Reinforcing cage transfer mechanism track slab production line
By using truss structures and automated transfer equipment in the track slab production workshop, the safety hazards of transferring steel cages in confined working spaces have been solved, and automated and safe transfer of steel cages has been achieved.
Patent Information
- Application Number
- CN202510991527.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2025-07-18
- Publication Date
- 2026-11-17
- Estimated Expiration
- 2045-07-18
AI Technical Summary
The limited working space in the existing track slab production workshop makes it difficult for equipment to interfere and for personnel to avoid obstacles during the transfer of steel cages, posing a safety hazard.
A truss structure is used to form a transfer channel, which is combined with a steel cage transportation mechanism and a clamping and hoisting mechanism to realize the automated transfer of steel cages. The transfer channel at the top of the truss avoids equipment interference and difficulties in personnel avoidance.
It improves the safety and automation of the steel cage transfer process, eliminates equipment interference and personnel avoidance difficulties, and realizes fully automated operation.
Smart Images

Figure CN120621995B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of track slab production technology, and in particular to a track slab production line with a steel cage transfer mechanism. Background Technology
[0002] With the rapid development of high-speed railway construction in my country, track slabs, as a core component of ballastless track systems, have received increasing attention for their production processes and manufacturing technologies. Reinforcing cages, as a crucial structural element of track slabs, have undergone a development process in their transfer technology, evolving from manual handling to mechanized transfer, and then to automated transfer. Early reinforcing cage transfer relied primarily on manual labor combined with simple lifting equipment. However, with the expansion of track slab production scale and the increasing standardization requirements, specialized mechanized transfer equipment has gradually developed, continuously evolving towards intelligent and automated processes.
[0003] Currently, the rebar cage transfer technology in track slab production mainly employs a combination of overhead cranes and manual operation. Specifically, the rebar cage is delivered to the designated feeding area via transport vehicles or conveyor equipment. Then, operators use overhead cranes or lifting equipment to clamp and lift the rebar cage, transferring it from the feeding position to the mold or designated unloading position. During the transfer process, operators need to position, adjust, and monitor within the work area to ensure the rebar cage is accurately placed in the target location. The entire transfer process requires the coordinated operation of multiple processes, including positioning, clamping, lifting, moving, and placing.
[0004] However, due to the limited working space in the track slab production workshop, existing transfer equipment is prone to problems such as equipment interference and difficulty in personnel avoidance when operating in a narrow working area, which poses safety hazards during the transfer of steel cages. Summary of the Invention
[0005] The main objective of this invention is to propose a track slab production line for the transfer mechanism of steel cages, aiming to solve the technical problem that existing transfer equipment is prone to problems such as equipment interference and difficulty in personnel avoidance when operating in a narrow working area due to the limited working space in the track slab production workshop, which makes the transfer of steel cages a safety hazard.
[0006] To achieve the above objectives, in a first aspect, the present invention provides a steel cage transfer mechanism, comprising:
[0007] A truss, the top of which forms a transfer channel extending along a first horizontal direction, the two ends of which along the first horizontal direction form a feeding position and a discharging position, and a steel cage is placed at the feeding position;
[0008] A rebar cage transport mechanism, wherein the rebar cage is carried on the rebar cage, and the rebar cage transport mechanism is capable of transporting the rebar cage to the feeding position; and...
[0009] The clamping and hoisting mechanism includes a traveling component and a clamping component. The clamping component is mounted on the traveling component and is slidably engaged with the transfer channel. The traveling component can travel along the transfer channel, and the clamping component can descend to clamp the steel cage located at the feeding position. When the clamping and hoisting mechanism clamps the steel cage, the traveling component can drive the clamping component to transfer the steel cage along the transfer channel and place it at the unloading position.
[0010] In one embodiment, the steel cage transport mechanism includes:
[0011] A guide rail extends along a second horizontal direction to the feeding position, the second horizontal direction being perpendicular to the first horizontal direction;
[0012] A transport vehicle, mounted on the guide rail, capable of moving along the guide rail to the feeding position; and...
[0013] A rebar cage mounting component is installed on the top of the transport vehicle, and the rebar cage is mounted on the rebar cage.
[0014] In one embodiment, the steel cage mounting component includes:
[0015] A base, detachably connected to the top of the transport vehicle, and extending beyond the transport vehicle; and,
[0016] A mounting component is installed on top of the base, and the steel cage is mounted on the mounting component.
[0017] In one embodiment, there are multiple mounting components, all of which are grouped in pairs and spaced apart on the top of the base.
[0018] In one embodiment, each of the mounting components includes:
[0019] Multiple columns are spaced apart on the top of the base, and all the columns enclose each other to form a mounting space for mounting the steel cage. At least one pair of lifting blocks are provided on any two adjacent columns. Each pair of lifting blocks is located at the same elevation and supports and lifts the steel cage together.
[0020] In one embodiment, the lifting blocks are in multiple pairs, and the multiple pairs of lifting blocks are distributed at intervals along the height direction of the column to form a corresponding number of steel cage placement positions on the column.
[0021] In one embodiment, the gripping component includes:
[0022] Mounting plate, which is mounted on the walking component, has two pin holes spaced apart along the first horizontal direction at its bottom.
[0023] Two clamping plates are arranged side-by-side and rotatably inserted through two pin holes, respectively, so that both clamping plates are hinged to the mounting plate. Both clamping plates can rotate about their corresponding pins. Receiving grooves are recessed on the opposite sides of both clamping plates, and these receiving grooves are joined together to form receiving holes for accommodating the main rib. The end of each clamping plate away from the mounting plate is formed with a pointed tip.
[0024] An elastic reset member is connected between the two clamping plates, and the elastic reset member causes the two clamping plates to clamp the main rib.
[0025] In one embodiment, each of the two clamping plates has two interlocking arc-shaped toothed rings at one end near the mounting plate.
[0026] In one embodiment, one of the clamping plates is fixed to the corresponding pin, and the clamping component further includes a drive motor mounted on the mounting plate. The output shaft of the drive motor is connected to the pin fixed to the corresponding clamping plate to drive the output shaft to rotate and open the corresponding clamping plate and lower the steel cage.
[0027] Based on the same technical concept, in a second aspect, the present invention also proposes a track slab production line, comprising:
[0028] The steel cage transfer mechanism described in the first aspect; and,
[0029] A track slab casting and forming mechanism is provided, wherein a track slab casting and forming space is formed within the track slab casting and forming mechanism. The track slab casting and forming mechanism is installed at the feeding position. The transfer mechanism can clamp the reinforcing cage at the feeding position and transfer the reinforcing cage along the transfer channel and place it in the track slab casting and forming space, so as to form the track slab after pouring concrete in the casting and forming space.
[0030] The technical solution of this invention, by setting up a truss, a rebar cage transport mechanism, and a clamping and hoisting mechanism, achieves the following in use: A transfer channel is formed at the top of the truss, and feeding and unloading positions are spaced apart along a first direction within the truss, i.e., in the space below the truss, creating a transfer channel between the feeding and unloading positions. The rebar cage transport mechanism is installed on the transfer channel and can travel along it. The clamping and hoisting mechanism is installed on the rebar cage transport mechanism, and the rebar cage transport mechanism drives the clamping and hoisting mechanism to descend and clamp the rebar cage located at the feeding position. Furthermore, when the clamping and hoisting mechanism clamps the rebar cage, the traveling part... The device can drive the clamping and hoisting components to transfer the steel cage along the transfer channel and place it at the unloading position. This means that when hoisting and transferring the steel cage, the invention does not suffer from equipment interference or difficulties in personnel avoidance due to the limitations of the working environment, thus improving the safety of the track slab steel cage during the transfer process. At the same time, since the entire transfer process uses the steel cage transport mechanism to drive the clamping and hoisting mechanism to switch between the feeding position, transfer channel and unloading position in the truss, the invention can achieve fully automated operation without manual operation, thus ensuring the automation function of the steel cage transfer process. Attached Figure Description
[0031] To more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on the structures shown in these drawings without creative effort.
[0032] Figure 1 A schematic diagram of the structure of the steel cage transfer mechanism provided by the present invention;
[0033] Figure 2 for Figure 1 The structural schematic diagram of the steel cage transportation mechanism in the example is shown below;
[0034] Figure 3 for Figure 1 A schematic diagram of the gripping component in the example;
[0035] Figure 4 for Figure 1 A structural schematic diagram of the gripping component from another perspective in the example;
[0036] Figure 5 This is a schematic diagram of the track slab production line as an example of the present invention.
[0037] Reference numerals: 100, Truss; 140, Transfer channel; 120, Feeding position; 130, Discharging position; 200, Rebar cage transport mechanism; 300, Rebar cage; 400, Clamping and hoisting mechanism; 410, Traveling component; 420, Clamping component; 210, Guide rail; 220, Transport vehicle; 230, Rebar cage mounting component; 231, Base; 232, Mounting assembly; 233, Column; 234, Lifting block; 421, Mounting plate; 422, Clamping plate; 423, Receiving groove; 424, Tip; 425, Elastic reset component; 426, Arc-shaped toothed ring; 427, Drive motor; 10, Transfer mechanism; 20, Track slab casting and forming mechanism.
[0038] The realization of the objective, functional features and advantages of the present invention will be further explained in conjunction with the embodiments and with reference to the accompanying drawings. Detailed Implementation
[0039] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative effort are within the scope of protection of the present invention.
[0040] It should be noted that if the embodiments of the present invention involve directional indications (such as up, down, left, right, front, back, etc.), the directional indications are only used to explain the relative positional relationship and movement of the components in a specific posture. If the specific posture changes, the directional indications will also change accordingly.
[0041] Furthermore, if the embodiments of this invention involve descriptions such as "first" or "second," these descriptions are for descriptive purposes only and should not be construed as indicating or implying their relative importance or implicitly specifying the number of technical features indicated. Thus, a feature defined with "first" or "second" may explicitly or implicitly include at least one of those features. Additionally, the use of "and / or" or "and / or" throughout the text includes three parallel solutions. For example, "A and / or B" includes solution A, solution B, or a solution where both A and B are satisfied simultaneously. Furthermore, the technical solutions of the various embodiments can be combined with each other, but this must be based on the ability of those skilled in the art to implement them. When the combination of technical solutions is contradictory or impossible to implement, it should be considered that such a combination of technical solutions does not exist and is not within the scope of protection claimed by this invention.
[0042] With the rapid development of high-speed railway construction in my country, track slabs, as a core component of ballastless track systems, have received increasing attention for their production processes and manufacturing technologies. Reinforcing cages, as a crucial structural element of track slabs, have undergone a development process in their transfer technology, evolving from manual handling to mechanized transfer, and then to automated transfer. Early reinforcing cage transfer relied primarily on manual labor combined with simple lifting equipment. However, with the expansion of track slab production scale and the increasing standardization requirements, specialized mechanized transfer equipment has gradually developed, continuously evolving towards intelligent and automated processes.
[0043] Currently, the rebar cage transfer technology in track slab production mainly employs a combination of overhead cranes and manual operation. Specifically, the rebar cage is delivered to the designated feeding area via transport vehicles or conveyor equipment. Then, operators use overhead cranes or lifting equipment to clamp and lift the rebar cage, transferring it from the feeding position to the mold or designated unloading position. During the transfer process, operators need to position, adjust, and monitor within the work area to ensure the rebar cage is accurately placed in the target location. The entire transfer process requires the coordinated operation of multiple processes, including positioning, clamping, lifting, moving, and placing.
[0044] However, the applicant's research found that due to the limited working space in the track slab production workshop, the existing transfer equipment is prone to problems such as equipment interference and difficulty in personnel avoidance when operating in a narrow working area, which poses a safety hazard to the steel cage during the transfer process.
[0045] This invention proposes a track plate production line for the transfer mechanism of steel cages.
[0046] Please see Figures 1 to 5 For ease of understanding, the steel cage transfer mechanism 10 includes:
[0047] A truss 100 has a transfer channel 140 extending along a first horizontal direction at its top. The two ends of the transfer channel 140 along the first horizontal direction form a feeding position 120 and a discharging position 130, respectively. A steel cage 300 is placed on the feeding position 120.
[0048] A rebar cage transport mechanism 200 carries a rebar cage 300 and is capable of transporting the rebar cage 300 to the feeding position 120; and...
[0049] The clamping and hoisting mechanism 400 includes a traveling component 410 and a clamping component 420. The clamping component 420 is installed on the traveling component 410. The traveling component 410 is slidably engaged with the transfer channel 140. The traveling component 410 can travel along the transfer channel 140. The clamping component 420 can descend to clamp the steel cage 300 located at the feeding position 120. When the clamping and hoisting mechanism 400 clamps the steel cage 300, the traveling component 410 can drive the clamping component 420 to transfer the steel cage 300 along the transfer channel 140 and place it at the unloading position 130.
[0050] Specifically, the truss 100, as the load-bearing structure of the entire transfer system, provides a stable movement path for the clamping and hoisting mechanism 400 through its top transfer channel 140, avoiding spatial interference problems that may occur when equipment moves on the ground in traditional transfer methods. The rationally planned feeding position 120, unloading position 130, and transfer channel 140 inside the truss 100 provide clear spatial positioning for the orderly transfer of the rebar cage 300, eliminating operational chaos under limited working space conditions. The rebar cage transport mechanism 200 can accurately transport the rebar cage 300 to the feeding position 120, providing accurate initial positioning for subsequent clamping operations and avoiding positioning errors and safety risks during manual handling. The clamping and hoisting mechanism 400 achieves stable movement at the top of the truss 100 through the sliding engagement of the traveling component 410 on the transfer channel 140. Its clamping component 420 can accurately descend to the feeding position 120 to clamp the steel cage 300, and complete the entire transfer process along the transfer channel 140 under the drive of the traveling component 410, effectively solving the problems of equipment interference and personnel avoidance difficulties in narrow working areas.
[0051] The steel cage transfer mechanism 10 of this application uses a truss structure 100 to set the movement path of the transfer equipment in the space above the work area, making full use of vertical space resources and avoiding spatial conflicts in the ground work area. Compared with traditional ground-based mobile transfer equipment, the clamping and hoisting mechanism 400 of this application moves on the transfer channel 140 at the top of the truss 100, without interfering with other equipment or personnel on the ground, significantly improving operational safety. Moreover, through the sliding cooperation between the traveling component 410 and the transfer channel 140, the clamping and hoisting mechanism 400 can achieve precise position control and a smooth movement process, effectively ensuring the stability of the steel cage 300 during the transfer process and avoiding the risk of deformation or damage to the steel cage 300 due to equipment vibration or unstable movement.
[0052] In another embodiment, the truss 100 adopts a modular assembly structure, including multiple standardized truss 100 units. These truss 100 units are assembled into a complete truss 100 structure via connectors. The transfer channel 140 is formed by connecting the channel sections at the top of each truss 100 unit to create a continuous movement path. The feeding position 120 and the unloading position 130 are respectively located in designated areas at both ends of the truss 100. The width and height of the transfer channel 140 are optimized according to the external dimensions of the reinforcing cage 300. The reinforcing cage transport mechanism 200 adopts a rail-type transport method. The transport track connects with the feeding position 120 of the truss 100, and the transport platform achieves precise alignment with the feeding position 120 through track guidance. The walking component 410 of the clamping and hoisting mechanism 400 adopts a double-track walking method. Walking wheel systems are respectively provided on both sides of the walking frame. The walking wheel systems slide in cooperation with the guide rails 210 on both sides of the transfer channel 140. The walking drive unit adopts a motor-driven method, achieving precise movement of the walking frame through gear and rack transmission. The lifting device of the clamping component 420 is driven by a hydraulic cylinder or an electric cylinder. The clamping device includes multiple clamping arms, which can be adaptively adjusted according to the shape of the steel cage 300 to ensure the reliability and stability of the clamping process.
[0053] The steel cage transfer mechanism 10 of this application, through its modular truss structure 100, can be flexibly configured according to different work sites and steel cage 300 specifications, offering strong adaptability and convenient installation. The dual-track walking component 410 provides better stability and load-bearing capacity during movement, capable of supporting the weight of the steel cage 300 and maintaining smooth movement. The motor-driven walking drive unit, combined with gear and rack transmission, provides precise position control and adjustable moving speed to meet the needs of different transfer conditions. The hydraulically or electrically driven lifting device offers fast response and high control precision, enabling precise positioning of the clamping component 420. The multi-clamping arm adaptive clamping device can adapt to steel cages 300 of different specifications and shapes, improving the versatility and operational efficiency of the transfer mechanism 10, and further eliminating the operational complexity and safety hazards caused by poor equipment adaptability in traditional transfer methods.
[0054] By setting up a truss 100, a rebar cage transport mechanism 200, and a clamping and hoisting mechanism 400, in use, a transfer channel 140 is formed at the top of the truss 100, and feeding positions 120 and discharging positions 130 are formed at intervals along the first direction within the truss 100 (i.e., the space below the truss 100), so that the transfer channel 140 is formed between the feeding positions 120 and the discharging positions 130. The rebar cage transport mechanism 200 is installed in the transfer channel 140 and can travel along the transfer channel 140. The clamping and hoisting mechanism 400 is installed in the rebar cage transport mechanism 200, and the rebar cage transport mechanism 200 drives the clamping and hoisting mechanism 400 to descend and clamp the rebar cage 300 located at the feeding position 120. When the rebar cage 300 is in place, the traveling component 410 can drive the clamping and hoisting component to transfer the rebar cage 300 along the transfer channel 140 and place it at the unloading position 130. This means that when the rebar cage 300 is hoisted and transferred, the present invention does not suffer from equipment interference or difficulties in personnel avoidance due to the limitations of the working environment, thus improving the safety of the track plate rebar cage 300 during the transfer process. At the same time, since the entire transfer process is driven by the rebar cage transport mechanism 200 to switch between the clamping and hoisting mechanism 400 in the truss 100, the feeding position 120, the transfer channel 140, and the unloading position 130, the present invention can achieve fully automated operation without manual operation during specific implementation, thus ensuring the automation function of the rebar cage 300 transfer process.
[0055] In one embodiment, the steel cage transport mechanism 200 includes:
[0056] Guide rail 210 extends along a second horizontal direction to feed position 120, and the second horizontal direction is perpendicular to the first horizontal direction;
[0057] Transport vehicle 220, transport vehicle 220 is mounted on guide rail 210, transport vehicle 220 can move along guide rail 210 to feed position 120; and,
[0058] The rebar cage 300 mounting component is installed on the top of the transport vehicle 220, and the rebar cage 300 is mounted on the rebar cage 300.
[0059] Specifically, the transport vehicle 220 slides on the guide rail 210 via a wheel set. The wheel set includes a load-bearing wheel and a guide wheel. The load-bearing wheel supports the weight of the transport vehicle 220 and the rebar cage 300, while the guide wheel provides lateral positioning through side contact with the guide rail 210. A drive unit is installed on the body of the transport vehicle 220, which drives the transport vehicle 220 to move along the guide rail 210 via a gear and rack transmission or friction wheel transmission. The rebar cage 300 mounting component is installed at the center of the top of the transport vehicle 220. The rebar cage 300 mounting component includes a support frame and a positioning device. The support frame provides a load-bearing platform for the rebar cage 300, and the positioning device secures the rebar cage 300 through an adjustable clamping structure to prevent displacement or tipping during transport. When the transport vehicle 220 reaches the feeding position 120, the rebar cage 300 on the rebar cage 300 mounting component is precisely within the clamping range of the clamping and lifting mechanism 400 within the truss 100, providing accurate spatial positioning for subsequent clamping operations.
[0060] This application achieves precise transport of the rebar cage 300 from the external storage area to the feeding position 120 of the truss 100 through the combined configuration of the guide rail 210, the transport vehicle 220, and the rebar cage 300 mounting components. The guide rail 210, extending along a second direction, provides a fixed movement path for the transport vehicle 220, avoiding path deviation and inaccurate positioning problems that may occur in traditional manual trolley or forklift transport. The sliding movement of the transport vehicle 220 on the guide rail 210 offers higher positioning accuracy and movement stability compared to free movement on the ground, ensuring that the rebar cage 300 is accurately delivered to the designated area of the feeding position 120. The rebar cage 300 mounting components, through the cooperation of the support frame and positioning device, not only provide stable load-bearing support for the rebar cage 300, but also effectively prevent displacement of the rebar cage 300 due to vibration or inertial forces during transport through the clamping and fixing function of the positioning device, ensuring the accurate positioning of the rebar cage 300 upon arrival at the feeding position 120.
[0061] More specifically, the guide rail 210 adopts a double-track structure, including two parallel track beams. The spacing between the track beams is configured according to the wheelbase of the transport vehicle 220. The transport vehicle 220 has a low center of gravity structure, with wheel sets distributed at the four corners of the vehicle body. Each wheel set includes a load-bearing wheel and a side guide wheel. The load-bearing wheel makes rolling contact with the top surface of the track beam, while the side guide wheel makes contact with the side of the track beam to provide lateral constraint. The drive unit of the transport vehicle 220 is driven by an electric motor. The motor is connected to the drive wheel through a reducer, and the drive wheel meshes with the rack on the surface of the track beam to achieve precise position control. The support frame for the components mounted on the rebar cage 300 uses adjustable-height hydraulic support columns. The hydraulic support columns can be adjusted according to the height of different specifications of the rebar cage 300. The positioning device includes multiple retractable clamping arms, which are pneumatically driven to achieve automatic clamping and releasing operations. When the transport vehicle 220 approaches the feeding position 120, the on-board position sensor detects the position signal, and the drive unit automatically decelerates and stops precisely. At this time, the steel cage 300 on the steel cage 300 mounting component is exactly below the clamping component 420 of the clamping and hoisting mechanism 400, providing accurate spatial alignment for the descent and clamping of the clamping component 420.
[0062] The dual-track guide rail 210 configuration further enhances the stability and load-bearing capacity of the transport vehicle 220 during movement. The parallel arrangement of the dual tracks effectively distributes the weight load of the rebar cage 300, avoiding deformation or wear problems that may occur with single-track bearing. The low center of gravity of the transport vehicle 220 lowers the overall center of gravity of the transport system, improving its anti-overturning ability during transport, especially maintaining good stability when carrying large rebar cages 300. The precise control method of motor drive combined with rack and pinion transmission enables precise positioning and smooth start and stop of the transport vehicle 220, avoiding speed fluctuations and positioning errors that may exist in traditional hydraulic or pneumatic drives. The combination of adjustable-height hydraulic support columns and pneumatic clamping arms allows the rebar cage 300 mounting components to adapt to rebar cages 300 of different specifications and shapes, improving the versatility and automation of the transport mechanism, reducing the need for manual adjustment and intervention, and further eliminating safety hazards for personnel operation under limited working space conditions.
[0063] In one embodiment, the steel cage 300 mounting component includes:
[0064] A base 231 is detachably connected to the top of the transport vehicle 220, and the base 231 extends out of the transport vehicle 220; and,
[0065] The mounting component 232 is installed on the top of the base 231, and the mounting component 232 is equipped with a steel cage 300.
[0066] Specifically, the base 231 is detachably connected to the top of the transport vehicle 220 via bolt or snap-fit connections, facilitating installation or removal as needed. The main body of the base 231 matches the dimensions of the top of the transport vehicle 220, while a portion of the base 231 extends beyond the edge of the transport vehicle 220, forming a cantilever structure. This extension allows the mounting position of the rebar cage 300 to extend beyond the transport vehicle 220 itself, providing more flexible support space for rebar cages 300 of different sizes. The mounting assembly 232 is installed on top of the base 231 and includes a support frame and a positioning unit. The support frame consists of multiple support rods arranged to conform to the shape of the rebar cage 300. The positioning unit includes multiple positioning blocks distributed around the perimeter of the support frame to restrict the lateral movement of the rebar cage 300. When the reinforcing cage 300 is placed on the mounting component 232, the bottom of the reinforcing cage 300 contacts the support frame, and the side of the reinforcing cage 300 abuts against the positioning block, thereby achieving stable placement of the reinforcing cage 300 on the mounting component 232.
[0067] This application achieves flexible configuration of the rebar cage 300 mounting components through a detachable connection structure between the base 231 and the top of the transport vehicle 220. Different types of bases 231 and mounting components 232 can be replaced according to different rebar cage 300 specifications and transportation requirements, improving the adaptability of the transportation mechanism 10. The base 231 extends from the structure of the transport vehicle 220, expanding the mounting space of the rebar cage 300, allowing rebar cages 300 exceeding the width of the transport vehicle 220 to be stably mounted, solving the problem of transporting large rebar cages 300 in limited space. The mounting component 232, through the cooperation of the support frame and positioning unit, provides stable and reliable load-bearing support and positional constraint for the rebar cage 300, effectively preventing displacement and tilting of the rebar cage 300 during transportation, ensuring accurate positioning of the rebar cage 300 when it reaches the feeding position 120, and providing good initial conditions for the subsequent clamping and lifting operation of the lifting mechanism 400.
[0068] In more detail, the base 231 is made of lightweight aluminum alloy. The main body of the base 231 is a frame structure, formed by the intersecting connection of crossbeams and longitudinal beams, enhancing the overall strength and rigidity of the base 231. The connection between the base 231 and the top of the transport vehicle 220 uses a quick-locking device, which includes locking bolts and a locking handle. The base 231 can be quickly installed and removed by rotating the locking handle without the need for special tools. The portion of the base 231 extending beyond the transport vehicle 220 is equipped with reinforcing ribs distributed along the extension direction of the base 231, improving the load-bearing capacity of the extended portion. The support frame for the mounting component 232 uses height-adjustable support columns, which are connected to the base 231 via adjusting bolts, allowing for height adjustment according to the height requirements of the rebar cage 300. The positioning block of the positioning unit adopts a detachable structure, connecting to the base 231 via a sliding groove. It can move along the groove and be fixed in different positions to accommodate rebar cages 300 of different diameters. In addition, the mounting component 232 is also equipped with an anti-slip mat, which is laid on the support frame to increase the friction between the steel cage 300 and the support frame, and further improve the stability of the steel cage 300 during the mounting process.
[0069] This application utilizes a lightweight material and frame structure for the base 231, which reduces overall weight while maintaining load-bearing capacity, thereby lowering the load on the transport vehicle 220 and improving transportation efficiency. The application of a quick-locking device simplifies the installation and disassembly process of the base 231, shortens the time for replacing mounting components, and improves the flexibility and efficiency of the transfer system. The reinforcing rib structure of the extension effectively solves the strength deficiency problem that may arise from cantilever bearing, ensuring the safety of the large steel cage 300 when mounted on the extension. The combination of adjustable-height support columns and movable positioning blocks allows the mounting component 232 to adapt to various specifications of steel cages 300, improving the versatility and adaptability of the mounting components. The application of anti-slip pads further enhances the stability of the steel cage 300 in the mounted state, reducing the risk of displacement due to vibration or shaking, ensuring the positioning accuracy of the steel cage 300 during transportation, and providing a reliable guarantee for the smooth progress of the entire transfer process.
[0070] In one embodiment, there are multiple mounting components 232, and all mounting components 232 are grouped in pairs and spaced apart on the top of the base 231.
[0071] Specifically, each pair of mounting components 232 forms a group, and these groups are distributed along the periphery or a specific area of the top of the base 231. The spacing between the mounting components 232 not only considers space utilization efficiency but also structural stability and ease of operation. The spacing between each group of mounting components 232 is set according to actual needs, ensuring that the components do not interfere with each other while maintaining the compactness of the overall structure. The mounting components 232 are fixedly connected to the top of the base 231 via connectors, which can be bolts, welded structures, or snap-fit connections, ensuring that the mounting components 232 do not loosen or shift during use.
[0072] This application effectively solves the technical problems of insufficient load-bearing capacity, low space utilization, and inconvenient operation that may occur with traditional single-mounted components 232 by arranging multiple mounting components 232 in pairs and distributing them at intervals on the top of the base 231. The pairwise arrangement allows adjacent mounting components 232 to work together, forming a synergistic effect and improving the overall load-bearing capacity and stability. When one mounting component 232 bears a load, adjacent mounting components 232 can provide auxiliary support or balancing effects, effectively preventing structural deformation or damage caused by excessive force at a single point. The spaced-out layout not only optimizes the space utilization on the top of the base 231 but also provides sufficient operating space for operators, making loading, unloading, or adjustment operations more convenient and efficient.
[0073] In one embodiment, each mounting component 232 includes:
[0074] Multiple columns 233 are spaced apart on the top of the base 231. All columns 233 enclose each other to form a mounting space for the steel cage 300. At least one pair of lifting blocks 234 are provided on any two adjacent columns 233. Each pair of lifting blocks 234 is located at the same elevation and supports and lifts the steel cage 300 together.
[0075] Specifically, the uprights 233 are made of metal, possessing sufficient strength and rigidity to withstand the weight of the reinforcing cage 300. Multiple uprights 233 are spaced apart on top of the base 231 according to a specific geometric layout, typically four or six uprights 233, distributed along the edge of the base 231. The height of the uprights 233 is determined by the dimensions of the reinforcing cage 300, ensuring that the reinforcing cage 300 can be completely placed within the mounting space enclosed by the uprights 233. Lifting blocks 234 are installed on the top of each upright 233. The lifting blocks 234 are made of wear-resistant material with a smooth, flat surface, reducing friction when in contact with the reinforcing cage 300. All lifting blocks 234 are at the same elevation, meaning their upper surfaces are on the same horizontal plane. This ensures that the reinforcing cage 300 remains level during placement, preventing tilting or instability. The lifting blocks 234 are square or round in shape, and their upper surfaces can be designed with a slightly concave shape to increase stability when in contact with the reinforcing cage 300.
[0076] The mounting component 232 of this application forms a stable support structure for the reinforcing cage 300 through the cooperation of multiple columns 233 and multiple support blocks 234. The structure of multiple columns 233, spaced apart and mutually enclosing each other to form the mounting space, ensures that the reinforcing cage 300 is evenly supported, avoiding the problem of uneven local stress on the reinforcing cage 300 that may occur with traditional platform-type supports. The one-to-one correspondence between the support blocks 234 and the columns 233 ensures that each support point has a corresponding support structure, providing a more reliable support effect. The setting of all support blocks 234 at the same elevation ensures that the reinforcing cage 300 remains horizontal during placement and mounting, avoiding the risk of tilting or deformation of the reinforcing cage 300 due to inconsistent support point heights. This structural configuration is particularly suitable for use in the limited working space of a track slab production workshop. The combination of columns 233 and support blocks 234 occupies little space but provides sufficient support strength, effectively solving the problems of large space occupation and inconvenient adjustment associated with traditional platform-type supports.
[0077] In some preferred embodiments, the column 233 adopts a height-adjustable telescopic structure, comprising an outer cylinder and an inner cylinder. The inner cylinder can slide up and down within the outer cylinder and is fixed at the desired height position by a locking device. The base 231 has a mounting plate at its top for mounting the column 233. The mounting plate is fixedly connected to the base 231 by bolts, and the bottom of the outer cylinder of the column 233 is connected to the mounting plate by threads or snap-fit. The lifting block 234 adopts a detachable structure and is connected to the top of the inner cylinder of the column 233 by bolts or a quick-connect mechanism. The top surface of the lifting block 234 is covered with an anti-slip rubber layer to increase friction when in contact with the reinforcing cage 300. The base 231 is also equipped with a leveling mechanism, including multiple adjusting bolts and a level. The levelness of the base 231 can be precisely adjusted by adjusting the bolts to ensure that all lifting blocks 234 are on the same horizontal plane. The number of columns 233 can be configured according to the size and weight of the steel cage 300. Small steel cages 300 can use four columns 233, while large or heavy steel cages 300 can use six or eight columns 233 to provide a more reliable support effect.
[0078] In one embodiment, the lifting blocks 234 are in multiple pairs, and the multiple pairs of lifting blocks 234 are distributed at intervals along the height direction of the column 233 to form a corresponding number of steel cage 300 placement positions on the column 233.
[0079] Specifically, the support blocks 234 are fixed to predetermined positions on the columns 233 by bolts or welding. Each support block 234 includes a horizontally extending support arm and a bearing platform at the end of the support arm. The surface of the bearing platform is provided with anti-slip texture or rubber padding to increase friction with the reinforcing cage 300. When the total number of support blocks 234 is at least twice the number of columns 233, it means that at least two support blocks 234 are installed on each column 233. The consistency of the number of support blocks 234 on each column 233 ensures a balanced distribution of bearing capacity among different columns 233. The spaced distribution of support blocks 234 along the height direction of the columns 233 forms multiple horizontal levels of reinforcing cage 300 placement positions. Each placement position is composed of multiple support blocks 234 at the same horizontal height, providing multi-point support for the reinforcing cage 300. After completing the transfer of the steel cage 300, the clamping and hoisting mechanism 400 can accurately place the steel cage 300 at the designated height on the steel cage 300 placement position. The bearing platform of the lifting block 234 bears the weight of the steel cage 300 and maintains its stability.
[0080] By configuring the number of lifting blocks 234 in a multiple relationship with the number of columns 233, a three-dimensional storage capacity is achieved at the material placement position 130, effectively increasing the storage density of the rebar cages 300 within the limited working space. The spaced distribution of the lifting blocks 234 along the height of the columns 233 expands the original single-horizontal storage method into multi-layer vertical storage, fully utilizing the vertical space resources of the truss 100 structure. The consistent configuration of the number of lifting blocks 234 on each column 233 ensures that each rebar cage 300 placement position has the same number of support points and load-bearing capacity, avoiding deformation or tilting of the rebar cage 300 due to uneven support. The formation of multiple rebar cage 300 placement positions allows the transfer mechanism 10 to continuously process multiple rebar cages 300 without waiting for the previous rebar cage 300 to be removed, significantly improving transfer efficiency and operational continuity.
[0081] In one embodiment, the gripping component 420 includes:
[0082] Mounting plate 421 is mounted on the walking component 410. The bottom of the mounting plate 421 is provided with two pin holes spaced apart along the first horizontal direction.
[0083] Two clamping plates 422 are arranged side by side and rotatably passed through two pin holes by pins, so that both clamping plates 422 are hinged to the mounting plate 421. Both clamping plates 422 can rotate around their corresponding pins. Receiving grooves 423 are recessed on the opposite sides of the two clamping plates 422. The receiving grooves 423 on the two clamping plates 422 are joined together to form receiving holes for accommodating the main reinforcing bars. The end of each clamping plate 422 furthest from the mounting plate 421 is formed with a pointed tip 424.
[0084] The elastic reset member 425 is connected between the two clamping plates 422, and the elastic reset member 425 causes the two clamping plates 422 to clamp the main rib.
[0085] Specifically, the two pin holes at the bottom of the mounting plate 421 are spaced apart along a third direction (i.e., the transverse direction perpendicular to the transfer channel 140). The spacing of the pin holes is configured according to the spacing of the main reinforcement bars of the reinforcing cage 300 to ensure that the clamping plate 422 can be accurately aligned with the main reinforcement bars of the reinforcing cage 300. The two clamping plates 422 are made of wear-resistant steel plates. The upper end of the clamping plate 422 is riveted to the pin holes at the bottom of the mounting plate 421 by high-strength pins. A bearing or lubrication sleeve is provided at the riveting point to reduce the frictional resistance when the clamping plate 422 rotates. The clamping plate 422 can rotate freely around the pins, and the rotation angle range is usually 0° to 45° to adapt to the clamping requirements of main reinforcement bars of different diameters. The receiving grooves 423 formed by the recesses on the opposite sides of the clamping plates 422 are semi-circular or V-shaped. The receiving grooves 423 of the two clamping plates 422 are arranged opposite each other to form circular or rhomboid receiving holes. The diameter or diagonal size of the receiving holes matches the diameter of the main reinforcement bars of the reinforcing cage 300. The end of the clamping plate 422 furthest from the mounting plate 421 forms a pointed tip 424, which is inverted V-shaped or conical, facilitating insertion into the gap between the main reinforcement bars of the steel cage 300. An elastic reset member 425, in the form of a tension spring or torsion spring, is installed between the two clamping plates 422. Both ends of the elastic reset member 425 are connected to the two clamping plates 422 respectively. The elastic force generated by the elastic reset member 425 causes the lower parts of the two clamping plates 422 to move closer together, thereby causing the receiving hole to contract and clamp the main reinforcement bars.
[0086] The connection between the two clamping plates 422 and the mounting plate 421 via pins allows the clamping plates 422 to rotate freely around the pins, automatically adjusting the clamping angle according to the diameter and position of the main reinforcement bars, thus improving the adaptability and flexibility of the clamping operation. The receiving holes formed by the accommodating grooves 423 on the clamping plates 422 provide a shape-matched support structure for the main reinforcement bars, increasing the contact area and improving the stability and reliability of the clamping. The pointed tip 424 formed at the end of the clamping plate 422 away from the mounting plate 421 facilitates the insertion of the clamping plate 422 into the gap between the main reinforcement bars of the rebar cage 300, reducing interference with the rebar cage 300 structure during clamping and lowering the risk of clamping failure or jamming. The elastic force generated by the elastic reset member 425 causes the two clamping plates 422 to automatically clamp the main reinforcement bars without the need for an additional drive device, simplifying the structure and improving operational reliability. Simultaneously, the elastic clamping method can adapt to main reinforcement bars of different diameters, enhancing the versatility of the clamping component 420.
[0087] In one embodiment, two clamping plates 422 are respectively formed with two interlocking arc-shaped toothed rings 426 at one end near the mounting plate 421.
[0088] Specifically, the end of each clamping plate 422 closest to the mounting plate 421 is the hinge end, on which an arc-shaped toothed ring 426 structure is machined. Each arc-shaped toothed ring 426 of the clamping plate 422 is partially annular, with its center located on the hinge axis. The outer circumference of the arc-shaped toothed ring 426 is machined with toothed structures, and the toothed structures of the two arc-shaped toothed rings 426 correspond to each other and can mesh. When the two clamping plates 422 open and close, the two arc-shaped toothed rings 426 remain meshed. The meshing of the teeth of the arc-shaped toothed rings 426 ensures that the opening and closing angles of the two clamping plates 422 remain synchronized, that is, the deflection angles of the two clamping plates 422 relative to the center line remain consistent. The arc-shaped toothed rings 426 are made of high-strength alloy steel, and the surface is hardened to improve wear resistance. The module and pressure angle of the teeth are optimized according to the size and load-bearing requirements of the clamping plates 422 to ensure uniform force transmission and smooth movement during meshing.
[0089] This application achieves synchronous control of the opening and closing movements of the clamping plates 422 by forming mutually meshing arc-shaped toothed rings 426 at one end of the two clamping plates 422 near the mounting plate 421. This effectively solves the problems of clamping instability and deformation of the reinforcing cage 300 caused by asynchronous opening and closing of the clamping plates 422 in traditional clamping devices. The meshing transmission method of the arc-shaped toothed rings 426 directly transmits the movement state of one clamping plate 422 to the other clamping plate 422 through tooth meshing, without the need for additional synchronization mechanisms or control systems. The structure is simple and the transmission is reliable. The center of the arc-shaped toothed rings 426 coincides with the hinge axis of the clamping plates 422, ensuring the continuity and smoothness of the tooth meshing process and avoiding impacts and vibrations caused by transmission gaps or positional deviations. The synchronous opening and closing characteristics of the two clamping plates 422 enable the clamping component 420 to apply a uniform clamping force to the rebar cage 300, preventing the risk of deformation or damage to the rebar cage 300 due to uneven clamping force. Especially when clamping and transferring the rebar cage 300 in a confined working space, this synchronous clamping capability can effectively improve the accuracy and safety of the operation.
[0090] In one embodiment, one of the clamping plates 422 is fixed with a corresponding pin, and the clamping component 420 further includes a drive motor 427. The drive motor 427 is mounted on the mounting plate, and the output shaft of the drive motor 427 is connected to the pin fixed to the corresponding clamping plate 422 so as to drive the output shaft to rotate and open the corresponding clamping plate 422 and lower the steel cage 300.
[0091] Specifically, one of the two clamping plates 422 is connected to its corresponding pin using an interference fit, forming an integrated output shaft structure. An interference fit means the outer diameter of the pin is slightly larger than the inner diameter of the corresponding hole on the clamping plate 422. Through pressure assembly, the two are tightly joined as a whole. This connection method ensures that there is no relative rotation between the clamping plate 422 and the pin, allowing the pin to reliably transmit torque to the clamping plate 422. The drive motor 427 is mounted on a mounting plate 421, which has a motor mounting plate. The motor mounting plate is fixed to the mounting plate 421 with bolts, and the drive motor 427 is connected to the motor mounting plate with bolts. The output shaft of the drive motor 427 is connected to the output shaft (i.e., the interference-fit pin). The connection method can be a coupling, spline, or key connection, ensuring that the torque of the motor output shaft can be effectively transmitted to the output shaft. When the drive motor 427 starts and outputs torque, the output shaft rotates under the drive of the motor. Since the output shaft and one of the clamping plates 422 are interference-fitted as one unit, the clamping plate 422 rotates synchronously with the output shaft. When the clamping plate 422 rotates open, the clamping force between the clamping plate 422 and the rebar cage 300 disappears, and the rebar cage 300 falls from between the clamping plates 422 under the action of gravity, realizing the placement operation.
[0092] The output shaft is formed by the interference fit between the clamping plate 422 and the pin, and the drive motor 427 is connected to the output shaft, achieving precise control of the clamping plate 422 and reliable placement of the rebar cage 300. The interference fit output shaft structure eliminates the gaps and looseness problems that may exist in traditional connection methods, ensuring that the torque of the drive motor 427 can be transmitted to the clamping plate 422 without loss, improving transmission efficiency and control accuracy. The configuration of the drive motor 427 mounted on the mounting plate 421 makes the drive system and the clamping mechanism form a compact whole, reducing the complexity of the transmission chain and the number of failure points, and improving the reliability of the system. Compared with traditional hydraulic or pneumatic drives, the motor drive method has the advantages of fast response speed and high control accuracy, enabling precise control of the opening angle and speed of the clamping plate 422. Especially during the placement of the rebar cage 300, the opening and closing speed of the clamping plate 422 can be adjusted according to actual needs, avoiding the impact and vibration caused by the sudden release of the rebar cage 300, and ensuring that the rebar cage 300 falls smoothly into the designated position.
[0093] Based on the same technical concept, in a second aspect, the present invention also proposes a track slab production line, comprising:
[0094] The first aspect involves the transfer mechanism 10 for the steel cage; and,
[0095] The track slab casting and forming mechanism 20 has a track slab casting and forming space. The track slab casting and forming mechanism 20 is installed at the feeding position 120. The transfer mechanism 10 can clamp the steel cage 300 at the feeding position 120 and transfer the steel cage 300 along the transfer channel 140 and place it in the track slab casting and forming space so that concrete can be poured in the casting and forming space to form the track slab.
[0096] Specifically, the installation position of the track slab casting and forming mechanism 20 corresponds spatially to the feeding position 120 of the truss 100, allowing the clamping and hoisting mechanism 400 to directly transfer the reinforcing cage 300 clamped from the feeding position 120 into the track slab casting and forming space. The dimensions of the track slab casting and forming space are configured according to the specifications of the track slab; the length, width, and depth of the space can accommodate the reinforcing cage 300 and reserve space for concrete pouring. After clamping the reinforcing cage 300, the clamping and hoisting mechanism 400 of the transfer mechanism 10 moves along the transfer channel 140 to above the track slab casting and forming mechanism 20. The clamping component 420 descends and precisely places the reinforcing cage 300 at a predetermined position within the track slab casting and forming space. The placement position of the reinforcing cage 300 within the track slab casting and forming space is precisely controlled by a positioning device to ensure that the reinforcing cage 300 maintains an appropriate distance from the mold wall, providing a uniform coverage thickness for concrete pouring. The concrete pouring system delivers concrete to the track slab pouring space through the pouring pipe. The concrete flows around the steel cage 300 and fills the entire forming space. After vibration and curing, a complete track slab product is formed.
[0097] This application's track slab production line, through the integrated configuration of the rebar cage transfer mechanism 10 and the track slab casting and forming mechanism 20, achieves a continuous production process from the transfer of the rebar cage 300 to the forming of the track slab, effectively solving the problems of production efficiency and safety under the limited working space conditions of the track slab production workshop. The automated transfer capability of the transfer mechanism 10 eliminates the safety hazards of traditional manual handling of the rebar cage 300, especially in confined working areas, avoiding the risk of injury from contact between personnel and the heavy rebar cage 300. The docking configuration of the track slab casting and forming mechanism 20 and the feeding position 120 allows the rebar cage 300 to be directly transferred from the transfer channel 140 to the casting and forming space without additional transfer links, significantly improving production efficiency and the positioning accuracy of the rebar cage 300. The precise control capability of the transfer mechanism 10 ensures the accurate positioning of the rebar cage 300 within the track slab casting and forming space, providing a stable steel reinforcement skeleton foundation for subsequent concrete pouring and ensuring the quality stability of the track slab product. The automation level of the entire production line significantly reduces the need for manual operation, lowering the risk of quality problems and safety accidents caused by human error.
[0098] Of course, the track slab casting and forming mechanism 20 adopts a movable structure, including a movable base 231 and a forming mold assembly mounted on the movable base 231. The movable base 231 is adjusted in position by cooperating with the ground track through a wheel system. The track slab casting and forming space is composed of a detachable mold assembly, which includes a bottom mold, side molds, and a top mold with adjustable height. The internal dimensions of the mold assembly can be adjusted according to the requirements of different specifications of track slabs. The installation position of the track slab casting and forming mechanism 20 can be moved and adjusted between the feeding position 120 and the discharging position 130 of the truss 100, and precise docking with the transfer mechanism 10 is achieved through position sensors and a control system. The control system of the transfer mechanism 10 and the control system of the track slab casting and forming mechanism 20 are connected through a communication interface to achieve coordinated control of the transfer and casting process of the reinforcing cage 300. After the reinforcing cage 300 is placed in the track slab casting and forming space, the forming mold assembly automatically adjusts to the preset casting state, and the concrete casting system performs quantitative casting according to the specifications of the track slab. After the pouring is completed, the track slab pouring and forming mechanism 20 moves to the curing area for concrete curing, while making room for the pouring and forming of the next steel cage 300.
[0099] This application, through the configuration of a movable track slab casting and molding mechanism 20, further enhances the flexibility and production capacity of the track slab production line, enabling it to adapt to the production needs of different specifications of track slabs and varying workspace requirements. Adjustable mold components allow the same casting and molding mechanism to produce track slabs of multiple specifications, improving equipment utilization and production line economy. The movable structure of the casting and molding mechanism allows it to be promptly removed from the work area after casting, providing space for the continuous operation of the transfer mechanism 10 and avoiding production interruptions caused by the casting and molding mechanism occupying workspace. The integrated configuration of the control system achieves automated coordination of the transfer and casting processes, reducing manual intervention and waiting time, and significantly improving the overall production line efficiency.
[0100] The above description is merely an exemplary embodiment of the present invention and does not limit the patent scope of the present invention. Any equivalent structural transformations made using the contents of the present invention specification and drawings under the technical concept of the present invention, or direct / indirect applications in other related technical fields, are included within the patent protection scope of the present invention.
Claims
1. A transfer mechanism for reinforcement cages, characterised in that, include: A truss, the top of which forms a transfer channel extending along a first horizontal direction, the two ends of which form a feeding position and a discharging position respectively, and a reinforcing cage is placed at the feeding position; the truss adopts a modular assembly structure, including multiple standardized truss units, which are assembled into a complete truss structure by connecting parts, and the transfer channel is formed by connecting the channel sections at the top of each truss unit to form a continuous movement path; A rebar cage transport mechanism, on which the rebar cage is carried, is capable of transporting the rebar cage to the feeding position. The rebar cage transport mechanism includes: a guide rail extending to the feeding position along a second horizontal direction perpendicular to a first horizontal direction; a transport vehicle mounted on the guide rail, capable of moving along the guide rail to the feeding position; and a rebar cage mounting component mounted on the top of the transport vehicle, on which the rebar cage is mounted. When the transport vehicle approaches the feeding position, an onboard position sensor detects a position signal, and a drive unit automatically decelerates and precisely stops the vehicle. At this time, the rebar cage on the rebar cage mounting component is directly below the clamping component of the clamping and lifting mechanism. The clamping and hoisting mechanism includes a traveling component and a clamping component. The clamping component is mounted on the traveling component and is slidably engaged with the transfer channel. The traveling component can travel along the transfer channel, and the clamping component can descend to clamp the steel cage located at the feeding position. When the clamping and hoisting mechanism clamps the steel cage, the traveling component can drive the clamping component to transfer the steel cage along the transfer channel and place it at the unloading position. The traveling component adopts a double-track traveling method, and traveling wheel systems are respectively provided on both sides of the traveling frame. The traveling wheel systems are slidably engaged with the guide rails on both sides of the transfer channel. The traveling drive unit adopts a motor drive method, and the movement of the traveling frame is realized through gear and rack transmission.
2. The steel cage transfer mechanism as described in claim 1, characterized in that, The steel cage mounting components include: A base, detachably connected to the top of the transport vehicle, and extending beyond the transport vehicle; and, A mounting component is installed on top of the base, and the steel cage is mounted on the mounting component.
3. The steel cage transfer mechanism as described in claim 2, characterized in that, The mounting components are multiple, and all the mounting components are grouped in pairs and distributed at intervals on the top of the base.
4. The steel cage transfer mechanism as described in claim 3, characterized in that, Each of the aforementioned mounting components includes: Multiple columns are spaced apart on the top of the base, and all the columns enclose each other to form a mounting space for mounting the steel cage. At least one pair of lifting blocks are provided on any two adjacent columns. Each pair of lifting blocks is located at the same elevation and supports and lifts the steel cage together.
5. The steel cage transfer mechanism as described in claim 4, characterized in that, The lifting blocks are in multiple pairs, and the multiple pairs of lifting blocks are distributed at intervals along the height direction of the column to form a corresponding number of steel cage placement positions on the column.
6. The steel cage transfer mechanism as described in any one of claims 1 to 5, characterized in that, The clamping component includes: Mounting plate, which is mounted on the walking component, has two pin holes spaced apart along the first horizontal direction at its bottom; Two clamping plates are arranged side-by-side and rotatably inserted through two pin holes, respectively, so that both clamping plates are hinged to the mounting plate. Both clamping plates can rotate about their corresponding pins. Receiving grooves are recessed on the opposite sides of both clamping plates, and these receiving grooves are joined together to form receiving holes for accommodating the main reinforcement bars of the steel cage. The end of each clamping plate away from the mounting plate is formed with a pointed tip. An elastic reset member is connected between the two clamping plates, and the elastic reset member causes the two clamping plates to clamp the main rib.
7. The steel cage transfer mechanism as described in claim 6, characterized in that, Two interlocking arc-shaped toothed rings are formed at one end of each of the two clamping plates near the mounting plate.
8. The steel cage transfer mechanism as described in claim 7, characterized in that, One of the clamping plates is fixed to the corresponding pin. The clamping component also includes a drive motor, which is mounted on the mounting plate. The output shaft of the drive motor is connected to the pin fixed to the corresponding clamping plate to drive the output shaft to rotate and open the corresponding clamping plate and lower the steel cage.
9. A track slab production line, characterized in that, include: The transfer mechanism for the steel cage as described in any one of claims 1 to 8; as well as, A track slab casting and forming mechanism is provided, wherein a track slab casting and forming space is formed within the track slab casting and forming mechanism. The track slab casting and forming mechanism is installed at the feeding position. The transfer mechanism can clamp the reinforcing cage at the feeding position and transfer the reinforcing cage along the transfer channel and place it in the track slab casting and forming space, so as to form the track slab after pouring concrete in the casting and forming space.
Citation Information
Patent Citations
Prestress rail plate continuous production complete equipment