Simple and convenient construction method for exhaust passage of large roof thermal insulation layer
By using wooden squares and fine stones on the roof insulation layer, the problems of delayed construction period, workers' operation hazards and exhaust duct blockage in the prior art are solved, and construction costs savings, safety hazards and quality improvement are achieved.
Patent Information
- Application Number
- CN202510015375.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-01-06
- Publication Date
- 2025-03-14
AI Technical Summary
During the construction of the existing technology, plastic pipes need to be purchased separately and large-area rotary processing is carried out, resulting in delays in construction periods, hazards in workers' operations and problems of exhaust duct blockage.
Wooden squares and fine stones are used instead of plastic pipes. By laying wooden squares on the insulation layer and forming spacer grooves therebetween, fine stones are laid to achieve water and vapor circulation.
It saves construction costs, reduces safety hazards, avoids exhaust duct blockage, and improves construction efficiency and quality.
Smart Images

Figure CN119616151A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, in particular to a simple construction method for an exhaust duct of a large roof insulation layer. Background Art
[0002] Roof structures are divided into upright roofs and inverted roofs. The upright roof consists of a structural layer, a leveling layer, an insulation layer, a mortar leveling layer, and a waterproof layer from bottom to top. The insulation layer is set below the waterproof layer. In order to discharge the water vapor accumulated between the insulation layer and the mortar leveling layer, thereby preventing the membrane from cracking, bulging, and other damages, a criss-cross exhaust duct must be set in the insulation layer of the upright roof.
[0003] The common exhaust duct is the left-pipe exhaust duct, such as Figure 1 , Figure 2 As shown, this type of exhaust duct 2 is arranged in a mesh within the roof boundary 1, and it is necessary to purchase a φ25-φ32 plastic pipe 8. In order to ensure that the exhaust duct can effectively collect water vapor, it is also necessary to use a hand drill on site to drill dense small holes on the exhaust duct to form a collection flower pipe; This type of exhaust duct requires the purchase of pipe materials separately. When performing large-area hole-turning processing, the construction period may be delayed and work may be delayed. The drilling workload of the collection flower pipe is large. During on-site processing, workers may be easily injured when operating flashlights. At the same time, the waterproof leveling layer applied above the insulation layer is mortar, which has fluidity and will enter the exhaust duct through the small holes, causing the exhaust duct to be blocked. Therefore, a simple construction method for the exhaust duct of the large roof insulation layer is proposed. Summary of the invention
[0004] The present invention aims to solve the above problems, thereby providing a simple construction method for the exhaust duct of a large roof insulation layer.
[0005] The present invention solves the above-mentioned problem by adopting the following technical solution: A simple construction method for the exhaust duct of a large roof insulation layer is carried out according to the following steps: Step 1: After the construction of the structural layer and the leveling layer is completed, the wood planks are arranged according to the designed exhaust duct line. The wood planks can be made of the remaining wood from the main structure construction stage; Step 2: construct the insulation layer and mortar leveling layer; lay the insulation board on the leveling layer, clamp the insulation board tightly around the wood, and after laying the insulation board, spread the mortar over a large area to make the mortar leveling layer; the insulation board clamps the wood to prevent the wood from moving when spreading the mortar; Step 3: Dig out the wood to form a spacing groove; after the mortar leveling layer has finally set and reached 5MPa, dig out the wood; when digging out the wood, avoid damaging the edges and corners of the mortar and protect the finished product; Step 4: Lay fine stones in the spacing grooves; spread the fine stones in the spacing grooves on site. After laying the fine stones, scrape the upper surface flat to the same height as the mortar leveling layer; Step 5: Construction of waterproof layer and air vents; Lay waterproof membrane over a large area. Before laying the waterproof membrane, evenly distribute several ventilation pipes above the spacing grooves.
[0006] Furthermore, before the waterproof layer is constructed, an additional waterproof layer is laid on top of the fine stones, and the width of the additional waterproof layer is greater than the width of the spacing groove to prevent the fine stones from breaking the main waterproof layer.
[0007] Furthermore, in step one, the size of the wood should be determined in advance, with the width equal to the designed width of the exhaust duct and the height exceeding the designed elevation of the mortar leveling layer.
[0008] Furthermore, in step 4, the particle size of the fine stone should be 10-25 mm to ensure the porosity.
[0009] Compared with the prior art, the present invention adopting the above technical solution has the following outstanding features: Use existing materials on site to save construction costs. Fine stone and wood are common materials on the construction site, and there is enough surplus material, so there is no need to purchase plastic round pipes separately and spend construction expenses.
[0010] Eliminate the need for on-site electric drill drilling, reducing safety hazards. Use fine stones in the spacing groove instead of collecting flower tubes, do not use a flashlight to operate, and reduce the risk of injury to workers when using electric drills.
[0011] Avoid blockage of the exhaust duct and improve the quality of construction. Fine stones are used to fill the interval grooves. There are a lot of gaps between the fine stones, which can meet the needs of water vapor circulation; at the same time, the fine stones play a role in supporting the additional waterproof layer, and the additional waterproof layer plays a role in preventing the fine stones from breaking the main waterproof layer.
[0012] The on-site operation is simple and convenient, which significantly improves the project efficiency. On-site workers pour fine stones into the spacing grooves and flatten the upper surface, and waterproof workers cover the upper surface with roll materials. The construction is fast, simple and effective. It can shorten the original on-site construction time by more than 90% and significantly reduce the on-site installation workload. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1 Schematic diagram of exhaust duct distribution structure; Figure 2 for Figure 1 Schematic diagram of the AA section structure; Figure 3 This is a schematic diagram of the wooden arrangement structure of an embodiment of the present invention; Figure 4 This is a schematic diagram of the construction structure of the thermal insulation layer and the mortar leveling layer according to an embodiment of the present invention; Figure 5This is a schematic diagram of the structure after the wood is removed according to an embodiment of the present invention; Figure 6 This is a schematic diagram of the structure of fine stone paving according to an embodiment of the present invention; Figure 7 This is a schematic diagram of the structure of laying the additional waterproof layer according to an embodiment of the present invention; Figure 8 This is a schematic diagram of the overall structure of the embodiment of the present invention after construction is completed; Marked in the figure are: roof boundary 1, exhaust duct 2, structural layer 3, leveling layer 4, insulation layer 5, mortar leveling layer 6, waterproof layer 7, wooden square 8, spacing groove 9, fine stone 10, waterproof additional layer 11, ventilation pipe 12, plastic pipe 13. DETAILED DESCRIPTION
[0014] The present invention will be further described below in conjunction with embodiments, the purpose of which is only to provide a better understanding of the content of the present invention. Therefore, the examples given do not limit the protection scope of the present invention.
[0015] A simple construction method for the exhaust duct of a large roof insulation layer is carried out according to the following steps: Step 1: See Figure 1 , Figure 3 After the construction of the structural layer 3 and the leveling layer 4 is completed, the wood blocks 8 are arranged according to the designed exhaust duct 2 line. The wood blocks 8 can be made of the remaining wood in the main structure construction stage; Step 2: See Figure 4 , construct the insulation layer 5 and the mortar leveling layer 6; lay the insulation board on the leveling layer 4, tightly clamp the insulation board to the wood 8, after laying the insulation board, spread the mortar over a large area to make the mortar leveling layer 6; the insulation board clamps the wood 8 to prevent the wood 8 from moving when spreading the mortar; Step 3: See Figure 5 , dig out the wood square 8 to form a spacing groove 9; after the mortar leveling layer 6 is finally set and reaches 5MPa, dig out the wood square 8; when digging out the wood square 8, prevent the mortar edges and corners from being damaged and protect the finished product; Step 4: See Figure 6 , paving fine stones 10 in the spacing grooves 9; spreading the fine stones 10 in the spacing grooves 9 on site, after paving the fine stones 10, scraping the upper surface flat to the same height as the mortar leveling layer 6; Step 5: See Figure 8 , waterproof layer 7 and air vent construction; large area paving waterproof membrane, waterproof membrane paving before, above the spacing groove 9 evenly distributed a number of ventilation pipes 12; ventilation pipe 12 top is inverted J shape.
[0016] For further information, see Figure 7 , Figure 8Before the construction of the waterproof layer 7, a waterproof additional layer 11 is laid on the fine stones 10. The width of the waterproof additional layer 11 is greater than the width of the spacing groove 9 to prevent the fine stones 10 from breaking the main waterproof layer 7; the bottom of the ventilation pipe 12 penetrates the waterproof additional layer 11 and is inserted into the spacing groove 9.
[0017] For further information, see Figure 3 , Figure 4 In step one, the size of the wooden square 8 must be mastered in advance, the width is equal to the designed width of the exhaust duct 2, and the height exceeds the designed elevation of the mortar leveling layer 6.
[0018] Furthermore, in step 4, the particle size of the fine stone 10 is preferably 10-25 mm to ensure the porosity.
[0019] Use existing materials on site to save construction costs. Fine stone and wood are common materials on the construction site, and there is enough surplus material, so there is no need to purchase plastic round pipes separately and spend construction expenses.
[0020] Eliminate the need for on-site electric drill drilling, reducing safety hazards. Use fine stones in the spacing groove instead of collecting flower tubes, do not use a flashlight to operate, and reduce the risk of injury to workers when using electric drills.
[0021] Avoid blockage of the exhaust duct and improve the quality of construction. Fine stones are used to fill the interval grooves. There are a lot of gaps between the fine stones, which can meet the needs of water vapor circulation; at the same time, the fine stones play a role in supporting the additional waterproof layer, and the additional waterproof layer plays a role in preventing the fine stones from breaking the main waterproof layer.
[0022] The on-site operation is simple and convenient, which significantly improves the project efficiency. On-site workers pour fine stones into the spacing grooves and flatten the upper surface, and waterproof workers cover the upper surface with roll materials. The construction is fast, simple and effective. It can shorten the original on-site construction time by more than 90% and significantly reduce the on-site installation workload.
[0023] The above description is only a preferred feasible embodiment of the present invention, and does not limit the scope of rights of the present invention. All equivalent changes made using the contents of the present invention specification and its drawings are included in the scope of rights of the present invention.
Claims
1. A simple construction method for the exhaust duct of a large roof insulation layer, characterized in that: Follow these steps: Step 1: After the construction of the structural layer and the leveling layer is completed, the wood planks are arranged according to the designed exhaust duct line. The wood planks can be made of the remaining wood from the main structure construction stage; Step 2: construct the insulation layer and mortar leveling layer; lay the insulation board on the leveling layer, clamp the insulation board tightly around the wood, and after laying the insulation board, spread the mortar over a large area to make the mortar leveling layer; clamp the wood around the insulation board to prevent it from moving when spreading the mortar; Step 3: Dig out the wood to form a spacing groove; after the mortar leveling layer has finally set and reached 5MPa, dig out the wood; when digging out the wood, avoid damaging the edges and corners of the mortar and protect the finished product; Step 4: Lay fine stones in the spacing grooves; spread the fine stones in the spacing grooves on site. After laying the fine stones, scrape the upper surface flat to the same height as the mortar leveling layer; Step 5: Construction of waterproof layer and air vents; Lay waterproof membrane over a large area. Before laying the waterproof membrane, evenly distribute several ventilation pipes above the spacing grooves.
2. A simple construction method for a large roof insulation layer exhaust duct according to claim 1, characterized in that: Before the construction of the waterproof layer, an additional waterproof layer is laid on top of the fine stones. The width of the additional waterproof layer is greater than the width of the spacing groove to prevent the fine stones from breaking the main waterproof layer.
3. The simple construction method of a large roof insulation layer exhaust duct according to claim 1 is characterized by: In step one, the size of the wood should be determined in advance. The width should be equal to the designed width of the exhaust duct, and the height should exceed the designed elevation of the mortar leveling layer.
4. A simple construction method for a large roof insulation layer exhaust duct according to claim 1, characterized in that: In step 4, the particle size of fine stone should be 10~25mm to ensure the porosity.