unit of the nuclear power plant × 24) / 100000;

[0066] When there is no planned overhaul for each unit of a nuclear power plant in the year, the annual planned power generation of each unit of the nuclear power plant = ((annual calendar days - annual planned loss days of valve test for each unit of the nuclear power plant) × rated power of each unit of the nuclear power plant × 24) / 100000;

[0067] The annual power generation of each unit in a nuclear power plant is in billion kWh;

[0068] The annual planned overhaul start-up and shutdown loss days of each unit in a nuclear power plant, the annual planned tuning test loss days of each unit in a nuclear power plant, the rated power of each unit in a nuclear power plant and the rated power of 1 million units in a nuclear power plant are all obtained through settings. Among them, the annual planned overhaul start-up and shutdown loss days of each unit in a nuclear power plant is 1.5 days, and the annual planned tuning test loss days of each unit in a nuclear power plant is 0.5 days;

[0069] The annual planned overhaul days for each unit of a nuclear power plant is the sum of the overhaul durations of each annual planned overhaul for each unit of the nuclear power plant.

[0070] The annual planned overhaul days of a nuclear power plant are the sum of the annual planned overhaul days of each unit of the nuclear power plant, and the annual planned overhaul days of each unit of a nuclear power plant are the sum of the overhaul durations of each overhaul planned annually by each unit of the nuclear power plant; when the overhauls planned by each unit of a nuclear power plant span multiple years, the overhaul durations of the annual planned overhauls of each unit of the nuclear power plant shall be calculated separately according to the year in which they occur. For example, if the overhaul duration of a certain overhaul planned by a unit of a nuclear power plant is 30 days, of which 10 days fall in 2022 and 20 days fall in 2023, then when calculating the planned overhaul days of the unit of the nuclear power plant in 2022, the planned overhaul duration of the unit of the nuclear power plant is 10 days; when calculating the planned overhaul days of the unit of the nuclear power plant in 2023, the planned overhaul duration of the unit of the nuclear power plant is 20 days.

[0071] In this embodiment, as one of the feasible ways, the calculation module identifies the overhaul planning data of the nuclear power plant whose overhaul start time and overhaul end time fall into the Spring Festival, the peak summer period and the peak winter period, and the overhaul planning data with overlap, and calculates the overlapping data of the overhaul planning data with overlap in the overhaul planning data of the nuclear power plant, including the overhaul numbers of the overlapping overhauls and the number of overlapping days; the display module marks the overhaul planning data of the nuclear power plant overhaul planning data whose overhaul start time and overhaul end time fall into the Spring Festival, the peak summer period and the peak winter period, and the overhaul planning data with overlap on the overhaul planning map of the nuclear power plant, and displays the overlapping data of the overhaul planning data with overlap in the overhaul planning data of the nuclear power plant on the overhaul planning map.

[0072] In this embodiment, as one of the feasible ways, the display module is provided with an editable overhaul planning page and a release version overhaul planning page; both the editable overhaul planning page and the release version overhaul planning page are provided with a "time interval" input box for entering a time interval; the time interval includes a start year and an end year; when the time interval is not entered in the time interval input box, the time interval is a default value; when the time interval is entered in the time interval input box, the time interval is an input value; the display module generates overhaul planning statistical data within the nuclear power plant time interval according to the overhaul planning data within the nuclear power plant time interval and displays it on the corresponding overhaul planning page, and generates an overhaul planning diagram within the nuclear power plant time interval according to the overhaul planning data within the nuclear power plant time interval and displays it on the corresponding overhaul planning page.

[0073] In this embodiment, as one of the achievable methods, when no time interval is entered in the "time interval" input box, the starting year defaults to the current year and the ending year defaults to 4 years after the current year.

[0074] In this embodiment, as one of the feasible ways, both the edited overhaul planning page and the published overhaul planning page are provided with a "full life cycle" query button; click the "full life cycle" query button, and the display module generates overhaul planning statistical data for the full life cycle of the nuclear power plant based on the overhaul planning data for the full life cycle of the nuclear power plant, and refreshes and displays it on the corresponding overhaul planning page, and generates an overhaul planning diagram for the full life cycle of the nuclear power plant based on the overhaul planning data for the full life cycle of the nuclear power plant, and refreshes and displays it on the corresponding overhaul planning page.

[0075] In this embodiment, as one of the achievable methods, the edit version overhaul planning page is provided with a "Spring Festival, Peak Summer Period and Peak Winter Period" setting window for setting the start and end time of the Spring Festival, Peak Summer Period and Peak Winter Period; the edit version overhaul planning page and the release version overhaul planning page are both provided with "Spring Festival, Peak Summer Period and Peak Winter Period" display options;

[0076] After checking the "Spring Festival, Peak Summer and Peak Winter" display option, the calculation module identifies the overhaul planning data within the time interval or the entire life cycle of the nuclear power plant whose overhaul start time and overhaul end time fall within the Spring Festival, peak summer and peak winter periods; the display module marks the overhaul planning data within the time interval or the entire life cycle of the nuclear power plant whose overhaul start time and overhaul end time fall within the Spring Festival, peak summer and peak winter periods with color ribbons on the overhaul planning diagram within the time interval or the entire life cycle of the nuclear power plant.

[0077] Summer and winter are generally the peak periods for electricity consumption in the power grid. The power grid has relevant requirements on whether overhaul can be arranged during the peak summer and peak winter periods. The overhaul planning data that uses color bands to mark the overhaul start time and the overhaul end time that fall into the peak summer and peak winter periods is convenient for overhaul planners to identify the overhauls related to the peak summer and peak winter periods during overhaul planning, so as to make appropriate adjustments to meet the overhaul planning requirements.

[0078] The Spring Festival is a period of low electricity consumption for the power grid. The power grid will require some units of the nuclear power plant to participate in mediation, and the power grid's start and shutdown requirements for units during the Spring Festival are also different from usual times. Nuclear power plants must also consider human resource arrangements when arranging overhauls during and around the Spring Festival. The overhaul start time and overhaul end time are marked with color bands and included in the overhaul planning data for the Spring Festival, making it convenient for overhaul planners to identify overhauls related to the Spring Festival during overhaul planning so that appropriate adjustments can be made to meet the overhaul planning requirements.

[0079] In this embodiment, as one of the achievable ways, both the editing version overhaul planning page and the publishing version overhaul planning page are provided with an "overlapping overhaul" highlighting option;

[0080] After checking the "Overlapping Overhaul" highlight option, the calculation module identifies the overhaul planning data with overlapping overhaul start time and overhaul end time in the overhaul planning data within the time interval or within the whole life cycle of the nuclear power plant, and calculates the overlapping data of the overhaul planning data with overlapping overhaul start time and overhaul end time in the overhaul planning data within the time interval or within the whole life cycle of the nuclear power plant; the display module marks the overhaul planning data with overlapping overhaul start time and overhaul end time in the overhaul planning data within the time interval or within the whole life cycle on the overhaul planning diagram within the time interval or within the whole life cycle of the nuclear power plant with a color band, and displays the overlapping data of the overhaul planning data with overlapping overhaul start time and overhaul end time in the overhaul planning data within the time interval or within the whole life cycle on the overhaul planning diagram within the time interval or within the whole life cycle of the nuclear power plant.

[0081] On the overhaul planning page, there is an option to highlight "overlapping overhauls" to prompt overhaul planners to assess whether it is necessary to re-plan the overlapping overhauls.

[0082] In this embodiment, as one of the achievable methods, both the edit version overhaul planning page and the release version overhaul planning page are provided with a "real-time data" display option;

[0083] After checking the "Real-time Data" display option, the acquisition module acquires the real-time data of the nuclear power plant overhaul; the display module displays the real-time data of the nuclear power plant overhaul on the overhaul planning diagram within the time interval or the entire life cycle of the nuclear power plant, which is convenient for the overhaul planners to compare the overhaul planning data of the nuclear power plant with the real-time data of the overhaul. At the same time, the statistical data of the overhaul planning within the time interval or the entire life cycle of the nuclear power plant are generated based on the real-time data of the nuclear power plant overhaul and displayed on the corresponding overhaul planning page;

[0084] The real-time data of nuclear power plant overhaul includes the real-time data of each overhaul of each unit in the nuclear power plant; the real-time data of each overhaul of each unit in the nuclear power plant includes the following field information of each overhaul that has been started and completed for each unit in the nuclear power plant: power plant, unit, overhaul number, overhaul type, overhaul duration, target duration, power grid duration, non-standard items, end time of last overhaul, overhaul start time, overhaul end time, fuel cycle number, standard fuel cycle length, required fuel cycle length, other loss days in the unit cycle, fuel cycle days due to increase or decrease of fuel components in the unit, unit adjustment and peak regulation days and unit power reduction and extended operation days.

[0085] In this embodiment, as one of the feasible ways, both the edited version of the overhaul planning page and the published version of the overhaul planning page are provided with a "data required for overhaul planning" modification window, which is used to display the data required for the overhaul planning within the time interval or the entire life cycle of the nuclear power plant and support modification; the data required for the overhaul planning within the time interval or the entire life cycle of the nuclear power plant includes the following field information of each overhaul planned within the time interval or the entire life cycle of each unit of the nuclear power plant: overhaul construction period, target construction period, power grid construction period, non-standard projects, standard fuel cycle length, other loss days in the unit cycle, unit adjustment and peak regulation days, unit fuel cycle days for increase or decrease of fuel components, and unit power reduction and extended operation days, among which the unit adjustment and peak regulation days are divided into the unit's adjustment and peak regulation days before the year and the unit's adjustment and peak regulation days after the year, which is convenient for the subsequent calculation of the overhaul planning statistical data within the time interval or the entire life cycle of the nuclear power plant.

[0086] In this embodiment, as one of the feasible methods, the edited overhaul planning page is provided with a "Publish" button for publishing the nuclear power plant overhaul planning map and nuclear power plant overhaul planning statistical data displayed on the edited overhaul planning page; the published overhaul planning page saves the nuclear power plant overhaul planning map and nuclear power plant overhaul planning statistical data published by the edited overhaul planning page and displays the latest published nuclear power plant overhaul planning map and nuclear power plant overhaul planning statistical data.

[0087] In this embodiment, as one of the feasible methods, both the edited overhaul planning page and the published overhaul planning page are provided with "Export Picture" and "Export Table" buttons; click the "Export Picture" button, the display module will export the nuclear power plant overhaul planning map displayed on the corresponding overhaul planning page; click the "Export Table" button, the display module will export the nuclear power plant overhaul planning data displayed on the corresponding overhaul planning page.

[0088] In this embodiment, as one of the feasible ways, the edited overhaul planning page is provided with a "Save" button for saving the nuclear power plant overhaul planning diagram and nuclear power plant overhaul planning statistical data displayed on the edited overhaul planning page.

[0089] In this embodiment, as one of the feasible methods, the edited overhaul planning page is provided with a "save" button for saving the nuclear power plant overhaul planning diagram and nuclear power plant overhaul planning statistical data displayed on the edited overhaul planning page, so as to facilitate overhaul planners to save multiple versions of nuclear power plant overhaul plans for comparison.

[0090] The above-mentioned embodiments only express several implementation methods of the present invention, and the description thereof is relatively specific and detailed, but it cannot be understood as limiting the scope of the patent of the present invention. It should be pointed out that, for ordinary technicians in this field, several variations and improvements can be made without departing from the concept of the present invention, which all belong to the protection scope of the present invention. Therefore, the protection scope of the patent of the present invention shall be subject to the attached claims.

Claims

1. A nuclear power plant overhaul planning system, characterized in that: include: The acquisition module is used to obtain the data required for the overhaul planning of nuclear power plants; A calculation module is used to carry out nuclear power plant overhaul planning according to the data required for nuclear power plant overhaul planning and generate nuclear power plant overhaul planning data; Identify the overhaul planning data of nuclear power plants that fall into the Spring Festival, the peak summer period and the peak winter period, as well as the overhaul planning data that overlap, and calculate the overlapping data of the overhaul planning data that overlap in the overhaul planning data of nuclear power plants; A display module is used to generate and display a nuclear power plant overhaul planning diagram based on the nuclear power plant overhaul planning data; Generate and display nuclear power plant overhaul planning statistics based on nuclear power plant overhaul planning data; The nuclear power plant overhaul planning data that falls into the Spring Festival, the peak summer period and the peak winter period, as well as the overhaul planning data that overlap, are marked on the nuclear power plant overhaul planning map; the overlapping overhaul planning data that overlaps in the nuclear power plant overhaul planning data are displayed on the nuclear power plant overhaul planning map; The nuclear power plant overhaul planning map displays the nuclear power plant overhaul planning data.

2. The nuclear power plant overhaul planning system according to claim 1, characterized in that: The calculation module is further used to adjust the nuclear power plant overhaul plan according to the data required for the modified nuclear power plant overhaul plan, and generate adjusted nuclear power plant overhaul plan data; identify the overhaul plan data that falls into the Spring Festival, the peak summer period and the peak winter period in the adjusted nuclear power plant overhaul plan data, and calculate the overlapping data of the overhaul plan data that overlaps in the adjusted nuclear power plant overhaul plan data; The display module is also used to modify the data required for the nuclear power plant overhaul plan and generate the modified data required for the nuclear power plant overhaul plan; According to the adjusted nuclear power plant overhaul planning data, an adjusted nuclear power plant overhaul planning diagram is generated and displayed; Generate and display adjusted nuclear power plant overhaul planning statistical data based on the adjusted nuclear power plant overhaul planning data; The adjusted nuclear power plant overhaul planning data that falls within the Spring Festival, the peak summer period and the peak winter period, as well as the overhaul planning data with overlaps, are marked on the adjusted nuclear power plant overhaul planning map; the overlapping overhaul planning data that overlaps in the adjusted nuclear power plant overhaul planning data are displayed on the adjusted nuclear power plant overhaul planning map; The adjusted overhaul planning map of the nuclear power plant shows the adjusted overhaul planning data of the nuclear power plant.

3. The nuclear power plant overhaul planning system according to claim 1 or 2, characterized in that: The data required for the overhaul planning of nuclear power plants include the data required for the overhaul planning of each unit of the nuclear power plant; the data required for the overhaul planning of each unit of the nuclear power plant include the following field information of each overhaul planned for each unit of the nuclear power plant: power plant, unit, overhaul number, overhaul type, overhaul duration, target duration, power grid duration, non-standard items, end time of the last overhaul, fuel cycle number, standard fuel cycle length, other loss days in the unit cycle, fuel cycle days increased or decreased by adding or reducing fuel assemblies of the unit, unit adjustment and peak regulation days, and unit power reduction and extended operation days; The overhaul planning data of a nuclear power plant includes the overhaul planning data of each unit of the nuclear power plant; the overhaul planning data of each unit of the nuclear power plant includes the following field information of each overhaul planned for each unit of the nuclear power plant: power plant, unit, overhaul number, overhaul type, overhaul duration, target duration, power grid duration, non-standard items, end time of the last overhaul, start time of overhaul, end time of overhaul, fuel cycle number, standard fuel cycle length, required fuel cycle length, other loss days in the unit cycle, fuel cycle days increased or decreased by adding or reducing fuel assemblies of the unit, unit adjustment and peak regulation days, and unit power reduction and extended operation days; The overhaul start time of each planned overhaul for each unit of a nuclear power plant is the sum of the end time of the previous overhaul and the required fuel cycle length; the overhaul end time of each planned overhaul for each unit of a nuclear power plant is the sum of the overhaul start time and the overhaul duration; the required fuel cycle length of each planned overhaul for each unit of a nuclear power plant is the sum of the standard fuel cycle length of each planned overhaul for each unit of the nuclear power plant, other loss days within the unit cycle, fuel cycle days due to increase or decrease of fuel assemblies for the unit, unit adjustment and peak regulation days, and unit power reduction and extended operation days.

4. The nuclear power plant overhaul planning system according to claim 1 or 2, characterized in that: The statistical data of nuclear power plant overhaul planning include the planned overhaul times of nuclear power plants, the planned overhaul times of various types of nuclear power plants, the annual planned overhaul times of nuclear power plants, the annual planned overhaul days of nuclear power plants, the annual planned equivalent million-kilowatt overhaul days of nuclear power plants, the annual planned capacity factors of nuclear power plants and the annual planned power generation of nuclear power plants.

5. The nuclear power plant overhaul planning system according to claim 1 or 2, characterized in that: The display module has an edit version overhaul planning page and a release version overhaul planning page; both the edit version overhaul planning page and the release version overhaul planning page have a "time interval" input box for entering a time interval; The display module generates overhaul planning statistics within the time interval of the nuclear power plant according to the overhaul planning data within the time interval of the nuclear power plant and displays it on the corresponding overhaul planning page; According to the overhaul planning data within the time interval of the nuclear power plant, an overhaul planning diagram within the time interval of the nuclear power plant is generated and displayed on the corresponding overhaul planning page; Both the editing version overhaul planning page and the release version overhaul planning page have a "full life" query button; Click the "Life Cycle" query button. The display module generates statistical data on the overhaul planning of the nuclear power plant during its life cycle based on the overhaul planning data during its life cycle, and refreshes and displays them on the corresponding overhaul planning page. It also generates an overhaul planning diagram for the nuclear power plant during its life cycle based on the overhaul planning data during its life cycle, and refreshes and displays them on the corresponding overhaul planning page.

6. The nuclear power plant overhaul planning system according to claim 5, characterized in that: The editing version of the overhaul planning page has a "Spring Festival, Peak Summer Period and Peak Winter Period" setting window, which is used to set the start and end time of the Spring Festival, Peak Summer Period and Peak Winter Period; the editing version of the overhaul planning page and the release version of the overhaul planning page both have "Spring Festival, Peak Summer Period and Peak Winter Period" display options; After checking the "Spring Festival, Peak Summer and Peak Winter" display option, the calculation module identifies the overhaul planning data that falls on the Spring Festival, Peak Summer or Peak Winter period in the overhaul planning data within the time interval or the entire life cycle of the nuclear power plant; the display module marks the overhaul planning data that falls on the Spring Festival, Peak Summer and Peak Winter period in the overhaul planning data within the time interval or the entire life cycle of the nuclear power plant on the overhaul planning diagram within the time interval or the entire life cycle of the nuclear power plant.

7. The nuclear power plant overhaul planning system according to claim 5, characterized in that: Both the editorial version overhaul planning page and the release version overhaul planning page have an "overlapping overhaul" highlighting option; After checking the "Overlapping Overhaul" highlight option, the calculation module identifies the overlapping overhaul planning data in the time interval or the whole life cycle of the nuclear power plant, and calculates the overlapping data of the overhaul planning data in the time interval or the whole life cycle of the nuclear power plant; The display module marks the overhaul planning data that overlaps in the overhaul planning data within the time interval or within the entire life cycle of the nuclear power plant on the overhaul planning map within the time interval or within the entire life cycle of the nuclear power plant, and displays the overlapping overhaul planning data that overlaps in the overhaul planning data within the time interval or within the entire life cycle on the overhaul planning map within the time interval or within the entire life cycle of the nuclear power plant.

8. The nuclear power plant overhaul planning system according to claim 5, characterized in that: Both the editorial version overhaul planning page and the release version overhaul planning page have a "real-time data" display option; After checking the "Real-time data" display option, the acquisition module obtains the real-time data of nuclear power plant overhaul; the display module displays the real-time data of nuclear power plant overhaul on the overhaul planning diagram within the time interval or the entire life cycle of the nuclear power plant, and generates overhaul planning statistical data within the time interval or the entire life cycle of the nuclear power plant based on the real-time data of nuclear power plant overhaul and displays it on the corresponding overhaul planning page.

9. The nuclear power plant overhaul planning system according to claim 5, characterized in that: Both the edited version of the overhaul planning page and the published version of the overhaul planning page are equipped with a "Data Required for Overhaul Planning" modification window, which is used to display the data required for the overhaul planning within the time range or the entire life cycle of the nuclear power plant and support modification.

10. The nuclear power plant overhaul planning system according to claim 5, characterized in that: The edited overhaul planning page is provided with a "Publish" button, which is used to publish the nuclear power plant overhaul planning diagram and nuclear power plant overhaul planning statistical data displayed on the edited overhaul planning page; the published overhaul planning page saves the nuclear power plant overhaul planning diagram and nuclear power plant overhaul planning statistical data published on the edited overhaul planning page and displays the latest published nuclear power plant overhaul planning diagram and nuclear power plant overhaul planning statistical data.

11. The nuclear power plant overhaul planning system according to claim 5, characterized in that: The edited version of the overhaul planning page is provided with a "Save" button for saving the nuclear power plant overhaul planning diagram and nuclear power plant overhaul planning statistical data displayed on the edited version of the overhaul planning page; the edited version of the overhaul planning page is provided with a "Save As" button for saving the nuclear power plant overhaul planning diagram and nuclear power plant overhaul planning statistical data displayed on the edited version of the overhaul planning page.