Multi-stage energy consumption high-altitude falling object intercepting and buffering device and early warning method

By designing a multi-stage energy-consuming high-altitude fall object interception and buffering device, using the first- and second-level buffering mechanisms to intercept the fall object, and equipped with early warning methods, the existing protection performance is solved, and more effective high-altitude material fall prevention is achieved, reducing the risk of safety accidents.

CN119593601APending Publication Date: 2025-03-11SHANGHAI BAOYE GRP CORP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411525490.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-30
Publication Date
2025-03-11

AI Technical Summary

Technical Problem

The protective performance of high-altitude materials in existing construction construction is insufficient, making it difficult to effectively intercept and buffer fallen objects with large kinetic energy, which poses safety hazards.

Method used

A multi-stage energy-consuming high-altitude fall object interception buffer device is designed, including two load-bearing units, two layers of anti-fall mesh and steel cables. The fall object is intercepted through the first and second-stage buffer mechanisms, and an early warning method is provided to monitor and alarm the displacement of the guide rails.

Benefits of technology

It significantly improves the interception range and effect of high-altitude fallen objects, can effectively deal with falling objects with different kinetic energy, reduce the risk of falling objects at high-altitude, provide more reliable safety guarantees for construction, and reduce the occurrence of safety accidents.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119593601A_ABST
    Figure CN119593601A_ABST
Patent Text Reader

Abstract

The invention provides a multi-stage energy consumption high-altitude falling object intercepting and buffering device and an early warning method, and relates to the technical field of building construction. The device comprises two parallel bearing units arranged in a spaced mode, each bearing unit is composed of a guide rail, a damping spring and I-shaped steel, and the guide rails are connected with the I-shaped steel through the damping springs. A first anti-falling gauze element is arranged between the two guide rails, a second anti-falling gauze element parallel to the first anti-falling gauze element and a plurality of steel cables used for bearing are arranged between the two I-shaped steel, and the steel cables are arranged at intervals in the extending direction of the I-shaped steel. The two-stage anti-falling structure has obvious advantages, enlarges the interception range, can effectively cope with falling objects with different kinetic energies, and greatly reduces the danger of the falling objects from high altitudes. Compared with a traditional single-stage anti-falling structure, a more reliable safety guarantee is provided for personnel and equipment below a building, and the anti-falling structure has extremely high practicability in building construction and use.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of building construction, and in particular to a multi-level energy-consuming high-altitude falling object interception and buffering device and an early warning method. Background Art

[0002] Fall prevention of high-altitude materials in construction is extremely important. It is a series of measures implemented in construction scenarios to prevent materials from accidentally falling from heights. During the construction process, if materials at high altitudes, such as steel pipes, formwork, tools, etc., fall, it is very likely to cause serious damage to the construction workers, pedestrians and equipment below. Therefore, fall prevention control needs to be implemented from many aspects. First, scientifically plan the material stacking area to ensure that the materials are stacked neatly and firmly away from the edges, and fix the materials that are easy to roll and slide. Second, during the transportation and lifting of materials, strictly follow the standard operation, use qualified lifting equipment and slings, tightly bundle the materials, and control the lifting speed and height. At the same time, set up protective railings, covers or safety nets at the edges and openings of the building to prevent materials from falling from these locations. In addition, safety education and training for construction personnel should be strengthened to improve their safety awareness and operating specifications, jointly ensure the safety of high-altitude materials in construction, and reduce the hazards caused by falling risks.

[0003] Setting up protective structures at the edges and openings of buildings is one of the commonly used anti-falling methods in construction. The protective structure under the existing technology is mainly composed of brackets and anti-falling mesh, which can intercept some falling materials to a certain extent. However, when materials fall and the impact force is large, the materials will pass through the anti-falling mesh and continue to fall, which may cause safety accidents in serious cases. This is because the strength of the anti-falling mesh is limited and it is difficult to withstand a large impact force. This situation fully highlights the problem of poor protective performance of existing protective structures.

[0004] The harm caused by falling materials from high altitudes is huge. It not only threatens the lives of construction workers, but also may cause serious damage to construction projects, affecting the progress and quality of construction. If the problem of poor protection performance of existing protective structures cannot be solved in time, safety hazards in construction will always exist, which may cause major safety accidents at any time, causing irreparable losses to enterprises and society. Therefore, it is necessary to find an effective solution as soon as possible to improve the performance of protective structures and ensure the safety of construction. Summary of the invention

[0005] The purpose of the present invention is to provide a high-altitude falling object interception and buffering device and an early warning method with a multi-stage energy consumption, aiming to solve the technical problems in the above-mentioned background technology.

[0006] The technical solution of the present invention is achieved in this way:

[0007] In the first aspect, the technical solution of the present application provides a high-altitude falling object interception and buffering device with multi-level energy consumption, comprising:

[0008] The bearing unit comprises a guide rail, a shock absorbing spring and an I-beam, wherein the guide rail and the I-beam are arranged in parallel and at intervals, and the shock absorbing spring is arranged between the guide rail and the I-beam to reduce shock between the guide rail and the I-beam;

[0009] There are two load-bearing units, the two load-bearing units are arranged in parallel and at intervals, the guide rails of the two load-bearing units are located in a first horizontal plane, the I-beams of the two load-bearing units are located in a second horizontal plane, and the first horizontal plane is parallel to the second horizontal plane;

[0010] A first anti-falling screen is arranged between the two guide rails;

[0011] A second anti-falling screen parallel to the first anti-falling screen, disposed between the two I-beams; and

[0012] A steel cable disposed between the two I-beams for supporting the second anti-falling screen;

[0013] Among them, the above-mentioned steel cable and the above-mentioned first anti-falling mesh are respectively located on both sides of the above-mentioned second anti-falling mesh, and the number of the above-mentioned steel cables is multiple, and the multiple steel cables are arranged at intervals along the extension direction of the above-mentioned I-beam.

[0014] Based on the first aspect, a further technical solution is that the two guide rails are both equipped with electric wheels, and the two electric wheels are commonly connected with a connecting rod;

[0015] Among them, one end of the above-mentioned first anti-falling gauze is arranged on the first end part of the above-mentioned guide rail, and the other end is wound around the above-mentioned connecting rod.

[0016] Based on the first aspect, a further technical solution is that the guide rail is provided with a limit column for limiting the movement of the electric wheel toward the second end of the guide rail.

[0017] Based on the first aspect, a further technical solution is that a first connecting bolt is provided at the first end of any of the above guide rails;

[0018] A positioning and mounting piece is disposed at the first end of any of the above-mentioned I-beams, and the above-mentioned positioning and mounting piece is disposed with a second connecting bolt.

[0019] Based on the first aspect, a further technical solution is that there are multiple shock-absorbing springs, and the multiple shock-absorbing springs are arranged at intervals along the extension direction of the guide rail.

[0020] Based on the first aspect, a further technical solution is that the steel cable is detachably arranged on the I-beam.

[0021] Based on the first aspect, a further technical solution is to further include a processor and a displacement detector that cooperate with each other, and the above-mentioned displacement detector is used to monitor the vertical displacement of the outermost end of the second end of the above-mentioned guide rail.

[0022] In a second aspect, an embodiment of the present application provides an early warning method for a high-altitude falling object interception and buffering device with a multi-level energy consumption, comprising the following steps:

[0023] Based on the displacement detector, the vertical displacement ω of the outermost end of the second end of the guide rail is obtained. A ;

[0024] The processor obtains data ω A , and the data ω A Compare with its internal preset threshold S;

[0025] If A If it is greater than or equal to S, an alarm will be triggered based on the preset alarm.

[0026] Based on the second aspect, a further technical solution is that the threshold value inside the processor

[0027] Where λ is the length of the guide rail.

[0028] Compared with the prior art, the technical solution of the present invention has at least the following advantages or beneficial effects:

[0029] In view of the first aspect, the present application proposes a multi-stage energy-consuming high-altitude falling object interception and buffering device, which is mainly used for the exterior of buildings, and its core function is to receive falling objects from buildings. In the actual installation process, ensure that the I-beam and the guide rail are firmly connected to the building, and the guide rail is located above the I-beam. When a material falls from a high altitude, the falling object will first contact the first anti-falling gauze. At this time, through the mutual cooperation of the first anti-falling gauze and the shock-absorbing spring, a primary buffering of the falling object can be achieved. If the kinetic energy of the falling object is small, the falling object will be intercepted on the first anti-falling gauze, thereby preventing it from continuing to fall and causing harm. However, if the kinetic energy of the falling object is large and passes through the first anti-falling gauze, the falling object will continue to fall and contact the second anti-falling gauze. In this case, through the coordinated cooperation of the second anti-falling gauze and the steel cable, a secondary buffering of the falling object can be achieved, so that the falling object is finally intercepted on the second anti-falling gauze. Compared with the traditional single-stage anti-falling structure, the double-stage anti-falling structure proposed in this application has obvious advantages. It greatly increases the interception range and can more effectively deal with falling objects of different kinetic energy. This design greatly reduces the danger of falling objects from high altitudes and provides more reliable safety protection for personnel and equipment under the building. In the actual construction and use process, it has extremely high practicality, can effectively reduce safety accidents caused by falling objects from high altitudes, and provide strong support for safe production in the construction industry.

[0030] Regarding the second aspect, the present application proposes an early warning method for a multi-level energy-consuming high-altitude falling object interception and buffer device. The method can monitor the displacement of the guide rail, and once the displacement of the guide rail is too large, an alarm will be issued in time. This makes it easier for staff to maintain and repair the interception and buffer device. It has the function of early warning of danger, can issue a warning before potential problems occur, greatly reduce the probability of safety accidents, and provide strong protection for building safety. BRIEF DESCRIPTION OF THE DRAWINGS

[0031] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required for use in the embodiments are briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present invention and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without creative work.

[0032] Figure 1 This is a schematic structural diagram of a high-altitude falling object interception and buffering device with multiple energy consumption according to an embodiment of the present invention;

[0033] Figure 2 This is a schematic structural diagram of a multi-stage energy-consuming high-altitude falling object interception and buffer device according to an embodiment of the present invention, in which the first anti-falling gauze and the second anti-falling gauze are removed.

[0034] Icon: 1- first anti-falling mesh, 2- guide rail, 3- electric wheel, 4- connecting rod, 5- second anti-falling mesh, 6- I-beam, 7- shock-absorbing spring, 8- limiting column, 9- steel cable. DETAILED DESCRIPTION

[0035] Example 1

[0036] Please refer to Figure 1 and Figure 2 The embodiment of the present application provides a multi-stage energy-consuming high-altitude falling object interception and buffering device, which is mainly composed of a bearing unit, a first anti-falling screen 1, a second anti-falling screen 5 and a steel cable 9. The bearing unit includes a guide rail 2, a shock-absorbing spring 7 and an I-beam 6. The guide rail 2 is parallel to the I-beam 6 and is arranged at intervals. The shock-absorbing spring 7 is installed between the guide rail 2 and the I-beam 6, and plays a shock-absorbing role between the guide rail 2 and the I-beam 6. The number of bearing units is two, and the two bearing units are parallel and arranged at intervals. The guide rails 2 of the two bearing units are in a first horizontal plane together, and the I-beams 6 of the two bearing units are in a second horizontal plane together, and the first horizontal plane and the second horizontal plane are parallel to each other. The first anti-falling screen 1 is arranged between the two guide rails 2. The second anti-falling screen 5 parallel to the first anti-falling screen 1 is arranged between the two I-beams 6. In addition, a steel cable 9 for supporting the second anti-falling screen 5 is also provided between the two I-beams 6. The steel cable 9 and the first anti-falling screen 1 are respectively located on both sides of the second anti-falling screen 5. There are multiple steel cables 9, which are arranged at intervals along the extension direction of the I-beam 6. Such a structural design can achieve multi-level energy dissipation buffering through the synergistic effect of different components when falling objects occur, effectively intercept falling objects, and reduce the harm caused by falling objects.

[0037] The present application proposes a multi-level energy-consuming high-altitude falling object interception and buffering device, which is mainly used for the exterior of buildings, and its core function is to receive falling objects from buildings. In the actual installation process, it is ensured that the I-beam 6 and the guide rail 2 are firmly connected to the building, and the guide rail 2 is located above the I-beam 6. When a material falls from a high altitude, the falling object will first contact the first anti-falling gauze 1. At this time, through the mutual cooperation of the first anti-falling gauze 1 and the shock-absorbing spring 7, a primary buffering of the falling object can be achieved. If the kinetic energy of the falling object is small, the falling object will be intercepted on the first anti-falling gauze 1, thereby preventing it from continuing to fall and causing harm. However, if the kinetic energy of the falling object is large and passes through the first anti-falling gauze 1, the falling object will continue to fall and contact the second anti-falling gauze 5. In this case, through the coordinated cooperation of the second anti-falling gauze 5 and the steel cable 9, a secondary buffering of the falling object can be achieved, so that the falling object is finally intercepted on the second anti-falling gauze 5. Compared with the traditional single-stage anti-fall structure, the double-stage anti-fall structure proposed in this application has obvious advantages. It greatly increases the interception range and can more effectively deal with falling objects with different kinetic energy. This design greatly reduces the danger of falling objects from high altitudes and provides more reliable safety protection for personnel and equipment under the building. In the actual construction and use process, it has extremely high practicality, can effectively reduce safety accidents caused by falling objects from high altitudes, and provide strong support for safe production in the construction industry.

[0038] In some embodiments of the present invention, the two guide rails 2 are both equipped with electric wheels 3, and the two electric wheels 3 are commonly connected with a connecting rod 4;

[0039] Among them, one end of the above-mentioned first anti-falling gauze is arranged on the first end part of the above-mentioned guide rail 2, and the other end is wound around the above-mentioned connecting rod 4.

[0040] In the above embodiment, when the guide rail 2 is installed, its first end is connected to the building, and the second end extends to the outside of the building. When the first anti-falling screen 1 is laid, the connecting rod 4 is driven by the electric wheel 3 to move toward the second direction of the guide rail 2. Since the connecting rod 4 can rotate with the electric wheel 3, the first anti-falling screen 1 wrapped on the connecting rod 4 can be automatically laid between the two guide rails 2. This method effectively replaces the traditional manual laying, greatly reduces the safety risks during the construction process, and significantly improves the safety of the device during construction. When the first anti-falling screen 1 needs to be replaced, the electric wheel 3 is moved toward the first end of the guide rail 2, and the operator removes the old anti-falling screen on the connecting rod 4, and replaces the new anti-falling screen before laying it. Among them, the connecting rod 4 is designed to be cylindrical, so as to better wrap the first anti-falling screen 1.

[0041] In some embodiments of the present invention, the guide rail 2 is provided with a limiting column 8 for limiting the movement of the electric wheel 3 toward the second end of the guide rail 2 .

[0042] In the above embodiment, the design of the limiting column 8 plays a role in limiting the electric wheel 3, which can prevent the electric wheel 3 from sliding too far on the guide rail 2 and slipping off the second end of the guide rail 2. At the same time, the distance R from the limiting column 8 to the first end of the guide rail 2 depends on the height H of the guide rail 2 to the top of the building, specifically: when 2m≤H is less than or equal to 5m, R is 3m; 5m<H≤15m, R is 4m; 15m<H≤30m, R is 5m; when H>30m, R is 6m.

[0043] Specifically, another limiting column 8 is provided at the first end of the guide rail 2 to prevent the electric wheel 3 from slipping on the first end.

[0044] In some embodiments of the present invention, a first connecting bolt is provided at the first end of any of the guide rails 2;

[0045] A first end portion of any of the above-mentioned I-beams 6 is provided with a positioning and mounting piece, and the above-mentioned positioning and mounting piece is provided with a second connecting bolt.

[0046] In the above embodiment, the building structure is provided with a screw hole adapted to the above first connecting bolt, and the first connecting bolt can realize the quick connection or disassembly of the guide rail 2 and the building structure. The building structure is provided with a screw hole adapted to the second connecting bolt, and the cooperation of the second connecting bolt and the positioning mounting plate can realize the quick connection or disassembly of the I-beam 6 and the building structure.

[0047] Preferably, when installing the I-beam 6, it should be ensured that the I-beam 6 is slightly raised upward (toward the top of the building), and it is strictly forbidden for the I-beam 6 to tilt downward.

[0048] In some embodiments of the present invention, there are multiple damping springs 7 , and the multiple damping springs 7 are arranged at intervals along the extension direction of the guide rail 2 .

[0049] In the above embodiment, the design of multiple shock-absorbing springs 7 makes the interception and buffering effect of the present application better.

[0050] In some embodiments of the present invention, the steel cable 9 is detachably mounted on the I-beam 6. When the steel cable 9 is damaged, the steel cable 9 can be easily replaced.

[0051] In some embodiments of the present invention, a processor and a displacement detector that cooperate with each other are also included. The displacement detector is used to monitor the vertical displacement of the outermost end of the second end of the guide rail 2.

[0052] Example 2

[0053] Please refer to Figure 1 and Figure 2The embodiment of the present application provides an early warning method for a high-altitude falling object interception and buffering device with a multi-level energy consumption, comprising the following steps:

[0054] Based on the displacement detector, the vertical displacement ω of the outermost end of the second end of the guide rail 2 is obtained. A ;

[0055] Processor gets dataω A , and the data ω A Compare with its internal preset threshold S;

[0056] If A If it is greater than or equal to S, an alarm will be triggered based on the preset alarm.

[0057] This application proposes an early warning method for a multi-level energy-consuming high-altitude falling object interception and buffer device. This method can monitor the displacement of the guide rail, and once the displacement of the guide rail is too large, an alarm will be issued in time. This makes it easier for staff to maintain and repair the interception and buffer device. It has the function of early warning of danger, can issue a warning before potential problems occur, greatly reduce the probability of safety accidents, and provide strong protection for building safety.

[0058] In some embodiments of the present invention, the threshold value inside the processor

[0059] Wherein, λ is the length of the guide rail 2.

[0060] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A multi-level energy-consuming high-altitude falling object interception and buffering device, characterized in that: include: A bearing unit comprises a guide rail (2), a shock absorbing spring (7) and an I-beam (6), wherein the guide rail (2) and the I-beam (6) are arranged in parallel and at intervals, and the shock absorbing spring (7) is arranged between the guide rail (2) and the I-beam (6) to reduce shock between the guide rail (2) and the I-beam (6); There are two load-bearing units, the two load-bearing units are arranged in parallel and at intervals, the guide rails (2) of the two load-bearing units are located in a first horizontal plane, the I-beams (6) of the two load-bearing units are located in a second horizontal plane, and the first horizontal plane is parallel to the second horizontal plane; A first anti-falling gauze net (1) is arranged between the two guide rails (2); a second anti-falling gauze (5) parallel to the first anti-falling gauze (1), and arranged between the two I-beams (6); and A steel cable (9) disposed between the two I-beams (6) for supporting the second anti-falling gauze (5); The steel cable (9) and the first anti-falling gauze (1) are respectively located on both sides of the second anti-falling gauze (5), and there are multiple steel cables (9), which are arranged at intervals along the extension direction of the I-beam (6).

2. A multi-stage energy-consuming high-altitude falling object interception and buffering device according to claim 1, characterized in that: The two guide rails (2) are both equipped with electric wheels (3), and the two electric wheels (3) are commonly connected with a connecting rod (4); Wherein, one end of the first anti-falling gauze net (1) is arranged on the first end portion of the guide rail (2), and the other end is wound around the connecting rod (4).

3. A multi-stage energy-consuming high-altitude falling object interception and buffering device according to claim 2, characterized in that: The guide rail (2) is provided with a limiting column (8) for limiting the movement of the electric wheel (3) towards the second end of the guide rail (2).

4. The multi-stage energy-consuming high-altitude falling object interception and buffering device according to claim 1 is characterized in that: A first connecting bolt is provided at the first end of any one of the guide rails (2); A first end portion of any of the I-beams (6) is provided with a positioning mounting piece, and the positioning mounting piece is provided with a second connecting bolt.

5. A multi-stage energy-consuming high-altitude falling object interception and buffering device according to claim 4, characterized in that: The number of the shock absorbing springs (7) is multiple, and the multiple shock absorbing springs (7) are arranged at intervals along the extension direction of the guide rail (2).

6. The multi-stage energy dissipation high-altitude falling object interception and buffering device according to claim 1 is characterized in that: The steel cable (9) is detachably mounted on the I-beam (6).

7. A multi-stage energy-consuming high-altitude falling object interception and buffering device according to any one of claims 1 to 6, further comprising a processor and a displacement detector that cooperate with each other, wherein the displacement detector is used to monitor the vertical displacement of the outermost end of the second end of the guide rail (2).

8. An early warning method based on the multi-level energy consumption high-altitude falling object interception and buffering device according to claim 7, characterized in that: The following steps are involved: The vertical displacement ω of the outermost end of the second end of the guide rail (2) is obtained based on the displacement detector. A ; The processor obtains data ω A , and the data ω A Compare with its internal preset threshold S; If A If it is greater than or equal to S, an alarm will be triggered based on the preset alarm.

9. The early warning method of the multi-level energy consumption high-altitude falling object interception and buffering device according to claim 8 is characterized in that: The processor internal threshold Here, λ is the length of the guide rail (2).