Freeze-dried soup block production line and technological process
By using a partition box and automation process process in the frozen soup block, the problem of residue and waste during the cutting process of the frozen dried soup block is solved, and the distribution of solid components and higher product quality is achieved.
Patent Information
- Application Number
- CN202411771310.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-04
- Publication Date
- 2025-01-24
AI Technical Summary
Freeze-dried soup cubes are prone to produce a large amount of residue or small pieces falling off during the cutting process, resulting in waste and reduced product quality.
A freeze-dried soup cube production line is designed, which uses a partition frame to divide the material frame into multiple areas, and realizes the automatic separation and removal of the partition frame and freeze-dried cubes through an automated process.
It effectively improves the uniformity of the distribution of solid components in the soup, reduces the probability of debris generated during the cutting process of freeze-dried soup cubes, reduces waste and improves product quality.
Smart Images

Figure CN119348960A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of freeze-dried soup cube production, and in particular to a freeze-dried soup cube production line and process flow. Background Art
[0002] With the popularization and development of pre-prepared and convenient foods, soup products have also evolved from the original combination of packaged seasonings and concentrated oil packets to freeze-dried products.
[0003] The production of freeze-dried soup cubes requires that the soup be boiled and concentrated, then poured into a container, and then frozen and vacuum dried to extract the water to form freeze-dried soup cubes. After being soaked in water, the freeze-dried soup cubes will be restored to the corresponding soup, which is more convenient and quick to eat, has a long shelf life, and is easy to transport.
[0004] In the industrial production process of freeze-dried soup cubes, in order to ensure that the solid materials in the soup are evenly distributed in each soup cube, they are not placed directly in a compartmented container. Instead, the soup cubes are poured into a large container, and cut into small pieces after freezing and vacuum drying. However, after the freeze-dried production is completed, due to the lack of moisture, the texture is relatively crisp, and a large amount of residue or small pieces are easily lost during the cutting process. This not only causes a lot of waste, but also reduces product quality. Summary of the invention
[0005] In order to improve the defect that a large amount of residue waste is generated and product quality is reduced during the cutting process of freeze-dried soup cubes, the present application provides a freeze-dried soup cube production line and process flow.
[0006] The freeze-dried soup cube production line provided in this application adopts the following technical solution: A freeze-dried soup cube production line, comprising The first conveyor belt is used for intermittent transmission and has a plurality of material frames for holding the soup installed on its upper surface; A material injection pipe, mounted above the first conveyor belt, used to inject the thick soup into the material frame; The partition frame is a uniform grid-shaped frame composed of multiple vertical plates, which can be inserted into the material frame and abut against the inner wall of the material frame to divide the material frame into multiple areas. The top is higher than the top of the material frame, and lifting plates abutting against the side walls of the material frame are fixed on both sides. The upper surface of the lifting plate is inclined, and the lower surface is provided with an arc groove; An installation station is erected above the first conveyor belt, on a side of the injection pipe facing the conveying direction of the first conveyor belt, and is used to install the partition frame in the material frame; The material frame is transported to the vacuum freeze-drying equipment at the end of the first conveyor belt; The second conveyor belt is used to receive and transport the material frames transferred from the vacuum freeze-drying equipment; A turntable is rotatably mounted on one side of the second conveyor belt and driven to rotate by a motor. A plurality of station frames are fixedly arranged at equal intervals on the circumferential outer wall, and the station frames can be rotated to the top of the second conveyor belt; The installation frame is vertically slidably connected to the circumferential inner wall of the station frame, the station frame is fixed with a first spring, the other end of the first spring is fixed to the top of the installation frame, so that the installation frame is completely located in the station frame, and the first spring is a tension spring; A disengagement hole is provided at the bottom of the installation frame at a position facing the partition formed by the partition frame, a disengagement rod is slidably connected in the disengagement hole, a same extension plate is fixedly provided at the top of the disengagement rod, a second spring is fixedly provided at the bottom of the extension plate, and the bottom end of the second spring is fixedly connected to the bottom wall of the installation frame; The side block is vertically slidably connected to both sides of the installation frame, can be located above the lifting plate of the lower partition frame, has a traction rope on the top, a pulley is installed on the top of the side wall of the installation frame, the traction rope passes through the pulley and is tied to the extension plate, the side block can keep the traction rope in an extended state by gravity, the side wall of the side block is rotatably connected to an arc clamp, a lifting rod is mounted on the bottom of the arc clamp, and the rotation axis of the arc clamp is provided with a torsion spring that allows the bottom end of the arc clamp to rotate toward the middle of the installation frame; The first telescopic cylinder is mounted above the second conveyor belt and is located above the mounting frame. A top plate is fixedly arranged on the circumferential outer wall of the piston rod. A third spring is fixedly arranged on the lower surface of the top plate. A bottom plate is fixedly arranged on the bottom end of the third spring. The bottom plate is slidably connected to the piston rod. The elastic force of the third spring is greater than the tension of the first spring. The bottom plate can abut against the top of the mounting frame, and the piston rod of the first telescopic cylinder can extend into the mounting frame. The bottom plate is in contact with the top of the installation frame and can drive the installation frame to move to a position where the lifting rod is in contact with the side wall of the material frame, and the lifting rod is located below the lifting plate; The piston rod of the first telescopic cylinder can abut against the extension plate until the disengagement rod abuts against the freeze-drying surface, and at this time, the side block moves to the position where the lifting rod pulls out the partition frame; A third conveyor belt is located on one side of the turntable, the mounting frame can be located above the third conveyor belt, and a placement component for placing the partition frame on the third conveyor belt is provided above the third conveyor belt; The third conveyor belt transports the partition frame to the installation station after passing through the ultrasonic cleaning area and the drying and sterilization area.
[0007] Optionally, a plurality of guide cylinders are fixedly provided at the bottom of the installation frame, the guide cylinders are communicated with the disengagement holes, and the disengagement rods can extend from the bottom of the guide cylinders.
[0008] Optionally, a baffle is fixedly provided on the side wall of the installation frame, a fourth spring is fixedly provided on the lower surface of the baffle, a bottom end of the fourth spring is fixedly connected to the side block, and the fourth spring is a compression spring.
[0009] Optionally, the placement assembly includes a second telescopic cylinder, an extension plate, and an insertion plate; The second telescopic cylinder is mounted above the third conveyor belt, and the top plate, the bottom plate and the third spring are also mounted on the piston rod of the second telescopic cylinder. The positional relationship after installation is the same as that on the first telescopic cylinder. The bottom plate can drive the installation frame to move down to a position where the partition frame is placed on the third conveyor belt and the lifting rod is located below the lifting plate. There are two extension plates, which are fixed on the piston rod of the second telescopic cylinder, located above the top plate, extending to both sides of the installation frame and then extending downward. An insertion groove is provided at the bottom end of the downwardly extending portion of the extension plate, and a fifth spring is fixedly provided on the top wall of the insertion groove. The bottom end of the fifth spring is fixedly connected to the insertion plate, and the insertion plate partially extends out of the insertion groove. A hook groove is provided on the side wall of the portion of the insertion plate extending out of the insertion groove. The arc-shaped clamp side wall is fixed with an unlocking rod, and the piston rod of the second telescopic cylinder can drive the insertion plate to move to a position where it abuts against the unlocking rod and makes the unlocking rod located in the insertion groove, at which time the lifting rod and the lifting plate are staggered; After the mounting frame is reset, the force applied to the lifting rod can be disengaged from the hook groove.
[0010] Optionally, a separation plate is mounted on the workstation frame, the separation plate is vertically arranged and the bottom end is an inclined surface, and after the installation frame is reset, the separation plate abuts against the unlocking rod and disengages the unlocking rod from the hook groove.
[0011] Optionally, the installation station includes a material unloading rack and a third telescopic cylinder; The unloading rack is a vertical shaft structure formed by connecting a plurality of vertical rods to each other. The unloading rack is erected above the first conveyor belt, and the vertical rods of the unloading rack abut against the lifting plate or the partition frame of the partition frame. The side wall of the unloading rack is provided with multiple one-way grooves at equal intervals. A cardboard is rotatably connected to the top of the one-way groove. The cardboard can be completely located in the one-way groove after rotation. The rotation axis of the cardboard is provided with a torsion spring to keep the cardboard in a horizontal state. The distance between the one-way grooves is not less than the height of the partition frame. Multiple cardboards can hold up the partition frame together. The third telescopic cylinder is arranged above the unloading rack, and the piston rod is arranged downward and can extend into the unloading rack, and the piston rod can move the partition frame in the unloading rack to a position abutting against the lower card plate; The third conveyor moves the partition frame to above the unloading rack.
[0012] Optionally, the bottom edge portion of the partition frame is chamfered, and the inner wall of the material frame is convexly arranged at a position opposite to the chamfer of the bottom of the partition frame and can fit with the chamfered portion of the material frame.
[0013] The freeze-dried soup cube production process provided in this application adopts the following technical solution: A freeze-dried soup cube production process, using the above-mentioned freeze-dried soup cube production line, comprises the following steps: S1. After the soup is produced, it is injected into the material frame, and the solid components in the soup are evenly spread in the material frame, and then a partition frame is inserted into the material frame; S2, transfer the material frame to the vacuum freeze drying equipment for freeze drying, first freeze it at -30℃~-40℃ for 2-4h, then evacuate it to make the vacuum degree below 130pa, then slowly increase the temperature to -15℃~-10℃, and finally slowly increase the temperature to 10℃~25℃, and the whole heating time is controlled within 8h; S3, after taking out the material frame, the partition frame is taken out, and finally the freeze-dried blocks are separated from the material frame, and the freeze-dried blocks are screened and packaged.
[0014] In summary, the present application includes at least one of the following beneficial technical effects: 1. The partition frame is inserted after the soup is injected into the material frame, which can effectively improve the uniformity of the solid components in the soup in each partition, and can also save the subsequent freeze-dried cutting process to reduce the probability of debris generated during the cutting process of freeze-dried soup cubes; 2. After the first telescopic cylinder moves downward, it abuts against the installation frame through the bottom plate, so that the installation frame moves downward. After the lifting rod abuts against the lifting plate, it abuts against the side wall of the installation frame. Then, the piston rod of the first telescopic cylinder abuts against the extension plate and moves the extension plate downward. The separation rod extends and the side block moves upward, so that the lifting rod abuts against the lifting plate and drives the partition frame to move upward. The bottom end of the separation rod abuts against the freeze-dried block, so that the partition frame is separated from the freeze-dried block. Then, after the installation frame is reset, the partition frame is lifted and moves toward the third conveyor belt as the turntable rotates, so that the partition frame is automatically taken out, thereby improving the efficiency of taking out the partition frame; 3. After the second telescopic cylinder is extended, the installation frame is moved down to the position where the partition frame is placed on the second conveyor belt through the bottom plate, and then the piston rod of the second telescopic cylinder continues to move down, so that the insertion plate abuts against the unlocking rod and the arc clamp is rotated to the side of the lifting plate, and the unlocking rod is located in the hook groove. Then, during the resetting process of the piston rod of the second telescopic cylinder, since the unlocking rod is in the hook groove, the length of the insertion plate extending out of the insertion groove increases, and after the installation frame is reset, the separation plate abuts against the unlocking rod to separate the unlocking rod from the hook groove, and the insertion plate is reset, thereby realizing automatic separation of the partition frame, thereby facilitating the cleaning of the partition frame for the next use, and realizing the integration of the partition frame on the freeze-drying production line. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 It is a schematic diagram of the structure of an embodiment of the present application; Figure 2 is a partial cross-sectional view showing the mounting frame; Figure 3 is a partial cutaway view showing the placed components; Figure 4 It is a partial schematic diagram showing the unlocking lever being disengaged from the hook groove; Figure 5 It is a partial schematic diagram showing the installation station; Figure 6 It is a partial schematic diagram of the display card board.
[0016] In the figure, 1, first conveyor belt; 11, material frame; 12, partition frame; 121, lifting plate; 2, injection pipe; 3, installation station; 31, unloading rack; 311, one-way slot; 312, clamping plate; 32, third telescopic cylinder; 4, turntable; 41, station frame; 411, first spring; 412, separation plate; 42, installation frame; 421, disengagement hole; 4211, guide cylinder; 422, extension plate; 4221, disengagement rod; 4222, second spring; 43 , side block; 431, traction rope; 432, arc clamp; 4321, lifting rod; 4322, unlocking rod; 44, pulley; 45, baffle; 451, fourth spring; 5, first telescopic cylinder; 51, top plate; 52, third spring; 53, bottom plate; 6, second conveyor belt; 7, third conveyor belt; 8, placement component; 81, second telescopic cylinder; 82, extension plate; 821, insertion slot; 8211, fifth spring; 83, insertion plate; 831, hook slot;. DETAILED DESCRIPTION
[0017] The following is combined with Figure 1-6 This application is described in further detail.
[0018] The embodiments of the present application disclose a freeze-dried soup cube production line and process flow.
[0019] refer to Figure 1 and Figure 2 The freeze-dried soup cube production line includes a first conveyor belt 1, a feeding pipe 2, an installation station 3, a turntable 4, a first telescopic cylinder 5, a second conveyor belt 6, a third conveyor belt 7, a placement component 8 and a partition frame 12.
[0020] The first conveyor belt 1 is intermittently conveyed, and a plurality of material frames 11 for holding thick soup are installed on the upper surface. The injection pipe 2 is set above the first conveyor belt 1, and is used to inject the thick soup into the material frame 11. The partition frame 12 is a uniform grid-shaped frame structure composed of a plurality of vertical plates, which can be inserted into the material frame 11 and abut against the inner wall of the material frame 11 and divide the material frame 11 into a plurality of areas. The top of the partition frame 12 is higher than the top of the material frame 11, and lifting plates 121 abutting against the side walls of the material frame 11 are fixed on both sides. The upper surface of the lifting plate 121 is inclined, and an arc groove is opened on the lower surface. The bottom edge of the partition frame 12 is chamfered, and the inner wall of the material frame 11 is convexly arranged at the position opposite to the chamfer of the bottom of the partition frame 12 and can fit with the chamfered part of the material frame 11. The installation station 3 is set above the first conveyor belt 1, on the side of the injection pipe 2 facing the conveying direction of the first conveyor belt 1, and is used to install the partition frame 12 in the material frame 11. The material frame 11 is transported into the vacuum freeze-drying device at the end of the first conveyor belt 1 .
[0021] The second conveyor belt 6 is intermittently conveyed and is used to transport the material frame 11 transferred from the vacuum freeze-drying device. The turntable 4 is rotatably mounted on one side of the second conveyor belt 6 and driven to rotate by a motor. A plurality of station frames 41 are fixedly arranged at equal intervals on the circumferential outer wall of the turntable 4. The station frame 41 can be rotated to the top of the second conveyor belt 6. The station frame 41 is provided with an installation frame 42 for taking out the partition frame 12 in the lower material frame 11.
[0022] The third conveyor belt 7 is located on one side of the turntable 4 and is also intermittently conveyed. The installation frame 42 can be located above the third conveyor belt 7, and the placement component 8 is arranged above the third conveyor belt 7 to place the partition frame 12 on the third conveyor belt 7. The third conveyor belt 7 transports the partition frame 12 to the installation station 3 after passing through the ultrasonic cleaning area and the drying and sterilization area.
[0023] The first conveyor belt 1 drives the material frame 11 to move below the injection nozzle, and the injection nozzle injects the soup into the material frame 11 and spreads it evenly. Then the first conveyor belt 1 drives the material frame 11 to move to the installation station 3, and inserts the partition frame 12 into the material frame 11. The partition frame 12 divides the material frame 11 into multiple uniform spaces. Then the material frame 11 is transferred to the vacuum freeze-drying equipment at the end of the first conveyor belt 1 for freeze-drying. After freeze-drying, the material frame 11 is taken out and placed on the second conveyor belt 6 for conveyance. The second conveyor belt 6 drives the material frame 11 to move below the installation frame 42 and takes out the partition frame 12. The second conveyor belt 6 drives the material frame 11 to continue to move, and the freeze-dried soup cubes are taken out and the subsequent processes are carried out. After the turntable 4 moves the partition frame 12 to the top of the third conveyor belt 7, the partition frame 12 is placed on the third conveyor belt 7 through the placement component 8. The third conveyor belt 7 drives the partition frame 12 to move, and then after passing through the ultrasonic cleaning station and the drying and disinfection station, the partition frame 12 is transported back to the installation station 3 to realize the circulation of the partition frame 12 and the addition of the partition frame 12 to the freeze-dried soup cube production line. By adding the partition frame 12, the cutting process of the freeze-dried soup cube can be omitted, thereby reducing the debris and partial detachment generated in the cutting process of the freeze-dried soup cube, reducing product waste, and improving product quality.
[0024] refer to Figure 2The installation frame 42 is vertically slidably connected to the circumferential inner wall of the station frame 41. The station frame 41 is fixed with a first spring 411. The other end of the first spring 411 is fixedly arranged on the top of the installation frame 42, so that the installation frame 42 is completely located in the station frame 41. The first spring 411 is a tension spring. The bottom of the installation frame 42 is provided with a disengagement hole 421 at the position of the partition formed by the partition frame 12. The bottom of the installation frame 42 is fixedly provided with a plurality of guide cylinders 4211, and the guide cylinders 4211 are connected to the disengagement hole 421. A disengagement rod 4221 is slidably connected in the disengagement hole 421. The top of the disengagement rod 4221 is fixedly provided with the same extension plate 422. The bottom of the extension plate 422 is fixedly provided with a second spring 4222. The bottom end of the second spring 4222 is fixedly connected to the inner bottom wall of the installation frame 42. When the second spring 4222 is in a natural state, the bottom end of the disengagement rod 4221 is located in the guide cylinder 4211, and the disengagement rod 4221 can extend from the bottom of the guide cylinder 4211. The side walls of the installation frame 42 are vertically slidably connected with side blocks 43, and the side blocks 43 are located above the lifting plate 121 of the lower partition frame 12. A pulley 44 is installed on the top of the side wall of the installation frame 42, and a traction rope 431 is tied to the top of the side block 43. The traction rope 431 passes through the pulley 44 and is tied to the extension plate 422. The side block 43 can keep the traction rope 431 in an extended state through gravity. A baffle 45 is fixedly provided on the side wall of the installation frame 42, and a fourth spring 451 is fixedly provided on the lower surface of the baffle 45. The bottom end of the fourth spring 451 is fixedly connected to the side block 43, and the fourth spring 451 is a compression spring. The side wall of the side block 43 is rotatably connected with an arc clamp 432, and a lifting rod 4321 is mounted on the bottom of the arc clamp 432. The rotation axis of the arc clamp 432 is provided with a torsion spring that allows the bottom end of the arc clamp 432 to rotate toward the middle of the installation frame 42.
[0025] The first telescopic cylinder 5 is mounted above the second conveyor belt 6 and is located above the mounting frame 42. A top plate 51 is fixed to the circumferential outer wall of the piston rod of the first telescopic cylinder 5, and a third spring 52 is fixed to the lower surface of the top plate 51. A bottom plate 53 is fixed to the bottom end of the third spring 52, and the bottom plate 53 is slidably connected to the piston rod. The elastic force of the third spring 52 is greater than the pulling force of the first spring 411. The bottom plate 53 can abut against the top of the mounting frame 42, and the piston rod of the first telescopic cylinder 5 can extend into the mounting frame 42. The bottom plate 53 abuts against the top of the mounting frame 42 and can drive the mounting frame 42 to move to a position where the lifting rod 4321 is tightly against the side wall of the material frame 11, and the lifting rod 4321 is located below the lifting plate 121. The piston rod of the first telescopic cylinder 5 can abut with the extension plate 422 to the position where the disengagement rod 4221 abuts against the freeze-drying surface, and at this time, the side block 43 moves to the position where the lifting rod 4321 pulls out the partition frame 12.
[0026] The second conveyor belt 6 drives the material frame 11 to move to the bottom of the first telescopic cylinder 5 and then stops. The piston rod of the first telescopic cylinder 5 extends, and the bottom plate 53 abuts against the mounting frame 42 and drives the mounting frame 42 to move downward. When the mounting frame 42 moves to the bottom, the lifting rod 4321 abuts against the inclined surface of the lifting plate 121 and then abuts against the side wall of the material frame 11 and is located below the lifting plate 121. Then, the piston rod of the first telescopic cylinder 5 continues to move downward, and the third spring 52 is compressed at this time. The piston rod of the first telescopic cylinder 5 abuts against the extension plate 422 and drives the extension plate 422 to move downward. During the downward movement of the extension plate 422, the disengagement rod 4221 extends from the guide cylinder 4211, and drives the side block 43 to move upward through the traction rope 431. When the side block 43 moves upward, the lifting rod 4321 abuts against the lifting plate 121 and drives the partition frame 12 to move upward. At the same time, the disengagement rod 4221 abuts against the freeze-dried product to separate the freeze-dried product from the partition frame 12. The setting of the guide cylinder 4211 can provide space for the upward movement of the partition frame 12. Then, during the resetting process of the installation frame 42, the first spring 411 causes the partition frame 12 to move upward, thereby realizing the separation of the partition frame 12 from the material frame 11 and the freeze-dried food, and the partition frame 12 moves toward the third conveyor belt 7 as the turntable 4 rotates.
[0027] refer to Figure 3 and Figure 4, the placement assembly 8 includes a second telescopic cylinder 81, an extension plate 82 and an insertion plate 83. The second telescopic cylinder 81 is mounted above the third conveyor belt 7. The top plate 51, the bottom plate 53 and the third spring 52 are also mounted on the piston rod of the second telescopic cylinder 81, and the positional relationship after installation is the same as that on the first telescopic cylinder 5. The bottom plate 53 can drive the installation frame 42 to move down to a position where the partition frame 12 is placed on the third conveyor belt 7 and the lifting rod 4321 is located below the lifting plate 121. There are two extension plates 82, which are fixed on the piston rod of the second telescopic cylinder 81 and located above the top plate 51. The extension plate 82 extends to both sides of the installation frame 42 and then extends downward. An insertion groove 821 is provided at the bottom end of the downwardly extending portion of the extension plate 82, and a fifth spring 8211 is fixed on the top wall of the insertion groove 821. The insertion plate 83 is slidably connected in the insertion groove 821 and fixedly connected to the fifth spring 8211. The insertion plate 83 partially extends out of the insertion slot 821, and the side wall of the part of the insertion plate 83 extending out of the insertion slot 821 is provided with a hooking slot 831, and the bottom of the insertion plate 83 is inclined and transitionally arranged. An unlocking rod 4322 is fixedly arranged on the side wall of the arc clamp 432, and the piston rod of the second telescopic cylinder 81 can drive the insertion plate 83 to move to abut against the unlocking rod 4322 and make the unlocking rod 4322 located in the insertion slot 821, at which time the lifting rod 4321 is staggered from the lifting plate 121. After the installation frame 42 is reset, the force exerted on the lifting rod 4321 can be disengaged from the hooking slot 831. A separation plate 412 is mounted on the station frame 41, and the separation plate 412 is vertically arranged and has an inclined surface at the bottom. After the installation frame 42 is reset, the separation plate 412 abuts against the unlocking rod 4322 and disengages the unlocking rod 4322 from the hooking slot 831. If the lifting rod 4321 is located in the groove at the bottom of the lifting plate 121 , when the unlocking rod 4322 abuts against the separation plate 412 , the lifting rod 4321 will abut against the groove at the bottom of the lifting plate 121 , and the arc clamp 432 will not rotate and open.
[0028] The turntable 4 rotates to rotate the partition frame 12 to the bottom of the second telescopic cylinder 81 and then stops. The piston rod of the second telescopic cylinder 81 extends, so that the bottom plate 53 abuts against the installation frame 42 and drives the installation frame 42 to move down to the position where the partition frame 12 is placed on the third conveyor belt 7. Then the telescopic cylinder continues to move down, so that the extension plate 82 drives the insertion plate 83 to abut against the insertion rod and the arc clamp 432 rotates and opens. The lifting rod 4321 is located on one side of the lifting plate 121, and the unlocking rod 4322 is located in the hook groove 831, so that the partition frame 12 is completely placed on the third conveyor belt 7. Then the third conveyor belt 7 can move to take the partition frame 12 away. During the resetting process of the second telescopic cylinder 81, the extension plate 82 moves up first. Due to the abutment relationship between the unlocking rod 4322 and the hook groove 831, the length of the insertion plate 83 extending out of the insertion groove 821 increases, so that the arc clamp 432 remains in an open state. During the subsequent resetting process of the mounting frame 42 , the unlocking rod 4322 opens at a larger angle under the contact of the separation plate 412 , and then separates from the insertion plate 83 , and the insertion plate 83 is reset.
[0029] refer to Figure 5 and Figure 6 The installation station 3 includes a material unloading rack 31 and a third telescopic cylinder 32. The material unloading rack 31 is a vertical shaft structure formed by connecting multiple vertical rods. The material unloading rack 31 is erected above the first conveyor belt 1, and the vertical rods of the material unloading rack 31 abut against the lifting plate 121 of the partition frame 12 or the partition frame 12. The side wall of the material unloading rack 31 is equidistantly provided with multiple one-way grooves 311, and the top of the one-way groove 311 is rotatably connected with a card plate 312, and the card plate 312 can be completely located in the one-way groove 311 after rotation. The rotating shaft of the card plate 312 is provided with a torsion spring, so that the card plate 312 maintains a horizontal state, and the distance between the one-way grooves 311 is not less than the height of the partition frame 12, and multiple card plates 312 can lift the partition frame 12 together. The third telescopic cylinder 32 is erected above the material unloading rack 31, and the piston rod is arranged downward and can extend into the material unloading rack 31, and the piston rod can move the partition frame 12 in the material unloading rack 31 to a position abutting against the lower card plate 312. The third conveyor belt 7 moves the partition frame 12 to above the unloading rack 31 .
[0030] The third conveyor belt 7 delivers the partition frame 12 to the top of the unloading rack 31 and stacks it on the top of the partition frame 12 below. The piston rod of the third telescopic cylinder 32 extends to press the partition frame 12 downward, so that the partition frame 12 moves downward to a position abutting against the next card plate 312, thereby moving the partition frame 12 downward together by one unit, and pressing the lowest partition frame 12 down into the material frame 11. The partition frame 12 is installed in the material frame 11. The automatic circulation of the partition frame 12 on the freeze-drying production line is also realized.
[0031] In combination with the above freeze-dried soup cube production line, this embodiment also discloses the process flow of freeze-dried soup cube production as follows: S1, after the soup is produced, it is injected into the material frame 11, and after the solid components in the soup are evenly diffused in the material frame 11, a partition frame 12 is inserted into the material frame 11; S2, transfer the material frame 11 to the vacuum freeze drying equipment for freeze drying, first freeze it at -30℃~-40℃ for 2-4h, then evacuate it to make the vacuum degree below 130pa, then slowly increase the temperature to -15℃~-10℃, and finally slowly increase the temperature to 10℃~25℃, and the whole heating time is controlled within 8h; S3, after taking out the material frame 11, take out the partition frame 12, and finally separate the freeze-dried blocks from the material frame 11, screen the freeze-dried blocks, and then package them.
[0032] The implementation principle of the embodiment of the present application is: by introducing the partition frame 12 into the production line of freeze-dried soup cubes, and realizing the automatic circulation of the partition frame 12 through the production line design. The introduction of the partition frame 12 can effectively save the process of cutting the freeze-dried soup cubes, and thus will not produce excessive product loss caused by excessive soup cube debris generated in the cutting process, which not only improves the product quality, but also improves the product utilization rate. On the other hand, through the detachable setting of the partition frame 12, it can be effectively made that after the partition frame 12 is added to the material frame 11, the solid components in each area separated by the partition frame 12 are more balanced, thereby improving the quality of the freeze-dried soup cube products produced.
[0033] The embodiments of this specific implementation method are all preferred embodiments of the present application, and are not intended to limit the protection scope of the present application. Therefore, all equivalent changes made based on the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A freeze-dried soup cube production line, characterized by: include A first conveyor belt (1) for intermittent transmission, with a plurality of material frames (11) for holding soup installed on its upper surface; A material injection pipe (2), mounted above the first conveyor belt (1), and used for injecting the thick soup into the material frame (11); The partition frame (12) is a uniform grid-shaped frame composed of a plurality of vertical plates, which can be inserted into the material frame (11) and abut against the inner wall of the material frame (11) to divide the material frame (11) into a plurality of areas, the top of which is higher than the top of the material frame (11), and the two sides of which are fixed with lifting plates (121) abutting against the side walls of the material frame (11), the upper surface of the lifting plates (121) is inclined, and the lower surface is provided with an arc groove; An installation station (3) is erected above the first conveyor belt (1), on the side of the injection pipe (2) facing the conveying direction of the first conveyor belt (1), and is used to install the partition frame (12) in the material frame (11); The material frame (11) is transported to the vacuum freeze-drying equipment at the end of the first conveyor belt (1); A second conveyor belt (6) is used to receive and transport the material frame (11) transferred out of the vacuum freeze-drying equipment; A turntable (4) is rotatably mounted on one side of the second conveyor belt (6) and driven to rotate by a motor. A plurality of workstation frames (41) are fixedly arranged at equal intervals on the circumferential outer wall. The workstation frames (41) can be rotated to the top of the second conveyor belt (6); The installation frame (42) is vertically slidably connected to the circumferential inner wall of the work station frame (41), the work station frame (41) is fixedly provided with a first spring (411), the other end of the first spring (411) is fixedly provided on the top of the installation frame (42), so that the installation frame (42) is completely located in the work station frame (41), and the first spring (411) is a tension spring; A disengagement hole (421) is provided at a position of the bottom of the installation frame (42) facing the partition formed by the partition frame (12), a disengagement rod (4221) is slidably connected in the disengagement hole (421), a same extension plate (422) is fixedly provided at the top of the disengagement rod (4221), a second spring (4222) is fixedly provided at the bottom of the extension plate (422), and the bottom end of the second spring (4222) is fixedly connected to the inner bottom wall of the installation frame (42); The side block (43) is vertically slidably connected to both sides of the installation frame (42) and can be located above the lifting plate (121) of the lower partition frame (12). A traction rope (431) is tied to the top. A pulley (44) is installed on the top of the side wall of the installation frame (42). The traction rope (431) passes through the pulley (44) and is tied to the extension plate (422). The side block (43) can keep the traction rope (431) in an extended state through gravity. The side wall of the side block (43) is rotatably connected to an arc clamp (432). A lifting rod (4321) is mounted on the bottom of the arc clamp (432). The rotation axis of the arc clamp (432) is provided with a torsion spring that enables the bottom end of the arc clamp (432) to rotate toward the middle of the installation frame (42). The first telescopic cylinder (5) is mounted above the second conveyor belt (6) and is located above the mounting frame (42). A top plate (51) is fixedly provided on the circumferential outer wall of the piston rod. A third spring (52) is fixedly provided on the lower surface of the top plate (51). A bottom plate (53) is fixedly provided at the bottom end of the third spring (52). The bottom plate (53) is slidably connected to the piston rod. The elastic force of the third spring (52) is greater than the pulling force of the first spring (411). The bottom plate (53) can abut against the top of the mounting frame (42), and the piston rod of the first telescopic cylinder (5) can extend into the mounting frame (42). The bottom plate (53) is in contact with the top of the installation frame (42) and can drive the installation frame (42) to move to a position where the lifting rod (4321) is in contact with the side wall of the material frame (11), and the lifting rod (4321) is located below the lifting plate (121); The piston rod of the first telescopic cylinder (5) can abut against the extension plate (422) to the position where the disengagement rod (4221) abuts against the freeze-drying surface, and at this time, the side block (43) moves to the position where the lifting rod (4321) pulls out the partition frame (12); A third conveyor belt (7) is located on one side of the turntable (4); the mounting frame (42) can be located above the third conveyor belt (7); and a placement component (8) for placing the partition frame (12) on the third conveyor belt (7) is provided above the third conveyor belt (7); The third conveyor belt (7) transports the partition frame (12) to the installation station (3) after passing through the ultrasonic cleaning area and the drying and sterilization area.
2. A freeze-dried soup cube production line according to claim 1, characterized in that: A plurality of guide cylinders (4211) are fixedly arranged at the bottom of the installation frame (42); the guide cylinders (4211) are communicated with the disengagement holes (421); and the disengagement rods (4221) can extend from the bottom of the guide cylinders (4211).
3. The freeze-dried soup cube production line according to claim 1, characterized in that: A baffle (45) is fixedly arranged on the side wall of the installation frame (42), a fourth spring (451) is fixedly arranged on the lower surface of the baffle (45), the bottom end of the fourth spring (451) is fixedly connected to the side block (43), and the fourth spring (451) is a compression spring.
4. The freeze-dried soup cube production line according to claim 1, characterized in that: The placement assembly (8) comprises a second telescopic cylinder (81), an extension plate (82) and an insertion plate (83); The second telescopic cylinder (81) is mounted above the third conveyor belt (7), and the top plate (51), the bottom plate (53) and the third spring (52) are also mounted on the piston rod of the second telescopic cylinder (81). The positional relationship after installation is the same as that on the first telescopic cylinder (5). The bottom plate (53) can drive the installation frame (42) to move downward to a position where the partition frame (12) is placed on the third conveyor belt (7) and the lifting rod (4321) is located below the lifting plate (121); There are two extension plates (82), which are fixed on the piston rod of the second telescopic cylinder (81), located above the top plate (51), extending to both sides to both sides of the installation frame (42) and then extending downward, an insertion groove (821) is provided at the bottom end of the downwardly extending portion of the extension plate (82), a fifth spring (8211) is fixedly provided on the top wall of the insertion groove (821), the bottom end of the fifth spring (8211) is fixedly connected to the insertion plate (83), the insertion plate (83) partially extends out of the insertion groove (821), and a hook groove (831) is provided on the side wall of the portion of the insertion plate (83) extending out of the insertion groove (821); The side wall of the arc-shaped clamp (432) is fixedly provided with an unlocking rod (4322), and the piston rod of the second telescopic cylinder (81) can drive the insertion plate (83) to move to a position where the unlocking rod (4322) abuts against the unlocking rod (4322) and the unlocking rod (4322) is located in the insertion groove (821), at which time the lifting rod (4321) and the lifting plate (121) are staggered; After the mounting frame (42) is reset, the force applied to the lifting rod (4321) can be disengaged from the hook groove (831).
5. A freeze-dried soup cube production line according to claim 4, characterized in that: A separation plate (412) is mounted on the workstation frame (41), the separation plate (412) is vertically arranged and the bottom end is an inclined surface. After the installation frame (42) is reset, the separation plate (412) abuts against the unlocking rod (4322) and causes the unlocking rod (4322) to be separated from the hook groove (831).
6. The freeze-dried soup cube production line according to claim 1, characterized in that: The installation station (3) comprises a material unloading rack (31) and a third telescopic cylinder (32); The unloading rack (31) is a vertical shaft structure formed by connecting a plurality of vertical rods to each other. The unloading rack (31) is erected above the first conveyor belt (1), and the vertical rods of the unloading rack (31) abut against the lifting plate (121) of the partition frame (12) or the partition frame (12). The side wall of the unloading rack (31) is provided with a plurality of one-way grooves (311) at equal intervals, and a clamping plate (312) is rotatably connected to the top of the one-way groove (311). The clamping plate (312) can be completely located in the one-way groove (311) after rotation, and a torsion spring is provided on the rotation axis of the clamping plate (312) so that the clamping plate (312) maintains a horizontal state. The distance between the one-way grooves (311) is not less than the height of the partition frame (12), and the plurality of clamping plates (312) can hold up the partition frame (12) together. The third telescopic cylinder (32) is mounted above the material unloading rack (31), and the piston rod is arranged downward and can extend into the material unloading rack (31). The piston rod can move the partition frame (12) in the material unloading rack (31) to a position abutting against the lower clamping plate (312); The third conveyor belt (7) moves the partition frame (12) to above the unloading rack (31).
7. The freeze-dried soup cube production line according to claim 1, characterized in that: The bottom edge of the partition frame (12) is chamfered, and the inner wall of the material frame (11) is convexly arranged at a position opposite to the chamfer of the bottom of the partition frame (12) and can fit with the chamfered portion of the material frame (11).
8. A freeze-dried soup cube production process, using the freeze-dried soup cube production line according to claim 1, characterized in that: The steps include: S1, after the soup is produced, it is injected into the material frame (11), the solid components in the soup are evenly diffused in the material frame (11), and then a partition frame (12) is inserted into the material frame (11); S2, transferring the material frame (11) to a vacuum freeze-drying device for freeze-drying, first freezing at -30°C to -40°C for 2-4h, then evacuating the vacuum to a vacuum degree below 130 Pa, then slowly raising the temperature to -15°C to -10°C, and finally slowly raising the temperature to 10°C to 25°C, with the entire heating time controlled within 8h; S3, after taking out the material frame (11), take out the partition frame (12), and finally separate the freeze-dried blocks from the material frame (11), screen the freeze-dried blocks, and then package them.