Method for detecting anti-sliding stability failure risk rate of tunnel plug in main flood season of ultra-high dam construction

By establishing a risk model and random simulation method for tunnel plugs during the main flood season of ultra-high dam construction, the problem of inaccurate and incomplete analysis of anti-slip stability of plug structures in the existing technology is solved, and more accurate and comprehensive Risk assessment, optimize design and reduce engineering costs.

CN119416528AActive Publication Date: 2025-02-11CHINA HYDROELECTRIC ENGINEERING CONSULTING GROUP CHENGDU RESEARCH HYDROELECTRIC INVESTIGATION DESIGN AND INSTITUTE
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411574352.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-06
Publication Date
2025-02-11
Estimated Expiration
2044-11-06

AI Technical Summary

Technical Problem

The existing technology cannot accurately and comprehensively analyze the anti-slip stability of the tunnel plug structure during the main flood season of ultra-high dam construction, especially under the influence of random factors such as rock mechanical parameters, concrete parameters and contact coefficients between sliding surface materials.

Method used

A method for detecting the anti-slip and stable failure risk rate of tunnel plugs during the main flood season of ultra-high dam construction is proposed. By establishing a risk model, the distribution parameters of the main random factors affecting water load and anti-slip force are determined, and random simulation is carried out to estimate the plugs. Anti-slip stable failure risk rate.

Benefits of technology

This method can more scientifically and reasonably estimate the risk rate of anti-slip stability of tunnel plug plugs, improve the accuracy and comprehensiveness of anti-slip stability evaluation of plug plug structures, help optimize design, reduce project investment and shorten construction period.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119416528A_ABST
    Figure CN119416528A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of water conservancy and hydropower engineering construction, provides a method for detecting the anti-sliding stability failure risk rate of a tunnel plug in the main flood season of ultra-high dam construction, and solves the problem that an analysis result of an analysis scheme for the stability of a plug structure in the prior art is inaccurate and incomplete. The method comprises the following steps: firstly, establishing an anti-sliding stable failure risk model of the tunnel plug in the main flood season of the ultra-high dam construction; then determining distribution parameters of main random factors influencing the water load and the anti-sliding force; then, based on the designed length of the tunnel plug, in combination with distribution parameters of main random factors influencing the water load and the anti-sliding force, random simulation of the water load generated by the maximum flood level of dam flood control in the main flood season and the total anti-sliding force generated by the tunnel plug is carried out; and finally, according to a stochastic simulation result, estimating the anti-sliding stability failure risk rate of the plug.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of water conservancy and hydropower engineering construction, and in particular to a method for detecting the risk rate of anti-sliding stability failure of a tunnel plug during the main flood season of ultra-high dam construction. Background Art

[0002] A number of super-high dams above 200m in Southwest China, such as Shuangjiangkou, Yagen Second Grade, Mengdigou, Yebatan, Gangtuo, and Rumei, are under construction and planning. Most of these super-high dams are built in the high mountain canyon areas of Southwest China. Their construction diversion generally adopts a tunnel diversion method with cofferdams breaking the flow once and foundation pits constructed throughout the year. The construction of super-high dam hydropower projects is difficult and has a long construction period. The construction process is affected by many uncertain factors. The calculation and analysis of the plugging stability of tunnels such as hydraulics, transportation, construction branch tunnels, and temporary construction passages has always been a key technical issue in the design and research of underground engineering for large hydropower stations. With the continuous advancement of the construction of super-high dam hydropower projects in Southwest China, more and more super-high dams are facing the safety and stability of plugging structures such as construction tunnels and hydraulic tunnels under the conditions of flood season. For example, the lining of the ecological water supply tunnel of a 300m super-high core wall rockfill dam was not completed before the flood season, and it was necessary to arrange plugging of the construction branch tunnel to ensure that there was no water in the water supply tunnel during the main flood season of that year and the construction was safe.

[0003] At present, the conventional method for engineering and technical personnel to conduct stability analysis of hydraulic tunnel plugging structures is mainly to use the overall anti-sliding stability method, anti-shear calculation method, etc. to conduct stability review on the designed tunnel plugging structure. These methods are simple in principle and easily accepted by engineering designers.

[0004] However, the above-mentioned plug structure stability analysis method cannot reflect the influence of major random factors such as rock mechanical parameters, concrete parameters and contact coefficient between sliding surface materials on the structural stability, and the analysis results are inaccurate.

[0005] In recent years, with the development of hydraulic reliability theory, the application of limit state design method based on probability theory in engineering design has been continuously deepened. Wang Kui et al. considered the influence of geotechnical engineering uncertainty factors and introduced reliability theory to calculate and analyze the stability of the designed hydraulic tunnel plug. However, for the tunnel plug structure used for flood protection during the main flood season, the model is mainly for circular hydraulic tunnels, and is difficult to apply to the gate tunnel type tunnels that are widely used; on the other hand, the model ignores the influence of the randomness of the upstream water pressure load during the flood season, making the reliability analysis of the tunnel plug not comprehensive enough. Summary of the invention

[0006] The technical problem to be solved by the present invention is to propose a method for detecting the risk rate of anti-sliding stability failure of tunnel plugs during the main flood season of ultra-high dam construction, so as to solve the problem of inaccurate and incomplete analysis results of the analysis scheme of plug structure stability in traditional technology.

[0007] The technical solution adopted by the present invention to solve the above technical problems is:

[0008] The method for detecting the risk rate of failure of anti-sliding stability of tunnel plugging during the main flood season of ultra-high dam construction includes the following steps:

[0009] S1. Establish a risk model for the failure of tunnel plugging resistance during the main flood season of ultra-high dam construction;

[0010] S2. Determine the distribution parameters of the main random factors affecting water load;

[0011] S3. Determine the distribution parameters of the main random factors affecting the anti-slip force;

[0012] S4. Based on the designed tunnel plug length and the distribution parameters of the main random factors affecting water load and anti-sliding force, a random simulation of the water load generated by the highest flood level of the dam during the main flood season and the total anti-sliding force that the tunnel plug can generate is conducted;

[0013] S5. Based on the random simulation results, estimate the risk rate of anti-sliding stability failure of tunnel plugs during the main flood season of ultra-high dam construction.

[0014] Furthermore, in step S1, the established risk model for the anti-sliding stability failure of the tunnel plug during the main flood season of the ultra-high dam construction is:

[0015] R=P(P H (max(Z m (t)))>f'∑W+C'(λA1+A2))

[0016] Among them, R represents the risk of failure of anti-sliding stability of tunnel plugging during the main flood season of ultra-high dam construction; Z m (t) represents the dynamic change process of the water level of the reservoir in front of the dam during the main flood season; P H (max(Z m (t))) is the thrust of the water load generated by the highest flood level on the upstream face of the plug; f' is the shear friction coefficient between the plug and the surrounding rock; ∑W is the sum of all normal forces on the control sliding surface; C' is the cohesion between the plug and concrete or between concrete and surrounding rock; λ is the effective bonding area coefficient of the side wall; A1 is the effective shear surface contact area of ​​the side wall; A2 is the effective shear surface contact area of ​​the bottom surface; P(·) represents the probability that the (·) condition is met.

[0017] Furthermore, in step S2, the distribution parameters of the main random factors affecting the water load are determined to include:

[0018] The construction flood peak is assumed to follow the P-III type distribution;

[0019] The discharge capacity coefficient of the diversion tunnel is assumed to follow a triangular distribution;

[0020] The water level-reservoir capacity relationship coefficient is assumed to obey a triangular distribution.

[0021] Furthermore, in step S3, the distribution parameters of the main random factors affecting the anti-slip force are determined, including:

[0022] The effective bonding area coefficient of the side wall is assumed to obey a triangular distribution, and its probability density function is:

[0023]

[0024] Among them, k d is the lower limit, i.e. the minimum effective bonding area coefficient of the side wall; k m is the median value, estimated based on the technical level of the construction unit and on-site management; k u is the upper limit value, i.e. the maximum bonding effective area coefficient of the side wall;

[0025] The shear friction coefficient and cohesion of the plug material are assumed to obey the normal distribution, and their probability density functions are:

[0026]

[0027] Wherein, μ is the mean of the random variable parameter of the shear friction coefficient f' or the cohesion C'; σ is the standard deviation of the random variable parameter of the shear friction coefficient f' or the cohesion C'.

[0028] Furthermore, in step S4, based on the designed tunnel plug length and in combination with the distribution parameters of the main random factors affecting the water load and the anti-sliding force, a random simulation of the water load generated by the highest flood level of the dam during the main flood season and the total anti-sliding force that can be generated by the tunnel plug is performed, including:

[0029] First, the total number of model simulation calculations N that meets the calculation accuracy requirements is determined based on the Monte Carlo method. C ;

[0030] Then, combining the distribution parameters of the main random factors affecting water load and anti-sliding force, N C Random simulation of the water load generated by the highest flood level of the dam during the secondary flood season and the total anti-sliding force generated by the tunnel plug.

[0031] Furthermore, the random simulation process of the water load generated by the highest flood level of the dam during the main flood season includes:

[0032] ① Generate random numbers of construction flood peaks to simulate the construction flood process;

[0033] ② Generate random numbers of reservoir capacity relationship coefficients and simulate and fit the water level capacity relationship curve;

[0034] ③ Generate random numbers of discharge capacity coefficients and simulate and fit the diversion and discharge capacity curve;

[0035] ④ The maximum flood level in front of the dam during the main flood season is obtained by simulating flood control calculations. m (t));

[0036] ⑤ Calculate the water load P by simulating the highest flood level in front of the dam during the main flood season H (max(Z m (t))).

[0037] Furthermore, the random simulation process of the total anti-sliding force that can be generated by the tunnel plug includes:

[0038] ① Generate a random number for the bonding effective area coefficient λ of the side wall;

[0039] ② Generate random numbers of shear friction coefficient f' and cohesion C';

[0040] ③ Calculate the total anti-sliding force f'∑W+C'(λA1+A2)) that the tunnel plug can generate.

[0041] Furthermore, in step S5, based on the random simulation results, the risk rate of failure of the anti-sliding stability of the tunnel plug during the main flood season of the ultra-high dam construction is estimated, including:

[0042] According to N C The simulation results of random simulation of the water load generated by the highest flood level of the dam during the secondary flood season and the total anti-sliding force generated by the tunnel plugging are analyzed statistically. The water load P of the highest flood level in front of the dam is H (max(Z m The number of times (t))) exceeds the total anti-sliding force f'∑W+C'(λA1+A2)) that the tunnel plug can generate is recorded as N T ;

[0043] According to Estimate the risk rate R of anti-sliding stability failure of tunnel plugs during the main flood season of ultra-high dam construction.

[0044] The beneficial effects of the present invention are:

[0045] (1) The present invention introduces risk analysis theory and methods to construct a mathematical model for the risk of anti-sliding stability failure of ultra-high dam tunnel plugs before flood season, taking into account the randomness of the main factors affecting water load and the randomness of the main factors affecting anti-sliding force, and more scientifically and reasonably estimating the risk rate of anti-sliding stability failure of tunnel plugs, thereby improving the accuracy and comprehensiveness of the anti-sliding stability evaluation of the designed plug structure.

[0046] (2) The anti-slip stability failure risk rate detection scheme of the plug based on the present invention can facilitate the subsequent optimization design of the designed plug structure, thereby reducing the scale of the tunnel plug project while ensuring compliance with the design requirements, thereby reducing the investment in the plug project and shortening the construction period, which has good social, economic and safety benefits. BRIEF DESCRIPTION OF THE DRAWINGS

[0047] Figure 1 This is a flow chart of the method for detecting the risk rate of anti-sliding stability failure of tunnel plugging during the main flood season of ultra-high dam construction in the present invention. DETAILED DESCRIPTION

[0048] The present invention aims to provide a method for detecting the risk rate of anti-sliding stability failure of tunnel plugs during the main flood season of ultra-high dam construction, so as to solve the problem of inaccurate and incomplete analysis results of the analysis scheme of plug structure stability in traditional technology. The present invention first establishes a risk model of anti-sliding stability failure of tunnel plugs during the main flood season of ultra-high dam construction; then, by systematically analyzing the randomness of the main factors affecting water load and anti-sliding force, the distribution parameters of the main random factors are determined; then, based on the designed tunnel plug length, combined with the distribution parameters of the main random factors affecting water load and anti-sliding force, a random simulation of the water load generated by the highest flood level of the dam flood control during the main flood season and the total anti-sliding force that can be generated by the tunnel plug is performed; finally, according to the random simulation results, the risk rate of anti-sliding stability failure of tunnel plugs during the main flood season of ultra-high dam construction is estimated. This scheme can estimate the risk rate of anti-sliding stability failure of tunnel plugs more scientifically and reasonably, and provide a scientific theoretical basis and technical support for the subsequent determination of the appropriate scale of tunnel plug projects, thereby reducing project investment, ensuring construction safety during the flood season, and accelerating project progress.

[0049] For specific implementation, see Figure 1 The method for detecting the risk rate of anti-sliding stability failure of tunnel plugs during the main flood season of ultra-high dam construction provided by the present invention comprises the following implementation steps:

[0050] S1. Establish a risk model for the failure of tunnel plugging resistance during the main flood season of ultra-high dam construction;

[0051] In this step, according to the hydraulic structure theory and in combination with relevant regulations and specifications, taking the gate-type tunnel plug, which is the most widely used in hydropower projects, as an example, the sliding of the tunnel plug along the interface is the main structural failure mode of the tunnel plug. The load effect of the tunnel plug is mainly the thrust of the water load generated by the highest construction flood level on the upstream face of the plug, and the structural resistance is the friction between the plug and the concrete or between the concrete and the surrounding rock and the cohesion of the material. Based on this, the anti-sliding stability limit state equation of the tunnel plug during the main flood season of the super-high dam construction can be described as:

[0052] Z=P H (max(Z m(t)))-(f'∑W+C'(λA1+A2))=0

[0053] Among them, Z m (t) is the dynamic change process of the water level of the reservoir in front of the dam during the main flood season; P H (max(Z m (t))) is the thrust of the water load generated by the highest flood level on the upstream side of the plug; f' is the shear friction coefficient between the plug and concrete or between concrete and surrounding rock; ∑W is the sum of all normal forces on the sliding surface, unit MN; C' is the cohesion between the plug and concrete or between concrete and surrounding rock, unit MPa; λ is the effective bonding area coefficient of the side wall; A1 is the effective shear surface contact area of ​​the side wall, unit m 2 ; A2 is the effective shear contact area of ​​the bottom surface, unit: m 2 .

[0054] After research, it was found that the risk of structural sliding failure of tunnel plugs during the construction flood season is mainly affected by the combined influence of random factors such as hydrology, hydraulics, and material mechanics parameters. Among them, the water load generated by the highest water level in the upstream reservoir is affected by random factors such as hydrology, hydraulics, and the relationship between water level and storage capacity, and has a certain randomness; the randomness of material mechanics parameters makes the total anti-sliding force of the plug have a certain randomness. The present invention defines the risk of anti-sliding stability failure of the plug during the main flood season of ultra-high dam construction as the probability of the tunnel plug suffering from anti-sliding stability failure due to the water load generated by the highest upstream flood level during the main flood season. Therefore, taking into account the randomness of the main influencing factors, the mathematical model of the anti-sliding stability failure risk R of the ultra-high dam tunnel plug before the flood season is established:

[0055] R=P(P H (max(Z m (t)))>f'∑W+C'(λA1+A2))

[0056] Among them, R represents the risk of failure of anti-sliding stability of tunnel plugging during the main flood season of ultra-high dam construction; Z m (t) represents the dynamic change process of the water level of the reservoir in front of the dam during the main flood season; P H (max(Z m (t))) is the thrust of the water load generated by the highest flood level on the upstream face of the plug; f' is the shear friction coefficient between the plug and the surrounding rock; ∑W is the sum of all normal forces on the control sliding surface; C' is the cohesion between the plug and concrete or between concrete and surrounding rock; λ is the effective bonding area coefficient of the side wall; A1 is the effective shear surface contact area of ​​the side wall; A2 is the effective shear surface contact area of ​​the bottom surface; P(·) represents the probability that the (·) condition is met.

[0057] S2. Determine the distribution parameters of the main random factors affecting water load;

[0058] In this step, the distribution parameters of the main random factors affecting the water load are determined by systematically analyzing the randomness of the main factors affecting the water load. The water load generated by the highest flood level is the only load on the plug structure. The cofferdam storage capacity of the super-high dam hydropower project is generally large, and the regulation and storage effect is more obvious. The highest flood level in front of the dam during the main flood season is affected by the hydrological and hydraulic randomness and has a large randomness, specifically:

[0059] (1) Randomness of construction flood process:

[0060] The construction flood process is random due to the randomness of precipitation in the catchment area upstream of the dam and the randomness of the catchment time. At present, the simulation of the construction flood process is basically based on the simulation of the flood peak, that is, the randomness of the construction flood peak is the basis for the simulation of the construction flood process. Therefore, in order to facilitate calculation and analysis, the hydrological random factors mainly consider the randomness of the peak, assuming its P-Ⅲ type distribution. On the basis of determining the probability distribution model of the construction flood peak, the construction flood process is determined by the method of amplifying the typical flood process according to the peak flow value.

[0061] (2) Randomness of diversion tunnel discharge capacity:

[0062] The flood discharge capacity of the construction diversion tunnel is affected by many random factors such as the tunnel water cross-sectional area, wetted perimeter and bottom slope. The discharge capacity density function curve is obtained through random simulation, and then the goodness of fit between the normal distribution and the triangular distribution is compared. It is believed that the discharge capacity of the diversion tunnel is closer to the triangular distribution.

[0063] (3) Randomness of water level and storage capacity relationship:

[0064] Considering the influence of factors such as slope collapse and construction slag in the reservoir area, the actual water level and storage capacity relationship is also random, and the reservoir storage capacity relationship coefficient is also assumed to obey the triangular distribution.

[0065] S3. Determine the distribution parameters of the main random factors affecting the anti-slip force;

[0066] In this step, the distribution parameters of the main random factors affecting the anti-slip force are determined by systematically analyzing the randomness of the main factors affecting the anti-slip force, specifically:

[0067] (1) Randomness of side wall contact coefficient:

[0068] The effective bonding area coefficient of the side wall of the city gate tunnel plug affects the anti-slip force provided by the side wall of the plug, and then affects the total anti-slip force of the plug. However, affected by many uncertain factors such as concrete shrinkage, concrete pouring quality, grouting technology level, on-site construction management, and construction equipment, the effective bonding area coefficient of the side wall has a certain randomness. According to the specific conditions of the project, 0.3 to 0.8 is generally used. Since the value is within a certain range, and in actual projects, the technical strength of the construction unit and the on-site management situation can be combined to give a preference for good or bad structural construction quality, the coefficient for good construction quality is large, and the contact coefficient for poor construction quality is small. Therefore, it is assumed that the effective bonding area coefficient λ of the side wall follows a triangular distribution, and its probability density function is:

[0069]

[0070] Among them, k d is the lower limit, i.e. the minimum effective bonding area coefficient of the side wall; k m is the median value. The design is estimated based on the technical level of the construction unit and the on-site management. A larger value can be taken for good construction quality and a smaller value can be taken for poor construction quality. u It is the upper limit value, that is, the maximum bonding effective area coefficient of the side wall.

[0071] (2) Randomness of material parameters:

[0072] According to the anti-sliding stability limit equation, the main material parameters affecting the total resistance are the random variable parameters of the shear friction coefficient f' and the cohesion C'. Their distributions are assumed to obey the normal distribution, and their probability density functions are:

[0073]

[0074] Wherein, μ is the mean of the random variable parameter of the shear friction coefficient f' or the cohesion C'; σ is the standard deviation of the random variable parameter of the shear friction coefficient f' or the cohesion C'.

[0075] S4. Based on the designed tunnel plug length and the distribution parameters of the main random factors affecting water load and anti-sliding force, a random simulation of the water load generated by the highest flood level of the dam during the main flood season and the total anti-sliding force that the tunnel plug can generate is conducted;

[0076] In this step, the total number of model simulation calculations N that meets the calculation accuracy requirements is first determined based on the Monte Carlo method. C ; Then, combined with the distribution parameters of the main random factors affecting water load and anti-sliding force, N C Random simulation of the water load generated by the highest flood level of the dam during the secondary flood season and the total anti-sliding force generated by the tunnel plug.

[0077] The random simulation process of the water load generated by the highest flood level of the dam during the main flood season includes:

[0078] ① Generate random numbers of construction flood peaks to simulate the construction flood process;

[0079] ② Generate random numbers of reservoir capacity relationship coefficients and simulate and fit the water level capacity relationship curve;

[0080] ③ Generate random numbers of discharge capacity coefficients and simulate and fit the diversion and discharge capacity curve;

[0081] ④ The maximum flood level in front of the dam during the main flood season is obtained by simulating flood control calculations. m (t));

[0082] ⑤ Calculate the water load P by simulating the highest flood level in front of the dam during the main flood season H (max(Z m (t))).

[0083] The random simulation process of the total anti-sliding force that the tunnel plug can generate includes:

[0084] ① Generate a random number for the bonding effective area coefficient λ of the side wall;

[0085] ② Generate random numbers of shear friction coefficient f' and cohesion C';

[0086] ③ Calculate the total anti-sliding force f'∑W+C'(λA1+A2)) that the tunnel plug can generate.

[0087] Based on the above simulation process, we can get N C The random simulation results of the water load generated by the highest flood level of the dam during the main flood season and N C Simulation results of the total anti-sliding force that a tunnel plug can generate.

[0088] S5. Estimate the risk rate of failure of anti-sliding stability of tunnel plugs during the main flood season of ultra-high dam construction based on random simulation results;

[0089] In this step, according to N C The simulation results of random simulation of the water load generated by the highest flood level of the dam during the secondary flood season and the total anti-sliding force generated by the tunnel plugging are analyzed statistically. The water load P of the highest flood level in front of the dam is H (max(Z m The number of times (t))) exceeds the total anti-sliding force f'∑W+C'(λA1+A2)) that the tunnel plug can generate is recorded as N T ;

[0090] According to Estimate the risk rate R of anti-sliding stability failure of tunnel plugs during the main flood season of ultra-high dam construction.

[0091] Example

[0092] Taking the application of the solution of the present invention to the SJK Hydropower Station, a super-high core rockfill dam in the upper reaches of the Dadu River Basin in China, as an example, the detection method for the anti-sliding stability failure risk rate of tunnel plugs during the main flood season is exemplarily described.

[0093] The SJK Hydropower Station is a control reservoir in the upper reaches of the Dadu River Basin in China. The dam is a super-high core rockfill dam with a height of 315.00m, which is currently the highest dam in the world. The project is a first-class large (1) type project. The hub project consists of a dam, flood discharge structures, and a water diversion and power generation system. The valley slope of the project is steep and the bedrock is exposed. The project adopts a tunnel diversion method with a cofferdam to cut off the flow once and the foundation pit to be constructed throughout the year.

[0094] The project takes into account ecological water supply, maintenance, emergency, etc., and specially designs an ecological water supply tunnel during the construction period. The project level is 3. Affected by various complex factors such as on-site management and emergencies, the progress of the project construction has been seriously delayed. According to the actual progress of the project, the filling elevation of the dam before the flood season in a certain year reached 2316.00m, exceeding the upstream cofferdam by 2308.00m, and the flood standard of the dam is once in 100 years. However, the ecological water supply tunnel is still in the stage of concrete lining in the tunnel. The project needs to rush to carry out concrete construction lining during the flood season. In order to ensure that after the water level rises during the main flood season, floods will not enter the ecological water supply tunnel to cause structural damage and damage, and to ensure the safety of construction personnel and equipment in the tunnel, it is necessary to set up a tunnel water retaining plug upstream.

[0095] When preliminarily designing the plug length, according to the relevant regulations and specifications "Specifications for the Design of Hydraulic Tunnels" (NB / T 10391-2020), the plugging body of the tunnel construction branch tunnel should be consistent with the level of the tunnel building. Therefore, the plug level of this tunnel is level 3, the flood standard for water retention is once in 20 years, and the design flood level is 2294.50m. The cross-section of the construction branch tunnel is 7.0m×8.0m, and the bottom elevation of the plugging body layout position is 2259.00, from which it can be known that the working head is 35.5m. Since the construction branch tunnel of this project is not lined, the interface between concrete and surrounding rock is taken as the controlling sliding surface. Using the partial factor limit state design method, the designed tunnel plug length is calculated to be 14.46m.

[0096] In order to detect the anti-sliding stability failure risk rate of the water retaining plug designed above, the solution provided by the present invention is implemented as follows:

[0097] 1. Establish a risk model for the failure of anti-sliding stability of tunnel plugging during the main flood season of ultra-high dam construction:

[0098] The sliding of the tunnel plugging body along the interface is the main structural failure mode of the tunnel plug. The load effect of the tunnel plug is mainly the thrust of the water load generated by the highest construction flood level on the upstream face of the plug. The structural anti-sliding force is the friction between the concrete and the surrounding rock and the cohesion of the material. The anti-sliding stability limit state equation of the tunnel plug during the main flood season of the super-high dam construction is established as:

[0099] Z=P H (max(Z m (t)))-(f'∑W+C'(λA1+A2))=0

[0100] Among them, Z m (t) is the dynamic change process of the water level of the reservoir in front of the dam during the main flood season; P H (max(Z m (t))) is the thrust of the water load generated by the highest flood level on the upstream side of the plug; f' is the shear friction coefficient between the plug concrete and the surrounding rock; ∑W is the sum of all normal forces on the sliding surface, unit MN; C' is the cohesion between the plug and concrete or between concrete and surrounding rock, unit MPa; λ is the effective bonding area coefficient of the side wall; A1 is the effective shear surface contact area of ​​the side wall, unit m 2 ; A2 is the effective shear contact area of ​​the bottom surface, unit: m 2 .

[0101] The tunnel plugging during the main flood season of this project is subject to the combined influence of random factors such as hydrology, hydraulics, and material mechanical parameters, and there is a risk of structural sliding failure. Among them, the water load generated by the highest water level in the upstream reservoir is subject to a certain degree of randomness due to the influence of random factors such as hydrology, hydraulics, and water level-reservoir capacity; the randomness of material mechanical parameters makes the total resistance of the plugging have a certain degree of randomness. Taking into account the randomness of the main influencing factors, the mathematical model of the anti-sliding stability failure risk R of the ultra-high dam tunnel plugging before the flood season is established:

[0102] R=P(P H (Z m (t))>f'∑W+C'(λA1+A2))

[0103] Among them, P(·) represents the probability that the (·) condition is true.

[0104] 2. Conduct a systematic analysis of the randomness of the main factors affecting water load and determine the distribution parameters of each random factor:

[0105] (1) Hydrological random parameters:

[0106] Based on the measured annual maximum flow series of the hydrological station, the investigated annual historical floods are added to form a discontinuous series for frequency calculation. The empirical frequencies of historical floods and measured series are calculated according to the expectation formula, the moment method is used to calculate the initial estimated parameters, and the eye estimation line fitting method is used to determine the hydrological random parameter as μ Q =2540m 3 / s,C v =0.33,C s / C v =5.0.

[0107] (2) Hydraulic random parameters:

[0108] The initial cross-sectional dimensions of the diversion tunnel are 15.0m×19.0m, and the discharge capacity coefficient of the discharge structure obeys a triangular distribution, with a value range generally between 0.97 and 1.05. Based on the experience of similar projects, the distribution parameter values ​​are 0.97 (lower limit), 1.00 (median value), and 1.05 (upper limit), respectively.

[0109] (3) Random parameters of water level and storage capacity relationship coefficient:

[0110] Considering that the water level-reservoir capacity relationship coefficient of the project follows a triangular distribution, and referring to relevant engineering experience, its distribution parameters are 0.99 (lower limit), 1.00 (median value), and 1.01 (upper limit).

[0111] 3. Conduct a systematic analysis of the randomness of the main factors affecting resistance and determine the distribution parameters of each random factor:

[0112] (1) Random parameter analysis of side wall contact coefficient:

[0113] The side wall contact coefficient follows a triangular distribution and generally ranges from 0.3 to 0.8. Based on the experience of similar projects and the construction management and technical level of the construction unit of this project, the median of the random distribution parameter of the side wall contact coefficient is taken as 0.5. Finally, the distribution parameter values ​​of the side wall contact coefficient λ are determined to be 0.3 (lower limit), 0.5 (median value), and 0.8 (upper limit).

[0114] (2) Material random parameter analysis:

[0115] The plugging concrete grade is C25, the surrounding rock grade is IV, and referring to relevant data and combining the construction site conditions, the statistical characteristics of the random parameters of the materials are shown in Table 1:

[0116] Table 1 Statistical characteristics of random parameters of materials

[0117] random variable Mean Coefficient of variation Distribution Type f' 0.7 0.2 Normal C' 0.4 0.1 Normal

[0118] 4. Carry out random simulation of the water load generated by the highest flood level of the dam during the main flood season and the total anti-sliding force generated by the tunnel plug, and calculate the risk rate of anti-sliding stability failure:

[0119] Determine the total number of model simulation calculations that meet the calculation accuracy requirements, conduct random simulation of the water load generated by the highest flood level of the dam flood control during the main flood season and the total anti-sliding force that can be generated by the tunnel plug, and simulate and calculate the risk rate R of anti-sliding stability failure of the tunnel plug during the main flood season of ultra-high dam construction.

[0120] To ensure the calculation accuracy, when the number of simulations is greater than 100,000 times, the calculation results tend to be stable and small. Therefore, the total number of simulations is designed to be 100,000 times. When the designed plug length is 14.46m, after 100,000 simulation calculations, it is statistically found that the number of anti-sliding stability failures of the plug caused by the water load at the highest flood level in front of the dam exceeding the total anti-sliding force that the tunnel plug can generate is 24 times, and the failure risk R is 0.24%, which shows that the designed plug length has high safety reliability, and the failure risk R is much smaller than the design risk rate of 5% of the 20-year design standard, which also shows that the designed plug length has a large safety margin. The plug length can be optimized in the future, so that the calculated anti-sliding stability failure risk rate is close to the design risk rate of 5%, so as to obtain the optimal plug length design value under the premise of meeting the reliability requirements of the design, thereby reducing the investment in the plug project and shortening the construction period.

[0121] Finally, it should be noted that the above embodiments are only preferred implementations and are not intended to limit the present invention. It should be pointed out that for those skilled in the art, several modifications, equivalent replacements, improvements, etc. can be made without departing from the scope of the present invention and the scope of protection of the claims, and all of these should be included in the protection scope of the present invention.

Claims

1. A method for detecting the risk rate of failure of anti-sliding stability of tunnel plugging during the main flood season of ultra-high dam construction, characterized in that: The following steps are involved: S1. Establish a risk model for the failure of tunnel plugging resistance during the main flood season of ultra-high dam construction; S2. Determine the distribution parameters of the main random factors affecting water load; S3. Determine the distribution parameters of the main random factors affecting the anti-slip force; S4. Based on the designed tunnel plug length and the distribution parameters of the main random factors affecting water load and anti-sliding force, a random simulation of the water load generated by the highest flood level of the dam during the main flood season and the total anti-sliding force that the tunnel plug can generate is conducted; S5. Based on the random simulation results, estimate the risk rate of anti-sliding stability failure of tunnel plugs during the main flood season of ultra-high dam construction.

2. The method for detecting the risk rate of failure of anti-sliding stability of tunnel plugs during the main flood season of ultra-high dam construction according to claim 1 is characterized in that: In step S1, the established risk model for the failure of anti-sliding stability of tunnel plugging during the main flood season of ultra-high dam construction is: R=P(P H (max(Z m (t)))>f'∑W+C'(λA1+A2)) Among them, R represents the risk of failure of anti-sliding stability of tunnel plugging during the main flood season of ultra-high dam construction; Z m (t) represents the dynamic change process of the water level of the reservoir in front of the dam during the main flood season; P H (max(Z m (t))) is the thrust of the water load generated by the highest flood level on the upstream face of the plug; f' is the shear friction coefficient between the plug and the surrounding rock; ∑W is the sum of all normal forces on the control sliding surface; C' is the cohesion between the plug and concrete or between concrete and surrounding rock; λ is the effective bonding area coefficient of the side wall; A1 is the effective shear surface contact area of ​​the side wall; A2 is the effective shear surface contact area of ​​the bottom surface; P(·) represents the probability that the (·) condition is met.

3. The method for detecting the risk rate of failure of anti-sliding stability of tunnel plugs during the main flood season of ultra-high dam construction according to claim 1 is characterized in that: In step S2, the distribution parameters of the main random factors affecting the water load are determined to include: The construction flood peak is assumed to follow the P-III type distribution; The discharge capacity coefficient of the diversion tunnel is assumed to follow a triangular distribution; The water level-reservoir capacity relationship coefficient is assumed to obey a triangular distribution.

4. The method for detecting the risk rate of failure of anti-sliding stability of tunnel plugs during the main flood season of ultra-high dam construction according to claim 3 is characterized in that: In step S3, the distribution parameters of the main random factors affecting the anti-slip force are determined, including: The effective bonding area coefficient of the side wall is assumed to obey a triangular distribution, and its probability density function is: Among them, k d is the lower limit, i.e. the minimum effective bonding area coefficient of the side wall; k m is the median value, estimated based on the technical level of the construction unit and on-site management; k u is the upper limit value, i.e. the maximum bonding effective area coefficient of the side wall; The shear friction coefficient and cohesion of the plug material are assumed to obey the normal distribution, and their probability density functions are: Wherein, μ is the mean of the random variable parameter of the shear friction coefficient f' or the cohesion C'; σ is the standard deviation of the random variable parameter of the shear friction coefficient f' or the cohesion C'.

5. The method for detecting the risk rate of failure of anti-sliding stability of tunnel plugs during the main flood season of ultra-high dam construction according to claim 4, characterized in that: In step S4, based on the designed tunnel plug length and in combination with the distribution parameters of the main random factors affecting the water load and the anti-sliding force, a random simulation of the water load generated by the highest flood level of the dam during the main flood season and the total anti-sliding force that can be generated by the tunnel plug is performed, including: First, the total number of model simulation calculations N that meets the calculation accuracy requirements is determined based on the Monte Carlo method. C ; Then, combining the distribution parameters of the main random factors affecting water load and anti-sliding force, N C Random simulation of the water load generated by the highest flood level of the dam during the secondary flood season and the total anti-sliding force generated by the tunnel plug.

6. The method for detecting the risk rate of failure of anti-sliding stability of tunnel plugs during the main flood season of ultra-high dam construction according to claim 5, characterized in that: The random simulation process of the water load generated by the highest flood level of the dam during the main flood season includes: ① Generate random numbers of construction flood peaks to simulate the construction flood process; ② Generate random numbers of reservoir capacity relationship coefficients and simulate and fit the water level capacity relationship curve; ③ Generate random numbers of discharge capacity coefficients and simulate and fit the diversion and discharge capacity curve; ④ The maximum flood level in front of the dam during the main flood season is obtained by simulating flood control calculations. m (t)); ⑤ Calculate the water load P by simulating the highest flood level in front of the dam during the main flood season H (max(Z m (t))).

7. The method for detecting the risk rate of failure of anti-sliding stability of tunnel plugs during the main flood season of ultra-high dam construction according to claim 6, characterized in that: The random simulation process of the total anti-sliding force that the tunnel plug can generate includes: ① Generate a random number for the bonding effective area coefficient λ of the side wall; ② Generate random numbers of shear friction coefficient f' and cohesion C'; ③ Calculate the total anti-sliding force f'∑W+C'(λA1+A2)) that the tunnel plug can generate.

8. The method for detecting the risk rate of failure of anti-sliding stability of tunnel plugs during the main flood season of ultra-high dam construction according to claim 7, characterized in that: In step S5, based on the random simulation results, the risk rate of failure of the tunnel plugging anti-sliding stability during the main flood season of the ultra-high dam construction is estimated, including: According to N C The simulation results of random simulation of the water load generated by the highest flood level of the dam during the secondary flood season and the total anti-sliding force generated by the tunnel plugging are analyzed statistically. The water load P of the highest flood level in front of the dam is H (max(Z m The number of times (t))) exceeds the total anti-sliding force f'∑W+C'(λA1+A2)) that the tunnel plug can generate is recorded as N T ; According to Estimate the risk rate R of anti-sliding stability failure of tunnel plugs during the main flood season of ultra-high dam construction.

Citation Information

Patent Citations

  • High rock-fill dam medium-term food season water retaining risk rate detection method

    CN104050391A

  • Method for detecting the risk rate of high arch dam construction in the early-middle period

    CN108959816A

  • Flood risk prediction method for construction of high rock-fill dam by considering uncertainty of shutdown and filling strength

    CN109934505A

  • Flood risk prediction method for construction of high rock-fill dam based on flood peak-flood volume combination

    CN110020792A

  • Method for compiling a flood hazard map using a hydrograph and developing a hydrograph tryggered by dam-break from flood

    KR1020160064277A