Fireproof insulation cotton exterior protection system for fixed drilling platforms
By adopting a fire-proof and thermal insulation cotton external protection system on the fixed drilling platform, combined with the coordinated cooperation of the fire-proof and thermal insulation cotton layer, wire mesh layer, deck dressing layer, interface agent layer and ceramic tile layer, the problem of insufficient wind resistance in traditional systems in harsh sea conditions is solved, achieving a more efficient fire-proof and thermal insulation and a simplified maintenance process, while reducing construction costs.
Patent Information
- Application Number
- CN202411967969.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-30
- Publication Date
- 2025-04-08
AI Technical Summary
The traditional fire-proof insulation cotton outer protection system lacks wind resistance under harsh sea conditions, resulting in the fire-proof insulation cotton outer protection system of the fixed drilling platform being vulnerable to damage, difficult to maintain and degraded performance.
A fire-proof insulation cotton outer protection system including a first fire-proof insulation cotton layer, a wire mesh layer, a deck dressing layer, an interface agent layer and a ceramic tile layer is adopted. Through the coordinated cooperation of these layers, the fire-proof insulation of the deck to the chamber area is realized, and the chamber area is arranged for indoor maintenance.
It achieves improving fire resistance and insulation performance under harsh sea conditions, simplifies the maintenance process, reduces construction costs, and reduces system wear through the outer tile layer.
Smart Images

Figure CN119777554A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of fireproofing and heat preservation of offshore platforms, and in particular to a fireproofing and heat preservation cotton outer protection system for a fixed drilling platform. Background Art
[0002] In the South China Sea and other sea areas, due to frequent typhoons and harsh marine environment, the fireproof and thermal insulation cotton outer protection system of the modules and living buildings on fixed drilling platforms is often damaged, resulting in maintenance difficulties and performance degradation. The traditional fireproof and thermal insulation cotton outer protection system cannot meet the requirements of use in harsh sea conditions due to its insufficient wind resistance. Summary of the invention
[0003] In order to overcome the deficiencies of the prior art, the purpose of the present invention is to provide a fireproof and heat-insulating cotton outer protection system for a fixed drilling platform, which has fireproof and heat-insulating properties and is also advantageous in reducing maintenance difficulty and construction costs.
[0004] To solve the above problems, the technical solution adopted by the present invention is as follows:
[0005] A fireproof and heat-insulating cotton outer protection system for a fixed drilling platform, comprising:
[0006] a deck having an upper surface having a chamber area for constructing the chamber;
[0007] A floating floor structure, the floating floor structure comprising a first fireproof and thermal insulation cotton layer, a metal wire mesh layer and a deck covering layer, the first fireproof and thermal insulation cotton layer being laid in the chamber area, the metal wire mesh layer being laid on the end surface of the first fireproof and thermal insulation cotton layer away from the upper surface, and the deck covering layer being arranged to cover the metal wire mesh layer;
[0008] an interface agent layer, provided on the end surface of the deck covering layer facing away from the metal wire mesh layer; and
[0009] The tile layer is laid on the end surface of the interface agent layer facing away from the deck covering layer.
[0010] In some possible implementations, the number of the first fireproof and heat-insulating cotton layers is at least two, and two adjacent first fireproof and heat-insulating cotton layers are spliced with staggered seams.
[0011] In some possible implementations, the metal mesh layer includes metal wires and a plurality of laid metal meshes, two adjacent metal meshes are overlapped, and the metal wires tightly bind the two adjacent metal meshes.
[0012] In some possible implementations, the overlapping distance between two adjacent metal wire meshes is 15-20 cm, and the mesh distance between the metal wire meshes is 15-20 cm.
[0013] In some possible implementations, the following further includes:
[0014] A fire wall structure, comprising a second fireproof and heat-insulating cotton layer and two corrugated walls arranged at intervals, wherein the corrugated walls are protrudingly installed in the chamber area, and the second fireproof and heat-insulating cotton layer is attached to the surface of one of the corrugated walls opposite to the other corrugated wall.
[0015] In some possible implementations, the deck has a lower surface disposed away from the upper surface, and the fireproof and heat-insulating cotton outer protection system further includes:
[0016] A third fireproof and heat-insulating cotton layer is attached to the lower surface, and a projection of the third fireproof and heat-insulating cotton layer on the deck is located outside the chamber area;
[0017] A plurality of support columns are laid, each of which is protrudingly installed on the lower surface and is arranged through the third fireproof and heat-insulating cotton layer;
[0018] A lining frame, fixed to an end of the support column away from the lower surface; and
[0019] At least two metal plates are installed on the lining frame, two adjacent metal plates are overlapped, and two rivets are used to connect the metal plate and the lining frame at the overlapped position of the metal plates.
[0020] In some possible implementations, a single rivet is used to connect the metal plate and the liner frame at the non-overlapping portion of the metal plate.
[0021] In some possible implementations, a glue layer is provided at the gap between two adjacent metal plates and at the gap between the metal plate and the lining frame for sealing.
[0022] In some possible implementations, the overlapping distance between two adjacent metal plates is greater than or equal to 20 mm.
[0023] In some possible implementations, the interface agent layer includes:
[0024] A first layer, attached to the deck covering layer, wherein the weight ratio of the interface agent to water is 1:5; and
[0025] The second layer is attached between the first layer and the tile layer. In the components of the second layer, the weight ratio of the interface agent to water is 1:3.
[0026] Compared with the prior art, the present invention has the following beneficial effects:
[0027] In the present application, the fireproof and heat-insulating properties of the deck corresponding to the chamber area are achieved through the coordinated cooperation of the first fireproof and heat-insulating cotton layer, the metal wire mesh layer, the deck dressing layer, the interface agent layer and the ceramic tile layer. In addition, the above structure is arranged in the chamber area, so that the above structure can be repaired indoors, thereby helping to reduce the interference of environmental factors and thus helping to reduce the difficulty of maintenance. In addition, the first fireproof and heat-insulating cotton layer can be effectively and stably protected through the coordinated cooperation of the metal wire mesh layer, the deck dressing layer, the interface agent layer and the ceramic tile layer 30, which helps to simplify the system structure and thus help to reduce the construction cost. In addition, the use of a ceramic tile layer on the outer layer helps to reduce system wear and tear, which also helps to reduce costs.
[0028] The present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] Figure 1 A schematic diagram of the structure of a deck, a floating floor structure and a tile layer provided in one embodiment of the present application;
[0030] Figure 2 for Figure 1 A cross-section of the floating floor structure shown;
[0031] Figure 3 A schematic diagram of a firewall structure provided in an embodiment of the present application;
[0032] Figure 4 Schematic diagram for installation of lining frame, deck, metal plate and perimeter wall;
[0033] Figure 5 It is a structural schematic diagram of the lining frame.
[0034] Description of Figure Numbers:
[0035] 10 - deck; 11 - upper surface; 12 - lower surface; 20 - floating floor structure; 21 - first fireproof insulation layer; 22 - wire mesh layer; 23 - deck dressing layer; 30 - tile layer; 40 - fire wall structure; 41 - second fireproof insulation layer; 42 - corrugated wall; 50 - support column; 60 - lining frame; 61 - rivet; 70 - metal plate. DETAILED DESCRIPTION
[0036] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.
[0037] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by those skilled in the art of the present invention. The terms used in the specification of the present invention herein are only for the purpose of describing specific embodiments and are not intended to limit the present invention.
[0038] The terms "first", "second", etc. in the specification and claims of this application and the above-mentioned drawings are used to distinguish different objects, rather than to describe a specific order. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions. It should be noted that when an element is referred to as "fixed to" another element, it can be directly on the other element or there can be a centered element. When an element is referred to as "connected to" another element, it can be directly connected to the other element or there can be a centered element. When an element is referred to as "arranged on" another element, it can be arranged on the other element or there can be a centered element.
[0039] One embodiment of the present application provides a fireproof and heat-insulating cotton outer protection system for a fixed drilling platform, hereinafter referred to as the fireproof and heat-insulating cotton outer protection system. Figure 1 and Figure 2 The fireproof heat-insulating wool outer protection system comprises a deck 10, a floating floor structure 20, an interface agent layer (not shown in the figure) and a tile layer 30. The floating floor structure 20 comprises a first fireproof heat-insulating wool layer 21, a metal wire mesh layer 22 and a deck covering layer 23.
[0040] The deck 10 has an upper surface 11, and the upper surface 11 has a chamber area for building a chamber. A first fireproof and heat-insulating wool layer 21 is laid in the chamber area. Exemplarily, the material of the first fireproof and heat-insulating wool layer 21 can be rock wool.
[0041] The metal mesh layer 22 is laid on the end face of the first fireproof and heat-insulating cotton layer 21 away from the upper surface 11. Exemplarily, the metal mesh layer 22 can be a steel mesh layer. Exemplarily, the specification of the metal mesh is: Ф5*150*150mm. The deck covering layer 23 is arranged to cover the metal mesh layer 22. Exemplarily, the components of the deck covering layer 23 can include AC-JIII type self-leveling deck covering and water. The mixing weight ratio of AC-JIII type self-leveling deck covering and clean water is: 1: (0.17-0.19). The interface agent layer is arranged on the end face of the deck covering layer 23 away from the metal mesh layer 22. The tile layer 30 is laid on the end face of the interface agent layer away from the deck covering layer 23. Exemplarily, the components of the interface agent layer can include at least one of putty powder, mortar or glue. Exemplarily, the tile layer 30 can use anti-slip tiles to further improve the anti-slip property.
[0042] The specific construction steps include: Step 1: Before the project construction, clean the room, clean the floor, polish the floor, and apply primer to the room floor. Step 2: Prepare the construction area by hoisting each layer of materials. Step 3: Lay and install the first fireproof and thermal insulation cotton layer 21 and check the effect. Step 4: Lay the metal mesh layer 22 on the first fireproof and thermal insulation cotton layer 21. Step 5: Cut the self-leveling deck dressing, use a mixer to stir the AC-JIII type deck dressing and water, and pour the dressing on the metal mesh layer 22 after stirring. After the dressing is leveled, use tools (defoaming roller, scraper) to remove bubbles and control the flatness. Step 6: After the deck dressing is constructed for 12 hours, use a small roller to evenly apply a layer of interface agent. The weight ratio of the interface agent to water is 1:5. After the interface agent is cured, use a small roller to evenly apply a layer of interface agent. The weight ratio of the interface agent to water is 1:3. Step 7: Laying, leveling, caulking and inspection of tile layer 30.
[0043] In the present application, the fireproof and heat-insulating properties of the deck 10 corresponding to the chamber area are achieved through the coordinated cooperation of the first fireproof and heat-insulating cotton layer 21, the metal mesh layer 22, the deck dressing layer 23, the interface agent layer and the ceramic tile layer 30. In addition, the above-mentioned structure is arranged in the chamber area, so that the above-mentioned structure can be repaired indoors, thereby helping to reduce the interference of environmental factors and thus helping to reduce the difficulty of maintenance. In addition, the first fireproof and heat-insulating cotton layer 21 can be effectively and stably protected through the coordinated cooperation of the metal mesh layer 22, the deck dressing layer 23, the interface agent layer and the ceramic tile layer 30, which helps to simplify the system structure and thus help to reduce the construction cost. In addition, the use of the ceramic tile layer 30 as the outer layer helps to reduce system wear and tear, which also helps to reduce costs.
[0044] In some embodiments, the number of first fireproof thermal insulation cotton layers 21 is at least two (two first fireproof thermal insulation cotton layers 21 are shown in the figure), and the two adjacent first fireproof thermal insulation cotton layers 21 are staggered and spliced, so as to increase the heat dissipation path to improve the thermal insulation effect. In addition, the staggered splicing is also beneficial to improve the support stability of the system in the plane, thereby also helping to increase the service life of the system to further help reduce the cost of use.
[0045] In some embodiments, the wire mesh layer 22 includes wires and a plurality of wire meshes, two adjacent wire meshes are overlapped, and the wires are used to bind the two adjacent wire meshes. The structure of the wire mesh layer 22 is convenient for construction and helps ensure the connection stability of the wire mesh layer 22.
[0046] In some embodiments, the overlap distance between two adjacent metal meshes is 15-20 cm, and the mesh distance between the metal meshes is 15-20 cm. The size of the mesh has the advantages of improving connection stability and reducing the amount of dressing to reduce costs.
[0047] In some embodiments, the deck covering layer 23 protrudes from the wire mesh layer 22 by at least 20 mm.
[0048] In some embodiments, reference Figure 3 , the fireproof and thermal insulation cotton outer protection system also includes a fire wall structure 40. The fire wall structure 40 includes a second fireproof and thermal insulation cotton layer 41 and two corrugated walls 42 arranged at intervals. The corrugated wall 42 is installed protrudingly in the chamber area. The second fireproof and thermal insulation cotton layer 41 is attached to the surface of one corrugated wall 42 relative to the other corrugated wall 42. Exemplarily, the second fireproof and thermal insulation cotton layer 41 can be fixed by insulation nails and a pressure cover. Exemplarily, the second fireproof and thermal insulation cotton layer 41 can be a rock wool layer. The construction of the fire wall structure is conducive to improving stability and wind resistance. And the structure of the fire wall structure is simple to help reduce construction costs.
[0049] In some embodiments, the second fireproof heat-insulating cotton layer 41 is attached to the raised area of the corrugated wall 42 .
[0050] In some embodiments, reference Figure 4 -5, the deck 10 has a lower surface 12 that is set away from the upper surface 11, and the fireproof thermal insulation cotton outer protection system also includes a third fireproof thermal insulation cotton layer (not shown in the figure), a plurality of laid support columns 50, a lining frame 60 and at least two metal plates 70. The third fireproof thermal insulation cotton layer is attached to the lower surface 12, and the projection of the third fireproof thermal insulation cotton layer on the deck 10 is located outside the chamber area. Exemplarily, the third fireproof thermal insulation cotton layer can be a rock wool layer. Exemplarily, the third fireproof thermal insulation cotton layer can be fixed by insulation nails and pressure covers. The gap near the third fireproof thermal insulation cotton layer can be taped with aluminum foil tape. Each support column 50 is protrudingly installed on the lower surface 12 and is set through the third fireproof thermal insulation cotton layer. Exemplarily, the support column 50 can be an angle steel structure. The lining frame 60 is fixed to one end of the support column 50 away from the lower surface 12. The metal plate 70 is installed on the lining frame 60, and two adjacent metal plates 70 are overlapped. Two rivets 61 are laid at the overlap of the metal plates 70 to connect the metal plate 70 and the lining frame 60. For example, the metal plate 70 can be a stainless steel plate. The use of double-row rivets 61 reinforcement in conjunction with the third fireproof insulation cotton layer, the support column 50, the lining frame 60 and the metal plate 70 is conducive to improving the structural strength, thereby improving the wind resistance and reliability.
[0051] In some embodiments, a single rivet 61 is used at the non-overlapping portion of the metal plate 70 to connect the metal plate 70 and the lining frame 60 , thereby helping to reduce costs.
[0052] In some embodiments, a glue layer is provided at the gap between two adjacent metal plates 70 and the gap between the metal plate 70 and the lining frame 60 for sealing.
[0053] In some embodiments, the overlapping distance between two adjacent metal plates 70 is greater than or equal to 20 mm, thereby facilitating improving the connection strength between different metal plates 70 .
[0054] In some embodiments, the interface agent layer includes a first layer and a second layer, the first layer is attached to the deck covering layer 23, and the weight ratio of the interface agent to water in the first layer is 1:5. The second layer is attached between the first layer and the tile layer 30. In the second layer, the weight ratio of the interface agent to water is 1:3. The structural setting of the interface agent layer is conducive to improving the construction convenience and the connection strength between different layers.
[0055] The above-mentioned embodiments are only preferred embodiments of the present invention and cannot be used to limit the scope of protection of the present invention. Any non-substantial changes and substitutions made by technicians in this field on the basis of the present invention shall fall within the scope of protection required by the present invention.
Claims
1. A fireproof and heat-insulating cotton outer protection system for a fixed drilling platform, characterized in that: include: a deck having an upper surface having a chamber area for constructing the chamber; A floating floor structure, the floating floor structure comprising a first fireproof and thermal insulation cotton layer, a metal wire mesh layer and a deck covering layer, the first fireproof and thermal insulation cotton layer being laid in the chamber area, the metal wire mesh layer being laid on the end surface of the first fireproof and thermal insulation cotton layer away from the upper surface, and the deck covering layer being arranged to cover the metal wire mesh layer; an interface agent layer, provided on the end surface of the deck covering layer facing away from the metal wire mesh layer; and The tile layer is laid on the end surface of the interface agent layer facing away from the deck covering layer.
2. The fireproof and heat-insulating cotton outer protection system according to claim 1, characterized in that: The number of the first fireproof and heat-insulating cotton layers is at least two, and two adjacent first fireproof and heat-insulating cotton layers are spliced with staggered seams.
3. The fireproof and heat-insulating cotton outer protection system according to claim 2, characterized in that: The metal wire mesh layer includes metal wires and a plurality of laid metal wire meshes, two adjacent metal wire meshes are overlapped, and the metal wires tightly bind the two adjacent metal wire meshes.
4. The fireproof heat insulation cotton outer protection system according to claim 3, characterized in that: The overlapping distance between two adjacent metal wire meshes is 15-20 cm, and the mesh distance between the metal wire meshes is 15-20 cm.
5. The fireproof heat insulation cotton outer protection system as described in any one of claims 1 to 4, characterized in that: Also includes: A fire wall structure, comprising a second fireproof and heat-insulating cotton layer and two corrugated walls arranged at intervals, wherein the corrugated walls are protrudingly installed in the chamber area, and the second fireproof and heat-insulating cotton layer is attached to the surface of one of the corrugated walls opposite to the other corrugated wall.
6. The fireproof heat insulation cotton outer protection system according to claim 5, characterized in that: The deck has a lower surface disposed away from the upper surface, and the fireproof and heat-insulating cotton outer protection system further includes: A third fireproof and heat-insulating cotton layer is attached to the lower surface, and a projection of the third fireproof and heat-insulating cotton layer on the deck is located outside the chamber area; A plurality of support columns are laid, each of which is protrudingly installed on the lower surface and is arranged through the third fireproof and heat-insulating cotton layer; A lining frame, fixed to an end of the support column away from the lower surface; and At least two metal plates are installed on the lining frame, two adjacent metal plates are overlapped, and two rivets are used to connect the metal plate and the lining frame at the overlapped position of the metal plates.
7. The fireproof heat insulation cotton outer protection system according to claim 6, characterized in that: A single rivet is used to connect the metal plate and the lining frame at the non-overlapping portion of the metal plate.
8. The fireproof heat insulation cotton outer protection system according to claim 6, characterized in that: A glue layer is provided at the gap between two adjacent metal plates and the gap between the metal plate and the lining frame for sealing.
9. The fireproof heat insulation cotton outer protection system according to claim 6, characterized in that: The overlapping distance between two adjacent metal plates is greater than or equal to 20 mm.
10. The fireproof heat insulation cotton outer protection system according to claim 1, characterized in that: The interface agent layer comprises: A first layer, attached to the deck covering layer, wherein the weight ratio of the interface agent to water is 1:5; and The second layer is attached between the first layer and the tile layer. In the components of the second layer, the weight ratio of the interface agent to water is 1:3.