Method for reinforcing structure through settlement joint double-wall formwork construction

By setting round holes and fixing components on the double wall formwork of the settlement joint, the main keel is connected to the formwork, the problem of lack of operating space in the construction of the double wall formwork is solved, the template is conveniently removed and installed, and the rigidity of the wall reinforcement is improved .

CN119434610APending Publication Date: 2025-02-14SHANGHAI BAOYE GRP CORP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411640434.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-18
Publication Date
2025-02-14

AI Technical Summary

Technical Problem

In multi-story or high-rise buildings, the width of the settlement joints leads to the lack of operating space for double-wall formwork construction and is difficult to disassemble, and the polystyrene board cannot be removed in the prior art, which increases costs and affects structural settlement.

Method used

A construction reinforcement structure for double-wall formwork for settlement joints is designed. By setting round holes and fixing components on the surface of the formwork, the main keel is connected to the formwork using a screw and a steel bar head, which can facilitate the removal and installation of a single-sided integral formwork.

Benefits of technology

This method allows the formwork in the gap between the double walls to be easily removed, processed and installed, improves the stiffness of wall reinforcement, reduces the risk of construction quality accidents, and avoids the problem of the inability to remove polystyrene boards.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119434610A_ABST
    Figure CN119434610A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of civil engineering, and discloses a settlement joint double-wall formwork construction reinforcing structure which comprises two formworks, the sides, away from each other, of the two formworks are fixedly connected with a plurality of secondary keels through nails, and the secondary keels are vertically arranged on the side walls of the formworks; two hanging rings are fixedly connected to the top of the formwork located on the front face, and a plurality of main keels are arranged on the sides, away from the formworks, of the multiple auxiliary keels. According to the method, firstly, the three steel bars with the diameters are vertically arranged to weld the main keel into a whole, one end of the rotating lead screw penetrates through the round hole to be connected with the fixing block, so that the main keel and the formwork are connected together, the formwork in the double-wall gap can be easily taken out by arranging the single-side integral formwork, machining and mounting are very convenient, and the construction efficiency is improved. The device can be arranged at the position of a deformation joint of double walls, and two side formworks can be arranged at the positions of the double walls, so that construction quality accidents such as formwork expansion and displacement are reduced and avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of civil engineering equipment, in particular to a method for constructing a settlement joint double-wall formwork reinforced structure. Background Art

[0002] In multi-story or high-rise civil buildings, since the units of the buildings are numerous and the length is long, settlement joints need to be set at stress concentration or intermediate unit locations to prevent the various parts of the buildings from cracking due to uneven settlement of the foundation. However, the width of the settlement joints of buildings is generally 200mm, which leads to the problem of no operating space in the shear wall formwork construction on both sides of the expansion joint, making the installation and removal of the formwork very difficult.

[0003] In the prior art, in order to facilitate the demolding of the expansion joints during construction, soft foam materials such as extruded boards are placed between the double-wall formworks at the expansion joints, and then the double-wall formworks are connected to the steel pipe keel by tension bolts, thereby completing the reinforcement of the formworks of the two walls. However, after the polystyrene boards are set in the double walls, the polystyrene boards are poured into the settlement joints and cannot be removed, which not only has a high cost but is also unfavorable for the settlement of the structures on both sides of the settlement joints, and the settlement friction of the building generates noise during later use. Summary of the invention

[0004] The object of the present invention is to provide a method for constructing a double-wall formwork reinforcement structure of a settlement joint to solve the problems raised in the above-mentioned background technology.

[0005] In order to solve the above technical problems, the present invention is achieved through the following technical solutions: The present invention is a settlement joint double-wall formwork construction reinforcement structure, comprising two formworks, wherein the two formworks are fixedly connected with a plurality of secondary keels on the sides away from each other by nails, the secondary keels are vertically arranged on the side walls of the formwork, and two hanging rings are fixedly connected to the top of the formwork located on the front side, a plurality of main keels are arranged on the sides away from the formwork, the main keels are placed vertically with the secondary keels, three steel bars are fixedly connected to the surfaces of a plurality of main keels, and the three steel bars weld the plurality of main keels into one, a plurality of circular holes are opened on the side wall of the formwork located on the front side, and a plurality of fixing components are arranged on the inner walls of the circular holes, the fixing components comprise a screw rod slidably connected to the inner wall of the circular hole, the end of the screw rod close to the main keel is threadedly connected to a fixing block, the outer surface of the fixing block is fixedly connected to the side of the main keel away from the formwork, and the end of the screw rod away from the fixing block is fixedly connected to a steel bar head.

[0006] Furthermore, two calibration components are provided at the bottom of the template located on the front side, and the calibration component includes a support block fixedly connected to the side of the front template close to the main keel, a sliding block is provided on the top of the support block, and a push rod is fixedly connected to the side of the sliding block away from the main keel.

[0007] Furthermore, a spring is sleeved on the outer surface of the push rod, one end of the push rod away from the slider penetrates the side wall of the support block and extends to the outside, and the extended end of the push rod is fixedly connected to the limit block.

[0008] Furthermore, a plurality of support components are arranged between the two templates, and the support components include sleeve one, sleeve two is threadedly connected to the outer surface of sleeve one, and tension bolts are arranged inside sleeve one.

[0009] Furthermore, the side walls of the two templates are each provided with a screw hole, the outer surface of the tension bolt is slidably connected to the inner wall of the screw hole, a transverse groove is provided inside the main keel, and one end of the tension bolt close to the main keel extends from the inside of the transverse groove.

[0010] Furthermore, a butterfly clip is sleeved on the extended end of the tension bolt, and a nut is fixedly connected to the side of the butterfly clip away from the template.

[0011] Furthermore, the inner wall of the nut is threadedly connected to the extended end of the tension bolt, and the side of the butterfly clip close to the main keel is fixedly connected to the outer surface of the main keel.

[0012] Furthermore, a plurality of protrusions are fixedly connected to the sides of the two templates close to each other, and two U-shaped blocks are fixedly connected to the sides of the main keels close to the templates, and the inner walls of the two U-shaped blocks are slidably connected to the secondary keels.

[0013] The present invention has the following beneficial effects: (1) The present invention first vertically arranges three diameter steel bars to weld the main keel into one body, opens a circular hole on the surface of the template, and one end of the rotating screw rod passes through the circular hole to be connected to the fixed block, and the steel bar head arranged at the other end is welded to the fixed block, thereby connecting the main keel and the template together. By setting a single-sided integral template, the template in the gap between the double walls can be easily taken out, and the processing and installation are very convenient. It can be set at the deformation joint position of the double wall, and both side templates can be set at the double wall position, which can improve the rigidity of the wall reinforcement, so as to reduce and avoid construction quality accidents such as expansion and displacement.

[0014] (2) In the present invention, a U-shaped block is provided on the side of the main keel close to the template. The U-shaped block is aligned with the secondary keel to push the main keel to slide on the surface of the secondary keel. A calibration component is provided at the bottom of the template. When the main keel contacts the slider, the slider is pushed to move. The spring is squeezed to generate elastic force, and the main keel contacts the top of the support block. The vertical limit and the horizontal limit can make the main keel and the template quickly dock, which is convenient for the subsequent drilling and installation of the main keel and the template.

[0015] (3) In the present invention, sleeve 1 is inserted into the surface of the tension bolt, and the overall length of sleeve 1 and sleeve 2 is adjusted by rotating. The corresponding length is adjusted according to the thickness of the wall. The ends of sleeve 1 and sleeve 2 close to the side wall of the template are conical. Sleeve 1 and the tension bolt can not only protect the tension bolt to prevent it from being cast in the wall and unable to be removed, but also provide support for the templates on both sides during reinforcement, thereby preventing excessive reinforcement of the template from causing an uneven surface of the cast wall.

[0016] Of course, any product implementing the present invention does not necessarily need to achieve all of the advantages described above at the same time. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the accompanying drawings required for describing the embodiments will be briefly introduced below. Obviously, the accompanying drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other accompanying drawings can be obtained based on these accompanying drawings without paying creative work.

[0018] Figure 1 It is a schematic diagram of the structure of the present invention; Figure 2 This is a schematic diagram of the tension bolt structure of the present invention; Figure 3 For the present invention Figure 2 A is a schematic diagram of the structure enlargement; Figure 4 It is a schematic diagram of the support assembly of the present invention; Figure 5 It is a schematic diagram of a bump of the present invention; Figure 6 It is a schematic diagram of the support block of the present invention; Figure 7 For the present invention Figure 6 A schematic diagram of the structure of B in the middle; Figure 8 This is a schematic diagram of the main keel of the present invention; Fig. 9 For the present invention Figure 8 Schematic diagram of the enlarged structure of C in the middle.

[0019] In the accompanying drawings, the components represented by the reference numerals are listed as follows: In the figure: 1. template; 101. lifting ring; 102. secondary keel; 103. main keel; 104. steel bar; 105. screw hole; 106. round hole; 107. transverse groove; 2. support assembly; 201. sleeve one; 202. sleeve two; 203. tension bolt; 204. butterfly clip; 205. nut; 206. bump; 3. fixing assembly; 301. fixing block; 302. screw rod; 303. steel bar head; 4. calibration assembly; 401. support block; 402. push rod; 403. spring; 404. slider; 405. limit block; 501. U-shaped block. DETAILED DESCRIPTION

[0020] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0021] See also Figure 1 - Fig. 9 As shown, the present invention is a settlement joint double-wall formwork construction reinforcement structure, comprising two formworks 1, the two formworks 1 are fixedly connected with a plurality of secondary keels 102 on the sides away from each other by nails, the spacing of the secondary keels 102 is 150 mm, the formworks 1 and the secondary keels 102 are fixed by nails, the secondary keels 102 are vertically arranged on the side walls of the formworks 1, the top of the formworks 1 located on the front is fixedly connected with two hanging rings 101, a plurality of main keels 103 are arranged on the side away from the formworks 1, the main keels 103 are placed vertically with the secondary keels 102, and the surfaces of the plurality of main keels 103 are fixedly connected with three steel bars 104, and the three steel bars 104 connect the plurality of main keels 103. 3 are welded into one body, a plurality of circular holes 106 are opened on the side wall of the template 1 located at the front, and the inner walls of the plurality of circular holes 106 are all provided with fixing components 3, and the fixing components 3 include a screw rod 302 slidably connected to the inner wall of the circular hole 106, and one end of the screw rod 302 close to the main keel 103 is threadedly connected with a fixing block 301, and the outer surface of the fixing block 301 is fixedly connected to the side of the main keel 103 away from the template 1, and one end of the screw rod 302 away from the fixing block 301 is fixedly connected with a steel bar head 303, one end of the rotating screw rod 302 passes through the circular hole 106 and is connected to the fixing block 301, and the other end is provided with a φ12 steel bar head 303 welded thereto, so as to connect the main keel 103 and the template 1 together.

[0022] Two calibration components 4 are provided at the bottom of the front template 1. The calibration component 4 includes a support block 401 fixedly connected to the side of the front template 1 close to the main keel 103. A slider 404 is provided on the top of the support block 401. A push rod 402 is fixedly connected to the side of the slider 404 away from the main keel 103. The support block 401 provides support to the main keel 103, which facilitates the subsequent connection of the main keel 103 with the template 1.

[0023] A spring 403 is sleeved on the outer surface of the push rod 402, and one end of the push rod 402 away from the slider 404 passes through the side wall of the support block 401 and extends to the outside. The extended end of the push rod 402 is fixedly connected to the limiting block 405. A plurality of support components 2 are arranged between the two templates 1. The support component 2 includes a sleeve 1 201, and a sleeve 2 202 is threadedly connected to the outer surface of the sleeve 1 201. A tension bolt 203 is arranged inside the sleeve 1 201. The overall length between the sleeve 1 201 and the sleeve 2 202 is adjusted by rotation, and the corresponding length is adjusted according to the thickness of the wall.

[0024] The side walls of the two templates 1 are both provided with screw holes 105, the outer surface of the tension bolt 203 is slidably connected to the inner wall of the screw hole 105, and a transverse groove 107 is provided inside the main keel 103, and one end of the tension bolt 203 close to the main keel 103 extends from the inside of the transverse groove 107.

[0025] The extended end of the tension bolt 203 is sleeved with a butterfly clip 204, and a nut 205 is fixedly connected to the side of the butterfly clip 204 away from the template 1, and the butterfly clip 204 and the nut 205 are connected into one by welding.

[0026] The inner wall of the nut 205 is threadedly connected to the extended end of the tension bolt 203, and the side of the butterfly clip 204 close to the main keel 103 is fixedly connected to the outer surface of the main keel 103. One end of the tension bolt 203 is passed through the screw hole 105 on the surface of the formwork 1, and the tension bolt 203 is rotated to connect with the nut 205 on the front side of the formwork 1, thereby pulling the main keel 103.

[0027] A plurality of protrusions 206 are fixedly connected to the sides of the two templates 1 close to each other, and two U-shaped blocks 501 are fixedly connected to the sides of the main keels 103 close to the template 1. The inner walls of the two U-shaped blocks 501 are slidingly connected to the secondary keels 102. The protrusions 206 fit with the sleeves 1 201 and 202, which can not only maintain the sealing effect, but also prevent the concrete slurry from leaking into the surface of the tension bolts 203 from the gaps where the sleeves 1 201 and 202 contact the template 1.

[0028] When in use, first prepare the wooden formwork according to the length and height of the wall, then assemble it into a whole to form the formwork 1, and then vertically arrange the secondary purlins 102 on the surface of the formwork 1, with a spacing of 150mm between the formwork 1 and the secondary purlins 102, and fix them with nails.

[0029] The main keel 103 is placed on the side of the secondary keel 102 away from the template 1. The main keel 103 and the secondary keel 102 are placed vertically. The main keel 103 is set from the bottom. The first main keel 103 is 200mm from the ground, and then one is set at an interval of 450mm. The distance between the top three can be 500mm. First, three steel bars 104 with a diameter of 14 are vertically set to weld the main keel 103 into one, and the main keel 103 is connected to the template 1. A U-shaped block 501 is set on the side of the main keel 103 close to the template 1. The U-shaped block 501 and the secondary keel The main keel 103 is aligned with the secondary keel 102, pushing the main keel 103 to slide on the surface of the secondary keel 102. A calibration component 4 is provided at the bottom of the template 1. When the main keel 103 contacts the slider 404, the slider 404 is pushed to move, and the spring 403 is squeezed to generate elastic force. When the main keel 103 contacts the top of the support block 401, a circular hole 106 is opened on the surface of the template 1, and one end of the rotating screw rod 302 passes through the circular hole 106 and is connected to the fixed block 301, and a φ12 steel bar head 303 is provided at the other end and welded to it, so that the main keel 103 is connected to the template 1 together.

[0030] Two lifting rings 101 are set at the upper end of the single-sided formwork 1 connected as one, and the lifting ring 101 uses φ14 steel bars for lifting. Then the single-sided formwork 1 is transported to another wall of the same type, and then the other side formwork 1 is assembled. After temporary fixation, the formworks 1 on both sides of the wall are opened with screw holes 105 corresponding to the main keel 103 according to the horizontal spacing of 600mm and the vertical spacing, so that the tension bolts 203 can be accurately aligned in the later stage. After the screw holes 105 are opened, the butterfly clips 204 and nuts 205 are fixed on the main keel, and the positions correspond to the screw holes 105 opened and positioned first.

[0031] After the other wall of the double wall of the settlement joint is poured and the formwork is removed, the single-piece formwork 1 is erected in the settlement joint, and one end of the tension bolt 203 is passed through the screw hole 105 on the surface of the formwork 1, and the tension bolt 203 is rotated to connect with the nut 205 on the front side of the formwork 1, and then the main keel 103 is pulled, and a protrusion 206 is provided at the screw hole 105 opened in the formwork 1. After one end of the tension bolt 203 is installed, the surface of the tension bolt 203 is inserted into the sleeve 1 201, and the overall length between the sleeve 1 201 and the sleeve 2 202 is adjusted by rotation. The corresponding length is adjusted according to the thickness of the wall. The ends of the sleeve 1 201 and the sleeve 2 202 close to the side wall of the formwork 1 are conical, and the ends of the sleeve 1 201 and the sleeve 2 202 are fitted with the protrusions 206 provided on the side walls of the formwork 1 on both sides. The fit of the protrusion 206 with the sleeve 1 201 and the sleeve 2 202 can not only maintain the sealing effect, but also avoid The concrete slurry leaks into the surface of the tension bolt 203 from the gap between the sleeve 1 201 and the sleeve 202 and the template 1, thereby contaminating the tension bolt 203 and making it impossible to remove the tension bolt 203 for circulation. The sleeve 1 201 and the tension bolt 203 can not only protect the tension bolt 203 to prevent it from being cast in the wall and unable to be removed, but also form a supporting effect for the templates 1 on both sides during reinforcement, to prevent the template 1 from being reinforced too much, resulting in an uneven surface of the cast wall. The corresponding template 1 on the other side is installed, and the end of the tension bolt 203 extends out of the screw hole 105 of the template 1, and the butterfly clip 204 is inserted into the surface of the tension bolt 203. The nut 205 is rotated to fix the butterfly clip 204 on the surface of the main keel 103. The other tension bolts 203 are made in the same way. After tightening one by one, the wall is reinforced and the next pouring process can be carried out.

[0032] The preferred embodiments of the present invention disclosed above are only used to help illustrate the present invention. The preferred embodiments do not describe all the details in detail, nor do they limit the invention to the specific implementation methods described. Obviously, many modifications and changes can be made according to the content of this specification. This specification selects and specifically describes these embodiments in order to better explain the principles and practical applications of the present invention, so that those skilled in the art can understand and use the present invention well. The present invention is limited only by the claims and their full scope and equivalents.

Claims

1. A settlement joint double wall formwork construction reinforcement structure, comprising two formworks (1), wherein the two formworks (1) are fixedly connected to a plurality of secondary keels (102) on the sides away from each other by nails, wherein the secondary keels (102) are vertically arranged on the side walls of the formworks (1), and the top of the formwork (1) located at the front is fixedly connected to two hanging rings (101), and a plurality of main keels (103) are arranged on the sides away from the formworks (1), wherein the main keels (103) are placed vertically to the secondary keels (102), and the surfaces of the plurality of main keels (103) are fixedly connected to three steel bars (104), and the three steel bars (104) weld the plurality of main keels (103) into one body, wherein: A plurality of circular holes (106) are provided on the side wall of the template (1) at the front side, and the inner walls of the plurality of circular holes (106) are provided with fixing components (3), wherein the fixing components (3) comprise a screw rod (302) slidably connected to the inner wall of the circular hole (106), an end of the screw rod (302) close to the main keel (103) being threadedly connected to a fixing block (301), an outer surface of the fixing block (301) being fixedly connected to a side of the main keel (103) away from the template (1), and an end of the screw rod (302) away from the fixing block (301) being fixedly connected to a steel bar head (303).

2. A settlement joint double wall formwork construction reinforcement structure according to claim 1, characterized in that: Two calibration components (4) are arranged at the bottom of the template (1) located at the front, and the calibration component (4) comprises a support block (401) fixedly connected to a side of the front template (1) close to the main keel (103), a sliding block (404) is arranged on the top of the support block (401), and a push rod (402) is fixedly connected to a side of the sliding block (404) away from the main keel (103).

3. A settlement joint double wall formwork construction reinforcement structure according to claim 2, characterized in that: The outer surface of the push rod (402) is sleeved with a spring (403), one end of the push rod (402) away from the slider (404) penetrates the side wall of the support block (401) and extends to the outside, and the extended end of the push rod (402) is fixedly connected to the limit block (405).

4. A settlement joint double wall formwork construction reinforcement structure according to claim 3, characterized in that: A plurality of support assemblies (2) are arranged between the two templates (1), the support assemblies (2) comprising a sleeve 1 (201), the outer surface of the sleeve 1 (201) being threadedly connected to a sleeve 2 (202), and a tension bolt (203) being arranged inside the sleeve 1 (201).

5. A settlement joint double wall formwork construction reinforcement structure according to claim 4, characterized in that: The side walls of the two templates (1) are each provided with a screw hole (105), the outer surface of the tension bolt (203) is slidably connected to the inner wall of the screw hole (105), the interior of the main keel (103) is provided with a transverse groove (107), and one end of the tension bolt (203) close to the main keel (103) extends out from the interior of the transverse groove (107).

6. A settlement joint double wall formwork construction reinforcement structure according to claim 5, characterized in that: The extended end of the tension bolt (203) is sleeved with a butterfly clip (204), and a nut (205) is fixedly connected to the side of the butterfly clip (204) away from the template (1).

7. A settlement joint double wall formwork construction reinforcement structure according to claim 6, characterized in that: The inner wall of the nut (205) is threadedly connected to the extended end of the tension bolt (203), and the side of the butterfly clamp (204) close to the main keel (103) is fixedly connected to the outer surface of the main keel (103).

8. A settlement joint double wall formwork construction reinforcement structure according to claim 7, characterized in that: The two templates (1) are fixedly connected to a plurality of protrusions (206) on one side close to each other, and the plurality of main keels (103) are fixedly connected to two U-shaped blocks (501) on one side close to the template (1), and the inner walls of the two U-shaped blocks (501) are slidably connected to the secondary keels (102).

9. A settlement joint double wall formwork construction reinforcement method, the settlement joint double wall formwork construction reinforcement structure as claimed in claim 8, characterized in that: The following steps are involved: Step 1: First, prepare the wooden formwork according to the length and height of the wall, and then assemble it into a whole; then, arrange the secondary keel (102) vertically at a spacing of 150mm behind the formwork, and use nails to fix the formwork (1) and the square steel, and place the main keel (103) on the outside of the secondary keel (102) and place it vertically with the secondary keel. The main keel (103) is set from the bottom, and the first main keel (103) is 200mm from the ground, and then one is set at an interval of 450mm. The distance between the top three can be 500mm. First, three steel bars (104) with a diameter of 14 are vertically set to weld the main keel (103) into one; Step 2: two lifting rings (101) are arranged at the upper end of the single-side formwork (1) connected as one, and then the single-side formwork (1) is transported to another wall of the same type, and the other side formwork (1) is also assembled. After temporary fixation, holes are opened in the formworks (1) on both sides of the wall according to the horizontal spacing of 600 mm and the vertical spacing of the main keel (103), so that the tension bolts (203) can be accurately aligned with the holes later; Step 3: After the holes corresponding to the tension bolts (203) are set, the butterfly clips (204) and nuts (205) are then fixed on the main keel (103) at positions corresponding to the screw holes (105) previously drilled and positioned. After the other wall of the double wall of the settlement joint is cast and the formwork is removed, the single-piece formwork (1) is erected and temporarily fixed, and one end of the tension bolt (203) is passed through the screw hole (105) on the surface of the formwork (1). The tension bolt (203) is rotated to connect with the nut (205) on the front of the formwork (1). The sleeve 1 (201) is inserted into the surface of the tension bolt (203), and the corresponding formwork (1) on the other side is installed. The tension bolt (203) and the nut (205) are tightened. The other tension bolts (203) are done in the same way. After they are tightened one by one, the wall is reinforced and the next pouring process can be carried out.