Toilet partition wall construction method
By adopting overall construction and cast-in-place support technology, the problems of complex and high cost of traditional bathroom partition walls are solved, and higher integrity and stability are achieved, construction costs are reduced, and building structure safety is ensured.
Patent Information
- Application Number
- CN202510080222.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-01-19
- Publication Date
- 2025-04-22
AI Technical Summary
The construction process of traditional bathroom partition walls is complex, the integrity and stability are poor, and the cost is high, which affects the safety of the building structure.
The overall construction method is adopted to pour concrete through cast-in-place supporting formwork to reduce construction process and material costs, and improve the integrity and stability of the wall.
It reduces construction costs by 30%-40%, improves the integrity and stability of partition walls, ensures the safety of building structures, and shortens the construction cycle.
Smart Images

Figure CN119860085A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building partition walls, and in particular to a toilet partition wall construction method. Background Art
[0002] The main function of bathroom partition walls is to separate spaces and provide a certain degree of privacy protection, rather than bearing loads and the weight of building structures. Bathroom partition walls can be made into other structural forms, but they cannot be changed into load-bearing structural walls without authorization. If bathroom partition panels are made into load-bearing walls, it will not only increase the construction difficulty and cost, but also affect the overall structural safety of the building due to the change in its structural form, resulting in a decrease in the stability of the building and an increase in safety hazards.
[0003] Although the bathroom partition wall cannot be made into a load-bearing wall, in order to ensure the safety of the building structure, the bathroom partition wall is also required to have sufficient stability. The traditional bathroom partition wall structure includes a ground beam 1´ and a partition wall 2´. For the traditional bathroom partition wall structure, the method of first pouring the ground beam 1´ and then constructing the partition wall 2´ is adopted. The specific construction process steps of the ground beam 1´ include: first fixing the embedded steel bars 11´ on the working surface floor through the embedded steel bar process, then tying the connecting steel bars 12´ on the embedded steel bars 11´, and finally setting the template for concrete pouring; the specific construction process steps of the partition wall 2´ include: first installing a galvanized square tube 21´ on the ground beam 1´ (horizontally and longitudinally erected and fixed to form), then installing a fixing plate 22´ on both sides of the galvanized square tube 21´, and pulling a wire mesh 23´ on both sides of the fixing plate 22´, and finally painting cement mortar on the wire mesh 23´ to form the partition wall 2´.
[0004] The traditional construction process of bathroom partition walls is complicated, with poor integrity and stability, and high labor and material costs. Summary of the invention
[0005] At least one of the purposes of the present invention is to provide a bathroom partition wall construction method for overcoming the problems existing in the above-mentioned prior art. The construction method adopts an overall construction method to achieve one-time forming, and pouring is carried out through a cast-in-place formwork method during pouring, which not only reduces many tedious construction processes, but also reduces material costs and construction costs; improves the integrity and stability of the partition wall, and at the same time does not change the stress structure of the wall, thereby ensuring the safety of the building structure; the template products involved in bathroom partition walls of the same specifications are completed by modular prefabrication, which shortens the construction period and reduces the construction cost.
[0006] In order to achieve the above object, the technical solution adopted by the present invention includes the following aspects: A method for constructing a bathroom partition wall comprises the following construction steps: Step 1: Draw construction drawings of frame components; Step 2: Lay out and stake out on the floor slab of the working surface; Step 3, install the frame assembly within the basic surface line; Step 4: Install water and electricity embedded parts; Step 5: Install casting templates on both sides of the frame assembly, and connect and fix the casting templates to the frame assembly; Step 6: Install support members on the outer side of the casting formwork; Step 7: pour the concrete layer in the space between the inner side of the casting template and the frame assembly. When pouring, the concrete layer is poured in layers. The interval time of layer pouring is between 8-12 hours. The thickness of the first layer is more than 1m and does not exceed 2 / 3 of the height of the partition wall. Step 8: Remove the supports and casting formwork, and repair the holes in the wall.
[0007] Preferably, the step 1, drawing a layout diagram of a frame assembly including vertical bars and horizontal bars according to the size of the construction site, includes: Draw multiple vertical bars parallel to each other and perpendicular to the floor of the working surface, with the distance between two adjacent vertical bars being between 350-400mm; Draw multiple horizontal bars connected to the vertical bars, with the spacing between two adjacent horizontal bars being between 350-400mm.
[0008] Preferably, the step three of installing the frame assembly within the base line includes: According to the base line to be placed, select vertical poles with suitable specifications; Cut the vertical rod to a length close to the height of the bathroom partition wall, and open a plurality of circular holes along the length direction of the vertical rod; Select horizontal bars that match the vertical bar specifications and cut the horizontal bars to a length close to the width of the partition wall; Drill holes on the working surface floor and fix the corner brackets on the working surface floor; Weld the vertical rod to the angle bracket and remove the excess welding slag; Pass the horizontal rod through the corresponding round hole on the vertical rod one by one.
[0009] Preferably, when the angle brackets are fixedly connected to the working surface floor, two adjacent angle brackets are arranged relative to each other.
[0010] Preferably, the angle code adopts a three-leg angle code, including a main leg, and branch legs arranged on both sides of the main leg, the branch legs on both sides are symmetrically arranged, the main leg and the branch legs are an integrated structure, the main leg and the branch legs are both right-angled L-shaped, the first right-angled side of the main leg and the first right-angled side of the branch leg are arranged on one side of the same plane, the first right-angled side of the main leg is longer than the first right-angled side of the branch leg, the second right-angled side of the main leg and the second right-angled side of the branch leg are arranged on the other side of the same plane, and a gap is left between the second right-angled side of the main leg and the second right-angled side of the branch leg.
[0011] Preferably, the vertical rod is welded to the angle bracket, and during welding, the end of the vertical rod is fitted with the first right-angle side of the main leg and the second right-angle side of the main leg, and welding is performed at the fitting position.
[0012] Preferably, the step five, installing casting templates on both sides of the frame assembly, includes: cutting out casting templates corresponding to the size of the partition wall, and bolting the casting templates to the vertical rods with dovetail bolts.
[0013] Preferably, in step six, the support members are installed on the outer side of the casting formwork, and the support members on both sides are fastened and connected using through bolts.
[0014] Preferably, in step eight, the holes left by the through bolts and dovetail bolts are repaired by grouting, and then plastering is performed on the wall surface.
[0015] Preferably, the frame assembly is prefabricated in a factory by splicing horizontal bars and vertical bars to form an overall modular structure, and then installed as a whole after staking out and fixing the corner brackets on site.
[0016] In summary, due to the adoption of the above technical solution, the present invention has at least the following beneficial effects: 1. This application adopts an overall construction method, avoiding the construction process of first planting reinforcement, then pouring the ground beam, and finally constructing the partition part, reducing many cumbersome construction procedures, greatly reducing the construction labor cost, and avoiding the use of steel wire mesh with higher material cost for construction, reducing the overall construction cost by 30%-40%; 2. The construction method of bathroom partition walls adopts one-time forming, which improves the integrity and stability of the wall, and at the same time does not change the force structure of the wall, ensuring the safety of the building structure; the template products involved in bathroom partition walls of the same specifications are completed by modular prefabrication, which shortens the construction period and reduces the construction cost. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 It is a structural schematic diagram of an existing bathroom partition wall.
[0018] Figure 2It is a flow chart of the construction of a bathroom partition wall according to an exemplary embodiment of the present invention.
[0019] Figure 3 It is a schematic diagram of a cast-in-place structure of a bathroom partition wall according to an exemplary embodiment of the present invention.
[0020] Figure 4 Schematic diagram of the arrangement of angle codes according to an exemplary embodiment of the present invention.
[0021] Figure 5 It is a cross-sectional view of the completed bathroom partition wall of an exemplary embodiment of the present invention.
[0022] Figure 6 is a front view of an angle code according to an exemplary embodiment of the present invention.
[0023] Figure 7 is a top view of an angle code according to an exemplary embodiment of the present invention.
[0024] Markings in the figure: 1-frame assembly, 11-vertical bar, 12-cross bar, 2-casting formwork, 3-support, 4-concrete layer, 5-angle code, 51-main leg, 52-branch leg, 6-dovetail bolt, 7-through bolt, 1´-ground beam, 11´-embedded reinforcement, 12´-connecting reinforcement, 2´-partition wall, 21´-galvanized square tube, 22´-fixing plate, 23´-wire mesh. DETAILED DESCRIPTION
[0025] The present invention is further described in detail below in conjunction with the accompanying drawings and embodiments to make the purpose, technical solutions and advantages of the present invention more clearly understood. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention. Example
[0026] This exemplary embodiment describes a construction method for a cast-in-place structure of a bathroom partition wall. Figure 2 The construction flow chart shows that the frame components and casting templates of the same specification bathroom partition walls are completed by modular production and installation. Figure 3-5 , the construction method of the bathroom partition wall specifically includes the following steps: Step 1: Draw a construction drawing of the frame assembly 1. Draw a layout drawing of the frame assembly 1 including the vertical bars 11 and the horizontal bars 12 according to the size of the construction site, including: Draw a plurality of vertical bars 11 arranged side by side and perpendicular to the floor of the working surface, wherein the distance between two adjacent vertical bars 11 is between 350-400 mm, preferably 400 mm; Draw a plurality of cross bars 12 connected to the vertical bars 11, and the distance between two adjacent cross bars 12 is between 350-400 mm, preferably 400 mm; Step 2: Lay out and stake out on the floor slab of the working surface; Lay out the finished surface of the bathroom partition wall and lead it to the wall; Determine the base layer line by extrapolating inwards based on the size of the surface material; Step 3, installing the frame assembly 1 within the base line, including: According to the base surface line, select the vertical rod 11 with suitable specifications. The vertical rod 11 is preferably a galvanized square tube. The specific specifications are determined according to the size of the surface material, including 20mm×20mm, 25mm×25mm, 30mm×30mm, 40mm×40mm or 50mm×50mm. The wall thickness specifications are 1.0mm, 1.2mm, 1.5mm or 2.0mm, and the specification is preferably 30mm×30mm×1.5mm; Cut the vertical rod 11 to a length close to (or equal to) the height of the bathroom partition wall, with the error controlled within 10 mm, and open a plurality of circular holes along the length direction of the vertical rod 11; Select a crossbar 12 that matches the specifications of the vertical bar 11, and cut the crossbar 12 to a length close to (or equal to) the width of the partition wall, with the error controlled within 10 mm; Drill holes on the work surface floor and fix the corner bracket 5 on the work surface floor. When fixing and installing the corner bracket 5, two adjacent corner brackets 5 are arranged relative to each other to ensure the installation stability of the frame assembly 1, thereby ensuring the stability of the bathroom partition wall formed during the pouring process; the installed corner bracket 5 adopts a three-leg corner bracket, such as Figure 6-7 As shown, it includes a main leg 51 and branch legs 52 arranged on both sides of the main leg 51, the branch legs 52 on both sides are symmetrically arranged, the main leg 51 and the branch legs 52 are an integrated structure, the main leg 51 and the branch legs 52 are both right-angled L-shaped, including a first right-angled side and a second right-angled side, the first right-angled side of the main leg 51 and the first right-angled side of the branch leg 52 are arranged on the same plane side, the first right-angled side of the main leg 51 is longer than the first right-angled side of the branch leg 52, the second right-angled side of the main leg 51 and the second right-angled side of the branch leg 52 are arranged on the other side of the same plane, and a gap is left between the second right-angled side of the main leg 51 and the second right-angled side of the branch leg 52, which can ensure that when concrete is poured later, concrete can be accommodated between the main leg 51 and the branch leg 52, so that the legs are completely embedded in the concrete, thereby increasing the structural strength of the bathroom; The vertical rod 11 is welded to the angle bracket 5. During welding, the end of the vertical rod 11 is aligned with the first right angle side of the main leg 51 and the second right angle side of the main leg 51. The welding is performed at the aligned part to remove the excess welding slag. Pass the horizontal rod 12 through the circular hole 1 on the corresponding vertical rod 11 in sequence; Step 4: Install water and electricity embedded parts; Install the pre-buried water and electricity pipelines according to the water and electricity construction drawings and protect them to prevent concrete from entering the junction box when pouring concrete layer 4; Step 5: Install the casting template 2 on both sides of the frame assembly 1; Cut out a casting template 2 corresponding to the size of the partition wall, and bolt the casting template 2 to the vertical rod 11 using dovetail bolts 6; Step 6: Install the support member 3 on the outer side of the casting template 2; Install the support member 3 on the outer side of the casting formwork 2, and fasten the support members 7 on both sides with through bolts 7; Step 7, pouring a concrete layer 4 in the spacing space between the inner side of the casting template 2 and the frame assembly 1; When pouring the concrete layer 4, adopt layered pouring to avoid bursting of the mold making the base surface uneven and affecting the subsequent construction. The interval time of layered pouring is between 8-12 hours. The thickness of the first layer is more than 1m and does not exceed 2 / 3 of the height of the partition wall.
[0027] Step 8, dismantle the support member 3 and the casting formwork 2, and repair the holes on the wall; After the concrete layer 4 meets the structural strength requirements, the support member 3 and the casting formwork 2 are removed; The holes left by the through bolts 7 and the dovetail bolts 6 are repaired by grouting, and then the wall surface is plastered to prevent the frame assembly 1 from being exposed to the air and rusting during the later use of the partition wall, thereby affecting the service life of the wall.
[0028] The present embodiment also provides a method for installing the frame assembly 1. The frame assembly 1 is prefabricated in a factory by splicing the horizontal bars 12 and the vertical bars 11 to form an overall modular structure. The structure is then installed as a whole after the angle brackets 5 are fixed on site. This method can further improve the installation and construction efficiency of the frame assembly 1.
[0029] The above is only a detailed description of the specific implementation of the present invention, rather than a limitation of the present invention. Various substitutions, modifications and improvements made by those skilled in the relevant art without departing from the principle and scope of the present invention should be included in the protection scope of the present invention.
Claims
1. A method for constructing a bathroom partition wall, characterized in that: The construction steps include: Step 1, drawing a construction drawing of the frame assembly (1); Step 2: Lay out and stake out on the floor slab of the working surface; Step 3, installing the frame assembly (1) within the basic surface line; Step 4: Install water and electricity embedded parts; Step 5: installing the casting template (2) on both sides of the frame assembly (1), and connecting and fixing the casting template (2) to the frame assembly (1); Step 6: Install the support member (3) on the outer surface of the casting template (2); Step 7, pouring a concrete layer (4) in the spacing space between the inner side of the casting template (2) and the frame assembly (1), and pouring the concrete layer (4) in layers, with an interval of 8-12 hours between the layer pouring, and the thickness of the first layer being greater than 1m and not exceeding 2 / 3 of the height of the partition wall; Step eight, removing the support member (3) and the casting formwork (2), and repairing the holes on the wall.
2. A toilet partition wall construction method according to claim 1, characterized in that: The first step is to draw a layout diagram of a frame assembly (1) including vertical bars (11) and horizontal bars (12) according to the dimensions of the construction site, including: Draw a plurality of vertical bars (11) arranged side by side and perpendicular to the floor of the working surface, wherein the distance between two adjacent vertical bars (11) is between 350-400 mm; A plurality of horizontal bars (12) connected to the vertical bars (11) are drawn, and the spacing between two adjacent horizontal bars (12) is between 350-400 mm.
3. A toilet partition wall construction method according to claim 1, characterized in that: The step three, installing the frame assembly (1) within the base line, comprises: According to the alignment of the base layer to be placed, select a vertical rod (11) with suitable specifications; Cutting the vertical rod (11) to a length corresponding to the height of the toilet partition wall, and opening a plurality of circular holes along the length direction of the vertical rod (11); Select a horizontal bar (12) that matches the specifications of the vertical bar (11), and cut the horizontal bar (12) to a length corresponding to the width of the partition wall; Drill holes in the work surface floor and fix the corner brackets (5) to the work surface floor; Weld the vertical rod (11) to the angle bracket (5) and remove the welding slag; The horizontal rod (12) is passed through the circular holes 1 on the corresponding vertical rods (11) in sequence.
4. A toilet partition wall construction method according to claim 3, characterized in that: When the angle brackets (5) are fixedly connected to the work surface floor, two adjacent angle brackets (5) are arranged relative to each other.
5. A toilet partition wall construction method according to claim 3, characterized in that: The angle bracket (5) adopts a three-leg angle bracket, comprising a main leg (51) and branch legs (52) arranged on both sides of the main leg (51), the branch legs (52) on both sides are symmetrically arranged, the main leg (51) and the branch legs (52) are an integrated structure, the main leg (51) and the branch legs (52) are both right-angled L-shaped, the first right-angle side of the main leg (51) and the first right-angle side of the branch leg (52) are arranged on one side of the same plane, the first right-angle side of the main leg (51) is longer than the first right-angle side of the branch leg (52), the second right-angle side of the main leg (51) and the second right-angle side of the branch leg (52) are arranged on the other side of the same plane, and a gap is left between the second right-angle side of the main leg (51) and the second right-angle side of the branch leg (52).
6. A toilet partition wall construction method according to claim 3, characterized in that: When the vertical rod (11) is welded to the angle bracket (5), the vertical rod (11) is fitted with the first right-angle side of the main leg (51), and is also fitted with the second right-angle side of the main leg (51), and welding is performed at the fitted parts.
7. A toilet partition wall construction method according to any one of claims 1 to 6, characterized in that: The step five is to install the casting template (2) on both sides of the frame assembly (1), including: cutting out the casting template (2) corresponding to the size of the partition wall, and bolting the casting template (2) to the vertical rod (11) using dovetail bolts (6).
8. A toilet partition wall construction method according to any one of claims 1 to 6, characterized in that: In the sixth step, the support member (3) is installed on the outer side of the casting formwork (2), and the support members (3) on both sides are fastened and connected using through bolts (7).
9. A toilet partition wall construction method according to any one of claims 1 to 6, characterized in that: In the eighth step, the holes left by the through bolts (7) and the dovetail bolts (6) are repaired by grouting, and then plastering is performed on the wall surface.
10. A toilet partition wall construction method according to any one of claims 1 to 6, characterized in that: The frame assembly (1) is prefabricated in a factory by splicing the horizontal bars (12) and the vertical bars (11) to form an overall modular structure, and then the overall structure is installed on site after the angle brackets (5) are set out and fixed.