System and method for evaluating state of model before balance in design process

By designing a pre-balance state evaluation system including basic information definition, project status feedback, model balance state feedback and project board module, the problem of inefficient tracking of traditional models is solved, and the progress state of the whole ship model balance is realized. Real-time monitoring and control have improved work efficiency and design quality.

CN119476910APending Publication Date: 2025-02-18SHANGHAI WAIGAOQIAO SHIP BUILDING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411424089.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-12
Publication Date
2025-02-18

AI Technical Summary

Technical Problem

Traditional model balanced state tracking is inefficient in ship design and construction, increasing management and communication costs, especially when the model balanced area division and division of labor of large cruise ships are relatively complex.

Method used

Design a model pre-balanced state evaluation system, including basic information definition module, project status feedback evaluation module, model balanced state feedback module and project board module, through these modules, model balanced type, balanced area, departmental major, evaluation project and whether It involves professional definitions, as well as the functions of project status feedback, model balance status feedback and project boards, to realize real-time monitoring and control of the progress status of the whole ship model balance.

Benefits of technology

Through this system, the progress of model balance can be accurately presented, problems and project delays can be avoided, model quality can be ensured, project progress can be controlled as a whole, work efficiency can be improved, and management and communication costs can be reduced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119476910A_ABST
    Figure CN119476910A_ABST
Patent Text Reader

Abstract

The invention discloses a system for evaluating the state of a model before balance in a design process, and the system comprises a basic information definition module which is used for defining a model balance type, a balance region, a department specialty, an evaluation project, and whether the specialty is involved or not; the project state feedback evaluation module is used for automatically generating each professional evaluation list of a certain region under different balance types according to the basic information definition module, and the principal of each modeling region feeds back the current state of an inspection project point according to the actual situation; the model balance state feedback module is used for making important balance node plan completion time according to the construction plan and the modeling plan, and holding a feedback progress according to an actual model balance conference; and the project billboard module is used for displaying the model balance progress state of all the areas of the whole ship through the model management matrix according to the plan and actual feedback under each balance area. The invention further discloses a method for evaluating the state of the model before balance in the design process. The design efficiency and the design quality are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a system and method for evaluating the state of a model before equilibrium in a design process. Background Art

[0002] The shipbuilding industry is complex and has a long construction cycle. There are many technical checkpoints and processes in the design and modeling process. Among them, the digitalization of model balance status assessment management is crucial. The traditional model balance status tracking is solved through meetings and Excel offline communication. Various professional designers are gathered together through large and small meetings to check the models one by one and communicate and coordinate the opinions generated. In particular, the model balance area division and division of labor of large cruise ships are more detailed than those of civil ships and marine engineering, so there are more areas to be balanced and more issues to be communicated. The traditional model greatly reduces work efficiency and increases management and communication costs.

[0003] Therefore, a system and method for evaluating the state of a model before equilibrium in a design process are provided. Summary of the invention

[0004] The purpose of the present invention is to overcome the existing defects and provide a system and method for evaluating the state of a model before equilibrium in a design process, thereby improving the design efficiency and design quality.

[0005] The technical solution to achieve the above purpose is:

[0006] A system for evaluating a model before equilibrium during a design process according to one embodiment of the present invention comprises:

[0007] Basic information definition module, used to define model balance type, balance area, department specialty, assessment items and whether specialty is involved;

[0008] A project status feedback and evaluation module is used to automatically generate a professional evaluation list for a certain area under different balance types according to the basic information definition module, and the person in charge of each modeling area feedbacks the current status of the project point according to the actual situation;

[0009] Model balance status feedback module, used to formulate the planned completion time of important balance nodes according to the construction plan and modeling plan, and to hold feedback progress according to the actual model balance meeting;

[0010] The project dashboard module is used to display the model balancing progress status of all areas of the ship through the model management matrix according to the plan and actual feedback in each balancing area, and to control the full-process time management of each node of the model balancing.

[0011] Preferably, in the basic information definition module,

[0012] Model balance type definition: define three important balance nodes, namely the first model balance assessment, the model balance assessment before drawing, and the background balance assessment;

[0013] Balance area definition: The ship is divided into 91 balance areas according to the schematic diagram;

[0014] Department and specialty definition: define the departments and specialties involved in the entire ship by project, including 7 departments and 24 specialties;

[0015] Definition of evaluation items: Each professional will sort out and define the items that need to be checked before balancing different types of models according to their different division of labor;

[0016] Whether it involves professional definition: Each profession shall provide feedback on whether the work content of all balancing areas is related to the profession based on the division of labor in the modeling plan and define the leading profession. The leading profession shall coordinate the communication among the involved professions, the preparation of preliminary matters and the resolution of routine problems encountered in the balancing process.

[0017] Preferably, in the project status feedback evaluation module, the project status includes three states: involved, not involved, and completed. The regional balance manager gives the model balance status assessment result based on the project status evaluated by professional feedback, clarifies the balance status and reasons, and selects whether to obtain no balance, obtain balance, balance with problems, or postpone balance.

[0018] Preferably, in the project status feedback evaluation module, when the evaluation project status is updated, color highlighting is used to remind the person in charge to pay attention to the status change, and then determine whether the model balance status needs to be re-evaluated.

[0019] Preferably, in the model equilibrium state feedback module, if the actual completion time is later than the planned completion time, it is highlighted.

[0020] A method for evaluating a model before equilibrium during a design process according to a second aspect of the present invention comprises:

[0021] Step S1, configuring the model balance type by project;

[0022] Step S2, dividing the balancing areas that need to be balanced according to project needs, and defining whether each discipline in different areas is involved in the work of the balancing area, and defining the evaluation items of each discipline;

[0023] Step S3, according to the configured model balancing type, dividing the balancing areas to be balanced and defining each professional assessment project to form assessment projects under each balancing area, and feedback the assessment project status according to the actual situation before the model is balanced;

[0024] Step S4, formulate the planned completion time of important balancing nodes according to the construction plan and modeling plan, and hold a balancing meeting to feedback the progress according to the actual model;

[0025] Step S5, based on the planned and actual feedback in each balancing area, the model management matrix is ​​used to display the model balancing progress status of all areas of the entire ship, and the full-process time management of each node of the model balancing is controlled.

[0026] Preferably, in step S1, the model balance type includes three important balance nodes, namely the first model balance evaluation, the model balance evaluation before outputting the drawing, and the background balance evaluation.

[0027] Preferably, in step S2, each professional assessment project is to sort out the project points that need to be checked before balancing different types of models according to different divisions of labor.

[0028] Preferably, in step S3, the assessment project status includes three states: involved, not involved, and completed, which provides a basis for judging the pre-balance status assessment for the person in charge of the regional model balance, and chooses to obtain balance, balance with problems, or postpone balance based on feedback from each professional office.

[0029] The beneficial effects of the present invention are as follows: based on the demand for improving the design quality of ship products, the present invention realizes the control of model balance status through time management of the entire process of each node of model balance, takes planning as the starting point and reality as the basis, accurately presents the progress of the current model balance, thereby avoiding model balance problems and project delays, ensuring model quality, and controlling the project progress as a whole. The management matrix diagram intuitively and in real time displays the control and tracking of the model balance plan, while saving time for collecting data and complex statistical work, and improving work efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0030] Figure 1 It is a module diagram of a system for evaluating the state of a model before equilibrium in a design process of the present invention;

[0031] Figure 2 It is a flow chart of a method for evaluating the state of a model before equilibrium in a design process of the present invention;

[0032] Figure 3 is a schematic diagram of defining a partial equilibrium region in the present invention;

[0033] Figure 4 It is a schematic diagram of some departments and corresponding specialties defined in the present invention;

[0034] Figure 5 It is a schematic diagram of the evaluation items corresponding to some of the majors defined in the present invention;

[0035] Figure 6 It is a schematic diagram of whether the work content of all balance areas is related to the profession according to the division of labor of some professions in the present invention according to the modeling plan;

[0036] Figure 7 is a schematic diagram of the model equilibrium state evaluation in the present invention;

[0037] Figure 8 It is a schematic diagram of the feedback of the equilibrium state of the model in the present invention;

[0038] Fig. 9 It is a schematic diagram of the equilibrium state dashboard of the model in the present invention. DETAILED DESCRIPTION

[0039] The technical solution of the present invention will be described clearly and completely below in conjunction with the accompanying drawings. In the description of the present invention, it should be noted that the terms "center", "up", "down", "left", "right", "vertical", "horizontal", "inside", "outside" and the like indicate directions or positional relationships based on the directions or positional relationships shown in the accompanying drawings, which are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as a limitation on the present invention. In addition, the terms "first", "second", and "third" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance.

[0040] The present invention will be further described below in conjunction with the accompanying drawings.

[0041] like Figure 1 As shown, a system for evaluating the state of a model before balance in a design process includes: a basic information definition module 1, a project state feedback evaluation module 2, a model balance state feedback module 3 and a project dashboard module 4.

[0042] Basic information definition module 1 is used to define the model balance type, balance area, department specialty, assessment items and whether a specialty is involved.

[0043] Specifically, in the basic information definition module 1,

[0044] Model balance type definition: define three important balance nodes, namely the first model balance evaluation, the model balance evaluation before drawing, and the background balance evaluation, as shown in Table 1 below;

[0045] Task Main work stage First model balance assessment Layout and process inspection of main system models After modeling is completed Model balance assessment before drawing Layout of main system models and process confirmation After opening reinforcement and opinion processing Background Balance Assessment Coordinated arrangement of hotel areas and decoration After the hotel drawings are released

[0046] Table 1

[0047] Balance area definition: According to the schematic diagram, the ship is divided into 91 balance areas. Some balance areas are as follows: Figure 3 As shown;

[0048] Department and specialty definition: Define the departments and specialties involved in the whole ship by project, including 7 departments and 24 specialties. Some departments and corresponding specialties are as follows: Figure 4As shown;

[0049] Definition of evaluation items: Each discipline sorts out and defines the items that need to be checked before balancing different types of models according to different divisions of labor. The evaluation items corresponding to some disciplines are as follows: Figure 5 As shown;

[0050] Whether it involves professional definition: Each major will provide feedback on whether the work content of all balancing areas is related to the major according to the division of labor in the modeling plan and define the leading major. Some majors will provide feedback on whether the work content of all balancing areas is related to the major according to the division of labor in the modeling plan. Figure 6 As shown, the lead professional needs to coordinate the communication between the professionals, the preparation of preliminary matters and the resolution of routine problems encountered in the balance.

[0051] The project status feedback evaluation module 2 is used to automatically generate the professional evaluation list of a certain area under different balance types according to the basic information definition module 1. The person in charge of each modeling area will feedback the current status of the project point according to the actual situation, such as Figure 7 shown.

[0052] Specifically, in the project status feedback evaluation module 2, the project status includes three states: involved, not involved, and completed. The regional balance manager gives the model balance status assessment result based on the project status evaluated by the professional feedback, clarifies the balance status and reasons, and selects whether to obtain balance, obtain balance, balance with problems, or postpone balance.

[0053] Specifically, in the project status feedback evaluation module 2, when the evaluation project status is updated, color highlighting is used to remind the person in charge to pay attention to the status change, and then determine whether the model balance status needs to be re-evaluated.

[0054] Model balance status feedback module 3 is used to formulate the planned completion time of important balance nodes according to the construction plan and modeling plan, and to hold feedback progress according to the actual model balance meeting, such as Figure 8 shown.

[0055] Specifically, in the model equilibrium state feedback module 3, if the actual completion time is later than the planned completion time, it is highlighted.

[0056] Specifically, in the model balance status feedback module 3, the design plan controller formulates a model balance plan at the beginning of the project according to the production and construction plan, and defines the planned time for the first model balance, balance before drawing, and background balance into the system. The actual completion time will be defined into the system for each completed balance.

[0057] Project dashboard module 4 is used to display the progress of model balancing in all areas of the ship through the model management matrix according to the planned and actual feedback in each balancing area, and to control the full-process time management of each node of model balancing, such as Fig. 9 shown.

[0058] like Figure 2 As shown, a method for evaluating the state of a model before equilibrium in a design process includes:

[0059] Step S1, configure the model balance type by project.

[0060] Specifically, the model balance type includes three important balance nodes, namely the first model balance evaluation, the model balance evaluation before drawing, and the background balance evaluation.

[0061] Step S2, divide the balance areas that need to be balanced according to project needs, define whether each discipline under different areas is involved in the work of the balance area, and define the evaluation items for each discipline.

[0062] Specifically, each professional assessment project is to sort out the project points that need to be checked before balancing different types of models according to different divisions of labor.

[0063] Step S3, according to the configured model balancing type, divide the balancing areas to be balanced and define each professional assessment project to form assessment projects under each balancing area, and feedback the assessment project status according to the actual situation before the model is balanced.

[0064] Specifically, the assessment project status includes three states: involved, not involved, and completed. It provides the person in charge of the model balance in this area with a basis for judging the status assessment before balancing, and chooses to obtain balance, balance with problems, or postpone balance based on the feedback from each professional office.

[0065] Step S4, formulate the planned completion time of important balancing nodes according to the construction plan and modeling plan, and hold a balancing meeting to feedback the progress according to the actual model.

[0066] Specifically, the design plan controller formulates a model balance plan at the beginning of the project based on the production and construction plan, and defines the planned time for the first model balance, balance before drawing, and background balance into the system. The actual completion time of each balance is defined into the system, and the balance areas whose completion time is later than the planned time are highlighted in color to enable the administrator to grasp the progress of the project process.

[0067] Step S5, based on the planned and actual feedback in each balancing area, the model management matrix is ​​used to display the model balancing progress status of all areas of the entire ship, and the full-process time management of each node of the model balancing is controlled.

[0068] The above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit the same. Although the present invention has been described in detail with reference to the above embodiments, those skilled in the art should understand that the technical solutions described in the above embodiments may still be modified, or some or all of the technical features may be replaced by equivalents. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the scope of the technical solutions of the embodiments of the present invention.

Claims

1. The model pre-equilibrium state evaluation system in the design process is characterized by: include: Basic information definition module, used to define model balance type, balance area, department specialty, assessment items and whether specialty is involved; The project status feedback evaluation module is used to automatically generate the professional evaluation list of a certain area under different balance types according to the basic information definition module, and the person in charge of each modeling area feedbacks the current status of the project point according to the actual situation; Model balance status feedback module, used to formulate the planned completion time of important balance nodes according to the construction plan and modeling plan, and to hold feedback progress according to the actual model balance meeting; The project dashboard module is used to display the model balancing progress status of all areas of the ship through the model management matrix according to the plan and actual feedback in each balancing area, and to control the full-process time management of each node of the model balancing.

2. The system for evaluating the state of a model before equilibrium in a design process according to claim 1, characterized in that: In the basic information definition module, Model balance type definition: define three important balance nodes, namely the first model balance assessment, the model balance assessment before drawing, and the background balance assessment; Balance area definition: The ship is divided into 91 balance areas according to the schematic diagram; Department and specialty definition: define the departments and specialties involved in the entire ship by project, including 7 departments and 24 specialties; Definition of evaluation items: Each professional will sort out and define the items that need to be checked before balancing different types of models according to their different division of labor; Whether it involves professional definition: Each profession shall provide feedback on whether the work content of all balancing areas is related to the profession based on the division of labor in the modeling plan and define the leading profession. The leading profession shall coordinate the communication among the involved professions, the preparation of preliminary matters and the resolution of routine problems encountered in the balancing process.

3. The system for evaluating the state of a model before equilibrium in a design process according to claim 1, characterized in that: In the project status feedback evaluation module, the project status includes three states: involved, not involved, and completed. The regional balance manager gives the model balance status assessment result based on the project status evaluated by the professional feedback, clarifies the balance status and reasons, and selects whether to obtain the balance, obtain the balance, balance with problems, or postpone the balance.

4. The system for evaluating the state of a model before equilibrium in a design process according to claim 1, characterized in that: In the project status feedback assessment module, when the assessment project status is updated, color highlighting is used to remind the person in charge to pay attention to the status change, and then determine whether the model balance status needs to be re-assessed.

5. The system for evaluating the state of a model before equilibrium in a design process according to claim 1, characterized in that: In the model equilibrium state feedback module, if the actual completion time is later than the planned completion time, it is highlighted.

6. A method for evaluating the state of a model before equilibrium in a design process, characterized by comprising: Step S1, configuring the model balance type by project; Step S2, dividing the balancing areas that need to be balanced according to project needs, and defining whether each discipline in different areas is involved in the work of the balancing area, and defining the evaluation items of each discipline; Step S3, according to the configured model balancing type, dividing the balancing areas to be balanced and defining each professional assessment project to form assessment projects under each balancing area, and feedback the assessment project status according to the actual situation before the model is balanced; Step S4, formulate the planned completion time of important balancing nodes according to the construction plan and modeling plan, and hold a balancing meeting to feedback the progress according to the actual model; Step S5, based on the planned and actual feedback in each balancing area, the model management matrix is ​​used to display the model balancing progress status of all areas of the entire ship, and the full-process time management of each node of the model balancing is controlled.

7. The method for evaluating the state of a model before equilibrium in a design process according to claim 6, characterized in that: In step S1, the model balance type includes three important balance nodes, namely the first model balance evaluation, the model balance evaluation before drawing, and the background balance evaluation.

8. The method for evaluating the state of a model before equilibrium in a design process according to claim 6, characterized in that: In step S2, each professional assessment project is to sort out the project points that need to be checked before balancing different types of models according to different divisions of labor.

9. The method for evaluating the state of a model before equilibrium in a design process according to claim 6, characterized in that: In step S3, the assessment project status includes three states: involved, not involved, and completed, which provides the person in charge of the regional model balance with a basis for judging the pre-balance status assessment and, based on the feedback from each professional office, chooses to obtain balance, balance with problems, or postpone balance.