By designing a concrete curing device including sprinkler, coating, horizontal perception, material conveying sealing and control mechanism, the problem of water loss on the inclined ground is solved and efficient maintenance of concrete building ground is achieved.
Patent Information
- Application Number
- CN202411792529.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-07
- Publication Date
- 2025-02-07
AI Technical Summary
When the prior art carries concrete on the ground with an inclined angle, the water in the film will flow out along the inclined ground, which will not be able to effectively lock the water, and the larger the inclination, the faster the water loss.
A concrete curing device for construction is designed, including a vehicle, a sprinkler maintenance mechanism, a coating water locking mechanism, a horizontal sensing mechanism, a material conveying sealing mechanism and a control mechanism. The device can automatically lay the membrane after sprinkling water on the concrete building floor, and ensure that the membrane is closely fitted with the building floor through the release and distribution of sand, thereby blocking moisture loss.
It effectively prevents the rapid evaporation of water and improves the effect of continuous maintenance of concrete building ground, especially on inclined ground, reducing water loss and improving maintenance effect.
Smart Images

Figure CN119392580A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of concrete curing, and in particular to a concrete curing device for building construction. Background Art
[0002] In construction, the reason why concrete can gradually solidify and harden after pouring is mainly due to the hydration of cement, and hydration requires appropriate temperature and humidity conditions. Therefore, in order to ensure that the concrete has suitable hardening conditions and its strength continues to increase, the concrete must be cured.
[0003] The patent with the announcement number CN110080544B discloses a concrete curing and coating device for construction, including a vehicle-mounted traveling device, a cleaning mechanism, a watering and curing mechanism, a power mechanism, a support frame, a coating roller, a baffle, a hinge block, an extension plate, an electric push rod and a film pressing and protecting device. The cleaning mechanism is located on the left side of the top of the vehicle-mounted traveling device, the watering and curing mechanism is located on the top of the vehicle-mounted traveling device, and the watering and curing mechanism is located on the right side of the cleaning mechanism. Through the forward movement of the vehicle-mounted traveling device, one end of the film on the coating roller is pressed against the bottom of the pressing roller. At this time, the film on the coating roller is flatly coated on the building floor, so that the film covers the surface of the concrete. After coating, water can be collected in the film to prevent water loss, create a self-curing environment, avoid the phenomenon of concrete dehydration after concrete casting and forming, and ensure sufficient strength of the concrete.
[0004] The above-mentioned related technology has the following defects: when maintaining the ground at an inclined angle, even if the film is laid flat on the ground, due to the inclination of the ground, the water in the film will still flow out along the inclined ground. In other words, it cannot lock water on the inclined ground, and the greater the inclination, the faster the water will be lost. Summary of the invention
[0005] The purpose of the present invention is to provide a concrete curing device for construction, so as to solve the problem in the prior art that when curing a concrete building floor with an inclined angle, even if a film is laid flat on the building floor, due to the inclination of the building floor, water in the film will still flow out along the inclined building floor, that is, in the inclined building floor, the film cannot lock in water, and the greater the inclination, the faster the water will flow out.
[0006] In order to achieve the above-mentioned object, the present invention provides the following technical solution: a concrete curing device for construction, comprising a carrier and a plurality of rollers installed at the bottom of the carrier, and further comprising:
[0007] A watering maintenance mechanism, which is installed on the carrier and is used to evenly spray water onto the concrete building floor;
[0008] The membrane-covering and water-locking mechanism is installed on the carrier and is used to lay the membrane after water is sprinkled on the concrete building floor, and to make the membrane fit tightly with the concrete building floor;
[0009] A level sensing mechanism, which is installed at the bottom of the vehicle and is used to sense changes in the level of the concrete building ground;
[0010] The material delivery blocking mechanism is installed on the top of the carrier and connected to the horizontal sensing mechanism, and is used to deliver sand and soil in a straight line to the top of the membrane located on the downward side of the concrete building ground;
[0011] The control mechanism is installed on the carrier and is respectively connected with the horizontal sensing mechanism and the material feeding blocking mechanism to control the release timing and release amount of the sand.
[0012] Furthermore, the watering maintenance mechanism includes a shunt pipe installed on an outer wall of one side of the carrier and a plurality of nozzles installed at the bottom of the shunt pipe;
[0013] A water pump and a water tank are installed inside the vehicle, one end of the water pump is connected to the water tank, and the other end of the water pump is connected to the shunt pipe.
[0014] Furthermore, the film-coating and water-locking mechanism comprises a bracket mounted on the top of the carrier and a pressure roller arranged on one side of the shunt pipe;
[0015] A rotating roller is installed inside the bracket, and a film roller is sleeved outside the rotating roller;
[0016] Two linkage frames are hinged on the outer wall of one side of the carrier, and the pressure roller is rotatably connected between the two linkage frames;
[0017] One end of the film on the film roll passes through the bottom of the pressure roller.
[0018] Furthermore, the horizontal sensing mechanism is provided with two, and the horizontal sensing mechanism comprises a movable seat arranged at the bottom of the carrier and a sphere rollingly connected to the bottom of the movable seat;
[0019] A slide bar is installed on the top of the movable seat, and the slide bar penetrates the carrier and is slidably connected with the carrier;
[0020] The top of the roller is connected to the bottom of the carrier via a damping spring.
[0021] Furthermore, a sand box is installed on the top of the carrier, and a main flow cylinder is installed on the bottom of the sand box.
[0022] Furthermore, two material delivery blocking mechanisms are provided, and the two material delivery blocking mechanisms are symmetrically arranged on both sides of the main flow cylinder;
[0023] The material delivery blocking mechanism includes a delivery cylinder installed on the top of the carrier and a material discharge pipe installed at one end of the delivery cylinder;
[0024] The conveying cylinder is rotatably connected to an auger, and a motor is installed at the other end of the conveying cylinder, and the output end of the motor is fixedly connected to one end of the auger;
[0025] The other end of the feed pipe is arranged to be inclined downward.
[0026] Furthermore, the control mechanism is provided with two, and the two control mechanisms are respectively connected to the two conveying cylinders, and the control mechanism includes a guide cylinder connected to the main cylinder, a through groove provided inside the guide cylinder, and a guide groove penetrating inside the slide bar;
[0027] The other end of the guide cylinder is connected to the top of the conveying cylinder;
[0028] The slide bar penetrates through the groove to divide the guide tube into two parts. When the guide groove is connected with the inside of the guide tube, the sand in the sand box enters the inside of the conveying tube through the main tube and the guide tube.
[0029] Furthermore, sealing blocks are provided on both sides of the slide bar, and the sealing blocks are fixedly connected to the outside of the guide tube for sealing the guide groove.
[0030] Furthermore, a limit block is provided above the slide bar, and the limit block is fixedly connected to the bottom of the sand box;
[0031] A slide groove is provided inside the movable seat, a slide seat is slidably connected inside the slide groove, a return spring is fixed to the bottom of the slide seat, the bottom end of the return spring is fixed to the inner wall of the bottom of the slide groove, and the bottom end of the slide bar extends to the inside of the slide groove and is fixed to the top of the slide seat.
[0032] Compared with the prior art, the concrete curing device for building construction provided by the present invention has the following beneficial effects:
[0033] 1. When the carrier moves, the film roller rotates accordingly, releasing the film so that it covers the building floor that has just been sprayed with water. At the same time, the pressure roller is affected by its own gravity. During the rotation process, the film is attached to the building floor through the action of water, which effectively prevents the rapid evaporation of water and can continuously maintain the concrete building floor;
[0034] 2. When the carrier moves on the inclined building ground, the guide tube on the side tilted downward is automatically controlled to open, so that the sand and soil can flow smoothly into the conveying tube and the discharge pipe on the side tilted downward. The sand and soil discharged through the discharge pipe fall on the edge of the membrane in a straight line as the carrier moves, so that the membrane and the concrete building ground fit more closely, the water inside the membrane is blocked, and the amount of water inside the membrane flowing out due to the tilt of the building ground is reduced, thereby improving the continuous maintenance effect of the inclined concrete building ground;
[0035] 3. The greater the inclination of the concrete building ground, the larger the connection area between the guide groove and the guide tube. The larger the connection area, the faster the sand passes through. Therefore, the more sand is put on the membrane, the more the membrane edge can be compacted, reducing water loss. Conversely, the smaller the inclination of the concrete building ground, the less sand is put in, which can reduce the amount of sand used. BRIEF DESCRIPTION OF THE DRAWINGS
[0036] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments recorded in the present invention. For ordinary technicians in this field, other drawings can also be obtained based on these drawings.
[0037] Figure 1 It is a schematic diagram of the overall structure of the present invention;
[0038] Figure 2 It is a schematic diagram of the structure of the watering maintenance mechanism and the level sensing mechanism of the present invention;
[0039] Figure 3 It is a schematic diagram of the structure of the horizontal sensing mechanism, the material feeding blocking mechanism and the control mechanism of the present invention;
[0040] Figure 4 It is a schematic cross-sectional view of the control mechanism structure of the present invention;
[0041] Figure 5 It is a schematic diagram of the internal structure of the movable seat of the present invention.
[0042] Description of reference numerals:
[0043] 1. Carrier; 2. Roller; 3. Diverter pipe; 4. Nozzle; 5. Bracket; 6. Pressure roller; 7. Rotating roller; 8. Membrane roller; 9. Linkage frame; 10. Movable seat; 11. Ball; 12. Slide bar; 13. Sand box; 14. Main flow cylinder; 15. Conveying cylinder; 16. Feeding pipe; 17. Auger; 18. Motor; 19. Guide cylinder; 20. Groove; 21. Guide groove; 22. Sealing block; 23. Limit block; 24. Slide groove; 25. Slide seat; 26. Reset spring. DETAILED DESCRIPTION
[0044] In order to enable those skilled in the art to better understand the technical solution of the present invention, the present invention will be further described in detail below with reference to the accompanying drawings.
[0045] Example: See Figure 1 - Figure 5 A concrete curing device for construction includes a carrier 1 and a plurality of rollers 2 mounted at the bottom of the carrier 1, a damping spring capable of reflecting a position difference is arranged between the rollers 2 and the bottom of the carrier 1, so that when the carrier 1 moves on an inclined construction ground, the roller 2 on the side inclined downward is subjected to a greater gravity, so that the damping spring connected to the roller 2 is compressed to a greater extent, and the perception of the horizontality of the construction ground is more obvious, wherein the concrete construction ground is a concrete pavement, and the concrete curing device for construction also includes:
[0046] A watering maintenance mechanism is installed on the carrier 1 and is used to evenly spray water onto the concrete building floor. The watering maintenance mechanism includes a shunt pipe 3 installed on the outer wall of one side of the carrier 1 and a plurality of nozzles 4 installed at the bottom of the shunt pipe 3. A water pump and a water tank are installed inside the carrier 1. One end of the water pump is connected to the water tank, and the other end of the water pump is connected to the shunt pipe 3.
[0047] When the vehicle 1 is moving, the water in the water tank is pumped out to the diversion pipe 3 by starting the water pump, and the water is evenly sprayed out through each nozzle 4 .
[0048] The film-coating and water-locking mechanism is installed on the carrier 1 and is used to lay the film after sprinkling water on the concrete building floor, and make the film and the concrete building floor fit closely together. The film-coating and water-locking mechanism includes a bracket 5 installed on the top of the carrier 1 and a pressure roller 6 arranged on one side of the shunt pipe 3. The bracket 5 and the carrier 1 are connected by bolts, that is, the bracket 5 can be removed from the carrier 1; a rotating roller 7 is installed inside the bracket 5, and the rotating roller 7 can be removed from the bracket 5 to facilitate the replacement of the film roller 8 outside the rotating roller 7, and the outer part of the rotating roller 7 is sleeved with the film roller 8; two linkage frames 9 are hinged on the outer wall of one side of the carrier 1, and the pressure roller 6 is rotatably connected between the two linkage frames 9; one end of the film on the film roller 8 passes through the bottom of the pressure roller 6;
[0049] When the operation is just started, the staff will first fix one end of the film. When the carrier 1 moves, the film roller 8 will rotate accordingly to release the film, so that the film covers the building floor that has just been sprayed with water. At the same time, the pressure roller 6 is affected by its own gravity. During the rotation process, the film is attached to the building floor through the action of water, which effectively prevents the rapid evaporation of water and can continuously maintain the concrete building floor.
[0050] A horizontal sensing mechanism is installed at the bottom of the carrier 1 to sense the change in the level of the concrete building ground. There are two horizontal sensing mechanisms, which include a movable seat 10 arranged at the bottom of the carrier 1 and a sphere 11 rollingly connected to the bottom of the movable seat 10; a slide bar 12 is installed on the top of the movable seat 10, and the slide bar 12 runs through the carrier 1 and is slidably connected to the carrier 1;
[0051] When the vehicle 1 moves on the inclined building ground, the roller 2 on the inclined downward side is subjected to a greater gravity, and thus the damping spring connected to the roller 2 is compressed to a greater extent. As a result, the distances between the rollers 2 on both sides and the bottom of the vehicle 1 become different. The roller 2 on the inclined downward side is closer to the bottom of the vehicle 1, and therefore the sphere 11 on the inclined downward side approaches the vehicle 1, and the slide bar 12 moves upward accordingly. The roller 2 on the inclined upward side is subjected to a reduced gravity, which increases the distance between the roller 2 and the vehicle 1, and thus the corresponding slide bar 12 moves downward. However, the slide bar 12 still closes the guide tube 19 when it moves downward, that is, only when the slide bar 12 moves upward can the guide tube 19 be controlled to be connected to the conveying tube 15.
[0052] The material feeding and blocking mechanism is installed on the top of the carrier 1 and connected to the horizontal sensing mechanism, and is used to transport sand and soil in a straight line to the top of the membrane located on the inclined downward side of the concrete building ground. A sand box 13 is installed on the top of the carrier 1, and a main flow cylinder 14 is installed at the bottom of the sand box 13. There are two material feeding and blocking mechanisms, and the two material feeding and blocking mechanisms are symmetrically arranged on both sides of the main flow cylinder 14; the material feeding and blocking mechanism includes a conveying cylinder 15 installed on the top of the carrier 1 and a discharge pipe 16 installed at one end of the conveying cylinder 15; the conveying cylinder 15 is rotatably connected with an auger 17, and the other end of the conveying cylinder 15 is installed with a motor 18, and the output end of the motor 18 is fixedly connected to one end of the auger 17; the other end of the discharge pipe 16 is arranged to be inclined downward;
[0053] The motor 18 always keeps running. When the sand in the sand box 13 enters the corresponding conveying cylinder 15 through the main cylinder 14 and the guide cylinder 19, the auger 17 in the rotation process conveys the sand to the inside of the discharge pipe 16. The sand discharged through the discharge pipe 16 falls on the edge of the membrane in a straight line as the carrier 1 moves, so that the membrane fits more closely with the concrete building floor, the water inside the membrane is blocked, the amount of water inside the membrane flowing out due to the tilt of the building floor is reduced, and the maintenance effect on the concrete building floor is improved.
[0054] A control mechanism is installed on the carrier 1 and is respectively connected to the horizontal sensing mechanism and the material feeding blocking mechanism to control the release time and release amount of sand and soil. Two control mechanisms are provided, and the two control mechanisms are respectively connected to the two conveying cylinders 15. The control mechanism includes a guide cylinder 19 connected to the main flow cylinder 14, a through groove 20 provided inside the guide cylinder 19, and a guide groove 21 penetrating through the inside of the slide bar 12; the other end of the guide cylinder 19 is connected to the top of the conveying cylinder 15; the slide bar 12 is provided with the through groove 20, dividing the guide cylinder 19 into two, and when the guide groove 21 is connected to the inside of the guide cylinder 19, the sand and soil inside the sand box 13 enters the inside of the conveying cylinder 15 through the main flow cylinder 14 and the guide cylinder 19;
[0055] When the slide bar 12 moves upward, the guide groove 21 inside it moves upward synchronously, and the guide groove 21 is then connected to the inside of the guide cylinder 19, and the sand inside the guide cylinder 19 enters the inside of the conveying cylinder 15 through the guide groove 21;
[0056] The area of connection between the guide groove 21 and the guide tube 19 is determined by the degree of inclination of the concrete building ground. That is, the greater the inclination of the concrete building ground, the larger the connection area between the guide groove 21 and the guide tube 19. The larger the connection area, the faster the sand passes through. Therefore, the more sand is put on the membrane, the more the membrane edge can be compacted, and the water loss can be reduced. On the contrary, the smaller the inclination of the concrete building ground, the less sand is put in, and the amount of sand used can be reduced.
[0057] Sealing blocks 22 are provided on both sides of the slide bar 12. The sealing blocks 22 are fixedly connected to the outside of the guide tube 19 to seal the guide groove 21.
[0058] When half of the area of the guide groove 21 is connected to the guide tube 19, the sand will enter the guide groove 21 when passing through the guide tube 19. The setting of the sealing block 22 can prevent the sand from being scattered when entering the guide groove 21. After the sand enters the guide groove 21, the part of the guide groove 21 that is not connected to the guide tube 19 will be filled up, and then flow into the conveying tube 15 along the space connected between the guide groove 21 and the guide tube 19.
[0059] A limit block 23 is provided above the slide bar 12, and the limit block 23 is fixedly connected to the bottom of the sand box 13; a slide groove 24 is provided inside the movable seat 10, and a slide seat 25 is slidably connected inside the slide groove 24, and a return spring 26 is fixedly connected to the bottom of the slide seat 25, and the bottom end of the return spring 26 is fixedly connected to the inner wall of the bottom of the slide groove 24. The return spring 26 is provided to facilitate the reset of the slide seat 25. The bottom end of the slide bar 12 extends to the inside of the slide groove 24 and is fixedly connected to the top of the slide seat 25;
[0060] When the slide bar 12 moves upward to make the guide groove 21 fully connected with the guide tube 19, that is, when the maximum flow area of the guide groove 21 is reached, the top of the slide bar 12 abuts against the bottom of the limit block 23, so the slide bar 12 will not continue to move upward, so that the guide groove 21 remains at the maximum flow area. In the current situation, if the carrier 1 continues to tilt, the slide bar 12 will drive the slide seat 25 to move downward along the inner wall of the slide groove 24 to compensate for the position difference caused by the continued tilt.
[0061] Working principle: When in use, one end of the film on the film roller 8 passes through the bottom of the pressure roller 6. The staff first fixes one end of the film. When the carrier 1 moves, the water in the water tank is pumped into the shunt pipe 3 by starting the water pump, and is evenly sprayed out through each nozzle 4. When the carrier 1 moves, the film roller 8 rotates accordingly to release the film so that the film covers the building ground that has just been sprayed with water. At the same time, the pressure roller 6 is affected by its own gravity. During the rotation process, the film is attached to the building ground through the action of water, which effectively prevents the rapid evaporation of water and can continuously maintain the concrete building ground. When the carrier 1 moves on the inclined building ground, the roller 2 on the inclined downward side is subjected to a greater gravity, so the damping spring connected to the roller 2 is compressed to a greater extent, so the distance between the rollers 2 on both sides and the bottom of the carrier 1 is The distance becomes different, the roller 2 tilted downward is closer to the bottom of the carrier 1, so the sphere 11 tilted downward approaches the carrier 1, and the slide bar 12 moves upward. When the slide bar 12 moves upward, it drives the guide groove 21 inside it to move upward synchronously, and the guide groove 21 is then connected with the inside of the guide cylinder 19, and the sand and soil inside the guide cylinder 19 enters the inside of the conveying cylinder 15 through the guide groove 21. The auger 17 in the rotation process transports the sand and soil to the inside of the discharge pipe 16, and the sand and soil discharged through the discharge pipe 16 falls on the edge of the membrane in a straight line as the carrier 1 moves, so that the membrane and the concrete building floor fit more closely, the water inside the membrane is blocked, and the amount of water inside the membrane flowing out due to the tilt of the building floor is reduced, thereby improving the maintenance effect on the concrete building floor.
[0062] It should be noted that the device structure and drawings of the present invention mainly describe the principle of the present invention. In terms of the technology of the design principle, the settings of the power mechanism, power supply system and control system of the device are not fully described. On the premise that the technical personnel in the field understand the principle of the above invention, the specific details of the power mechanism, power supply system and control system can be clearly known. The control method of the application document is to automatically control by a controller, and the control circuit of the controller can be realized by simple programming by the technical personnel in the field; the above only describes some exemplary embodiments of the present invention by way of explanation. Undoubtedly, for ordinary technicians in the field, the described embodiments can be modified in various different ways without departing from the spirit and scope of the present invention. Therefore, the above drawings and descriptions are illustrative in nature and should not be construed as limiting the scope of protection of the claims of the present invention.
[0063] In the description of the present invention, it is necessary to understand that the orientations or positional relationships indicated by “center”, “longitudinal”, “lateral”, “length”, “width”, “thickness”, “up”, “down”, “front”, “back”, “left”, “right”, “vertical”, “horizontal”, “top”, “bottom”, “inside”, “outside”, “clockwise”, “counterclockwise”, etc. are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.
[0064] In addition, the terms "first" and "second" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of the present invention, the meaning of "multiple" is two or more, unless otherwise clearly and specifically defined. In addition, the terms "installed", "connected" and "connected" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal connection of two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to the specific circumstances.
Claims
1. A concrete curing device for construction, comprising a carrier (1) and a plurality of rollers (2) mounted on the bottom of the carrier (1), characterized in that: Also includes: A watering maintenance mechanism, which is installed on the carrier (1) and is used to evenly spray water onto the concrete building floor; A film-covering and water-locking mechanism is installed on a carrier (1) and is used to lay a film on the concrete building floor after water is sprinkled, and to make the film and the concrete building floor fit tightly together; A level sensing mechanism, which is installed at the bottom of the vehicle (1) and is used to sense changes in the level of the concrete building floor; A material delivery blocking mechanism, which is installed on the top of the carrier (1) and connected to the horizontal sensing mechanism, and is used to deliver sand and soil in a straight line to the top of the membrane located on the downwardly inclined side of the concrete building ground; A control mechanism is installed on the carrier (1) and is respectively connected to the horizontal sensing mechanism and the material feeding blocking mechanism, and is used to control the release timing and release amount of the sand.
2. A concrete curing device for construction according to claim 1, characterized in that: The watering maintenance mechanism comprises a shunt pipe (3) installed on an outer wall of one side of the carrier (1) and a plurality of nozzles (4) installed at the bottom of the shunt pipe (3); A water pump and a water tank are installed inside the carrier (1); one end of the water pump is connected to the water tank, and the other end of the water pump is connected to the diversion pipe (3).
3. A concrete curing device for construction according to claim 2, characterized in that: The film-coating and water-locking mechanism comprises a bracket (5) mounted on the top of the carrier (1) and a pressure roller (6) arranged on one side of the diversion pipe (3); A rotating roller (7) is installed inside the bracket (5), and a film roller (8) is sleeved on the outside of the rotating roller (7); Two linkage frames (9) are hingedly connected on the outer wall of one side of the carrier (1), and the pressure roller (6) is rotatably connected between the two linkage frames (9); One end of the film on the film roller (8) passes through the bottom of the pressure roller (6).
4. A concrete curing device for construction according to claim 3, characterized in that: The horizontal sensing mechanisms are provided with two, and the horizontal sensing mechanisms include a movable seat (10) arranged at the bottom of the carrier (1) and a sphere (11) rollingly connected to the bottom of the movable seat (10); A slide bar (12) is installed on the top of the movable seat (10), and the slide bar (12) is arranged to penetrate the carrier (1) and is in sliding connection with the carrier (1); The top of the roller (2) and the bottom of the carrier (1) are connected via a damping spring.
5. A concrete curing device for construction according to claim 4, characterized in that: A sand box (13) is installed on the top of the carrier (1), and a main flow cylinder (14) is installed on the bottom of the sand box (13).
6. A concrete curing device for construction according to claim 5, characterized in that: There are two material delivery blocking mechanisms, which are symmetrically arranged on both sides of the main flow cylinder (14); The material delivery blocking mechanism comprises a delivery cylinder (15) installed on the top of the carrier (1) and a material discharge pipe (16) installed at one end of the delivery cylinder (15); The conveying cylinder (15) is rotatably connected to an auger (17), and a motor (18) is installed at the other end of the conveying cylinder (15), and the output end of the motor (18) is fixedly connected to one end of the auger (17); The other end of the feed pipe (16) is arranged to be inclined downward.
7. A concrete curing device for construction according to claim 6, characterized in that: The control mechanism is provided with two, and the two control mechanisms are respectively connected to the two conveying cylinders (15), and the control mechanism comprises a guide cylinder (19) connected to the main cylinder (14), a through groove (20) provided inside the guide cylinder (19), and a guide groove (21) penetrating and provided inside the slide bar (12); The other end of the guide cylinder (19) is connected to the top of the conveying cylinder (15); The slide bar (12) is arranged to penetrate the through groove (20) to divide the guide tube (19) into two parts. When the guide groove (21) is connected to the inside of the guide tube (19), the sand in the sand box (13) enters the inside of the conveying tube (15) through the main flow tube (14) and the guide tube (19).
8. A concrete curing device for construction according to claim 7, characterized in that: Sealing blocks (22) are provided on both sides of the slide bar (12), and the sealing blocks (22) are fixedly connected to the outside of the guide tube (19) and are used to seal the guide groove (21).
9. A concrete curing device for construction according to claim 8, characterized in that: A limit block (23) is provided above the slide bar (12), and the limit block (23) is fixedly connected to the bottom of the sand box (13); The movable seat (10) is provided with a slide groove (24) inside, a slide seat (25) is slidably connected inside the slide groove (24), a return spring (26) is fixedly connected to the bottom of the slide seat (25), the bottom end of the return spring (26) is fixedly connected to the inner wall of the bottom of the slide groove (24), and the bottom end of the slide bar (12) extends to the inside of the slide groove (24) and is fixedly connected to the top of the slide seat (25).
Citation Information
Patent Citations
A concrete curing and covering device for building construction
CN110080544B
Cited By
Temperature and humidity sensing intelligent maintenance device
CN120061213A