Concrete pouring equipment for pile foundation construction
By using pipe diameter adjustment modules in concrete pouring equipment for pile foundation construction, the pipe diameter of the pouring conduit is quickly changed, which solves the problem that existing equipment cannot effectively control the concrete filling speed, and achieves the effect of reducing resource waste and accelerating construction speed.
Patent Information
- Application Number
- CN202411960459.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-30
- Publication Date
- 2025-02-18
AI Technical Summary
The existing concrete pouring equipment for pile foundation construction cannot effectively control the speed of pouring concrete in the pouring conduit, resulting in the concrete being mixed with more impurities such as wall protection mud, resulting in waste of resources and delayed construction progress.
A concrete pouring equipment for pile foundation construction was designed, and the pipe diameter adjustment module was used to quickly change the pipe diameter of the bottom end outlet of the pouring conduit, adjust the speed and pressure of concrete filling, reduce the contact area between mud and concrete, and reduce the Possibility of doping.
It is realized that when the concrete volume is fixed, the speed and pressure of the pile inlet holes for concrete filling are changed, the amount of pile head concrete that needs to be cut after the cast pile is solidified and formed is reduced, the construction speed is accelerated, and resource consumption is reduced.
Smart Images

Figure CN119465978A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of pile foundation construction, and in particular to concrete pouring equipment used for pile foundation construction. Background Art
[0002] The pile foundation consists of piles and pile caps. Pile construction methods are divided into two categories: prefabricated piles and cast-in-place piles. In addition to the engineering geological conditions, the selection of the piling method must also consider the type, section, length, site environment and design requirements of the pile. In order to meet the needs of large-scale pile foundation projects, the pile foundation construction technology must increase the hammer weight and improve the lifting and hoisting operation process, while reducing vibration noise and environmental pollution.
[0003] When the existing concrete pouring equipment for pile foundation construction pours the first batch of concrete for the bored pile, the diameter of the pouring conduit is fixed, and it is impossible to effectively control the speed at which the concrete flows into the bottom of the pile, so that the entering concrete is mixed with a large amount of impurities such as wall protection mud. As a result, after the bored pile is formed, it is necessary to cut off the pile head mixed with a large amount of impurities, resulting in waste of resources and delay in construction progress. Summary of the invention
[0004] The invention discloses a concrete pouring device for pile foundation construction, aiming to solve the technical problem that the existing concrete pouring device for pile foundation construction in the background technology cannot effectively control the speed of pouring concrete by a pouring conduit.
[0005] The present invention proposes a concrete pouring equipment for pile foundation construction, including an operating table, wherein a positioning hole is opened on the operating table, a pouring conduit is arranged in the positioning hole, and an extension pipe is arranged above the pouring conduit, the outside of the pouring conduit and the extension pipe are provided with the same quick-install module, and a leveling and stabilizing module is arranged on the operating table, the leveling and stabilizing module is located between the operating table and the quick-install module, the outside of the pouring conduit is provided with a pipe diameter adjustment module, the pipe diameter adjustment module is located below the operating table, and the bottom of the operating table is fixedly connected to a plurality of circumferentially equidistantly distributed universal wheels, the bottom of the operating table is fixedly connected to a plurality of circumferentially equidistantly distributed hydraulic rods one, and the output ends of the hydraulic rods one are fixedly connected to equalizing plates.
[0006] By providing an operating table, a pouring conduit, an extension pipe, a positioning hole, a pipe diameter adjustment module, a quick-installation module, a leveling and stabilizing module, a universal wheel, a hydraulic rod and a pressure equalizing plate, the device can use the pipe diameter adjustment module to quickly and conveniently change the pipe diameter of the bottom outlet of the pouring conduit when pouring the first tank of concrete into the pile hole, so that the device can change the speed and pressure of concrete filling into the pile hole when the concrete volume is fixed, reduce the contact area between the wall protection mud and the concrete in the pile hole, reduce the possibility of mutual mixing of mud and concrete, reduce the amount of pile head concrete that needs to be cut off after the cast-in-place pile is solidified and formed, speed up the construction speed, and reduce resource consumption.
[0007] In a preferred solution, the pipe diameter adjustment module includes a fixed sleeve, the outside of the casting conduit is fixedly connected to the fixed sleeve, the outside of the fixed sleeve is fixedly connected to a mounting seat, the upper side of the mounting seat is provided with a plurality of movable grooves equidistantly distributed in the circumference, the movable grooves are slidably connected with sliders, and the upper sides of the sliders are fixedly connected with short shafts, and the mounting seat is provided with three guide grooves equidistantly distributed in the circumference; the outside of the fixed sleeve is movably connected to a rotating frame, the inner wall of the rotating frame is slidably connected to the outside of the mounting seat, and the rotating frame is provided with a plurality of equidistantly distributed in the circumference The inner walls of the plurality of arc grooves are respectively slidably connected to the outsides of the plurality of short shafts, and the upper side of the mounting seat is provided with three circular groove openings equidistantly distributed around the circumference, the inner walls of the circular groove openings are fixedly connected to drive motors, the output ends of the drive motors are connected to drive gears through couplings, and the drive gears are located in the rotating frame; the inner wall of the rotating frame is provided with an annular groove, an inner gear ring is fixedly connected in the annular groove, and the three drive gears are meshed with the inner gear ring, the bottom inner wall of the movable groove is provided with a strip groove, and a connecting rod is slidably connected in the strip groove, and is located in the same movable frame. The slider in the movable groove is fixedly connected to the opposite side of the connecting rod, and the inner wall of the fixed sleeve is fixedly connected with a plurality of circumferentially equidistant bosses, and the outside of the bosses is movably connected with an adjusting plate, and the inner wall of the fixed sleeve is fixedly connected with a plurality of circumferentially equidistant bosses, and the bosses are each provided with notches, and the notches are fixedly connected with a thin shaft, and the outside of the thin shaft is movably connected with an adjusting plate, and the side of the adjusting plate close to the fixed sleeve is fitted with the side of the two adjacent adjusting plates away from the fixed sleeve, and the outside of the thin shaft is surrounded by a torsion spring, and one end of the torsion spring They are all fixedly connected to the outside of the adjusting plate 2 on the same side, and the other ends are all fixedly connected to the outside of the boss 2 on the same side; the outside of the fixed sleeve is fixedly connected with a plurality of circumferentially equidistant supports, the outside of the supports are movably connected with a rotating rod, the connecting rod and the side opposite to the rotating rod on the same side are movably connected, and the end of the rotating rod away from the connecting rod is fixedly connected with a fixed block, a strip opening is opened on one side of the plurality of adjusting plates close to the fixed sleeve, a movable block is slidably connected in the strip opening, and the plurality of movable blocks are movably connected to the side opposite to the plurality of fixed blocks.
[0008] By providing a pipe diameter adjustment module, the pipe diameter adjustment module can quickly open, close and gather under the drive of the rotating rod by using the adjustment plate one and the adjustment plate two, so that the device can quickly adjust the pipe diameter, which greatly improves the adjustment sensitivity. In addition, the adjustment plate one and the adjustment plate two that can be adjusted within a certain range enable the device to adapt to the requirements of different pile hole sizes, thereby improving the applicability of the device.
[0009] In a preferred embodiment, the quick-release module includes an annular fixing part, the inner wall of the annular fixing part is fixedly connected to the outside of the casting conduit, an annular notch is provided on the upper side of the annular fixing part, a contact gasket is slidably connected in the annular notch, a spring is fixedly connected to the bottom of the contact gasket on the side opposite to the inner wall of the annular notch, and an engaging annular part is provided on the upper side of the contact gasket; the inner wall of the engaging annular part is fixedly connected to the outside of the extension tube, the outside of the engaging annular part is slidably connected to the inner wall of the annular notch, and the inner wall of the annular notch is provided with two locking grooves equidistantly distributed around the circumference, the inner walls of the locking grooves are both clamped with circular pins, the opposite sides of the two circular pins are both fixedly connected to the outside of the engaging annular part, and the inner wall of the annular notch is provided with a plurality of mud discharge holes equidistantly distributed around the circumference.
[0010] By providing a quick-release module, the quick-release module utilizes an annular notch and a locking groove to enable the device to quickly connect and separate the casting conduit and the extension tube, thereby ensuring the stability of the connection during casting while also improving the convenience of disassembly and installation, thereby improving the working efficiency of the device.
[0011] In a preferred solution, the leveling and stabilizing module comprises a supporting plate 1, which is located above the operating table, and the bottom of the supporting plate 1 is provided with three semicircular grooves with equal circumference distance, and the inner walls of the semicircular grooves are fixedly connected with rotating ball seats, and the operating table is provided with three circular holes with equal circumference distance distance, and threaded rods are arranged in the circular holes, and the upper sides of the threaded rods on the same side are fixedly connected with the outside of the rotating ball seats; the outsides of the threaded rods are provided with limit gears, and the bottoms of the limit gears are movably connected with the upper side of the operating table, and the outsides of the threaded rods are provided with knobs, and the knobs on the threaded rods on the same side are fixedly connected with the side opposite to the limit gears, and the outsides of the limit gears are provided with annular locking pieces, and the inner walls of the annular locking pieces are fixed A rack is connected, and the racks are clamped with the limit gear. A positioning block is arranged in the annular locking piece. The positioning block is fixedly connected to the side opposite to the operating table, and the outside of the positioning block is slidably connected to the inner wall of the annular locking piece. A reset spring is fixedly connected to the side of the positioning block away from the limit gear, and one end of the original proportional positioning block of the reset spring is fixedly connected to the inner wall of the annular locking piece; the upper side of the support plate one is fixedly connected to the support plate two, and the upper side of the support plate two is fixedly connected to two symmetrical clamp rods, and the opposite sides of the two clamp rods are clamped with the bottom of the annular fixing piece, and the upper side of the support plate two is movably connected to two symmetrical hydraulic rods two, and the output ends of the two hydraulic rods two are respectively movably connected to the side of the two clamp rods away from the annular fixing piece.
[0012] By providing a leveling and stabilizing module, the leveling and stabilizing module can use three threaded rods to conveniently enable the support plate to quickly level the pouring conduit for pouring concrete, so that the concrete flowing out of the pouring conduit can be accurately filled into the pile hole, ensuring the pile-forming effect of the concrete, and reducing the risk of overturning due to uneven force on the device caused by the skewness of the pouring conduit, thereby improving safety.
[0013] From the above, it can be seen that the concrete pouring equipment for pile foundation construction provided by the present invention has a pipe diameter adjustment module that can quickly and conveniently change the pipe diameter of the bottom outlet of the pouring conduit when pouring the first tank of concrete into the pile hole, so that the device can change the speed and pressure of concrete filling into the pile hole when the concrete volume is fixed, reduce the contact area between the wall protection mud and the concrete in the pile hole, reduce the possibility of mutual mixing of mud and concrete, reduce the amount of pile head concrete that needs to be cut off after the bored pile is solidified and formed, speed up the construction speed, and reduce resource consumption. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 This is a schematic diagram of the overall structure of a concrete pouring device for pile foundation construction proposed by the present invention;
[0015] Figure 2 A cross-sectional structural schematic diagram of a concrete pouring device for pile foundation construction proposed by the present invention;
[0016] Figure 3 This is a schematic structural diagram of a pipe diameter adjustment module of a concrete pouring equipment for pile foundation construction proposed by the present invention;
[0017] Figure 4 A schematic diagram of the structure of an adjustment plate 1 and an adjustment plate 2 of a concrete pouring device for pile foundation construction proposed by the present invention;
[0018] Figure 5 A concrete pouring device for pile foundation construction proposed by the present invention Figure 4 Schematic diagram of the structure of A;
[0019] Figure 6 A schematic diagram of the structure of a quick-assembly module of a concrete pouring device for pile foundation construction proposed by the present invention;
[0020] Figure 7 This is a schematic diagram of the structure of a leveling and stabilizing module of a concrete pouring equipment for pile foundation construction proposed by the present invention;
[0021] Figure 8 A concrete pouring device for pile foundation construction proposed by the present invention Figure 7 Schematic diagram of the structure of B.
[0022] In the figure: 1, operating table; 2, casting conduit; 3, extension pipe; 4, positioning hole; 5, pipe diameter adjustment module; 501, fixed sleeve; 502, mounting seat; 503, movable groove; 504, slider; 505, short shaft; 506, rotating frame; 507, arc groove; 508, circular groove opening; 509, driving motor; 510, driving gear; 511, annular groove; 512, inner gear ring; 513, guide groove; 514, strip groove; 515, adjusting plate 1; 516, adjusting plate 2; 517, connecting rod; 518, rotating rod; 519, boss 1; 520, strip opening; 521, movable block; 522, fixed block; 523 , boss two; 524, torsion spring; 6, quick-release module; 601, annular fixing piece; 602, annular notch; 603, contact gasket; 604, spring one; 605, interlocking annular piece; 606, locking groove; 607, round pin; 608, mud discharge hole; 7, leveling and stabilizing module; 701, supporting plate one; 702, supporting plate two; 703, clamp rod; 704, hydraulic rod two; 705, threaded rod; 706, rotating ball seat; 707, limit gear; 708, annular locking piece; 709, positioning block; 710, rack; 711, knob; 712, reset spring; 8, universal wheel; 9, hydraulic rod one; 10, equalizing plate. DETAILED DESCRIPTION
[0023] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.
[0024] The concrete pouring equipment for pile foundation construction disclosed by the present invention is mainly applied to the scenario where the existing concrete pouring equipment for pile foundation construction cannot effectively control the speed of pouring concrete by the pouring conduit.
[0025] Reference Figure 1-8 A concrete pouring equipment for pile foundation construction includes an operating platform 1, a positioning hole 4 is opened on the operating platform 1, a pouring conduit 2 is arranged in the positioning hole 4, and an extension pipe 3 is arranged above the pouring conduit 2, the casting conduit 2 and the extension pipe 3 are provided with the same quick-install module 6 outside, and a leveling and stabilizing module 7 is provided on the operating platform 1, the leveling and stabilizing module 7 is located between the operating platform 1 and the quick-installing module 6, a pipe diameter adjustment module 5 is arranged outside the pouring conduit 2, and the pipe diameter adjustment module 5 is located below the operating platform 1, and the bottom of the operating platform 1 is connected with a plurality of circumferentially equidistantly distributed universal wheels 8 by bolts, and the bottom of the operating platform 1 is connected with a plurality of circumferentially equidistantly distributed hydraulic rods 9 by bolts, and the output ends of the hydraulic rods 9 are connected with equalizing plates 10 by bolts.
[0026] Specifically, after the operating platform 1 is pushed to the pile hole position, the operating platform 1 is lifted and supported and fixed using a hydraulic rod 9, the pouring conduit 2 and the extension pipe 3 are fixedly connected using a quick-installation module 6, the pouring conduit 2 and the extension pipe 3 that have been connected are placed in the positioning hole 4 and hoisted into the pile hole, and in the process of the pouring conduit 2 penetrating into the pile hole, other extension pipes 3 are continuously connected through the quick-installation module 6 until the bottom of the pouring conduit 2 approaches the bottom of the pile hole, and the extension pipe 3 in the positioning hole 4 or the outside of the pouring conduit 2 is supported, fixed and leveled using a leveling and stabilizing module 7, so that the pouring conduit 2 and the extension pipe 3 can remain vertical, and pouring begins Concrete, in the process of pouring the first tank of concrete, the diameter of the pipe for conveying concrete is adjusted by using the pipe diameter adjustment module 5, so that the concrete can be quickly filled into the bottom of the pile hole; the device can use the pipe diameter adjustment module 5 to quickly and conveniently change the diameter of the bottom outlet of the pouring conduit 2 when pouring the first tank of concrete into the pile hole, so that the device can change the speed and pressure of concrete filling into the pile hole when the concrete volume is fixed, reduce the contact area between the wall protection mud and the concrete in the pile hole, reduce the possibility of mutual mixing of mud and concrete, reduce the amount of pile head concrete that needs to be cut off after the bored pile is solidified and formed, speed up the construction speed, and reduce resource consumption.
[0027] Reference Figure 3 , Figure 4 and Figure 5In a preferred embodiment, the pipe diameter adjustment module 5 includes a fixed sleeve 501, the outside of the casting conduit 2 is connected to the fixed sleeve 501 by bolts, the outside of the fixed sleeve 501 is connected to a mounting seat 502 by bolts, a plurality of movable grooves 503 with equidistant distribution around the circumference are provided on the upper side of the mounting seat 502, a slider 504 is slidably connected in the movable groove 503, and a short shaft 505 is bolted to the upper side of the slider 504, and three guide grooves 513 with equidistant distribution around the circumference are provided on the mounting seat 502; the outside of the fixed sleeve 501 is rotatably connected to a rotating frame 506 by a bearing, the inner wall of the rotating frame 506 is slidably connected to the outside of the mounting seat 502, and a plurality of movable grooves 503 with equidistant distribution around the circumference are provided on the rotating frame 506 The inner walls of the plurality of arc grooves 507 are respectively slidably connected with the outer parts of the plurality of short shafts 505, and the upper side of the mounting seat 502 is provided with three circular grooves 508 equidistantly distributed around the circumference, and the inner walls of the circular grooves 508 are all connected with drive motors 509 by bolts, and the output ends of the drive motors 509 are all connected with drive gears 510 by couplings, and the drive gears 510 are located in the rotating frame 506; the inner wall of the rotating frame 506 is provided with an annular groove 511, and an inner gear ring 512 is connected in the annular groove 511 by bolts, and the three drive gears 510 are all meshed with the inner gear ring 512, and the bottom inner wall of the movable groove 503 is provided with a strip groove 514, and the strip groove 514 is slidably connected with a connecting rod 517, which is located in the same movable groove 5 The slider 504 and the connecting rod 517 in 03 are connected on opposite sides by bolts, and the inner wall of the fixed sleeve 501 is connected with a plurality of circumferentially equidistant bosses 519 by bolts, and the outside of the bosses 519 is rotatably connected with an adjusting plate 515 by bearings, and the inner wall of the fixed sleeve 501 is connected with a plurality of circumferentially equidistant bosses 523 by bolts, and the bosses 523 are provided with notches, and a thin shaft is connected in the notches by bolts, and the outside of the thin shaft is rotatably connected with an adjusting plate 516 by bearings, and the side of the adjusting plate 516 close to the fixed sleeve 501 is fitted with the side of the two adjacent adjusting plates 515 away from the fixed sleeve 501, and the outside of the thin shaft is surrounded by a torsion spring 524, and one end of the torsion spring 524 is It is connected to the outside of the adjustment plate 2 516 on the same side by bolts, and the other end is connected to the outside of the boss 2 523 on the same side by bolts; the outside of the fixed sleeve 501 is connected to multiple circumferentially equidistant supports by bolts, and the outside of the supports are rotatably connected to the rotating rod 518 through bearings, and the connecting rod 517 and the rotating rod 518 on the same side are rotatably connected on the side opposite to the connecting rod 517, and the rotating rod 518 is connected to the fixed block 522 at one end away from the connecting rod 517 by bolts, and the multiple adjustment plates 1 515 are provided with a strip opening 520 on the side close to the fixed sleeve 501, and the strip opening 520 is slidably connected with a movable block 521, and the multiple movable blocks 521 are rotatably connected to the multiple fixed blocks 522 on the side opposite to the multiple fixed blocks 522 by bearings.
[0028] Specifically, when pouring the first tank of concrete, after the isolation ball is pushed out of the pouring conduit 2 by the concrete, the drive motor 509 is started. The drive motor 509 drives the inner gear ring 512 meshing with the drive gear 510 to rotate, so that the rotating frame 506 rotates and the arc groove 507 pushes the slider 504 connected to the short shaft 505 to move outward in the movable groove 503, and the connecting rod 517 connected to the slider 504 rotates at the support position point as the connecting rod 517 moves. The fixed block 522 connected to the end of the rotating rod 518 away from the connecting rod 517 drives the movable block 521 to slide on the strip mouth 520, so that the adjusting plate 1 515 presses the adjusting plate 2 516 to overcome the torsion of the torsion spring 524 and gather toward the axis of the pouring conduit 2, thereby shrinking the diameter of the pouring conduit 2, accelerating the flow rate of the concrete flowing out of the pouring conduit 2, and quickly filling it into the bottom of the pile hole.
[0029] In specific application scenarios, the pipe diameter adjustment module 5 is mainly suitable for the pipe diameter adjustment link in the pipe diameter adjustment process, that is, the pipe diameter adjustment module 5 uses the adjustment plate 516 and the adjustment plate 516 to be quickly opened and closed and gathered under the drive of the rotating rod 518, so that the device can quickly realize the pipe diameter adjustment, which greatly improves the adjustment sensitivity, and the adjustment plate 1 515 and the adjustment plate 2 516 that can be adjusted within a certain range enable the device to adapt to the requirements of different pile hole sizes, thereby improving the applicability of the device.
[0030] Reference Figure 6 In a preferred embodiment, the quick-install module 6 includes an annular fixing member 601, the inner wall of the annular fixing member 601 is connected to the outside of the casting conduit 2 by bolts, an annular notch 602 is provided on the upper side of the annular fixing member 601, a contact gasket 603 is slidably connected in the annular notch 602, a spring 604 is connected to the bottom of the contact gasket 603 on the side opposite to the inner wall of the annular notch 602 by bolts, and an engaging annular member 605 is provided on the upper side of the contact gasket 603; The inner wall of the annular member 605 is connected to the outside of the extension tube 3 by bolts, the outside of the engaging annular member 605 is slidably connected to the inner wall of the annular notch 602, and the inner wall of the annular notch 602 is provided with two circumferentially equidistantly distributed locking grooves 606, the inner walls of the locking grooves 606 are each clamped with a circular pin 607, and the opposite sides of the two circular pins 607 are each connected to the outside of the engaging annular member 605 by bolts, and the inner wall of the annular notch 602 is provided with a plurality of circumferentially equidistantly distributed mud discharge holes 608.
[0031] Specifically, when the extension tube 3 is connected to the casting conduit 2, the extension tube 3 is hoisted above the casting conduit 2 so that the engaging ring 605 can be inserted into the annular notch 602, and the circular pin 607 on the outside of the engaging ring 605 is inserted into the locking groove 606. The lower extension tube 3 makes the engaging ring 605 fit with the contact gasket 603 and makes the contact gasket 603 overcome the thrust of the spring 1 604 and descend. During the descent, the engaging ring 605 is rotated so that the circular pin 607 can be stuck and fixed along the locking groove 606 as the engaging ring 605 descends.
[0032] In specific application scenarios, the quick-install module 6 is mainly suitable for the quick-install link in the quick-install process, that is, the quick-install module 6 uses the annular groove 602 and the locking groove 606 to enable the device to quickly connect and separate the casting conduit 2 and the extension tube 3, while ensuring the stability of the connection during casting, it also improves the convenience of disassembly and installation, thereby improving the working efficiency of the device.
[0033] Reference Figure 7 and Figure 8In a preferred embodiment, the leveling and stabilizing module 7 includes a supporting plate 701, the supporting plate 701 is located above the operating table 1, and the bottom of the supporting plate 701 is provided with three semicircular grooves with equal circumference distance, and the inner walls of the semicircular grooves are connected with a rotating ball seat 706 by bolts, and the operating table 1 is provided with three circular holes with equal circumference distance, and the circular holes are provided with threaded rods 705, and the upper side of the threaded rods 705 on the same side is connected to the outer side of the rotating ball seat 706 by bolts. The outer part of the threaded rod 705 is provided with a limit gear 707, the bottom of the limit gear 707 is rotatably connected to the upper side of the operating table 1 through a bearing, the outer part of the threaded rod 705 is provided with a knob 711, the knob 711 on the threaded rod 705 on the same side is connected to the side opposite to the limit gear 707 through bolts, and the outer part of the limit gear 707 is provided with an annular locking piece 708, the inner wall of the annular locking piece 708 is connected with a rack 710 through bolts, and the rack 711 is connected to the upper side of the operating table 1 through a bearing, and the outer part of the threaded rod 705 is provided with a limit gear 707, and the inner wall of the limit gear 708 is connected with a rack 710 through bolts. 10 are all engaged with the limit gear 707, and a positioning block 709 is arranged in the annular locking member 708. The positioning block 709 is connected to the side opposite to the operating table 1 by bolts. The outer part of the positioning block 709 is slidably connected to the inner wall of the annular locking member 708. The side of the positioning block 709 away from the limit gear 707 is connected to a reset spring 712 by bolts. The reset spring 712 is connected to the inner wall of the annular locking member 708 by bolts at one end of the original proportional positioning block 709; The upper side of plate 1 701 is connected to supporting plate 2 702 by bolts, and the upper side of supporting plate 2 702 is connected to two symmetrical clamp rods 703 by bolts, and the opposite sides of the two clamp rods 703 are clamped with the bottom of the annular fixing member 601, and the upper side of supporting plate 2 702 is rotatably connected to two symmetrical hydraulic rods 2 704 by bearings, and the output ends of the two hydraulic rods 2 704 are respectively rotatably connected to the sides of the two clamp rods 703 away from the annular fixing member 601 by bearings.
[0034] Specifically, after the pouring conduit 2 and the extension tube 3 are connected and placed in the positioning hole 4, the hydraulic rod 704 is started, and the output end of the hydraulic rod 704 pushes the clamp rod 703 to rotate, thereby contacting the outside of the pouring conduit 2 or the extension tube 3, and the bottom of the annular fixing member 601 is clamped with the upper side of the clamp rod 703, and the annular locking member 708 is pushed toward the axis of the positioning hole 4, so that the annular locking member 708 overcomes the thrust of the reset spring 712 to release the rack 710 on the annular locking member 708. To engage the limit gear 707, turn the knob 711 to rotate the threaded rod 705 on the operating table 1, so that the threaded rod 705 drives the supporting plate 701 to rise and fall. Through the continuous adjustment of the three threaded rods 705, the casting conduit 2 or the extension tube 3 on the supporting plate 701 is finally placed in a vertical state, and the annular locking piece 708 is loosened. Under the push of the reset spring 712, the rack 710 and the limit gear 707 are restored to the engaged state, and the threaded rod 705 no longer moves.
[0035] In specific application scenarios, the leveling and stabilizing module 7 is mainly suitable for the leveling and stabilizing link in the leveling and stabilizing process, that is, the leveling and stabilizing module 7 can use three threaded rods 705 to conveniently enable the support plate 701 to quickly level the pouring conduit 2 for pouring concrete, so that the concrete flowing out of the pouring conduit 2 can be accurately filled into the pile hole, ensuring the pile-forming effect of the concrete, and reducing the risk of overturning due to uneven force on the device caused by the skewness of the pouring conduit 2, thereby improving safety.
[0036] Working principle: after pushing the operating platform 1 to the pile hole position, use the hydraulic rod 9 to lift the operating platform 1 for support and fixation. When connecting the extension pipe 3 to the casting conduit 2, hoist the extension pipe 3 to the top of the casting conduit 2, so that the interlocking ring 605 can be inserted into the annular notch 602, and the circular pin 607 on the outside of the interlocking ring 605 is aligned with the locking groove 606 and inserted. The lower extension pipe 3 makes the interlocking ring 605 fit with the contact gasket 603 and makes the contact gasket 603 overcome the thrust of the spring 604 and descend. During the descent, rotate the interlocking ring 605 so that the circular pin 607 can be stuck and fixed along the locking groove 606 as the interlocking ring 605 descends. The already connected pouring conduit 2 and extension tube 3 are placed in the positioning hole 4 and hoisted into the pile hole. In the process of the pouring conduit 2 penetrating into the pile hole, other extension tubes 3 are continuously connected through the quick-install module 6 until the bottom of the pouring conduit 2 is close to the bottom of the pile hole, and the hydraulic rod 704 is started. The output end of the hydraulic rod 704 pushes the clamp rod 703 to rotate, thereby contacting the outside of the pouring conduit 2 or the extension tube 3, and makes the bottom of the annular fixing member 601 engage with the upper side of the clamp rod 703, and pushes the annular locking member 708 toward the axis of the positioning hole 4, so that the annular locking member 708 overcomes the thrust of the reset spring 712 to release the rack 710 on the annular locking member 708 from the clamping of the limit gear 707. By turning the knob 711, the threaded rod 705 on the operating table 1 rotates, so that the threaded rod 705 drives the supporting plate 701 to rise and fall. Through the continuous adjustment of the three threaded rods 705, the pouring conduit 2 or the extension tube 3 on the supporting plate 701 is finally in a vertical state, and the annular locking piece 708 is loosened. Under the push of the reset spring 712, the rack 710 and the limit gear 707 resume the engaged state, and the threaded rod 705 no longer moves, and the pouring of concrete begins. In the process of pouring the first tank of concrete, after the isolation ball is pushed out of the pouring conduit 2 by the concrete, the drive motor 509 is started, and the drive motor 509 drives the inner gear ring 512 meshing with the drive gear 510 to rotate. The rotating frame 506 rotates and causes the arc groove 507 to push the slider 504 connected to the short shaft 505 to move outward in the movable groove 503, and the connecting rod 517 connected to the slider 504 rotates at the support position point as the connecting rod 517 moves, and the fixed block 522 connected to the end of the rotating rod 518 away from the connecting rod 517 drives the movable block 521 to slide on the strip opening 520, so that the adjusting plate 1 515 presses the adjusting plate 2 516 to overcome the torsion force of the torsion spring 524 and gather toward the axis of the casting conduit 2, thereby shrinking the diameter of the casting conduit 2, accelerating the flow rate of the concrete flowing out of the casting conduit 2, and quickly filling it into the bottom of the pile hole, and then continuing to pour concrete until the entire pile hole is poured.
[0037] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.
Claims
1. A concrete pouring device for pile foundation construction, comprising an operating table (1), characterized in that: The operating table (1) is provided with a positioning hole (4), a casting conduit (2) is arranged in the positioning hole (4), and an extension tube (3) is arranged above the casting conduit (2), the casting conduit (2) and the extension tube (3) are provided with a same quick-installation module (6) outside, and a leveling and stabilizing module (7) is provided on the operating table (1), and the leveling and stabilizing module (7) is located between the operating table (1) and the quick-installation module (6), a pipe diameter adjustment module (5) is provided outside the casting conduit (2), and the pipe diameter adjustment module (5) is located below the operating table (1), and the bottom of the operating table (1) is fixedly connected to a plurality of circumferentially equidistantly distributed universal wheels (8), and the bottom of the operating table (1) is fixedly connected to a plurality of circumferentially equidistantly distributed hydraulic rods (9), and the output ends of the hydraulic rods (9) are fixedly connected to equalizing plates (10).
2. A concrete pouring equipment for pile foundation construction according to claim 1, characterized in that: The pipe diameter adjustment module (5) comprises a fixed sleeve (501), the outside of the casting conduit (2) is fixedly connected to the fixed sleeve (501), the outside of the fixed sleeve (501) is fixedly connected to a mounting seat (502), a plurality of movable grooves (503) equidistantly distributed around the circumference are provided on the upper side of the mounting seat (502), a slider (504) is slidably connected in each of the movable grooves (503), and a short shaft (505) is fixedly connected to the upper side of each of the sliders (504), and three guide grooves (513) equidistantly distributed around the circumference are provided on the mounting seat (502).
3. A concrete pouring equipment for pile foundation construction according to claim 2, characterized in that: The fixed sleeve (501) is movably connected to a rotating frame (506) on the outside, the inner wall of the rotating frame (506) is slidably connected to the outside of the mounting seat (502), a plurality of arc grooves (507) equidistantly distributed around the circumference are provided on the rotating frame (506), the inner walls of the plurality of arc grooves (507) are respectively slidably connected to the outside of a plurality of short shafts (505), and the upper side of the mounting seat (502) is provided with three circular notches (508) equidistantly distributed around the circumference, the inner walls of the circular notches (508) are fixedly connected to drive motors (509), the output ends of the drive motors (509) are connected to drive gears (510) via couplings, and the drive gears (510) are located inside the rotating frame (506).
4. A concrete pouring equipment for pile foundation construction according to claim 3, characterized in that: The inner wall of the rotating frame (506) is provided with an annular groove (511), an inner gear ring (512) is fixedly connected in the annular groove (511), and the three driving gears (510) are all meshed with the inner gear ring (512). The bottom inner wall of the movable groove (503) is provided with a strip groove (514), and a connecting rod (517) is slidably connected in the strip groove (514). The slider (504) and the connecting rod (517) are fixedly connected on opposite sides in the same movable groove (503). The inner wall of the fixed sleeve (501) is fixedly connected with a plurality of bosses (519) distributed equidistantly around the circumference, and the outer side of the bosses (519) is movably connected with an adjustment plate (519). (515), the inner wall of the fixed sleeve (501) is fixedly connected with a plurality of circumferentially equidistantly distributed bosses (523), the bosses (523) are each provided with a notch, a thin shaft is fixedly connected in the notch, the outside of the thin shaft is movably connected with an adjustment plate (516), the side of the adjustment plate (516) close to the fixed sleeve (501) is in contact with the sides of the two adjacent adjustment plates (515) away from the fixed sleeve (501), the outside of the thin shaft is surrounded by a torsion spring (524), one end of the torsion spring (524) is fixedly connected to the outside of the adjustment plate (516) on the same side, and the other end is fixedly connected to the outside of the boss (523) on the same side.
5. A concrete pouring equipment for pile foundation construction according to claim 4, characterized in that: The fixed sleeve (501) is fixedly connected to the outside with a plurality of circumferentially equidistant supports, and the supports are movably connected to the outside with a rotating rod (518), and the connecting rod (517) and the rotating rod (518) on the same side are movably connected on the side opposite to each other, and the end of the rotating rod (518) away from the connecting rod (517) is fixedly connected to a fixed block (522), and the plurality of adjustment plates (515) are provided with a strip opening (520) on the side close to the fixed sleeve (501), and the strip opening (520) is slidably connected with a movable block (521), and the plurality of movable blocks (521) are movably connected to the side opposite to the plurality of fixed blocks (522).
6. The concrete pouring equipment for pile foundation construction according to claim 1, characterized in that: The quick-install module (6) comprises an annular fixing member (601), the inner wall of the annular fixing member (601) is fixedly connected to the outside of the casting conduit (2), an annular notch (602) is provided on the upper side of the annular fixing member (601), a contact gasket (603) is slidably connected inside the annular notch (602), a spring 1 (604) is fixedly connected to the bottom of the contact gasket (603) on the side opposite to the inner wall of the annular notch (602), and an engaging annular member (605) is provided on the upper side of the contact gasket (603).
7. A concrete pouring equipment for pile foundation construction according to claim 6, characterized in that: The inner wall of the interlocking annular component (605) is fixedly connected to the outside of the extension tube (3), the outside of the interlocking annular component (605) is slidably connected to the inner wall of the annular notch (602), and the inner wall of the annular notch (602) is provided with two locking grooves (606) equidistantly distributed around the circumference, the inner walls of the locking grooves (606) are both clamped with circular pins (607), the opposite sides of the two circular pins (607) are both fixedly connected to the outside of the interlocking annular component (605), and the inner wall of the annular notch (602) is provided with a plurality of mud discharge holes (608) equidistantly distributed around the circumference.
8. The concrete pouring equipment for pile foundation construction according to claim 1, characterized in that: The leveling and stabilizing module (7) comprises a supporting plate (701), wherein the supporting plate (701) is located above the operating table (1), and the bottom of the supporting plate (701) is provided with three semicircular grooves with equal circumference distances, and the inner walls of the semicircular grooves are fixedly connected to rotating ball seats (706), and the operating table (1) is provided with three circular holes with equal circumference distances, and threaded rods (705) are arranged in the circular holes, and the upper sides of the threaded rods (705) located on the same side are fixedly connected to the outside of the rotating ball seats (706).
9. The concrete pouring equipment for pile foundation construction according to claim 8, characterized in that: The threaded rod (705) is provided with a limit gear (707) on the outside, the bottom of the limit gear (707) is movably connected to the upper side of the operating table (1), the threaded rod (705) is provided with a knob (711) on the outside, the knob (711) on the threaded rod (705) on the same side is fixedly connected to the side opposite to the limit gear (707), and the limit gear (707) is provided with an annular locking piece (708) on the outside, the inner wall of the annular locking piece (708) is fixedly connected to a rack (710), and the rack (711) is fixedly connected to the inner wall of the rack (710). 710) are all engaged with the limit gear (707), a positioning block (709) is arranged inside the annular locking member (708), the positioning block (709) is fixedly connected to the side opposite to the operating table (1), the outside of the positioning block (709) is slidably connected to the inner wall of the annular locking member (708), the side of the positioning block (709) away from the limit gear (707) is fixedly connected to a return spring (712), and one end of the return spring (712) and the original proportional positioning block (709) is fixedly connected to the inner wall of the annular locking member (708).
10. The concrete pouring equipment for pile foundation construction according to claim 9, characterized in that: The upper side of the support plate 1 (701) is fixedly connected to the support plate 2 (702), and the upper side of the support plate 2 (702) is fixedly connected to two symmetrical clamp rods (703), and the opposite sides of the two clamp rods (703) are clamped with the bottom of the annular fixing member (601), and the upper side of the support plate 2 (702) is movably connected to two symmetrical hydraulic rods 2 (704), and the output ends of the two hydraulic rods 2 (704) are movably connected to the sides of the two clamp rods (703) away from the annular fixing member (601).