Strip mine turning method and device, electronic equipment and storage medium

By obtaining the mine data of the open-pit mine, the steering treatment plan is determined, including the open-pit mine boundary, work line layout plan, soil discharge plan and soil discharge site connection plan, the production continuity and transportation distance during the steering process of the open-pit mine is solved. The problem of sharp increase in height difference and lower economic benefits has achieved the improvement of production continuity and economic benefits.

CN119393142APending Publication Date: 2025-02-07BEIFANG WEIJIAMAO COAL POWER CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411431032.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-14
Publication Date
2025-02-07

AI Technical Summary

Technical Problem

During the steering process, there are problems such as production continuation difficulties, rapid increase in the height difference of waste transportation distances and reduced economic benefits.

Method used

By obtaining the mine data of the open-pit mine, the steering treatment plan is determined, including the open-pit mine boundary, the working line layout plan, the soil discharge plan and the soil discharge site connection plan. Based on these solutions, the work line layout is adjusted, the mining procedures are optimized, and the inclined base soil discharge and capacity-enhancing soil discharge site are carried out to achieve production continuity and economic benefits.

Benefits of technology

It has achieved improvement in the production continuity of open-pit mines, reduced the waste and transportation distance and improved economic benefits.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119393142A_ABST
    Figure CN119393142A_ABST
Patent Text Reader

Abstract

According to the strip mine steering method and device, the electronic equipment and the storage medium provided by the invention, the mine field data of the target strip mine is acquired, and the steering processing scheme of the target strip mine is determined according to the mine field data; the steering treatment scheme at least comprises a strip mine boundary approaching and working line arrangement scheme, a dumping scheme and a dumping site communication scheme; based on the working line arrangement scheme, an inclined pushing working line is arranged in a first preset direction of the target strip mine, the arranged target strip mine is obtained, and a target dumping site of the arranged target strip mine is arranged based on the dumping scheme; performing communication processing on the target dumping site and other dumping sites based on the dumping site communication scheme to obtain a processed target strip mine; and the forced pushing working line is pushed from the second preset direction of the processed target strip mine to the strip mine border, and steering transverse mining processing is carried out at the strip mine border. According to the embodiment of the invention, through mining program optimization, the effects of ensuring continuous production of the strip mine, reducing the discharge distance and improving the economic benefit are achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present disclosure relates to the field of coal mine production, and in particular to a method and device for turning an open-pit mine, an electronic device and a storage medium. Background Art

[0002] Open-pit coal mines with zoned mining all have the problem of internal drainage balance during the transition period, that is, the internal drainage is tight in the early stage, and the internal drainage space is suddenly released at the end, resulting in the internal drainage yard not being fully utilized, the external drainage area increasing, and difficulty in reclamation at the end.

[0003] During the production period of the open-pit mine, the first mining area is turning to the second mining area, the land acquisition of the village is delayed, the coal seam is extended downward, and the inclination of the coal seam is increased. Under the influence of these unfavorable conditions, the coal seam in the southern part of the first mining area and the second mining area of ​​the open-pit mine has a large inclination, with a slope of 10° to 19°, and the working face is gradually transformed into a method of advancing from north to south and horizontal arrangement (horizontal mining). In the process of advancing the working face, multiple layers of coal and rock will cross on the same flat plate, and there are problems such as great difficulty in large-scale equipment selection, large loss of raw coal, low coal selection rate, and difficulty in exerting equipment efficiency; after the turn, the working line of the first mining area becomes shorter, and the horizontal arrangement length of the working line is only 500-800m. The length of the working line is shortened, the operation cycle of each link of the production is accelerated, and the short working line, large extension depth, narrow working face, and fast advancement production lead to the difficulty of connecting each link of the production, the difficulty of exerting equipment efficiency, the reduction of exposed coal, and the reduction of the economic benefits of the open-pit mine; and with the continuous advancement of the mining field, the transportation distance and height difference will still have a tendency to increase, resulting in a sharp increase in the height difference of the soil discharge transportation distance during the turn of the open-pit mine.

[0004] Therefore, how to ensure the continuity of open-pit mine production, reduce the distance of waste disposal and transportation, and improve economic benefits is an urgent problem to be solved. Summary of the invention

[0005] The present invention provides a method and device for turning an open-pit mine, an electronic device and a storage medium, and its main purpose is to solve the problem of how to ensure the continuity of open-pit mine production, reduce the distance of waste transportation and improve economic benefits.

[0006] According to a first aspect of the present disclosure, a method for turning an open-pit mine is provided, comprising:

[0007] Acquire the mine data of the target open-pit mine, and determine the diversion processing scheme of the target open-pit mine according to the mine data; wherein the diversion processing scheme at least includes the open-pit mine boundary, the working line layout scheme, the dumping scheme and the dumping field connection scheme;

[0008] Based on the working line arrangement plan, an oblique push working line is arranged at a first preset orientation of the target open-pit mine to obtain the arranged target open-pit mine, and based on the dumping plan, a target dumping yard of the arranged target open-pit mine is set;

[0009] Based on the dump interconnection scheme, the target dump is interconnected with other dumps to obtain a processed target open-pit mine; wherein the other dumps are dumps of other open-pit mines except the target open-pit mine;

[0010] The forced pushing working line is advanced from the second preset position of the processed target open-pit mine to the boundary of the open-pit mine, and the turning and horizontal mining processing is carried out at the boundary of the open-pit mine.

[0011] Optionally, determining the steering treatment plan of the target open-pit mine according to the mine data includes:

[0012] Acquire the length of the forced-pushing working line, the mining and stripping engineering volume, and the earth-draining space contained in the mine data, and determine the boundary of the open-pit mine according to the length of the forced-pushing working line, the mining and stripping engineering volume, and the earth-draining space;

[0013] Acquire the working face transportation route data contained in the mine data, and determine the working line layout plan based on the working face transportation route data;

[0014] Acquire the supporting force data of the inclined bottom plate and the end wall contained in the mine data, and determine the soil discharge plan based on the supporting force data;

[0015] The spoil dump data included in the mine data is obtained, and a spoil dump connection solution is determined based on the spoil dump data.

[0016] Optionally, determining the open-pit mine boundary according to the length of the forced pushing working line, the mining and stripping engineering volume, and the earth removal space includes:

[0017] Determining the parameter relationship of the target open-pit mine according to the length of the forced pushing working line, the mining and stripping engineering volume, and the dumping space;

[0018] The parameter relationship is subjected to data analysis and processing to obtain the open-pit mine boundary.

[0019] Optionally, determining the working line layout scheme based on the working face transportation route data includes:

[0020] Performing data abstraction processing on the working face transport route data to obtain processed transport route data, and performing model construction processing according to the processed transport route data and a preset construction algorithm to obtain a transport distance model;

[0021] The amount of flat plate stripping material and the location of the waste dump contained in the mine data are obtained, and the working face transportation route data, the amount of flat plate stripping material and the location of the waste dump are input into the transportation distance model for data processing to obtain the working line layout plan.

[0022] Optionally, determining the soil discharge scheme based on the support force data includes:

[0023] Determine the earth discharge data of the two inclined towers based on the supporting force data;

[0024] The soil discharge plan is determined according to the soil discharge data of the two inclined towers and the bottom plate blasting position included in the mine data.

[0025] Optionally, determining the spoil dump connection solution based on the spoil dump data includes:

[0026] Determine the distance value between the target dump site and each of the other dump sites according to the dump site data;

[0027] Determine the connection mode between the target dump site and each of the other dump sites through the dump site data and the distance value;

[0028] The target spoil dump is connected to each of the other spoil dumps according to the connection method to obtain the spoil dump connection plan.

[0029] According to a second aspect of the present disclosure, there is provided an open-pit mine steering device, comprising:

[0030] An acquisition unit, used for acquiring mine data of a target open-pit mine;

[0031] A determination unit, configured to determine a diversion processing scheme of the target open-pit mine according to the mine data; wherein the diversion processing scheme at least includes an open-pit mine boundary, a working line layout scheme, a dumping scheme, and a dumping field connection scheme;

[0032] A layout unit, configured to layout an oblique push working line at a first preset orientation of the target open-pit mine based on the working line layout plan, obtain the arranged target open-pit mine, and set a target dumping site of the arranged target open-pit mine based on the dumping plan;

[0033] A connecting unit, used for connecting the target dump with other dumps based on the dump connection scheme to obtain a processed target open-pit mine; wherein the other dumps are dumps of other open-pit mines except the target open-pit mine;

[0034] The mining unit is used to advance the forced pushing working line from the second preset position of the processed target open-pit mine to the boundary of the open-pit mine, and to perform a turning horizontal mining process at the boundary of the open-pit mine.

[0035] Optionally, the determining unit includes:

[0036] An acquisition module, used to acquire the length of the forced pushing working line, the mining and stripping engineering volume and the earth discharge space contained in the mine data;

[0037] A determination module, used to determine the open-pit mine boundary according to the length of the forced pushing work line, the mining and stripping engineering volume and the earth removal space;

[0038] The acquisition module is also used to acquire the working face transportation route data contained in the mine data;

[0039] The determination module is also used to determine the working line layout plan based on the working face transportation route data;

[0040] The acquisition module is also used to acquire the supporting force data of the inclined bottom plate and the end wall contained in the mine data;

[0041] The determination module is further used to determine the soil discharge plan based on the support force data;

[0042] The acquisition module is also used to acquire the spoil dump data included in the mine data;

[0043] The determination module is also used to determine the spoil dump connection plan based on the spoil dump data.

[0044] Optionally, the determining module is further used for:

[0045] Determining the parameter relationship of the target open-pit mine according to the length of the forced pushing working line, the mining and stripping engineering volume, and the dumping space;

[0046] The parameter relationship is subjected to data analysis and processing to obtain the open-pit mine boundary.

[0047] Optionally, the determining module is further used for:

[0048] Performing data abstraction processing on the working face transport route data to obtain processed transport route data, and performing model construction processing according to the processed transport route data and a preset construction algorithm to obtain a transport distance model;

[0049] The amount of flat plate stripping material and the location of the waste dump contained in the mine data are obtained, and the working face transportation route data, the amount of flat plate stripping material and the location of the waste dump are input into the transportation distance model for data processing to obtain the working line layout plan.

[0050] Optionally, the determining module is further used for:

[0051] Determine the earth discharge data of the two inclined towers based on the supporting force data;

[0052] The soil discharge plan is determined according to the soil discharge data of the two inclined towers and the bottom plate blasting position included in the mine data.

[0053] Optionally, the determining module is further used for:

[0054] Determine the distance value between the target dump site and each of the other dump sites according to the dump site data;

[0055] Determine the connection mode between the target dump site and each of the other dump sites through the dump site data and the distance value;

[0056] The target spoil dump is connected to each of the other spoil dumps according to the connection method to obtain the spoil dump connection plan.

[0057] According to a third aspect of the present disclosure, there is provided an electronic device, including:

[0058] at least one processor; and

[0059] a memory communicatively connected to the at least one processor; wherein,

[0060] The memory stores instructions that can be executed by the at least one processor, and the instructions are executed by the at least one processor to enable the at least one processor to perform the method described in the first aspect.

[0061] According to a fourth aspect of the present disclosure, a non-transitory computer-readable storage medium storing computer instructions is provided, wherein the computer instructions are used to enable the computer to execute the method described in the first aspect.

[0062] According to a fifth aspect of the present disclosure, a computer program product is provided, comprising a computer program, wherein when the computer program is executed by a processor, the computer program implements the method as described in the first aspect above.

[0063] The present disclosure provides a method and device for turning an open-pit mine, an electronic device and a storage medium, which obtain the mine data of a target open-pit mine, and determine a turning processing plan for the target open-pit mine based on the mine data; wherein the turning processing plan at least includes an open-pit mine boundary, a work line layout plan, a soil dumping plan and a soil dumping yard connection plan; based on the work line layout plan, an oblique push work line is arranged at a first preset orientation of the target open-pit mine to obtain the arranged target open-pit mine, and a target soil dumping yard of the arranged target open-pit mine is set based on the soil dumping plan; based on the soil dumping yard connection plan, the target soil dumping yard is connected with other soil dumping yards to obtain the processed target open-pit mine; wherein the other soil dumping yards are soil dumping yards of other open-pit mines except the target open-pit mine; the forced push work line is pushed from the second preset orientation of the processed target open-pit mine to the open-pit mine boundary, and a turning and horizontal mining process is performed at the open-pit mine boundary. Compared with the related technologies, the embodiments of the present disclosure achieve the effects of ensuring the continuity of open-pit mine production, reducing the distance of discharge and transportation, and improving economic benefits by optimizing the mining procedure, adjusting the working line layout, dumping soil on the inclined base, and increasing the capacity of the spoil field.

[0064] It should be understood that the content described in this section is not intended to identify the key or important features of the embodiments of the present application, nor is it intended to limit the scope of the present application. Other features of the present application will become easily understood through the following description. BRIEF DESCRIPTION OF THE DRAWINGS

[0065] The accompanying drawings are used to better understand the present solution and do not constitute a limitation of the present disclosure.

[0066] Figure 1 A schematic flow chart of a method for turning an open-pit mine provided by an embodiment of the present disclosure;

[0067] Figure 2 A flowchart of a method for determining a steering processing solution provided by an embodiment of the present disclosure;

[0068] Figure 3 A schematic diagram of the structure of an open-pit mine steering device provided by an embodiment of the present disclosure;

[0069] Figure 4 A schematic diagram of the structure of another open-pit mine steering device provided by an embodiment of the present disclosure;

[0070] Figure 5 A schematic block diagram of an electronic device provided in an embodiment of the present disclosure. DETAILED DESCRIPTION

[0071] The following is a description of exemplary embodiments of the present disclosure in conjunction with the accompanying drawings, including various details of the embodiments of the present disclosure to facilitate understanding, which should be considered as merely exemplary. Therefore, it should be recognized by those of ordinary skill in the art that various changes and modifications may be made to the embodiments described herein without departing from the scope and spirit of the present disclosure. Similarly, for the sake of clarity and conciseness, descriptions of well-known functions and structures are omitted in the following description.

[0072] The following describes the method, device, electronic device and storage medium for open-pit mine steering according to the embodiments of the present disclosure with reference to the accompanying drawings.

[0073] Figure 1 A schematic flow chart of a method for diverting an open-pit mine provided in an embodiment of the present disclosure.

[0074] like Figure 1 As shown, the method comprises the following steps:

[0075] Step 101, obtaining the mine data of the target open-pit mine, and determining the steering treatment plan of the target open-pit mine according to the mine data; wherein the steering treatment plan at least includes the open-pit mine boundary, the working line layout plan, the dumping plan and the dumping field connection plan.

[0076] In the embodiments of the present disclosure, the present disclosure can be applied to the production process of open-pit mines with complex geological conditions. Specifically, the embodiments of the present disclosure do not limit the application scenarios of the present disclosure.

[0077] Among them, the mine data is data containing all parameters of the target open-pit mine, such as: the length of the forced pushing working line, the mining and stripping project volume, the earth-discharging space, the working face transportation route, the amount of material stripped from each flat plate, the location of the waste dump and the location of the waste dump of each mine in the mining group, etc. Specifically, the content of the mine data is not limited in the embodiments of the present disclosure.

[0078] The diversion treatment plan at least includes optimizing the mining procedure (determining the boundary of the open-pit mine), adjusting the work line layout (determining the work line layout plan), tilting the base to discharge soil (determining the discharge plan), increasing the capacity of the discharge yard (determining the discharge yard interconnection plan), etc. After the target open-pit mine is processed by various methods in the diversion treatment plan, the open-pit mine production can be continued, the discharge and transportation distance can be reduced, and the economic benefits can be improved.

[0079] Specifically, by optimizing the mining procedure, the effective internal drainage space can be increased and the tight situation of soil discharge space can be alleviated. By adjusting the work line layout, the comprehensive transportation distance, the corresponding transportation costs and the inclined push work line with lower impact on the electric shovel layout can be calculated, thereby reducing the drainage transportation distance. By tilting the base soil discharge, the soil yard discharge can be met, which effectively solves the problem of the rapid increase in the inclination angle of the bottom plate of the anticline coal seam and the limitation of the soil discharge space. By increasing the capacity of the soil discharge yard, the overall soil discharge cost of the open-pit mine group can be reduced and the economic benefits can be improved.

[0080] Step 102, based on the working line arrangement plan, arrange the oblique push working line at the first preset orientation of the target open-pit mine to obtain the arranged target open-pit mine, and set the target dumping yard of the arranged target open-pit mine based on the dumping plan.

[0081] In the embodiment of the present disclosure, the first preset direction is a user-selected direction, for example: the southeast of the target open-pit mine, the southwest of the target open-pit mine, etc. Specifically, the embodiment of the present disclosure does not limit the first preset direction.

[0082] Among them, the working line layout plan is to combine the amount of material stripped from each flat plate, the location of the waste dump, and the transportation route to calculate the comprehensive transportation distance, corresponding transportation costs, and the impact on the layout of the electric shovel, etc. of various layout plans, and finally determine the optimal layout plan of the working line that is pushed obliquely to the southeast among all the layout plans, that is, the layout plan with the highest economic benefits among all the layout plans. Regarding the layout of the oblique push working line, for example: the layout of the stripping working line in the southeastern mining area of ​​the first mining area, etc., by optimizing the layout of the stripping working line in the southeastern mining area of ​​the first mining area, and establishing a calculation model for the working line in the southeastern part of the mine pit to calculate the transportation distance of the mine pit, it is obtained that the transportation distance and transportation costs are saved after optimization, thereby increasing economic benefits.

[0083] The target dump can increase the dumping capacity of the target open-pit mine. The dumping plan is a plan determined by the data of the target open-pit mine, for example: the north side supported pseudo-inclined dumping plan, etc. By studying the inclined bottom plate dumping method of the target open-pit mine, the proposed dumping plan can increase the dumping capacity of the west inner dump.

[0084] Step 103, based on the dump interconnection scheme, the target dump is interconnected with other dumps to obtain a processed target open-pit mine; wherein the other dumps are dumps of other open-pit mines except the target open-pit mine.

[0085] In the disclosed embodiment, by interconnecting various spoil dumps, the spoil dumping problem of each open-pit mine can be comprehensively considered from the perspective of an open-pit mine group, and the spoil dumps of each mine in the mine group are uniformly planned. When an open-pit mine in the mine group has insufficient disposal space due to objective factors such as special geological conditions, consideration is given to formulating a spoil dump sharing plan to fully utilize the spatial resources within the mine group, use the internal spoil dumps of adjacent mines for spoil dumping, and use methods such as connecting spoil dumps and building intermediate bridges to shorten transportation distances and reduce the overall spoil dumping cost of the open-pit mine group.

[0086] Step 104, advancing the forced pushing working line from the second preset position of the processed target open-pit mine to the boundary of the open-pit mine, and performing a turning and horizontal mining process at the boundary of the open-pit mine.

[0087] In the embodiment of the present disclosure, the second preset orientation is a user-selected orientation, for example, the north of the target open-pit mine. Specifically, the embodiment of the present disclosure does not limit the second preset orientation.

[0088] When the second preset direction is the north of the target open-pit mine, the method of turning to horizontal mining of the target open-pit mine is to forcefully push the ultra-short working line in the north + realize the internal drainage in the north in advance, which can increase the effective internal drainage space in the north and alleviate the tense situation of the soil discharge space.

[0089] The present disclosure provides a method for turning an open-pit mine, which obtains mine data of a target open-pit mine, and determines a turning treatment plan for the target open-pit mine based on the mine data; wherein the turning treatment plan at least includes an open-pit mine boundary, a work line layout plan, a soil dumping plan, and a soil dumping yard connection plan; based on the work line layout plan, an oblique push work line is arranged at a first preset position of the target open-pit mine to obtain the arranged target open-pit mine, and a target soil dumping yard of the arranged target open-pit mine is set based on the soil dumping plan; based on the soil dumping yard connection plan, the target soil dumping yard is connected with other soil dumping yards to obtain the treated target open-pit mine; wherein the other soil dumping yards are soil dumping yards of other open-pit mines except the target open-pit mine; the forced push work line is pushed from the second preset position of the treated target open-pit mine to the open-pit mine boundary, and a turning and horizontal mining process is performed at the open-pit mine boundary. Compared with the related technologies, the embodiments of the present disclosure achieve the effects of ensuring the continuity of open-pit mine production, reducing the distance of discharge and transportation, and improving economic benefits by optimizing the mining procedure, adjusting the working line layout, dumping soil on the inclined base, and increasing the capacity of the spoil field.

[0090] In one implementable method of the embodiment of the present disclosure, when determining the steering treatment plan of the target open-pit mine according to the mine data, it is necessary to determine each strategy in the steering treatment plan separately, that is, it is necessary to separately determine the optimization of mining procedures (determine the open-pit mine boundary), work line layout adjustment (determine the work line layout plan), inclined base soil discharge (determine the soil discharge plan), soil dump capacity increase (determine the soil dump connection plan) and other contents. Therefore, in order to accurately and completely obtain the steering treatment plan, the embodiment of the present disclosure provides a flow chart of a method for determining a steering treatment plan, such as Figure 2 As shown, including:

[0091] Step 201, obtaining the length of the forced pushing line, the mining and stripping engineering volume and the earth-draining space contained in the mine data, and determining the boundary of the open-pit mine according to the length of the forced pushing line, the mining and stripping engineering volume and the earth-draining space.

[0092] In the disclosed embodiment, the open-pit mine boundary is determined by studying and analyzing the relationship between the length of the northern forced pushing work line, the mining and stripping project volume and the earth discharge space. For example, the 11 coal F12 fault is used as the boundary. At this time, the advancement plan for the target open-pit mine is an advanced advancement plan with the 11 coal F12 fault (the open-pit mine boundary) as the boundary, so as to quickly advance in the north and approach the boundary locally as a whole, thereby realizing internal discharge in the north, while the south is slowly advanced to make up for the insufficient production in the north. After the north is forced to the open-pit mine boundary, it is turned to horizontal mining to increase the effective internal discharge space in the north and alleviate the tense situation of earth discharge space.

[0093] Step 202: Acquire the working face transportation route data contained in the mine data, and determine the working line layout plan based on the working face transportation route data.

[0094] In the disclosed embodiment, the working face transportation line is abstracted according to the working line layout combined with the triangular characteristics, and a transportation distance model of the working face moving pit line under different working line layouts is established, and a transportation distance calculation method for different working line layouts is provided, which simplifies the design process. According to the established working face moving pit line transportation distance calculation model, combined with the amount of material stripped from each flat plate and the location of the waste dump and the transportation route, the comprehensive transportation distance, corresponding transportation cost, and the impact on the electric shovel layout of various layout schemes are calculated, and the optimal layout scheme is finally determined as the working line layout scheme among all the layout schemes. The optimal layout scheme refers to the layout scheme with the highest economic benefit among all the layout schemes.

[0095] The working surface distance of the working line that is not arranged using the working line arrangement scheme can be expressed by, but not limited to, formula (1):

[0096]

[0097] The working surface distance of the working line arranged using the working line arrangement scheme can be expressed by, but not limited to, formula (2):

[0098]

[0099] Step 203, obtaining the supporting force data of the inclined bottom plate and the end wall contained in the mine data, and determining the soil discharge plan based on the supporting force data.

[0100] In the disclosed embodiment, full use is made of the supporting force of the inclined bottom plate and the end sides, and soil is discharged obliquely with the two sides to form a stable triangular support structure. Combined with the grooves after blasting of the bottom plate, the obtained soil discharge scheme can effectively increase the stability of the soil discharge yard, thereby meeting the requirements of soil discharge in the yard and effectively solving the soil discharge problem in the anticline area.

[0101] Step 204, obtaining spoil dump data included in the mine data, and determining the spoil dump connection solution based on the spoil dump data.

[0102] In the disclosed embodiment, the soil discharge problem of each open-pit mine is comprehensively considered from the perspective of the open-pit mine group, and the soil discharge yards of each mine in the mine group are uniformly planned. When an open-pit mine in the mine group has insufficient discharge space due to objective factors such as special geological conditions, consideration is given to formulating a soil discharge yard sharing plan, that is, the soil discharge yard interconnection plan, to fully utilize the space resources within the mine group, use the internal soil discharge yards of adjacent mines for soil discharge, and use methods such as connecting the soil discharge yards and building intermediate bridges to shorten the transportation distance and reduce the overall soil discharge cost of the open-pit mine group.

[0103] In one implementable method of the embodiment of the present disclosure, it is necessary to study and analyze the annual mining and drainage volume and the mining and drainage space relationship during the diversion period of the open-pit mine based on the scale of raw coal production, combined with the mining status, topographic and geological data, etc., to determine the amount of drainage space shortage in the early stage of the diversion, so as to optimize the mining procedure and determine the boundary of the target open-pit mine. Therefore, in order to optimize the mining procedure, it can also be implemented by but not limited to the following methods: determine the parameter relationship of the target open-pit mine based on the length of the forced pushing working line, the mining and stripping volume and the drainage space; perform data analysis and processing on the parameter relationship to obtain the boundary of the open-pit mine.

[0104] In the disclosed embodiment, there is a close relationship between the length of the forced working line, the mining volume and the dumping space. They influence each other in mine design and jointly determine the production capacity and economic benefits of the mine. Therefore, after determining the parameter relationship of the target open-pit mine, the boundary of the open-pit mine can be directly obtained based on the parameter relationship.

[0105] Among them, the open-pit mine boundary refers to the boundary position of the ore body or ore layer during the mining process of the target open-pit mine, that is, the actual edge of the ore body or the limit of the mining range. The length of the forced push working line refers to the length of the working line for stripping ore or waste rock during the mining of the target open-pit mine. This working line usually refers to the front line along the mining front, that is, the area where stripping operations are being carried out at the edge of the mine pit. The stripping engineering volume refers to the total amount of soil and rock that needs to be stripped during the mining process of the target open-pit mine, including the waste rock covering the ore layer (cover layer) and the waste rock between the ore layers (interlayer). The soil discharge space refers to an area specially set up to store waste rock stripped from the mining process of the target open-pit mine.

[0106] In one implementable method of the embodiment of the present disclosure, it is necessary to study and optimize the layout of the stripping work line in the first mining area, and establish a mine working line calculation model to calculate the mine transportation distance, and obtain an optimized work line layout plan that saves transportation distance and transportation costs, thereby increasing economic benefits. Therefore, in order to increase economic benefits, it can also be implemented by but not limited to the following methods: data abstraction processing is performed on the working face transportation route data to obtain processed transportation route data, and model construction processing is performed based on the processed transportation route data and a preset construction algorithm to obtain a transportation distance model; the amount of flat plate stripping materials and the location of the waste dump contained in the mine data are obtained, and the working face transportation route data, the amount of flat plate stripping materials and the location of the waste dump are input into the transportation distance model for data processing to obtain the working line layout plan.

[0107] In the embodiment of the present disclosure, the preset construction algorithm is a custom-set algorithm, such as a supervised learning algorithm, an unsupervised learning algorithm, etc. Specifically, the embodiment of the present disclosure does not limit the preset construction algorithm.

[0108] Among them, according to the working line layout combined with the triangle characteristics, the working face transportation line is abstracted, and the transportation distance model of the working face moving pit line under different working line layouts is established, and the transportation distance calculation method of different working line layouts is provided, which simplifies the design process. According to the established working face moving pit line transportation distance calculation model, combined with the amount of material stripped from each flat plate, the location of the waste dump, and the transportation route, the comprehensive transportation distance of various layout schemes, the corresponding transportation cost, and the impact on the electric shovel layout are calculated, and the optimal layout scheme is finally determined as the working line layout scheme among all the layout schemes.

[0109] In one implementable method of the disclosed embodiment, in case that the bottom plate inclination of the coal seam in anticline structure in an open-pit mine increases sharply and the soil discharge space is limited, it is necessary to increase the soil discharge capacity through optimized design, that is, to solve the soil discharge problem in the anticline area by designing a new soil discharge plan. Therefore, in order to increase the soil discharge capacity to meet the soil field disposal, it can also be implemented by but not limited to the following methods: determine the soil discharge data of the two sides of the inclined tower based on the support force data; determine the soil discharge plan according to the soil discharge data of the two sides of the inclined tower and the bottom plate blasting position contained in the mine field data.

[0110] In the disclosed embodiment, full use is made of the supporting force of the inclined bottom plate and the end sides, and soil is discharged obliquely with the two sides to form a stable triangular support structure. Combined with the grooves after blasting of the bottom plate, the resulting soil discharge plan can effectively increase the stability of the soil discharge yard, thereby meeting the requirements of soil discharge in the yard and effectively solving the soil discharge problem in the anticline area.

[0111] In one implementable method of the embodiment of the present disclosure, the dumping problem of each open-pit mine is comprehensively considered from the perspective of an open-pit mine group, and the dumping yards of each mine in the mine group are uniformly planned. When an open-pit mine in the mine group has insufficient dumping space due to objective factors such as special geological conditions, consider formulating a dumping yard sharing plan, that is, a dumping yard interconnection plan. Regarding the determination of the dumping yard interconnection plan, it can also be implemented by but not limited to the following methods: determining the distance value between the target dumping yard and each of the other dumping yards based on the dumping yard data; determining the interconnection method between the target dumping yard and each of the other dumping yards through the dumping yard data and the distance value; and interconnecting the target dumping yard with each of the other dumping yards according to the interconnection method to obtain the dumping yard interconnection plan.

[0112] In summary, the embodiments of the present disclosure can achieve the following technical effects:

[0113] 1. The disclosed embodiments achieve the effects of ensuring the continuity of open-pit mine production, reducing the distance of waste transportation, and improving economic benefits by optimizing the mining procedure, adjusting the working line layout, dumping soil on the inclined base, and increasing the capacity of the waste dump.

[0114] 2. The disclosed embodiment adopts an advanced advancement scheme with the open-pit mine boundary as the boundary, so as to quickly advance in the north, locally and as a whole approach the boundary, thereby realizing internal discharge in the north, while the southern part, as a compensation for insufficient production in the north, advances slowly, and after the north is pushed to the boundary of the open-pit mine, it realizes the transition to horizontal mining, increases the effective internal discharge space in the north, and alleviates the tense situation of soil discharge space.

[0115] 3. The disclosed embodiment studies and optimizes the layout of the stripping work line in the southeastern part of the first mining area, and establishes a calculation model for the working line in the southeastern part of the mine to calculate the transportation distance of the mine, and obtains the transportation distance and transportation cost saved after optimization, thereby increasing economic benefits.

[0116] 4. The disclosed embodiment makes full use of the supporting force of the inclined bottom plate and the end sides, and forms a stable triangular supporting structure by diagonally stacking the soil on the two sides. Combined with the grooves after blasting on the bottom plate, the stability of the soil dump can be effectively increased, thereby meeting the requirements of soil dumping and effectively solving the soil dumping problem in the anticline area.

[0117] 5. The disclosed embodiment utilizes the north-south adjacent condition to study and implement the coordinated earth discharge of adjacent mining areas to solve the problem of tight earth discharge space.

[0118] Corresponding to the above-mentioned open-pit mine steering method, the present invention also provides an open-pit mine steering device. Since the device embodiment of the present invention corresponds to the above-mentioned method embodiment, details not disclosed in the device embodiment can be referred to the above-mentioned method embodiment, and will not be repeated in the present invention.

[0119] Figure 3 A schematic diagram of the structure of an open-pit mine steering device provided by an embodiment of the present disclosure, such as Figure 3 As shown, including:

[0120] An acquisition unit 31 is used to acquire mine data of a target open-pit mine;

[0121] A determination unit 32 is used to determine a diversion processing scheme of the target open-pit mine according to the mine data; wherein the diversion processing scheme at least includes an open-pit mine boundary, a working line layout scheme, a dumping scheme, and a dumping field connection scheme;

[0122] The arrangement unit 33 is used to arrange the oblique push working line at the first preset orientation of the target open-pit mine based on the working line arrangement plan to obtain the arranged target open-pit mine, and set the target dumping site of the arranged target open-pit mine based on the dumping plan;

[0123] A connecting unit 34 is used to connect the target dump with other dumps based on the dump connection scheme to obtain a processed target open-pit mine; wherein the other dumps are dumps of other open-pit mines except the target open-pit mine;

[0124] The mining unit 35 is used to advance the forced pushing working line from the second preset position of the processed target open-pit mine to the boundary of the open-pit mine, and to perform a turning and horizontal mining process at the boundary of the open-pit mine.

[0125] The device for turning an open-pit mine provided by the present disclosure obtains the mine data of a target open-pit mine, and determines a turning treatment plan for the target open-pit mine according to the mine data; wherein the turning treatment plan at least includes an open-pit mine boundary, a working line arrangement plan, a soil dumping plan and a soil dumping yard connection plan; based on the working line arrangement plan, an oblique push working line is arranged at a first preset position of the target open-pit mine to obtain the arranged target open-pit mine, and a target soil dumping yard of the arranged target open-pit mine is set based on the soil dumping plan; based on the soil dumping yard connection plan, the target soil dumping yard is connected with other soil dumping yards to obtain the treated target open-pit mine; wherein the other soil dumping yards are soil dumping yards of other open-pit mines except the target open-pit mine; the forced push working line is pushed from the second preset position of the treated target open-pit mine to the open-pit mine boundary, and a turning and horizontal mining treatment is performed at the open-pit mine boundary. Compared with the related technologies, the embodiments of the present disclosure achieve the effects of ensuring the continuity of open-pit mine production, reducing the distance of discharge and transportation, and improving economic benefits by optimizing the mining procedure, adjusting the working line layout, dumping soil on the inclined base, and increasing the capacity of the spoil field.

[0126] Furthermore, in a possible implementation of the embodiment of the present disclosure, as Figure 4 As shown, the determining unit 32 includes:

[0127] An acquisition module 321 is used to acquire the length of the forced pushing working line, the mining and stripping engineering volume, and the earth removal space contained in the mine data;

[0128] A determination module 322, for determining the open-pit mine boundary according to the length of the forced pushing working line, the mining and stripping engineering volume and the earth removal space;

[0129] The acquisition module 321 is also used to acquire the working face transportation route data contained in the mine data;

[0130] The determination module 322 is also used to determine the working line layout plan based on the working face transportation route data;

[0131] The acquisition module 321 is also used to acquire the supporting force data of the inclined bottom plate and the end wall contained in the mine data;

[0132] The determination module 322 is further used to determine the soil discharge plan based on the support force data;

[0133] The acquisition module 321 is also used to acquire the spoil dump data included in the mine data;

[0134] The determination module 322 is further used to determine the spoil dump connection solution based on the spoil dump data.

[0135] Furthermore, in a possible implementation of the embodiment of the present disclosure, the determining module 322 is further configured to:

[0136] Determining the parameter relationship of the target open-pit mine according to the length of the forced pushing working line, the mining and stripping engineering volume, and the dumping space;

[0137] The parameter relationship is subjected to data analysis and processing to obtain the open-pit mine boundary.

[0138] Furthermore, in a possible implementation of the embodiment of the present disclosure, the determining module 322 is further configured to:

[0139] Performing data abstraction processing on the working face transport route data to obtain processed transport route data, and performing model construction processing according to the processed transport route data and a preset construction algorithm to obtain a transport distance model;

[0140] The amount of flat plate stripping material and the location of the waste dump contained in the mine data are obtained, and the working face transportation route data, the amount of flat plate stripping material and the location of the waste dump are input into the transportation distance model for data processing to obtain the working line layout plan.

[0141] Furthermore, in a possible implementation of the embodiment of the present disclosure, the determining module 322 is further configured to:

[0142] Determine the earth discharge data of the two inclined towers based on the supporting force data;

[0143] The soil discharge plan is determined according to the soil discharge data of the two inclined towers and the bottom plate blasting position included in the mine data.

[0144] Furthermore, in a possible implementation of the embodiment of the present disclosure, the determining module 322 is further configured to:

[0145] Determine the distance value between the target dump site and each of the other dump sites according to the dump site data;

[0146] Determine the connection mode between the target dump site and each of the other dump sites through the dump site data and the distance value;

[0147] The target spoil dump is connected to each of the other spoil dumps according to the connection method to obtain the spoil dump connection plan.

[0148] It should be noted that the above explanation of the method embodiment is also applicable to the device of the embodiment of the present disclosure, and the principle is the same, which is no longer limited in the embodiment of the present disclosure.

[0149] According to an embodiment of the present disclosure, the present disclosure also provides an electronic device, a readable storage medium and a computer program product.

[0150] Figure 5 A schematic block diagram of an example electronic device 500 that can be used to implement an embodiment of the present disclosure is shown. The electronic device is intended to represent various forms of digital computers, such as laptop computers, desktop computers, workstations, personal digital assistants, servers, blade servers, mainframe computers, and other suitable computers. The electronic device can also represent various forms of mobile devices, such as personal digital processing, cellular phones, smart phones, wearable devices, and other similar computing devices. The components shown herein, their connections and relationships, and their functions are merely examples and are not intended to limit the implementation of the present disclosure described and / or required herein.

[0151] like Figure 5 As shown, the device 500 includes a computing unit 501, which can perform various appropriate actions and processes according to a computer program stored in a ROM (Read-Only Memory) 502 or a computer program loaded from a storage unit 508 to a RAM (Random Access Memory) 503. In the RAM 503, various programs and data required for the operation of the device 500 can also be stored. The computing unit 501, the ROM 502, and the RAM 503 are connected to each other via a bus 504. An I / O (Input / Output) interface 505 is also connected to the bus 504.

[0152] A number of components in the device 500 are connected to the I / O interface 505, including: an input unit 506, such as a keyboard, a mouse, etc.; an output unit 507, such as various types of displays, speakers, etc.; a storage unit 508, such as a disk, an optical disk, etc.; and a communication unit 509, such as a network card, a modem, a wireless communication transceiver, etc. The communication unit 509 allows the device 500 to exchange information / data with other devices through a computer network such as the Internet and / or various telecommunication networks.

[0153] The computing unit 501 may be a variety of general and / or special processing components with processing and computing capabilities. Some examples of the computing unit 501 include, but are not limited to, a CPU (Central Processing Unit), a GPU (Graphic Processing Units), various dedicated AI (Artificial Intelligence) computing chips, various computing units running machine learning model algorithms, a DSP (Digital Signal Processor), and any appropriate processor, controller, microcontroller, etc. The computing unit 501 performs the various methods and processes described above, such as the method of turning an open pit mine. For example, in some embodiments, the method of turning an open pit mine may be implemented as a computer software program, which is tangibly contained in a machine-readable medium, such as a storage unit 508. In some embodiments, part or all of the computer program may be loaded and / or installed on the device 500 via the ROM 502 and / or the communication unit 509. When the computer program is loaded into the RAM 503 and executed by the computing unit 501, one or more steps of the method described above may be performed. Alternatively, in other embodiments, the computing unit 501 may be configured to execute the aforementioned open-pit mine steering method in any other appropriate manner (for example, by means of firmware).

[0154] Various embodiments of the systems and techniques described above herein may be implemented in digital electronic circuit systems, integrated circuit systems, FPGAs (Field Programmable Gate Arrays), ASICs (Application-Specific Integrated Circuits), ASSPs (Application Specific Standard Products), SOCs (System On Chips), CPLDs (Complex Programmable Logic Devices), computer hardware, firmware, software, and / or combinations thereof. These various embodiments may include: being implemented in one or more computer programs that may be executed and / or interpreted on a programmable system including at least one programmable processor that may be a special purpose or general purpose programmable processor that may receive data and instructions from a storage system, at least one input device, and at least one output device, and transmit data and instructions to the storage system, the at least one input device, and the at least one output device.

[0155] The program code for implementing the method of the present disclosure may be written in any combination of one or more programming languages. These program codes may be provided to a processor or controller of a general-purpose computer, a special-purpose computer, or other programmable data processing device, so that the program code, when executed by the processor or controller, enables the functions / operations specified in the flow chart and / or block diagram to be implemented. The program code may be executed entirely on the machine, partially on the machine, partially on the machine and partially on a remote machine as a stand-alone software package, or entirely on a remote machine or server.

[0156] In the context of the present disclosure, a machine-readable medium may be a tangible medium that may contain or store a program for use by or in conjunction with an instruction execution system, device, or equipment. A machine-readable medium may be a machine-readable signal medium or a machine-readable storage medium. A machine-readable medium may include, but is not limited to, an electronic, magnetic, optical, electromagnetic, infrared, or semiconductor system, device, or device, or any suitable combination of the foregoing. More specific examples of machine-readable storage media may include an electrical connection based on one or more lines, a portable computer disk, a hard disk, a RAM, a ROM, an EPROM (Electrically Programmable Read-Only-Memory) or a flash memory, an optical fiber, a CD-ROM (Compact Dis sc Read-Only Memory), an optical storage device, a magnetic storage device, or any suitable combination of the foregoing.

[0157] To provide interaction with a user, the systems and techniques described herein can be implemented on a computer having: a display device (e.g., a CRT (Cathode-Ray Tube) or LCD (Liquid Crystal Display) monitor) for displaying information to the user; and a keyboard and a pointing device (e.g., a mouse or a trackball), through which the user can provide input to the computer. Other types of devices can also be used to provide interaction with the user; for example, the feedback provided to the user can be any form of sensory feedback (e.g., visual feedback, auditory feedback, or tactile feedback); and input from the user can be received in any form (including acoustic input, voice input, or tactile input).

[0158] The systems and techniques described herein may be implemented in a computing system that includes backend components (e.g., as a data server), or a computing system that includes middleware components (e.g., an application server), or a computing system that includes frontend components (e.g., a user computer with a graphical user interface or a web browser through which a user can interact with implementations of the systems and techniques described herein), or a computing system that includes any combination of such backend components, middleware components, or frontend components. The components of the system may be interconnected by any form or medium of digital data communication (e.g., a communication network). Examples of communication networks include: LAN (Local Area Network), WAN (Wide Area Network), the Internet, and blockchain networks.

[0159] A computer system may include a client and a server. The client and the server are generally remote from each other and usually interact through a communication network. The relationship between the client and the server is generated by computer programs running on the corresponding computers and having a client-server relationship with each other. The server may be a cloud server, also known as a cloud computing server or cloud host, which is a host product in the cloud computing service system to solve the defects of difficult management and weak business scalability in traditional physical hosts and VPS services ("Virtual Private Server", or "VPS" for short). The server may also be a server of a distributed system, or a server combined with a blockchain.

[0160] It should be noted that artificial intelligence is a discipline that studies how computers can simulate certain human thought processes and intelligent behaviors (such as learning, reasoning, thinking, planning, etc.), and includes both hardware-level and software-level technologies. Artificial intelligence hardware technologies generally include technologies such as sensors, dedicated artificial intelligence chips, cloud computing, distributed storage, and big data processing; artificial intelligence software technologies mainly include computer vision technology, speech recognition technology, natural language processing technology, as well as machine learning / deep learning, big data processing technology, knowledge graph technology, and other major directions.

[0161] It should be understood that the various forms of processes shown above can be used to reorder, add or delete steps. For example, the steps recorded in this disclosure can be executed in parallel, sequentially or in different orders, as long as the desired results of the technical solutions disclosed in this disclosure can be achieved, and this document does not limit this.

[0162] The above specific implementations do not constitute a limitation on the protection scope of the present disclosure. It should be understood by those skilled in the art that various modifications, combinations, sub-combinations and substitutions can be made according to design requirements and other factors. Any modification, equivalent substitution and improvement made within the spirit and principle of the present disclosure shall be included in the protection scope of the present disclosure.

Claims

1. A method for turning an open pit mine, characterized in that: include: Acquire the mine data of the target open-pit mine, and determine the diversion processing scheme of the target open-pit mine according to the mine data; wherein the diversion processing scheme at least includes the open-pit mine boundary, the working line layout scheme, the dumping scheme and the dumping field connection scheme; Based on the working line arrangement plan, an oblique push working line is arranged at a first preset orientation of the target open-pit mine to obtain the arranged target open-pit mine, and based on the dumping plan, a target dumping yard of the arranged target open-pit mine is set; Based on the dump interconnection scheme, the target dump is interconnected with other dumps to obtain a processed target open-pit mine; wherein the other dumps are dumps of other open-pit mines except the target open-pit mine; The forced pushing working line is advanced from the second preset position of the processed target open-pit mine to the boundary of the open-pit mine, and the turning and horizontal mining processing is carried out at the boundary of the open-pit mine.

2. The method according to claim 1, characterized in that The step of determining the steering treatment scheme of the target open-pit mine according to the mine data comprises: Acquire the length of the forced-pushing working line, the mining and stripping engineering volume, and the earth-draining space contained in the mine data, and determine the boundary of the open-pit mine according to the length of the forced-pushing working line, the mining and stripping engineering volume, and the earth-draining space; Acquire the working face transportation route data contained in the mine data, and determine the working line layout plan based on the working face transportation route data; Acquire the supporting force data of the inclined bottom plate and the end wall contained in the mine data, and determine the soil discharge plan based on the supporting force data; The spoil dump data included in the mine data is obtained, and a spoil dump connection solution is determined based on the spoil dump data.

3. The method according to claim 2, characterized in that Determining the open-pit mine boundary according to the length of the forced pushing work line, the mining and stripping engineering volume, and the earth removal space includes: Determining the parameter relationship of the target open-pit mine according to the length of the forced pushing working line, the mining and stripping engineering volume, and the dumping space; The parameter relationship is subjected to data analysis and processing to obtain the open-pit mine boundary.

4. The method according to claim 2, characterized in that: Determining the working line layout scheme based on the working face transportation route data includes: Performing data abstraction processing on the working face transport route data to obtain processed transport route data, and performing model construction processing according to the processed transport route data and a preset construction algorithm to obtain a transport distance model; The amount of flat plate stripping material and the location of the waste dump contained in the mine data are obtained, and the working face transportation route data, the amount of flat plate stripping material and the location of the waste dump are input into the transportation distance model for data processing to obtain the working line layout plan.

5. The method according to claim 2, characterized in that: Determining the soil discharge scheme based on the support force data includes: Determine the earth discharge data of the two inclined towers based on the supporting force data; The soil discharge plan is determined according to the soil discharge data of the two inclined towers and the bottom plate blasting position included in the mine data.

6. The method according to claim 2, characterized in that Determining the spoil dump connection solution based on the spoil dump data includes: Determine the distance value between the target dump site and each of the other dump sites according to the dump site data; Determine the connection mode between the target dump site and each of the other dump sites through the dump site data and the distance value; The target spoil dump is connected to each of the other spoil dumps according to the connection method to obtain the spoil dump connection plan.

7. A device for turning open-pit mines, characterized in that: include: An acquisition unit, used for acquiring mine data of a target open-pit mine; A determination unit, configured to determine a diversion processing scheme of the target open-pit mine according to the mine data; wherein the diversion processing scheme at least includes an open-pit mine boundary, a working line layout scheme, a dumping scheme, and a dumping field connection scheme; a layout unit, configured to arrange an oblique push working line at a first preset orientation of the target open-pit mine based on the working line layout plan, obtain the arranged target open-pit mine, and set a target dumping site of the arranged target open-pit mine based on the dumping plan; A connecting unit, used for connecting the target dump with other dumps based on the dump connection scheme to obtain a processed target open-pit mine; wherein the other dumps are dumps of other open-pit mines except the target open-pit mine; The mining unit is used to advance the forced pushing working line from the second preset position of the processed target open-pit mine to the boundary of the open-pit mine, and to perform a turning horizontal mining process at the boundary of the open-pit mine.

8. An electronic device, characterized in that: include: at least one processor; as well as a memory communicatively connected to the at least one processor; wherein, The memory stores instructions that can be executed by the at least one processor, and the instructions are executed by the at least one processor to enable the at least one processor to perform the method according to any one of claims 1 to 6.

9. A non-transitory computer-readable storage medium storing computer instructions, characterized in that: The computer instructions are used to cause the computer to execute the method according to any one of claims 1-6.

10. A computer program product, characterized in that The invention comprises a computer program which, when executed by a processor, implements the method according to any one of claims 1 to 6.