A graded pre-support replacement method for foundation pits based on dual control of strength and deformation

By constructing a collaborative stress model and real-time monitoring, and adopting a graded loading and unloading method, the problem of unsmooth load transfer during foundation pit support replacement was solved, achieving safe and efficient foundation pit construction, which meets the requirements of green and intelligent construction.

CN123064167APending Publication Date: 2026-11-10CHINA SHANXI SIJIAN GRP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611254592.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-08-18
Publication Date
2026-11-10

AI Technical Summary

Technical Problem

Existing foundation pit support replacement technology lacks a proactive support replacement concept, fails to achieve the proactive and orderly transfer of temporary support loads to permanent structures, lacks a scientific basis for decision-making on the timing of support replacement, lacks refined graded pre-jacking and synchronous unloading processes, and monitoring and control have not yet formed a closed loop, resulting in low construction safety and efficiency.

Method used

The graded pre-support replacement method for foundation pits based on dual control of strength and deformation constructs a collaborative stress model, monitors concrete strength and retaining structure deformation in real time, establishes load transfer paths by adopting graded loading and unloading, and forms dynamic closed-loop control through a monitoring and control system.

Benefits of technology

It achieves seamless load connection and smooth transfer, reduces the risk of structural instability, shortens the construction cycle, reduces material waste and labor costs, and is in line with the development direction of green and intelligent construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123064167A_ABST
    Figure CN123064167A_ABST
Patent Text Reader

Abstract

This invention relates to the field of foundation pit construction technology, and more specifically, to a graded pre-support replacement method for foundation pits based on dual control of strength and deformation. The method includes the following steps: constructing a collaborative stress model of soil layer-temporary support-permanent structure; constructing the base slab and sidewalls while monitoring concrete strength and structural stress in real time; using concrete strength reaching at least 80% of the design strength and the deep horizontal displacement rate of the retaining structure consistently below 0.02 mm / h as dual control indicators for support replacement decisions; responding to support replacement permission instructions, applying pre-support force in stages at 10%–15% increments and simultaneously unloading, stabilizing each stage for 10–15 minutes to smoothly transfer the temporary support load to the permanent structure; and completing the support replacement step-by-step from top to bottom. This invention achieves active and stable load transfer from temporary support to the permanent structure, improving the safety and controllability of foundation pit support replacement construction. This invention is mainly applied to graded pre-support replacement of foundation pits based on dual control of strength and deformation.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of foundation pit construction technology, and more specifically, to a graded pre-support replacement method for foundation pits based on dual control of strength and deformation. Background Technology

[0002] In foundation pit engineering, as the underground main structure is gradually constructed, the soil pressure and external loads borne by the temporary support system need to be transferred to the permanent main structure in an orderly manner. This process is called support replacement. The safety and efficiency of support replacement construction directly affect the overall quality and schedule of the foundation pit project.

[0003] Currently, existing foundation pit support replacement technologies have the following shortcomings: They lack a proactive support replacement concept; existing methods are mostly passive, involving "removal before replacement" or "support replacing support," failing to achieve an active and orderly transfer of temporary support loads to the permanent structure; they lack scientific basis for determining the timing of support replacement, relying heavily on engineering experience or single strength indicators, failing to fully consider the deformation coordination capacity of the permanent structure during its aging process, and lacking a scientific determination mechanism for "strength-deformation" dual control; they lack refined graded pre-loading and synchronous unloading processes; existing jack loading is mostly single-stage or two-stage loading, with significant impact on the retaining structure during the loading process, and no linkage and coordination mechanism between loading and unloading has been established; monitoring and control have not yet formed a closed loop, and real-time monitoring data is difficult to directly feed back to the construction control system for dynamic correction. Summary of the Invention

[0004] To overcome the shortcomings of the existing technology, the present invention provides a graded pre-support replacement method for foundation pits based on dual control of strength and deformation.

[0005] To solve the above-mentioned technical problems, the technical solution adopted by the present invention is as follows: A graded pre-support replacement method for foundation pits based on dual control of strength and deformation includes the following steps: S1. Construct a collaborative stress model of soil layer-temporary support-permanent structure, and conduct collaborative stress analysis based on various working conditions of foundation pit excavation and structural construction to determine the design axial force of each temporary support and the corresponding deformation control threshold of the retaining structure; wherein, the temporary support includes the retaining structure, steel walers and multiple temporary supports erected between the steel walers, and the permanent structure includes the bottom slab, side walls and top slab. S2. When constructing the base slab and side walls of the permanent structure, simultaneously prepare test specimens under the same curing conditions during concrete pouring, and pre-embed strain sensors in the key stress areas of the base slab and side walls to monitor the concrete curing strength and structural stress changes in real time. S3. Obtain the instantaneous compressive strength of the specimen cured under the same conditions and the real-time deep horizontal displacement rate of the retaining structure, input them into the support replacement decision model for dual control determination of strength and deformation, and generate a support replacement permission instruction when the instantaneous compressive strength reaches the strength threshold determined in S1 and the deep horizontal displacement rate is continuously lower than the rate threshold determined in S1. S4. In response to the permission instruction for replacement of the support, through-hole jacks are installed between the two ends of the target temporary support to be removed and the steel waler. Pre-jacking force is applied step by step according to the grading system of each loading amount being 10% to 15% of the design axial force. After each loading, the pressure is stabilized for 10 to 15 minutes until the pre-jacking force reaches the design axial force value of the temporary support determined in S1. Then, the unloading is carried out step by step synchronously according to the grading system of each unloading amount being 10% to 15% of the design axial force. After each unloading, the pressure is stabilized for 10 to 15 minutes to transfer the support load borne by the target temporary support to the constructed base plate and side wall. S5. After the through-hole jack is completely unloaded, the target temporary support is removed. After the construction of the top plate of the permanent structure is completed and its concrete strength is qualified by the dual control judgment of S2 to S3, S4 to S5 are executed on the remaining temporary supports above in sequence to complete the step-by-step replacement of multiple temporary supports in the foundation pit. Throughout the entire process of support replacement, the monitoring and control system performs real-time monitoring and threshold early warning of the support axial force, enclosure structure deformation, and permanent structural stress, forming a dynamic closed-loop control.

[0006] S1 specifically includes: S11. Obtain the physical and mechanical parameters of the soil layer in the foundation pit, the geometric and stiffness parameters of the temporary support, and the cross-section and reinforcement parameters of the permanent structure. S12. Establish a three-dimensional collaborative finite element calculation model that includes soil, retaining structure, temporary support and permanent structure; S13. Simulate the entire process of excavating the foundation pit in layers, erecting temporary supports, pouring permanent structures in sections, replacing and dismantling temporary supports in stages, according to the construction sequence. S14. Extract the internal force and displacement envelope of the retaining structure under each working condition, as well as the stress response of the ultimate limit state and serviceability limit state of the permanent structure section bearing capacity. Calculate the design axial force value of each temporary support, the maximum allowable displacement limit of the retaining structure, and the allowable displacement rate threshold.

[0007] S2 further includes: After the foundation pit is excavated to the design elevation of the foundation, the bottom slab and side walls of the permanent structure are poured. When pouring the concrete for the base slab and side walls, test specimens cured under the same conditions are prepared simultaneously on the construction site. Strain sensors are pre-embedded in the key stress areas of the base plate and side walls to monitor the changes in internal strain and structural stress during the concrete hydration and hardening process in real time.

[0008] S3 specifically includes: S31. Detect the instantaneous compressive strength of specimens cured under the same conditions, and verify the stress distribution state of the permanent structure through the monitoring data of the pre-embedded strain sensor; S32. Continuously collect deep horizontal displacement data using inclinometers installed within the enclosure structure, and calculate the horizontal displacement rate and cumulative displacement over a continuous 2-hour period. S33. Input the instantaneous compressive strength, horizontal displacement rate and cumulative displacement into the bracing replacement decision model. When the instantaneous compressive strength of the component reaches more than 80% of the design strength, and the deep horizontal displacement rate of the enclosure structure is continuously lower than 0.02 mm / h and the cumulative displacement does not exceed the maximum allowable displacement limit determined in S1, it is determined that the bracing replacement conditions are met and a bracing replacement permission command is output.

[0009] In step S4, the pre-load is applied in stages according to a grading system where each loading level is 10% to 15% of the design axial force. After each loading level, the pressure is stabilized for 10 to 15 minutes. During each stage of pressure stabilization, axial force gauge readings and retaining structure inclination data are collected in real time. Once the measured data fluctuations are within the preset stability tolerance range, the next stage of loading is triggered until the pre-jacking force reaches the design axial force value of the temporary support.

[0010] In S4, the unloading is carried out synchronously in stages according to a grading system where the unloading amount at each stage is 10% to 15% of the design axial force. During the process of stabilizing the pressure for 10 to 15 minutes after each unloading stage: After each unloading stage, the remaining axial force of the target temporary support, the displacement rate of the enclosure structure, and the stress increment of the strain sensor at the corresponding part of the permanent structure are obtained simultaneously. After confirming that the stress increment of the permanent structure does not exceed the preset allowable range of structural bearing capacity and that the displacement of the enclosure structure is stable, the next unloading stage is executed until the through-hole jack is completely unloaded.

[0011] During the staged pre-loading or staged synchronous unloading process, when the deep horizontal displacement rate of the retaining structure exceeds the allowable displacement rate threshold determined in S1, or the single-stage axial force change rate monitored by the axial force gauge exceeds 20%, the monitoring and control system automatically pauses the current loading or unloading action and extends the pressure stabilization time of the current stage to 30 minutes; the operation resumes after the monitored indicators return to the allowable range; if the indicators still exceed the allowable range after the pressure stabilization is extended, the pressure of the through-hole jack is adjusted in the reverse direction to compensate for the deformation of the retaining structure.

[0012] The process of replacing the remaining temporary supports in S5 specifically includes: S51. After the temporary support below is removed, pour the top slab concrete of the permanent structure and simultaneously prepare the top slab curing test specimen under the same conditions. S52. Perform the dual-control determination of the top slab concrete strength and the deformation rate of the retaining structure as described in step three. S53. After the concrete strength of the top slab and the deformation of the retaining structure meet the dual control criteria, install a through-type jack between the end of the upper temporary support and the steel waler near the top slab elevation. Apply pre-jacking force according to the method described in step four and perform staged synchronous unloading to transfer the load of the upper temporary support to the top slab and side walls, thus completing the removal of the upper temporary support. The process of real-time monitoring and threshold early warning through the monitoring and control system during the entire support replacement process specifically includes: Deploy support axial force sensors, deep inclinometers of the retaining structure, and pre-embedded strain sensors in the permanent structure, and transmit the data collected by each sensor to the monitoring and control system in real time; The monitoring and control system performs parallel threshold comparison analysis on the axial force change rate, deep horizontal displacement rate, cumulative displacement and concrete stress. Based on the deviation between the measured stress growth rate of the permanent structure and the theoretical calculation value, the unloading level difference and unloading rate of subsequent stages are dynamically adjusted to match the support load release rate with the stiffness growth rate of the permanent structure.

[0013] Compared with the prior art, the beneficial effects of the present invention are as follows: Before removing temporary supports, this invention applies pre-jacking force in stages using a through-hole jack, actively establishing a load transfer path from temporary supports through the enclosure structure to the permanent structure, achieving a seamless connection between "replace first, then dismantle," and effectively avoiding the structural instability risk caused by sudden load changes in the traditional "dismantle first, then repair" model.

[0014] This invention establishes a support replacement decision model with the strength development of permanent structural concrete and the deformation rate of the retaining structure as dual control indicators. It incorporates the strength of specimens cured under the same conditions and the deep horizontal displacement rate into a unified judgment framework, overcoming the shortcomings of traditional methods that rely solely on a single strength indicator or engineering experience.

[0015] This invention employs a 10%–15% incremental loading and unloading process, with each stage stabilizing for 10–15 minutes, significantly reducing the impact on the enclosure structure during load transfer. Simultaneously, it establishes a coordinated loading and unloading mechanism, enabling the gradual transfer of supporting internal forces to the permanent structure.

[0016] This invention directly connects real-time monitoring data such as supporting axial force, enclosure structure deformation, and permanent structural stress to the monitoring and control system. When the monitoring indicators exceed the limits, the operation is automatically suspended and the pressure stabilization time is extended. If necessary, the pressure of the jacks is adjusted in the reverse direction to actively compensate for the deformation, forming a dynamic closed loop of "monitoring-early warning-control".

[0017] This invention significantly shortens the support replacement construction cycle and reduces the time occupied by temporary supports through safe, fast, and green support conversion. At the same time, it reduces material consumption and labor costs, which is in line with the development direction of green and intelligent construction and has broad market promotion prospects. Attached Figure Description

[0018] Figure 1 This is a schematic diagram of the construction process of the present invention; Figure 2 This is a schematic diagram of the specific process in step S1 of the present invention; Figure 3 This is a schematic diagram of the specific process in step S3 of the present invention. Detailed Implementation

[0019] To better understand the above-mentioned objectives, features, and advantages of the present invention, the present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments. It should be noted that, unless otherwise specified, the embodiments and features described in these embodiments can be combined with each other.

[0020] Many specific details are set forth in the following description in order to provide a full understanding of the invention. However, the invention may also be implemented in other ways different from those described herein. Therefore, the scope of protection of the invention is not limited to the specific embodiments disclosed below.

[0021] like Figures 1 to 3 As shown, a graded pre-support replacement method for foundation pits based on dual control of strength and deformation includes the following steps: S1. Construct a collaborative stress model of soil layer-temporary support-permanent structure. Perform collaborative stress analysis based on various working conditions of foundation pit excavation and structural construction to determine the design axial force of each temporary support and the corresponding deformation control threshold of the retaining structure. Among them, the temporary support includes the retaining structure, steel walers and multiple temporary supports erected between the steel walers, and the permanent structure includes the bottom slab, side walls and top slab. S2. For the base slab and side walls of the permanent construction structure, test specimens with the same curing conditions are made simultaneously when pouring concrete, and strain sensors are pre-embedded in the key stress areas of the base slab and side walls to monitor the concrete curing strength and structural stress changes in real time. S3. Obtain the instantaneous compressive strength of the specimen cured under the same conditions and the real-time deep horizontal displacement rate of the retaining structure, input them into the replacement support decision model for dual control judgment of strength and deformation. When the instantaneous compressive strength reaches the strength threshold determined in S1 and the deep horizontal displacement rate is continuously lower than the rate threshold determined in S1, generate a replacement support permission command. S4. In response to the permission order for replacement of the support, through-hole jacks are installed between the two ends of the target temporary support to be removed and the steel waler. Pre-jacking force is applied step by step according to the grading system of each loading amount being 10% to 15% of the design axial force. After each loading, the pressure is stabilized for 10 to 15 minutes until the pre-jacking force reaches the design axial force value of the temporary support determined in S1. Then, unloading is carried out step by step synchronously according to the grading system of each unloading amount being 10% to 15% of the design axial force. After each unloading, the pressure is stabilized for 10 to 15 minutes to transfer the support load borne by the target temporary support to the already constructed base slab and side walls. S5. After the through-hole jack is completely unloaded, remove the target temporary support; after the construction of the permanent structure's top slab is completed and its concrete strength is qualified by the dual control judgment of S2 to S3, execute S4 to S5 on the remaining temporary supports above in sequence to complete the step-by-step replacement of multiple temporary supports in the foundation pit. Throughout the entire process of support replacement, the monitoring and control system performs real-time monitoring and threshold early warning of the support axial force, enclosure structure deformation, and permanent structural stress, forming a dynamic closed-loop control.

[0022] Preferably, S1 specifically includes: S11. Obtain the physical and mechanical parameters of the foundation pit soil layers, the geometric and stiffness parameters of the temporary support, and the cross-sectional and reinforcement parameters of the permanent structure. Specifically, the physical and mechanical parameters of the soil layers include the layer thickness, unit weight, cohesion, internal friction angle, and water and soil calculation mode for each soil layer. The geometric and stiffness parameters of the temporary support include the specifications and spacing of the retaining piles or steel sections, the cross-sectional form of the steel walers, the material and cross-sectional dimensions of the temporary supports, and the horizontal spacing. The cross-sectional and reinforcement parameters of the permanent structure include the thickness of the bottom slab, side walls, and top slab, the concrete strength grade, and the configuration of the reinforcing steel bars. S12. Establish a three-dimensional collaborative finite element calculation model that includes soil, retaining structure, temporary support and permanent structure; this model is used to simulate the load transfer path and collaborative deformation relationship between various structural components during the entire construction process. S13. Simulate the entire process of excavating the foundation pit in layers, erecting temporary supports, pouring permanent structures in sections, replacing and dismantling temporary supports in stages, according to the construction sequence. S14. Extract the internal force and displacement envelope of the retaining structure under each working condition, as well as the stress response of the ultimate limit state and serviceability limit state of the permanent structure section bearing capacity. Calculate the design axial force value of each temporary support, the maximum allowable displacement limit of the retaining structure, and the allowable displacement rate threshold, providing a data basis for subsequent graded pre-loading and support replacement decisions.

[0023] Preferably, S2 further includes: After the foundation pit is excavated to the design elevation of the foundation, the base slab and side walls of the permanent structure are poured. When pouring the concrete for the base slab and side walls, specimens cured under the same conditions are prepared simultaneously on the construction site. The specimens cured under the same conditions are in the same curing environment as the main structure, and their compressive strength is used to indirectly characterize the instantaneous strength development level of the concrete of the permanent structure. Strain sensors are pre-embedded in key stress areas of the base slab and side walls to monitor changes in internal strain and structural stress during the concrete hydration and hardening process in real time, in order to verify whether the permanent structure has the stress conditions to bear transferred loads.

[0024] Preferably, S3 specifically includes: S31. Detect the instantaneous compressive strength of specimens cured under the same conditions, and verify the stress distribution state of the permanent structure through the monitoring data of the pre-embedded strain sensor; S32. Continuously collect deep horizontal displacement data using inclinometers installed within the enclosure structure, and calculate the horizontal displacement rate and cumulative displacement over a continuous 2-hour period. S33. Input the instantaneous compressive strength, horizontal displacement rate, and cumulative displacement into the bracing replacement decision model. When the instantaneous compressive strength of the component reaches more than 80% of the design strength, and the deep horizontal displacement rate of the enclosure structure is continuously lower than 0.02 mm / h, and the cumulative displacement does not exceed the maximum allowable displacement limit determined in S1, it is determined that the bracing replacement conditions are met and a bracing replacement permission command is output. The strength index is used to ensure that the permanent structure has sufficient bearing capacity, and the deformation rate index is used to ensure that the enclosure structure is in a stable state during the load transfer process, avoiding the risk of instability caused by sudden load changes.

[0025] Preferably, in S4, the preload is applied in stages according to a gradation system where each loading level is 10% to 15% of the design axial force, and the pressure is stabilized for 10 to 15 minutes after each loading stage: During each stage of pressure stabilization, axial force gauge readings and inclination data of the retaining structure are collected in real time. Once the measured data fluctuations are within the preset stability tolerance range, the next stage of loading is triggered until the pre-jacking force reaches the design axial force value of the temporary support. Through step-by-step loading and pressure stabilization observation, a load transfer path is actively established from the temporary support through the jacks to the retaining structure and permanent structure.

[0026] Preferably, in S4, the unloading is carried out synchronously in stages according to a grading system where the unloading amount at each stage is 10% to 15% of the design axial force. During the process of stabilizing the pressure for 10 to 15 minutes after each unloading stage: After each unloading stage, the remaining axial force of the target temporary support, the displacement rate of the enclosure structure, and the stress increment of the strain sensor at the corresponding part of the permanent structure are simultaneously acquired. After confirming that the stress increment of the permanent structure does not exceed the preset allowable range of structural bearing capacity and that the displacement of the enclosure structure is stable, the next unloading stage is executed until the through-hole jack is completely unloaded. Through this step-by-step reverse unloading process, the internal force of the support is smoothly released and transferred to the permanent structure in stages, achieving a seamless connection of "replace first, then dismantle".

[0027] During the staged pre-loading or staged synchronous unloading process, when the deep horizontal displacement rate of the retaining structure exceeds the allowable displacement rate threshold determined in S1, or the single-stage axial force change rate monitored by the axial force gauge exceeds 20%, the monitoring and control system automatically pauses the current loading or unloading action and extends the pressure stabilization time of the current stage to 30 minutes; the operation resumes after the monitored indicators return to the allowable range; if the indicators still exceed the allowable range after the pressure stabilization is extended, the pressure of the through-hole jack is adjusted in the reverse direction to compensate for the deformation of the retaining structure.

[0028] Preferably, the process of performing support replacement operations on the remaining temporary supports above in S5 specifically includes: S51. After the temporary support below is removed, pour the concrete for the top slab of the permanent structure and simultaneously prepare test specimens of the top slab under the same curing conditions. S52. Perform the dual-control determination of the strength of the top slab concrete and the deformation rate of the retaining structure in step three. S53. After the concrete strength of the top slab and the deformation of the retaining structure meet the dual control judgment conditions, install a through-hole jack between the end of the upper temporary support located near the top slab elevation and the steel waler. Apply pre-jacking force according to the method in step four and perform graded synchronous unloading to transfer the load of the upper temporary support to the top slab and side walls, and complete the removal of the upper temporary support, thereby realizing the complete conversion of the full-section force system from temporary support to permanent structure.

[0029] Preferably, the process of real-time monitoring and threshold early warning through a monitoring and control system throughout the entire support replacement process specifically includes: Deploy support axial force sensors, deep inclinometers of the retaining structure, and pre-embedded strain sensors in the permanent structure, and transmit the data collected by each sensor to the monitoring and control system in real time; The monitoring and control system performs parallel threshold comparison analysis on the axial force change rate, deep horizontal displacement rate, cumulative displacement and concrete stress. Based on the deviation between the measured stress growth rate of the permanent structure and the theoretical calculation value, the unloading level difference and unloading rate of subsequent stages are dynamically adjusted to match the support load release rate with the stiffness growth rate of the permanent structure.

[0030] The above description only illustrates the preferred embodiments of the present invention. However, the present invention is not limited to the above embodiments. Within the scope of knowledge possessed by those skilled in the art, various changes can be made without departing from the spirit of the present invention, and all such changes should be included within the protection scope of the present invention.

Claims

1. A method for graded pre-support replacement of foundation pits based on dual control of strength and deformation, characterized in that, Includes the following steps: S1. Construct a collaborative stress model of soil layer-temporary support-permanent structure, and conduct collaborative stress analysis based on various working conditions of foundation pit excavation and structural construction to determine the design axial force of each temporary support and the corresponding deformation control threshold of the retaining structure; wherein, the temporary support includes the retaining structure, steel walers and multiple temporary supports erected between the steel walers, and the permanent structure includes the bottom slab, side walls and top slab. S2. When constructing the base slab and side walls of the permanent structure, simultaneously prepare test specimens under the same curing conditions during concrete pouring, and pre-embed strain sensors in the key stress areas of the base slab and side walls to monitor the concrete curing strength and structural stress changes in real time. S3. Obtain the instantaneous compressive strength of the specimen cured under the same conditions and the real-time deep horizontal displacement rate of the retaining structure, input them into the support replacement decision model for dual control determination of strength and deformation, and generate a support replacement permission instruction when the instantaneous compressive strength reaches the strength threshold determined in S1 and the deep horizontal displacement rate is continuously lower than the rate threshold determined in S1. S4. In response to the permission instruction for replacement of the support, through-hole jacks are installed between the two ends of the target temporary support to be removed and the steel waler. Pre-jacking force is applied step by step according to the grading system of each loading amount being 10% to 15% of the design axial force. After each loading, the pressure is stabilized for 10 to 15 minutes until the pre-jacking force reaches the design axial force value of the temporary support determined in S1. Then, the unloading is carried out step by step synchronously according to the grading system of each unloading amount being 10% to 15% of the design axial force. After each unloading, the pressure is stabilized for 10 to 15 minutes to transfer the support load borne by the target temporary support to the constructed base plate and side wall. S5. After the through-hole jack is completely unloaded, the target temporary support is removed. After the construction of the top plate of the permanent structure is completed and its concrete strength is qualified by the dual control judgment of S2 to S3, S4 to S5 are executed on the remaining temporary supports above in sequence to complete the step-by-step replacement of multiple temporary supports in the foundation pit. Throughout the entire process of support replacement, the monitoring and control system performs real-time monitoring and threshold early warning of the support axial force, enclosure structure deformation, and permanent structural stress, forming a dynamic closed-loop control.

2. The method for graded pre-jacking and support replacement of foundation pits based on dual control of strength and deformation as described in claim 1, characterized in that: S1 specifically includes: S11. Obtain the physical and mechanical parameters of the soil layer in the foundation pit, the geometric and stiffness parameters of the temporary support, and the cross-section and reinforcement parameters of the permanent structure. S12. Establish a three-dimensional collaborative finite element calculation model that includes soil, retaining structure, temporary support and permanent structure; S13. Simulate the entire process of excavating the foundation pit in layers, erecting temporary supports, pouring permanent structures in sections, replacing and dismantling temporary supports in stages, according to the construction sequence. S14. Extract the internal force and displacement envelope of the retaining structure under each working condition, as well as the stress response of the ultimate limit state and serviceability limit state of the permanent structure section bearing capacity. Calculate the design axial force value of each temporary support, the maximum allowable displacement limit of the retaining structure, and the allowable displacement rate threshold.

3. The method for graded pre-jacking and support replacement of foundation pits based on dual control of strength and deformation as described in claim 1, characterized in that: S2 further includes: After the foundation pit is excavated to the design elevation of the foundation, the bottom slab and side walls of the permanent structure are poured. When pouring the concrete for the base slab and side walls, test specimens cured under the same conditions are prepared simultaneously on the construction site. Strain sensors are pre-embedded in the key stress areas of the base plate and side walls to monitor the changes in internal strain and structural stress during the concrete hydration and hardening process in real time.

4. The method for graded pre-jacking and support replacement of foundation pits based on dual control of strength and deformation as described in claim 1, characterized in that: S3 specifically includes: S31. Detect the instantaneous compressive strength of specimens cured under the same conditions, and verify the stress distribution state of the permanent structure through the monitoring data of the pre-embedded strain sensor; S32. Continuously collect deep horizontal displacement data using inclinometers installed within the enclosure structure, and calculate the horizontal displacement rate and cumulative displacement over a continuous 2-hour period. S33. Input the instantaneous compressive strength, horizontal displacement rate and cumulative displacement into the bracing replacement decision model. When the instantaneous compressive strength of the component reaches more than 80% of the design strength, and the deep horizontal displacement rate of the enclosure structure is continuously lower than 0.02 mm / h and the cumulative displacement does not exceed the maximum allowable displacement limit determined in S1, it is determined that the bracing replacement conditions are met and a bracing replacement permission command is output.

5. The method for graded pre-jacking and support replacement of foundation pits based on dual control of strength and deformation as described in claim 1, characterized in that: In step S4, the pre-load is applied in stages according to a grading system where each loading level is 10% to 15% of the design axial force. After each loading level, the pressure is stabilized for 10 to 15 minutes. During each stage of pressure stabilization, axial force gauge readings and retaining structure inclination data are collected in real time. Once the measured data fluctuations are within the preset stability tolerance range, the next stage of loading is triggered until the pre-jacking force reaches the design axial force value of the temporary support.

6. The method for graded pre-jacking and support replacement of foundation pits based on dual control of strength and deformation as described in claim 1, characterized in that: In S4, the unloading is carried out synchronously in stages according to a grading system where the unloading amount at each stage is 10% to 15% of the design axial force. During the process of stabilizing the pressure for 10 to 15 minutes after each unloading stage: After each unloading stage, the remaining axial force of the target temporary support, the displacement rate of the enclosure structure, and the stress increment of the strain sensor at the corresponding part of the permanent structure are obtained simultaneously. After confirming that the stress increment of the permanent structure does not exceed the preset allowable range of structural bearing capacity and that the displacement of the enclosure structure is stable, the next unloading stage is executed until the through-hole jack is completely unloaded.

7. The method for graded pre-jacking and support replacement of foundation pits based on dual control of strength and deformation as described in claim 6, characterized in that: During the staged pre-loading or staged synchronous unloading process, when the deep horizontal displacement rate of the retaining structure exceeds the allowable displacement rate threshold determined in S1, or the single-stage axial force change rate monitored by the axial force gauge exceeds 20%, the monitoring and control system automatically pauses the current loading or unloading action and extends the pressure stabilization time of the current stage to 30 minutes; the operation resumes after the monitored indicators return to the allowable range; if the indicators still exceed the allowable range after the pressure stabilization is extended, the pressure of the through-hole jack is adjusted in the reverse direction to compensate for the deformation of the retaining structure.

8. The method for graded pre-jacking and support replacement of foundation pits based on dual control of strength and deformation as described in claim 1, characterized in that: The process of replacing the remaining temporary supports in S5 specifically includes: S51. After the temporary support below is removed, pour the top slab concrete of the permanent structure and simultaneously prepare the top slab curing test specimen under the same conditions. S52. Perform the dual-control determination of the top slab concrete strength and the deformation rate of the retaining structure as described in step three. S53. After the concrete strength of the top slab and the deformation of the retaining structure meet the dual control judgment conditions, install a through-hole jack between the end of the upper temporary support located near the top slab elevation and the steel waler. Apply pre-jacking force according to the method described in step four and perform graded synchronous unloading to transfer the load of the upper temporary support to the top slab and side walls, and complete the removal of the upper temporary support.

9. The method for graded pre-jacking and support replacement of foundation pits based on dual control of strength and deformation as described in claim 1, characterized in that: The process of real-time monitoring and threshold early warning through the monitoring and control system during the entire support replacement process specifically includes: Deploy support axial force sensors, deep inclinometers of the retaining structure, and pre-embedded strain sensors in the permanent structure, and transmit the data collected by each sensor to the monitoring and control system in real time; The monitoring and control system performs parallel threshold comparison analysis on the axial force change rate, deep horizontal displacement rate, cumulative displacement and concrete stress. Based on the deviation between the measured stress growth rate of the permanent structure and the theoretical calculation value, the unloading level difference and unloading rate of subsequent stages are dynamically adjusted to match the support load release rate with the stiffness growth rate of the permanent structure.