Construction geological information acquisition and data processing system and method based on total station
Through the combination of total station connection module and data processing module, the accuracy and efficiency of geological information collection and processing in civil engineering are solved, and accurate data collection and efficient processing in harsh environments are achieved, which is suitable for rapid international engineering Report generation.
Patent Information
- Application Number
- CN202311039927.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2023-08-17
- Publication Date
- 2025-01-14
AI Technical Summary
In the process of collecting geological information in civil engineering construction, the dataization, informationization and accuracy are low, the secondary input is frequent, the work efficiency is low, and the existing technology is difficult to achieve accurate data collection and processing in harsh environments.
Adopt a construction geological information collection and data processing system based on the total station, including the total station connection module, data collection module, data storage module and data processing module. The mobile terminal and the total station are connected through Bluetooth to realize the earth coordinates and mobile terminals. Coordinate conversion, accurately captures geological characteristics points, lines and surfaces, and collects data on the mobile terminal and processes it in the cloud, supports data storage, statistics and display, and generates standard reports.
It reduces the secondary entry time, improves the accuracy and work efficiency of data collection, reduces the human error rate, and realizes the digitalization and informatization of geological information, which is suitable for rapid report generation of international projects.
Smart Images

Figure CN119311681A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to a construction geological information collection and data processing system and method based on a total station, which can be applied to the construction geological cataloging information collection of tunnels, large caverns, vertical shafts, inclined shafts and slope dam foundations in hydropower, civil defense, underground laboratories, highways, subways, etc., and is particularly suitable for international projects that require the submission of formal reports for each construction cycle. Background Art
[0002] During the excavation process of civil engineering, the traditional method of collecting construction geological information and compiling reports requires geologists to enter and compile all the data of each cycle one by one. This is not only labor-intensive and time-consuming, but also prone to human errors, causing unnecessary troubles, especially in underground projects with many engineering parts and frequent compilation, which will cause a great burden on human resources. How to avoid duplication of work, improve work efficiency, and reduce the error rate is an urgent problem to be solved in the construction geological work of civil engineering.
[0003] The digitization, informatization and intelligence of engineering geology are the directions that the engineering industry urgently needs to develop. Exploring effective, fast, targeted and systematic geological information during the construction geological period is one of the technologies to be developed, and it is also the data basis for establishing a full life cycle BIM model. At present, in the field of underground cavern geological information collection, a structural surface automatic collection system based on three-dimensional laser scanning and image processing and a personal handheld mobile system have been developed, but they have high requirements for the construction environment of underground caverns and tunnels, such as light, noise, air, dust, and slag. These factors have a great impact on the recognition results. At present, there is no mature, stable and widely applicable system that can completely solve this problem. Although the field data collection has been automated, the current technical level cannot meet the accuracy requirements. Later data processing still requires manual intervention and interpretation, which may take more time and reduce efficiency. Summary of the invention
[0004] The first purpose of the present invention is to mainly solve the problems of low dataization, informatization and accuracy of geological information collection in civil engineering construction, and low efficiency of secondary input and timely output of geological information, and to provide a geological information collection and data processing system based on a total station suitable for tunnels, caverns, slope dam foundations, vertical shafts and inclined shafts during the construction geological period.
[0005] To this end, the above-mentioned purpose of the present invention is achieved through the following technical solutions: A construction geological information collection and data processing system based on a total station, characterized in that: the system comprises the following modules: a total station connection module, a total station, a data collection module, a data storage module, and a data processing module; The total station connection is used to connect the mobile terminal and the total station via Bluetooth to achieve the conversion of the geodetic coordinates measured by the total station and the coordinates catalogued by the mobile terminal, thereby completing the accurate collection of field data; The total station is used to accurately capture address feature points, lines and surfaces; The data acquisition module is used to collect data of four engineering categories: tunnels, caverns, vertical shafts and inclined shafts, and slope dam foundations, including three sub-directories: engineering overview, section definition, and excavation cycle; The data storage module is used for the storage and interaction of geological information, including offline local storage on the mobile terminal, cloud database storage, and computer data storage; The data processing module is used to process, count and display data, including cyclic statistics, structural surface analysis, surrounding rock category analysis, image information summary and standard report output, and can filter and output fixed-format Excel tables according to conditions to classify and display geological information on the three-dimensional model of the underground cavern.
[0006] While adopting the above technical solutions, the present invention may also adopt or combine the following technical solutions: As a preferred technical solution of the present invention: the project overview includes: recording the scale, location, person in charge, adopted specifications, surrounding rock classification standards, project category (tunnel, cavern, vertical shaft, inclined shaft, slope dam foundation), project status, start time, completion time, starting pile number, completion pile number, and total footage / height of the project.
[0007] As a preferred technical solution of the present invention: the section is defined as follows: The dimensions are defined through excavation sections of tunnels with different design pile numbers and elevations, and the sections can be automatically imported from CAD software Dwg / Dxf vector format files.
[0008] As a preferred technical solution of the present invention: the excavation cycle includes four secondary sub-directories: cycle information, display map drawing, geological information and image information.
[0009] As a preferred technical solution of the present invention: the cycle information includes: basic information collection for each new excavation cycle, including project location, cycle pile number, excavation elevation, excavation method, excavation direction, blasting time, burial depth, groundwater, cataloging time, cataloging personnel, and verification personnel.
[0010] As a preferred technical solution of the present invention: the drawing of the display diagram includes: the line drawing method includes manual touch drawing and total station precise drawing, the drawn lines include contour lines, partition boundaries, lithology boundaries, joint lines, fault lines, block lines and other lines, and the basic operations of color, thickness, node adjustment, deletion and addition can be performed, and the gyroscope of the tablet computer is set to be called in the lower left corner of the screen to realize the function of automatic measurement of the occurrence of the electronic compass, and can be automatically added to the structural surface or layer occurrence; after the display diagram is completed, the editable vector display diagram can be exported by one key on the computer; The contour line needs to generate a display map according to the section definition, the tunnel face and the side wall, which will serve as the basic plane base map for on-site geological line recording. For the tunnel face, the coordinate origin "O" is recorded in the middle of the tunnel, with the horizontal X axis and the vertical elevation Y axis. The corresponding cataloging contour base map is generated according to different sections, and the three-dimensional geological information coordinates collected by the total station can be converted into two-dimensional coordinates according to the display map drawing rules, and automatically drawn on the display map. The Kriging algorithm can be used for plane fitting according to the geological feature points to automatically calculate the plane occurrence and check it with the on-site compass data.
[0011] As a preferred technical solution of the present invention: the geological information includes: geological division, stratum lithology, geological structure, geological description and surrounding rock classification; The geological structure categories include: joints, long joints, faults, deformation zones, dislocation zones, fracture zones and dykes, and the collected information includes number, occurrence, spacing, opening, roughness, filling and weathering grade; The surrounding rock classification includes: the domestic national standard surrounding rock quality index BQ method, the hydropower and water conservancy surrounding rock classification standard HC method, and the international general standard RMR method, Q method, GSI value and RMi method.
[0012] As a preferred technical solution of the present invention: the image information includes calling the camera function of the mobile terminal to collect images of the tunnel face, cave top, left side wall, right side wall, and all and detailed photos of the excavation cycle.
[0013] Another object of the present invention is to provide a collection and processing method based on the construction geological information collection and data processing system based on the total station as described above.
[0014] To this end, the above-mentioned purpose of the present invention is achieved through the following technical solutions: A method for collecting and processing construction geological information based on the total station-based construction geological information collection and data processing system as described above comprises the following steps: The mobile terminal collects data and connects to the total station via Bluetooth. The total station assists in collecting geological information of geological feature points, lines, and surfaces. After the collection is completed, if the mobile terminal is not connected to the cloud network, it will be temporarily stored locally on the mobile terminal. If the mobile terminal is connected to the cloud network, the mobile terminal connected to the total station via Bluetooth will upload the collected geological information to the cloud, and the computer connected to the cloud will process and analyze the data.
[0015] The present invention provides a construction geological information collection and data processing system and method based on a total station, aiming at the problem of accurate collection of geological information systems during the construction geological period of tunnels, caverns, slope dam foundations, vertical shafts and inclined shafts such as hydropower stations, civil air defense, roads and subways. In each cycle, excavation acceptance needs to be carried out by relying on a total station, data collection is carried out on a mobile terminal, and data processing is carried out on a computer terminal, so that geological information is digitized and informationized, the accuracy is improved, secondary input is reduced, paperless office is realized, and the automatic drawing of display diagrams and the one-key generation of each cycle report can be completed according to preset templates.
[0016] Compared with the prior art, the present invention has the following beneficial effects: 1) The present invention collects geological information directly from traditional paper to the database, reducing the time for secondary entry, facilitating project personnel to review data online, reducing the error rate and improving work efficiency.
[0017] 2) The present invention integrates geological data sorting and analysis functions, and can output geological catalog reports in a certain format with one click, which is particularly suitable for foreign projects with little signed geological exploration data; it can conveniently query, count and analyze geological information of each project site.
[0018] 3) The present invention uses a total station to accurately capture geological feature points, lines, and surfaces, can automatically calculate the structural surface and layer occurrence on site, and directly convert the measured points and lines into coordinates and draw them on the display map, which accurately captures key geological feature information and improves the accuracy of information collection. In addition, since it is far away from the excavation surface, geologists do not need to make contact with the measurement, which is relatively safe. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 The present invention provides a flowchart of the collection and processing method of the construction geological information collection and data processing system based on the total station.
[0020] Figure 2 This is a module decomposition diagram of the construction geological information collection and data processing system based on the total station provided by the present invention.
[0021] Figure 3 This is the original interface of the engineering overview of the example of the present invention.
[0022] Figure 4This is the tunnel face display interface of the example of the present invention.
[0023] Figure 5 This is the original interface of the side wall display image of the example of the present invention.
[0024] Figure 6 This is the image information collection interface of the example of the present invention.
[0025] Figure 7 This is the surrounding rock category collection interface of the example of the present invention. DETAILED DESCRIPTION
[0026] In order to make the purpose, scheme and advantages of the present invention more clear and explicit, the present invention is further described below in conjunction with examples and drawings. The examples are only used to explain the present invention, but not to limit the present invention.
[0027] Taking a pumped storage project in the Middle East as an example, Figure 1 The geological information processing flow chart shown in the figure. The system collects data based on a tablet computer on the mobile end, and connects to the total station via Bluetooth to assist in the collection of geological feature points, lines, surfaces and other geological information. After completion, the data is uploaded to the cloud server through the 4G signal in the cave, and the data is processed and analyzed on the computer end.
[0028] like Figure 2 As shown, the system includes a total station connection module, a data acquisition module, a data storage module, and a data processing module. The basic information of the project is input in advance into the data acquisition system at the computer port, and the typical section and its applicable pile number range are defined.
[0029] After the surveying department has completed the installation and calibration of the total station, the geological technicians open the project management system collection system customized for the mobile terminal and connect to the total station with the help of the Bluetooth module. The geodetic coordinates (X / Y / Z) collected by the total station are interacted with the mobile terminal data to accurately collect field data.
[0030] Open the data collection module in the mobile application, select the project and project location, and input and select information in the three sub-directories of project overview, section definition, and excavation cycle.
[0031] like Figure 3 As shown, the information collected on its interface includes project overview, which records basic descriptive information such as the project's scale, location, person in charge, adopted specifications, and surrounding rock classification standards.
[0032] exist Figure 3 Select the section definition module in the interface to define the dimensions of different excavation sections of the upper horizontal tunnel (HRT). The section definition can also be automatically imported in the computer-side data management system in advance through .Dwg / .Dxf format files.
[0033] exist Figure 3 Select the excavation cycle menu in the interface to collect information from the four sub-menus: cycle information, display map drawing, geological information and image information.
[0034] The following steps are used to collect excavation cycle information: Step 1: If Figure 2 As shown, basic information is collected for each new excavation cycle, including project location [upper flat tunnel], cycle number
[010] , cycle pile number m [30.0~33.00], excavation elevation m [none], excavation method [drilling and blasting method], excavation direction [azimuth 270°], blasting time [9:00 am, October 30, 2021], burial depth m
[70] , groundwater [dry], cataloging time [16:00 pm, October 30, 2021, cataloging personnel [Zhang San], verification personnel [Li XX].
[0035] Step 2: Enter the upper horizontal tunnel [HRT] display drawing module, select the excavation section as Type A, such as Figure 4 As shown, the contour lines are defined according to the section and the tunnel face as the basic plane base map for on-site geological line recording. Figure 4 The left side is the geological information display module, and the right side is the tunnel face display map catalog area. According to the specific geological conditions on site, click on different line types such as geological division, lithology, structural surface, and set the attributes. The attribute settings of joints are as follows: Figure 4 As shown. Geological structure categories include joints, long joints, faults, deformation zones, dislocation zones, fracture zones, and dykes, and attributes include number, occurrence, spacing, opening, roughness, filling, and weathering grade. The tablet computer gyroscope is called in the lower left corner of the screen to realize the automatic occurrence measurement function of the electronic compass, which is convenient for on-site collection of structural surface occurrence.
[0036] Complete the attribute setting of the line, draw different lines, and use a stylus or total station to draw lines. For the face, the origin of the catalog coordinates O is located in the middle of the tunnel, the horizontal axis is the X axis, and the vertical axis is the Y axis. The system can generate corresponding base maps according to different sections, and convert the three-dimensional geological information coordinates collected by the total station into two-dimensional coordinates according to the rules and automatically draw them on the display map. And it can perform plane fitting according to geological feature points, automatically calculate the plane occurrence, and check with the on-site compass data.
[0037] Draw the side wall display map and collect geological information such as Figure 5 As shown in the figure, it is similar to the tunnel face. The length of the side wall display diagram is consistent with the side wall and the perimeter of the tunnel face, and the width is consistent with the excavation footage length of this cycle. For the side wall display diagram, the origin of the catalog coordinates is set at the starting point of the tunnel pile number, such as Figure 5As shown, the three-dimensional coordinates measured by the total station are converted into catalog coordinates through mathematical rules and automatically drawn on the display diagram.
[0038] After the display map and geological information collection are completed, click the Save button to complete the automatic saving of the information in this cycle, and upload it to the server with the help of wireless network. When there is no network, it will be automatically stored locally to ensure that the information is not lost.
[0039] Step 3: If Figure 6 As shown in the figure, the surrounding rock quality classification of underground engineering is carried out, and the surrounding rock classification adopted includes the domestic national standard surrounding rock quality index BQ method, the hydropower and water conservancy surrounding rock classification standard HC method, the international general standard RMR method, Q method, GSI value, etc. The influencing factors of each surrounding rock classification have the same value, which will automatically remain consistent. For the GSI value, the empirical formula is also used for conversion (GSI=0.5RQD+1.5R4, RQD is the integrity of the rock mass, and R4 is the structural surface state value of the RMR method).
[0040] Step 4: Collect image information of the excavation cycle, such as Figure 7 Click the corresponding button to call the camera function of the mobile tablet to collect photos of different parts of the tunnel. After completion, click to save to the local and database, and can be updated and downloaded on the computer.
[0041] Step 5: Data storage module, after completing the information collection, the data is stored in the cloud. To ensure that the data is not lost, each operation of the mobile port is automatically saved. Figure 1 As shown, when there is no network, the data is directly stored locally, and when there is a network, it is automatically uploaded to the cloud server.
[0042] Step 6: Data processing module, such as Figure 2 As shown. Open the construction geological information processing module of the computer port to process, count and display engineering data, including cycle statistics, structural surface analysis, surrounding rock category analysis, image information summary and standard report output. The data of each cycle can generate a geological catalog report in Chinese and English with one click according to the built-in report template. And according to the conditions, the data in a fixed format of Excel table can be output as a basis for further analysis and display.
[0043] The above description is only a preferred embodiment of the present invention and does not limit the present invention in any form. Any simple modification or equivalent changes made to the above embodiment based on the technical essence of the present invention shall fall within the protection scope of the present invention.
Claims
1. A construction geological information collection and data processing system based on a total station, characterized in that: The system includes the following modules: a total station connection module, a total station, a data acquisition module, a data storage module, and a data processing module; The total station connection is used to connect the mobile terminal and the total station via Bluetooth to achieve the conversion of the geodetic coordinates measured by the total station and the coordinates catalogued by the mobile terminal, thereby completing the accurate collection of field data; The total station is used to accurately capture address feature points, lines and surfaces; The data acquisition module is used to collect data of four engineering categories: tunnels, caverns, vertical shafts and inclined shafts, and slope dam foundations, including three sub-directories: engineering overview, section definition, and excavation cycle; The data storage module is used for the storage and interaction of geological information, including offline local storage on the mobile terminal, cloud database storage, and computer data storage; The data processing module is used to process, count and display data, including cyclic statistics, structural surface analysis, surrounding rock category analysis, image information summary and standard report output, and can filter and output fixed-format Excel tables according to conditions to classify and display geological information on the three-dimensional model of the underground cavern.
2. The construction geological information collection and data processing system based on total station according to claim 1 is characterized in that: The project overview includes: recording the scale, location, person in charge, adopted specifications, surrounding rock classification standards, project category, project status, start time, completion time, starting pile number, completion pile number, and total footage / height of the project.
3. The construction geological information collection and data processing system based on total station according to claim 1 is characterized in that: The section is defined as follows: The dimensions are defined through excavation sections of tunnels with different design pile numbers and elevations, and the sections can be automatically imported from CAD software Dwg / Dxf vector format files.
4. The construction geological information collection and data processing system based on total station according to claim 1 is characterized in that: The excavation cycle includes four secondary sub-directories: cycle information, display map drawing, geological information and image information.
5. The construction geological information collection and data processing system based on total station according to claim 4 is characterized in that: The cycle information includes: basic information collection for each new excavation cycle, including project location, cycle pile number, excavation elevation, excavation method, excavation direction, blasting time, burial depth, groundwater, cataloging time, cataloging personnel, and verification personnel.
6. The construction geological information collection and data processing system based on total station according to claim 4 is characterized in that: The drawing of the display diagram includes: the line drawing method includes manual touch drawing and total station precise drawing, the drawn lines include contour lines, partition boundaries, lithology boundaries, joint lines, fault lines, block lines and other lines, and the basic operations of color, thickness, node adjustment, deletion and addition can be performed, and the gyroscope of the tablet computer is set to be called in the lower left corner of the screen to realize the function of automatic measurement of the occurrence of the electronic compass, and it can be automatically added to the structural surface or layer occurrence; after the display diagram is completed, the editable vectorized display diagram can be exported by one key on the computer; The contour line needs to generate a display map according to the section definition, the tunnel face and the side wall, as the basic plane base map for on-site geological line recording; for the tunnel face, the recording coordinate origin "O" is located in the middle of the tunnel, with the horizontal X axis and the vertical elevation Y axis; the corresponding recording contour base map is generated according to different sections, and the three-dimensional geological information coordinates collected by the total station can be converted into two-dimensional coordinates according to the display map drawing rules, and automatically drawn on the display map; and the Kriging algorithm can be used for plane fitting according to the geological feature points, and the plane occurrence can be automatically calculated and checked with the on-site compass data.
7. The construction geological information collection and data processing system based on total station according to claim 4 is characterized in that: The geological information includes: geological division, stratum lithology, geological structure, geological description and surrounding rock classification; The geological structure categories include: joints, long joints, faults, deformation zones, dislocation zones, fracture zones and dykes, and the collected information includes number, occurrence, spacing, opening, roughness, filling and weathering grade; The surrounding rock classification includes: the domestic national standard surrounding rock quality index BQ method, the hydropower and water conservancy surrounding rock classification standard HC method, and the international general standard RMR method, Q method, GSI value and RMi method.
8. The construction geological information collection and data processing system based on total station according to claim 4 is characterized in that: The image information includes calling the camera function of the mobile terminal to collect images of the tunnel face, cave top, left side wall, right side wall, and all and detailed photos of the excavation cycle.
9. The method for collecting and processing construction geological information based on the total station and data processing system according to any one of claims 1 to 8, characterized in that: The method comprises the following steps: The mobile terminal collects data and connects to the total station via Bluetooth. The total station assists in collecting geological information of geological feature points, lines, and surfaces. After the collection is completed, if the mobile terminal is not connected to the cloud network, it will be temporarily stored locally on the mobile terminal. If the mobile terminal is connected to the cloud network, the mobile terminal connected to the total station via Bluetooth will upload the collected geological information to the cloud, and the computer connected to the cloud will process and analyze the data.