An RPC precast box culvert molding device with an integrated circulating thermal curing system

By integrating a circulating thermal curing system, the problems of low thermal energy utilization and high energy consumption in the RPC precast box culvert forming device were solved, realizing efficient recovery and recycling of waste heat, and improving production efficiency and component quality.

CN123103840APending Publication Date: 2026-11-17POLY CHANGDA ENGINEERING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611224919.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-08-13
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

Existing RPC precast box culvert forming and thermal curing equipment suffers from heat energy waste and high energy consumption, especially when waste heat is not effectively recovered and recycled.

Method used

An integrated circulating thermal curing system is adopted, including an insulation cover device, a thermal circulation device, and an intelligent control system. The system recovers the waste heat of high-temperature exhaust gas through a heat exchanger unit, stores thermal energy using a phase change heat storage device, and delivers the thermal energy to the curing space through a preheating circulation pipeline, thereby realizing the recycling and optimized allocation of thermal energy.

Benefits of technology

It significantly reduced energy consumption, improved maintenance efficiency, reduced waste heat, ensured temperature uniformity and component quality, and reduced production costs and operational complexity.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123103840A_ABST
    Figure CN123103840A_ABST
Patent Text Reader

Abstract

This invention discloses an RPC precast box culvert molding device with an integrated circulating thermal curing system, comprising a molding mold, a telescopic insulation cover device, a thermal circulation device, a heat source supply system, and an intelligent control system. The telescopic insulation cover can be closed to form a sealed curing space; the thermal circulation device recovers waste heat from curing exhaust gas via a heat exchanger, stores the heat energy through a phase change heat storage unit, and then transmits the waste heat to preheat new components; the intelligent control system achieves phased automatic temperature control based on multi-point temperature measurement. This invention recovers and recycles waste heat from curing, significantly reducing production energy consumption; the mechanically opening and closing insulation cover simplifies the process and reduces heat loss; precise temperature control reduces the risk of component cracking and improves finished product quality; it eliminates the need for dedicated steam curing soil construction facilities, making it suitable for various scenarios such as factory batch prefabrication and on-site production, and possesses advantages such as energy saving, high efficiency, and low operation and maintenance costs.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of box culvert technology, and in particular to an RPC precast box culvert forming device with an integrated circulating thermal curing system. Background Technology

[0002] Reactive powder concrete (RPC) precast box culverts are widely used in municipal infrastructure such as urban integrated pipe corridors and drainage tunnels due to their high strength, high durability, and excellent impermeability. RPC materials require high-temperature steam curing to fully complete the hydration reaction and achieve the designed mechanical properties. In actual use, the energy consumption and thermal energy utilization efficiency of the thermal curing process directly affect the production cost and market competitiveness of the product. Therefore, optimizing the thermal energy utilization method of the thermal curing system has become an important technical issue in the production of RPC precast box culverts.

[0003] However, existing RPC precast box culvert forming and thermal curing equipment still has significant shortcomings in terms of thermal energy utilization. On the one hand, most thermal curing systems adopt open or semi-open thermal circulation, and a large amount of waste heat is directly discharged into the atmosphere with the exhaust gas after curing, resulting in high energy consumption and high production costs. On the other hand, after each curing cycle, when a new precast component is placed into the mold, the heating system needs to be restarted to heat up the curing cavity, leading to a phased waste of energy and further exacerbating the energy burden.

[0004] To address the aforementioned problems, this invention aims to provide an RPC precast box culvert forming device with an integrated circulating thermal curing system, which enables the effective recovery and recycling of thermal energy, thereby significantly reducing energy consumption, improving curing efficiency, and achieving optimal configuration of thermal energy utilization. Summary of the Invention

[0005] The present invention aims to solve the technical problems of low thermal energy utilization, high energy consumption, and additional energy consumption required in the preheating stage of new components in the existing thermal curing system.

[0006] To address the above problems, this invention provides an RPC precast box culvert molding device with an integrated circulating thermal curing system, comprising: The molding die includes a working base and an outer mold and an inner mold set on the working base. The outer mold and the inner mold enclose a cavity for pouring RPC concrete. The heat insulation cover device includes two telescopic cover frames that are slidably set on the working base and a heat insulation film set on the telescopic cover frames. The heat insulation cover device wraps the forming mold and forms a curing space through the telescopic cover frames and the heat insulation film. The heat insulation cover device is equipped with a hot air inlet and a hot air outlet. The heat circulation device includes a heat exchanger unit, a thermal energy storage unit, and a preheating circulation pipeline. The heat exchanger unit is located on the pipeline at the hot air outlet and is used to receive high-temperature exhaust gas from the curing space and exchange heat with a low-temperature heat exchange medium. The thermal energy storage unit is connected to the heat exchanger unit and is used to store the heat energy transferred by the heat exchanger unit. One end of the preheating circulation pipeline is connected to the thermal energy storage unit, and the other end is connected to the hot air inlet, and is used to transport the heat energy released by the thermal energy storage unit to the curing space. The heat source supply system, with pipes connected to the hot air inlet, is used to provide the heat energy required for the initial heating of the curing space; The intelligent control system includes temperature sensors, controllers, and actuators, which coordinate and control the working status of the heat exchanger unit, thermal energy storage unit, and heat source supply system based on the temperature signals from each temperature measurement point.

[0007] Preferably, the telescopic cover includes a first frame and a second frame, a hydraulic telescopic rod is provided between the first frame and the second frame, and movable pulleys are provided at the bottom of both the first frame and the second frame. A track that cooperates with the movable pulleys is provided on the working base.

[0008] Preferably, the first frame and the second frame are provided with fixing ears for fixing the insulation film, and the insulation film is provided with straps; a tension spring is provided between the top of the first frame and the second frame, and a number of positioning blocks are provided on the tension spring, and the positioning blocks are detachably connected to the insulation film by Velcro.

[0009] Preferably, the heat exchanger unit adopts a plate heat exchanger or a tube heat exchanger and is configured as a counter-current heat exchange structure.

[0010] Preferably, the thermal energy storage unit is a phase change thermal storage device, which is filled with paraffin or salt phase change thermal storage material, and the phase change temperature range is 60°C to 120°C.

[0011] Preferably, a preheating fan is installed on the preheating circulation pipeline. The air volume of the preheating fan is adjustable from 500 m³ / h to 2000 m³ / h, and the air pressure is adjustable from 200 Pa to 800 Pa. The fan is used to drive hot air to circulate between the thermal energy storage unit and the maintenance space.

[0012] Preferably, the intelligent control system is configured in a phased control mode, including: During the curing phase, the controller controls the heat source supply system to supply heat to the curing space, maintaining the curing temperature at 80°C to 90°C, while simultaneously controlling the heat exchanger unit to transfer the discharged waste heat to the thermal energy storage unit. During the preheating stage, the controller controls the heat storage unit to release heat energy, and the hot air is delivered to the curing space by the preheating fan to preheat the newly molded components. The preheating temperature rise rate is 3℃ / min to 8℃ / min. During standby, the thermal energy storage unit maintains its thermal energy storage state, with the thermal storage temperature not lower than 60℃.

[0013] Preferably, the temperature sensors include an exhaust temperature sensor located at the hot air outlet, a heat storage temperature sensor located in the heat storage unit, and a curing zone temperature sensor located in the cavity.

[0014] The beneficial effects of this invention are as follows: In this invention, the heat exchanger unit, the thermal energy storage unit and the preheating circulation pipeline work together to efficiently recover and reuse the waste heat of the high-temperature exhaust gas directly discharged during the traditional RPC thermal curing process, effectively solving the industry pain points of high energy consumption and low thermal energy utilization in thermal curing.

[0015] The system employs counter-flow plate or tubular heat exchangers to efficiently recover waste heat from curing exhaust gases. It also utilizes phase change heat storage units for heat storage and peak regulation, ensuring that the temperature storage during standby is no lower than 60°C. The recovered heat energy is reused through a preheating circulation pipeline to preheat newly molded components. The heat source only undertakes initial heating and curing heat replenishment, significantly reducing operating energy consumption and peak power of the heat source under batch production conditions. The system is equipped with preheating fans with adjustable air volume and pressure to ensure uniform distribution of hot air in the curing space and enhance heat exchange efficiency.

[0016] The intelligent control system adopts a phased closed-loop control mode. During the preheating stage, the heating rate is strictly controlled at 3℃ / min~8℃ / min, and during the curing stage, the temperature is stably maintained at 80℃~90℃. The system achieves full-link temperature control feedback through multiple temperature sensors in the cavity curing area, hot air outlet, and heat storage unit. Combined with the sealed insulation space, the system maintains a uniform temperature field, effectively reducing the risk of temperature cracks and strength dispersion in RPC components, and ensuring uniform and sufficient hydration reaction.

[0017] After the components are poured, they are cured in situ to avoid damage to the microstructure of low-strength RPC during early transportation; the hydraulically driven telescopic cover opens and closes along the base track, replacing manual erection and dismantling of the insulation shed, which greatly shortens auxiliary time; the tensioned detachable insulation film has good airtightness and low reciprocating wear, and can be replaced separately after damage, resulting in low maintenance costs; the mechanical drive mode reduces safety hazards of high-altitude operations.

[0018] No supporting civil engineering facilities such as fixed curing kilns and steam curing tanks are required, and it can be quickly deployed in standardized factory areas or project sites; it has strong heat source compatibility and can be adapted to various forms such as electric heating, industrial waste heat, steam, and gas hot air; the heat storage unit can smooth out heat source power fluctuations and reduce heat source stability requirements and fixed infrastructure investment. Attached Figure Description

[0019] The accompanying drawings, which are included to provide a further understanding of the invention and form part of this application, illustrate exemplary embodiments of the invention and are used to explain the invention, but do not constitute an undue limitation of the invention.

[0020] In the attached image:

[0021] Figure 1 Schematic diagram of RPC precast box culvert molding device with integrated circulating thermal curing system Figure 1 ; Figure 2 Schematic diagram of RPC precast box culvert molding device with integrated circulating thermal curing system Figure 2 ; Figure 3 A flowchart of the RPC precast box culvert forming device for integrating a circulating thermal curing system.

[0022] In the diagram: 1. Molding mold; 11. Working base; 12. Outer mold; 13. Inner mold; 2. Insulation cover device; 21. Telescopic cover frame; 211. First frame; 2111. Fixing ear; 212. Second frame; 213. Hydraulic telescopic rod; 214. Moving pulley; 2141. Track; 215. Tension spring; 2151. Positioning block; 22. Insulation film; 24. Hot air inlet; 25. Hot air outlet; 3. Heat circulation device. Detailed Implementation

[0023] The technical solution of the present invention will now be described with reference to the accompanying drawings. However, the described embodiments are only some embodiments of the present invention. All other embodiments obtained by those skilled in the art based on the embodiments of the present invention without creative effort are within the scope of protection of the present invention.

[0024] like Figures 1 to 3 As shown, the present invention provides an RPC precast box culvert forming device with an integrated circulating thermal curing system, comprising: The molding die 1 includes a working base 11 and an outer mold 12 and an inner mold 13 disposed on the working base 11. The outer mold 12 and the inner mold 13 enclose a cavity for pouring RPC concrete. The heat insulation cover device 2 includes two telescopic cover frames 21 that are slidably mounted on the working base 11 and a heat insulation film 22 mounted on the telescopic cover frames 21. The heat insulation cover device 2 wraps the molding mold 1 and forms a curing space through the telescopic cover frames 21 and the heat insulation film 22. The heat insulation cover device 2 is provided with a hot air inlet 24 and a hot air outlet 25. The heat circulation device 3 includes a heat exchanger unit, a thermal energy storage unit, and a preheating circulation pipeline. The heat exchanger unit is located on the pipeline at the hot air outlet 25 and is used to receive high-temperature exhaust gas from the curing space and exchange heat with a low-temperature heat exchange medium. The thermal energy storage unit is connected to the heat exchanger unit and is used to store the heat energy transferred by the heat exchanger unit. One end of the preheating circulation pipeline is connected to the thermal energy storage unit, and the other end is connected to the hot air inlet 24, which is used to transport the heat energy released by the thermal energy storage unit to the curing space. The heat source supply system, connected to the hot air inlet 24, is used to provide the heat energy required for the initial heating of the curing space; The intelligent control system includes temperature sensors, controllers, and actuators, which coordinate and control the working status of the heat exchanger unit, thermal energy storage unit, and heat source supply system based on the temperature signals from each temperature measurement point.

[0025] Specifically, the molding die unit 1 is composed of a working base 11, an outer mold 12, and an inner mold 13. The working base 11 serves as the overall load-bearing foundation of the device, employing a frame structure welded from structural steel. A high-precision reference surface is set on its surface to provide a positioning and installation reference for the outer mold 12 and the inner mold 13, while also providing an installation carrier for the running track 2141 of the insulation cover device 2. Both the outer mold 12 and the inner mold 13 are fixedly installed on the positioning surface of the working base 11, arranged radially correspondingly to form a closed cavity that matches the cross-sectional shape of the precast box culvert. This cavity provides a spatial carrier for the casting and molding of the reactive powder concrete.

[0026] The outer mold 12 adopts a box-shaped steel structure, formed by splicing and welding high-strength steel plates. Longitudinal and transverse stiffening ribs are installed on the inner wall to enhance the overall structural rigidity of the outer mold 12 and resist the deformation risk caused by internal and external pressure differences and temperature stress during heat curing. A concrete pouring port is provided at the top of the outer mold 12, equipped with an openable and closable sealing cover. After pouring, the port can be sealed to reduce hot air leakage during the heat curing stage. The inner mold 13 adopts a hollow steel structure, made of carbon structural steel plates. The outer surface can be textured according to the requirements of the component to improve the surface performance of the molded component. High-temperature resistant sealing components are installed at the joint between the outer mold 12 and the inner mold 13 to ensure the sealing performance of the slurry during the pouring stage and the airtightness during the curing stage.

[0027] In this embodiment, the molding die 1 unit provides molding constraints for the reactive powder concrete, ensuring the dimensional and structural accuracy of the precast box culvert; simultaneously, it serves as the internal boundary of the thermal curing space, cooperating with the external insulation cover device 2 to form a layered thermal environment, bearing the temperature load of the thermal curing process. The integrated design of the working base 11 realizes the integrated layout of molding and curing functions, reducing installation errors of multi-system combinations.

[0028] The rigidity-enhancing design of the mold itself can reduce the amount of structural deformation during the heat curing process and ensure the consistency of the component molding dimensions; the joint sealing design can reduce the leakage of hot air along the mold gaps and reduce unnecessary heat loss; the integrated base design improves the overall integration of the device and facilitates on-site installation and production scheduling.

[0029] Specifically, the heat source supply system is connected to the air supply pipeline of the hot air inlet 24, and mainly consists of heating elements and air supply components, which can output hot air that meets the temperature requirements. The heating elements can be either electric heating elements or gas burners, which are adapted to different energy supply conditions; the air supply components provide power for the flow of hot air, ensuring that the hot air can be evenly delivered to all areas of the curing space.

[0030] The heat source supply system and the preheating circulation pipeline are linked by a three-way valve to switch between the two pipelines. The three-way valve is located on the front end of the hot air inlet 24 and can switch between the heat source supply path and the preheating circulation path. The three-way valve has a fast response capability.

[0031] The core function of the heat source supply system is to provide an external heat source to the curing space during the initial heating stage of curing, enabling the temperature of the curing space to rise rapidly to the curing temperature required for the hydration reaction of the reactive powder concrete, ensuring the full initiation and progress of the hydration reaction. When the heat stored in the thermal energy storage unit is insufficient to meet the preheating requirements, the heat source supply system can also participate in the preheating process as a supplementary heat source to ensure that the preheating temperature reaches the standard. The three-way valve enables the switching between two hot air paths, ensuring that the hot air supply at different stages is independent and does not interfere with each other.

[0032] The heat source supply system ensures that the temperature reaches the target level quickly during the initial curing stage, providing a suitable temperature environment for the hydration reaction of reactive powder concrete. The pipeline switching structure enables seamless connection between the curing heat source and the preheating heat source, avoiding temperature interruptions during batch switching and improving the continuity of the production process; at the same time, it avoids mutual interference between the waste heat recovery loop and the main heat source loop, ensuring the stability of each system's operation.

[0033] like Figure 2 As shown, in this embodiment, the telescopic cover 21 includes a first frame 211 and a second frame 212. A hydraulic telescopic rod 213 is provided between the first frame 211 and the second frame 212. The bottom of the first frame 211 and the second frame 212 are both provided with movable pulleys 214. The working base 11 is provided with a track 2141 that cooperates with the movable pulleys 214.

[0034] The first frame 211 and the second frame 212 are provided with fixing ears 2111 for fixing the heat insulation film 22, and the heat insulation film 22 is provided with straps; a tension spring 215 is provided between the top of the first frame 211 and the second frame 212, and a number of positioning blocks 2151 are provided on the tension spring 215. The positioning blocks 2151 and the heat insulation film 22 are detachably connected by Velcro.

[0035] Specifically, the heat insulation cover device 2 is composed of two sets of symmetrically arranged telescopic cover frames 21 and heat insulation film 22. The whole is set on the working base 11 through a sliding structure and can be opened and closed along the length of the working base 11.

[0036] The telescopic cover 21 includes a first frame 211 and a second frame 212, which are connected by a hydraulic telescopic rod 213. The hydraulic telescopic rod 213 can drive the first frame 211 and the second frame 212 to generate relative displacement in the lateral direction, realizing the telescopic adjustment of the cover width. Both the first frame 211 and the second frame 212 are equipped with movable pulleys 214 at their bottoms. The working base 11 has tracks 2141 on both sides that are adapted to the movable pulleys 214. The tracks 2141 extend along the length of the working base 11, allowing the telescopic cover 21 to move as a whole along the tracks 2141, realizing the overall opening and closing of the insulation cover. Fixed ears 2111 are evenly arranged around the perimeter of the first frame 211 and the second frame 212. Ties are correspondingly provided on the edges of the insulation film 22. The insulation film 22 is fixed to the frame by binding the ties to the fixed ears 2111. A tension spring 215 is provided between the top of the first frame 211 and the second frame 212. The axial direction of the tension spring 215 is arranged along the extension and contraction direction of the cover frame. Several positioning blocks 2151 are spaced apart on the spring body. The positioning blocks 2151 and the top inner surface of the insulation film 22 are detachably connected by a Velcro structure.

[0037] After the insulation cover device 2 is fully closed, it completely wraps around the outside of the molding mold 1, forming an independent and enclosed curing space. The side wall of the insulation cover device 2 has pre-reserved interfaces for a hot air inlet 24 and a hot air outlet 25, which are respectively connected to external hot air supply and exhaust pipes. The insulation film 22 adopts a multi-layer composite structure, including an airtight layer, a thermal insulation layer, and a protective surface layer, possessing low thermal conductivity and high-temperature resistance. The telescopic cover frame 21 is welded from lightweight metal profiles, ensuring structural strength while reducing moving load. Limit blocks are provided at the ends of the track 2141 to prevent the telescopic cover frame 21 from derailing due to excessive movement. The hydraulic telescopic rod 213 is equipped with a synchronous control component to ensure synchronized telescopic movements of the two sets of telescopic cover frames 21.

[0038] In this embodiment, the core function of the heat insulation cover device 2 is to form a closed heat insulation space during the heat curing stage, blocking heat exchange between the curing space and the external environment, reducing heat loss, and improving heat utilization efficiency. The telescopic and sliding structure can be fully opened during component casting, demolding, and other processes, avoiding the work space for mold assembly and disassembly and component hoisting, and can be quickly closed during the curing process to form a heat insulation space, adapting to the production rhythm of multiple alternating processes of precast components.

[0039] The combined structure of tension spring 215 and positioning block 2151 maintains the tension of insulation film 22 throughout the expansion and contraction of the cover, preventing the insulation film 22 from sagging and contacting the high-temperature mold surface and causing damage. It also ensures uniform coverage of the insulation layer within the cover, eliminating weak areas of localized insulation. The detachable connection facilitates regular replacement and maintenance of the insulation film 22, reducing the operation and maintenance costs of the device.

[0040] Compared to fixed insulation shells, the openable telescopic insulation cover balances insulation and sealing performance with ease of production operation. It can be opened and closed without additional hoisting equipment, making it suitable for the mass production pace of precast box culverts. The multi-layer composite insulation membrane 22 effectively reduces heat conduction and radiation loss in the curing space, improves heat retention efficiency within the curing space, and reduces the continuous output load of the heat source. The tensioning and positioning structure extends the service life of the insulation membrane 22, ensuring stable insulation performance during long-term use.

[0041] In this embodiment, the heat exchanger unit adopts a plate heat exchanger or a tube heat exchanger and is configured as a counter-current heat exchange structure.

[0042] The heat exchanger unit is located in the exhaust duct of the hot air outlet 25 and can be either a plate heat exchanger or a tubular heat exchanger, both configured as a counter-current heat exchange structure. The heat exchanger unit is internally divided into independent high-temperature medium channels and low-temperature medium channels. The inlet of the high-temperature medium channel connects to the exhaust duct of the hot air outlet 25, allowing the flow of high-temperature exhaust gas from the curing space. The low-temperature medium flows through the low-temperature heat exchange medium, and its inlet and outlet connect to the circulation duct of the thermal energy storage unit, forming a circulation loop for the heat exchange medium.

[0043] When using a plate heat exchanger, the heat exchange core is composed of multiple corrugated metal plates stacked together, forming staggered fluid channels between the plates. High-temperature exhaust gas and low-temperature heat exchange medium flow in opposite directions within adjacent channels, achieving heat transfer through the plate walls. When using a tubular heat exchanger, multiple heat exchange tubes are arranged inside the shell. The shell side serves as the high-temperature exhaust gas channel, and the tube side serves as the low-temperature heat exchange medium channel. The two fluids flow through the heat exchanger in opposite directions, exchanging heat through the tube walls. An electrically operated regulating valve is installed on the inlet pipe of the high-temperature medium channel to adjust the flow rate of the high-temperature exhaust gas; a circulating pump is installed on the circulation pipe of the low-temperature medium channel to provide power for the circulation of the heat exchange medium.

[0044] The core function of the heat exchanger unit is to extract waste heat from the high-temperature exhaust gas discharged from the curing space and transfer the heat energy to the low-temperature heat exchange medium through indirect heat exchange, thereby recovering waste heat and avoiding energy waste caused by the direct emission of high-temperature exhaust gas. The counter-current heat exchange structure can increase the average heat transfer temperature difference in the heat exchange process, enhance the heat transfer effect, and improve the adequacy of waste heat recovery. The electric regulating valve can adjust the exhaust gas flow rate according to the exhaust temperature to optimize the heat exchange conditions; the circulating pump provides circulation power for the heat exchange medium, ensuring that heat is continuously delivered to the heat storage unit.

[0045] The counter-current heat exchange structure effectively improves heat exchange efficiency, ensuring that the low-temperature heat exchange medium can fully absorb the heat energy from the high-temperature exhaust gas, thereby increasing the proportion of waste heat recovery. Two heat exchanger types can be selected and adapted based on the exhaust gas cleanliness, site space conditions, and maintenance requirements of the production site, enhancing the applicability of the equipment. Adjustable flow control can adapt to exhaust temperature changes at different maintenance stages, maintaining stable heat exchange conditions.

[0046] In this embodiment, the thermal energy storage unit is a phase change thermal storage device, which is filled with paraffin or salt phase change thermal storage material, and the phase change temperature range is 60°C to 120°C.

[0047] Specifically, the low-temperature medium circulation pipeline of the thermal energy storage unit is connected to the heat exchanger unit, and a phase change thermal energy storage device structure is adopted. The device shell is made of pressure-resistant metal material, and the interior is a sealed thermal energy storage cavity filled with paraffin-based or salt-based phase change thermal energy storage material. The phase change temperature range of the material covers the commonly used temperature range for heat curing of reactive powder concrete. Thermal conductivity enhancement components are installed inside the thermal energy storage cavity to improve the heat conduction rate within the thermal energy storage material and shorten the response time of the thermal storage and release processes. The exterior of the thermal energy storage device shell is covered with a thermal insulation layer to reduce the outward loss of thermal energy during the storage process.

[0048] The thermal energy storage unit is equipped with two independent media interfaces, which are respectively connected to the heat exchange circulation loop of the heat exchanger unit and the heat release circulation loop of the preheating circulation pipeline, so as to realize the independent operation of the heat storage process and the heat release process.

[0049] The core function of the thermal energy storage unit is to store the heat energy recovered by the heat exchanger unit: during the component curing stage, it absorbs the waste heat carried by the heat exchange medium and completes the accumulation of heat energy through the phase change material's physical state change; during the new component preheating stage, the phase change material undergoes a reverse physical state change to release the stored heat energy, which is then transported to the curing space through the preheating circulation pipeline to provide a heat source for the heating of the newly molded components, thus realizing the transfer and utilization of heat energy between different production batches.

[0050] Phase change thermal storage materials store and release latent heat through changes in state of matter. They have high heat storage density, allowing for the storage of large amounts of thermal energy in a relatively small device volume, reducing the space required for installation. The isothermal characteristics of the phase change process ensure temperature stability during heat release, providing a stable heat source output for the preheating stage and preventing thermal stress within the components caused by large temperature fluctuations. The shell insulation layer reduces heat loss during standby, extends the thermal energy storage time, and adapts to the needs of intermittent production.

[0051] In this embodiment, a preheating fan is installed on the preheating circulation pipeline. The air volume of the preheating fan is adjustable from 500 m³ / h to 2000 m³ / h, and the air pressure is adjustable from 200 Pa to 800 Pa. It is used to drive hot air to circulate between the thermal energy storage unit and the maintenance space.

[0052] Specifically, one end of the preheating circulation pipeline connects to the heat release circuit interface of the thermal energy storage unit, and the other end connects to the hot air inlet 24 of the insulation cover device 2, forming a closed preheating air supply circuit. A preheating fan is installed on the pipeline to provide power for the circulation of air within the pipeline; the outer wall of the pipeline is fully covered with an insulation layer to reduce heat loss during hot air delivery. Flanges are used to connect the various sections of the pipeline, and sealing gaskets are installed at the interfaces to ensure the airtightness of the pipeline. The preheating fan adopts an adjustable speed structure, allowing adjustment of the air supply parameters according to preheating requirements.

[0053] The function of the preheating circulation pipeline is to build a hot air circulation channel between the heat storage unit and the curing space during the preheating stage. The hot air is driven to circulate by the preheating fan, so that the heat energy released by the heat storage unit is continuously and evenly transported to the curing space, thereby achieving the gradual preheating and temperature rise of the newly molded components.

[0054] An independent preheating circulation loop enables the directional transport of recovered waste heat. Combined with an adjustable-speed preheating fan, it allows for precise control of the heating rate during the preheating stage, ensuring uniform heating of components and preventing internal stress defects caused by rapid heating. The pipeline insulation design reduces heat loss during transport and improves the effective utilization rate of thermal energy.

[0055] In this embodiment, the temperature sensors include an exhaust temperature sensor located at the hot air outlet 25, a heat storage temperature sensor located in the heat storage unit, and a curing zone temperature sensor located in the cavity.

[0056] Specifically, the intelligent control system consists of three parts: temperature sensor, controller and actuator, to monitor and control the operating status of the entire device.

[0057] Temperature sensors are categorized into three types: exhaust temperature sensors are installed inside the duct at the hot air outlet 25 to monitor the temperature of the exhaust gas; heat storage temperature sensors are installed inside the heat storage unit to monitor the real-time temperature of the heat storage material; and curing area temperature sensors are installed inside the curing space to monitor the actual temperature of the curing environment.

[0058] The controller adopts a programmable logic controller with built-in staged control logic program and temperature proportional-integral-derivative closed-loop control algorithm. It can receive monitoring signals from various temperature sensors, and output control commands to the actuator after logic operation.

[0059] The actuator includes all controllable actuators such as electric regulating valve, circulating pump, preheating fan, three-way valve drive device, and heating element control module. All of them are electrically connected to the controller, receive control commands, and complete corresponding actions.

[0060] In this embodiment, the intelligent control system is configured in a phased control mode, including: During the curing phase, the controller controls the heat source supply system to supply heat to the curing space, maintaining the curing temperature at 80°C to 90°C, while simultaneously controlling the heat exchanger unit to transfer the discharged waste heat to the thermal energy storage unit. Specifically, the controller receives real-time feedback from the temperature sensor in the curing area, controls the output power of the heat source supply system, and maintains the temperature in the curing space within the set curing temperature range. At the same time, it starts the circulation loop corresponding to the heat exchanger unit, controls the operation of the circulation pump and electric regulating valve, continuously transfers the waste heat carried by the exhaust air to the heat storage unit to complete heat storage, and adjusts the valve opening according to the feedback from the exhaust air temperature sensor to optimize the heat exchange conditions.

[0061] During the preheating stage, the controller controls the heat storage unit to release heat energy, and the hot air is delivered to the curing space by the preheating fan to preheat the newly molded components. The preheating temperature rise rate is 3℃ / min to 8℃ / min. Specifically, after the controller determines that the curing stage is over, it shuts off the heat source supply system, controls the three-way valve to switch to the preheating circulation pipeline, and starts the heat release circuit of the preheating fan and the heat storage unit to preheat the newly placed components in the curing space using the stored residual heat. The controller monitors the heat storage margin based on the feedback from the heat storage temperature sensor. When the stored heat is insufficient to maintain the preheating temperature, it activates the temperature compensation function and calls on the heat source supply system for supplementary heating to ensure that the preheating temperature meets the process requirements.

[0062] During standby, the thermal energy storage unit maintains its thermal energy storage state, and the thermal storage temperature is not lower than 60℃; Specifically, during production breaks, the controller maintains the thermal energy storage unit in a heat preservation state, controls the thermal storage circulation loop to operate at a low load, and ensures that the thermal storage temperature is maintained above the set threshold to store heat for the next production preheating. The remaining system components are in standby mode to reduce standby energy consumption.

[0063] During the transition between the curing and preheating stages, the controller first determines the completion of the curing stage by continuously monitoring data from the temperature sensor in the curing area. The curing stage is considered complete when the temperature in the curing space stabilizes within the set curing temperature range and remains there for the preset curing duration. The controller then shuts off the heat supply system. Once the temperature in the curing space naturally drops to the preset switching temperature, it controls the three-way valve to switch the pipeline and activate the preheating circulation system. This seamlessly connects the waste heat from the curing process with the heat source for the preheating process, preventing the waste of heat energy.

[0064] The temperature PID closed-loop control algorithm integrated within the controller is shown below: ; in, Output signal to the controller This is the temperature deviation value. This is the proportionality coefficient. The integral coefficient is... is the differential coefficient.

[0065] The controller calculates the deviation from the set temperature based on real-time temperature data collected by temperature sensors in the maintenance area. It then generates a control output signal through proportional, integral, and derivative calculations to drive actuators that adjust heat source power, valve opening, or fan speed. The proportional term quickly responds to temperature deviations, reducing the gap between the actual temperature and the set value; the integral term eliminates steady-state temperature deviations, ensuring long-term temperature stability at the set value; and the derivative term predicts temperature change trends and suppresses temperature fluctuations. These three terms work together to achieve precise temperature control in the maintenance space, keeping temperature fluctuations within a small range.

[0066] The intelligent control system enables the automated and intelligent operation of the entire molding and curing device, eliminating the need for frequent manual adjustments to equipment parameters and reducing the intensity of manual operation. Through multi-point temperature monitoring and closed-loop control, it ensures the stability and uniformity of temperature parameters at each stage, improving the consistency of component curing quality. Through phased thermal energy scheduling logic, it maximizes the recovery and recycling of waste heat, optimizes the allocation of thermal energy between different processes, and reduces overall energy consumption.

[0067] The intelligent control system can adapt to different production rhythms, such as continuous and intermittent production. In multi-batch alternating production scenarios, it can automatically complete the seamless utilization of thermal energy, avoiding delays and errors caused by manual switching. Precise closed-loop temperature control can reduce internal stress defects in components caused by uneven and fluctuating temperatures, improving the mechanical properties and finished product qualification rate of precast box culverts made of reactive powder concrete. The phased energy consumption optimization strategy can minimize production energy consumption and operating costs while ensuring process requirements are met.

[0068] like Figure 3 As shown, the working steps of the present invention are as follows: S1. Pouring preparation: The mold is closed on the working base to form a pouring cavity, and the RPC concrete is poured and the pouring port is sealed; the telescopic cover is driven to move and close along the track, and the mold is wrapped with the insulation film to form a closed curing space.

[0069] S2. Heat curing and waste heat recovery: Upon entering the curing stage, the intelligent control system activates the heat source supply system to deliver hot air to the curing space and maintain the set curing temperature to ensure the hydration reaction of the RPC material; simultaneously, the heat exchanger unit and circulation pump are activated to transfer the waste heat carried by the exhaust air to the heat storage unit to complete the heat energy storage.

[0070] S3, Stage Switching: After the maintenance time and temperature meet the standards, the controller determines that the maintenance is complete and shuts off the heat source supply system; when the temperature of the maintenance space drops to the preset switching temperature, the controller controls the three-way valve to switch the pipeline and connect the preheating circulation loop.

[0071] S4. Component replacement and residual heat preheating: Open the insulation cover to complete the demolding of the finished product, put in the new component and close the insulation cover again; enter the preheating stage, start the heat storage unit to release heat, drive the hot air circulation through the preheating fan, and use the recovered residual heat to preheat the newly put component in the mold in a gradient; if the heat storage is insufficient, the temperature compensation will be automatically started.

[0072] S5, Cycle and Standby: After preheating is completed, switch back to maintenance mode and start a new production cycle; during production breaks, enter the standby stage to maintain the heat storage temperature of the heat storage unit, while the rest of the system is on low-load standby to reserve heat energy for the next round of production.

[0073] This invention has many applications, including but not limited to the following described scenarios: For conventional RPC precast box culverts used in municipal integrated pipe corridors and urban drainage systems, multiple units can be arranged in the prefabrication plant to form an assembly line. Relying on continuous batch production, the energy-saving advantages of waste heat recovery and heat storage preheating can be fully utilized. At the same time, the rapid opening and closing mechanism of the insulation cover can be used to improve the mold turnover efficiency, so as to achieve high-quality, low-cost, and large-scale stable production of RPC box culverts.

[0074] For projects involving large-scale transportation that are difficult and costly, such as long-distance municipal utility tunnels and infrastructure projects in remote areas, this device can be directly deployed at the project site's temporary prefabrication yard. The device requires no supporting fixed maintenance facilities, has a short deployment cycle, and enables on-site production and installation of box culvert components, significantly reducing long-distance transportation costs and mitigating the risk of component damage during transport.

[0075] In northern winters or frigid environments, traditional thermal curing processes generally suffer from slow heating, high energy consumption, and susceptibility to frost damage to components. This device boasts excellent sealed insulation performance, and when combined with a heat storage circulation system, it can stably maintain the curing temperature, precisely control the heating rate, effectively resist the effects of low-temperature environments, prevent early frost damage and temperature cracks in components, and significantly reduce curing energy consumption under low-temperature conditions, ensuring the feasibility and economy of continuous production in winter.

[0076] When there are resources such as thermal power plants, chemical plants, and steel plants around the prefabrication plant that can provide industrial waste heat and residual heat steam, the device can use industrial waste heat as the main heat source, superimposed with its own waste gas waste heat recovery and circulation system, to achieve multi-level utilization of thermal energy, greatly reduce production energy costs, and meet the development requirements of green and low-carbon production.

[0077] For prefabricated box culvert tasks with stringent time requirements, such as flood control and disaster relief, and municipal emergency reconstruction and expansion, the heat storage and preheating function of this device can significantly shorten the single-batch curing cycle and accelerate mold turnover efficiency; at the same time, the automated temperature control and mechanical opening and closing mode can reduce manual preparation time and enable the rapid production of qualified RPC box culvert components in a short period of time, ensuring project schedule milestones.

Claims

1. An RPC precast box culvert molding device with an integrated circulating thermal curing system, characterized in that, include: The molding die includes a working base and an outer mold and an inner mold set on the working base. The outer mold and the inner mold enclose a cavity for pouring RPC concrete. The heat insulation cover device includes two telescopic cover frames that are slidably set on the working base and a heat insulation film set on the telescopic cover frames. The heat insulation cover device wraps the forming mold and forms a curing space through the telescopic cover frames and the heat insulation film. The heat insulation cover device is equipped with a hot air inlet and a hot air outlet. The heat circulation device includes a heat exchanger unit, a thermal energy storage unit, and a preheating circulation pipeline. The heat exchanger unit is located on the pipeline at the hot air outlet and is used to receive high-temperature exhaust gas from the curing space and exchange heat with a low-temperature heat exchange medium. The thermal energy storage unit is connected to the heat exchanger unit and is used to store the heat energy transferred by the heat exchanger unit. One end of the preheating circulation pipeline is connected to the thermal energy storage unit, and the other end is connected to the hot air inlet, and is used to transport the heat energy released by the thermal energy storage unit to the curing space. The heat source supply system, with pipes connected to the hot air inlet, is used to provide the heat energy required for the initial heating of the curing space; The intelligent control system includes temperature sensors, controllers, and actuators, which coordinate and control the working status of the heat exchanger unit, thermal energy storage unit, and heat source supply system based on the temperature signals from each temperature measurement point.

2. The RPC precast box culvert forming device with an integrated circulating thermal curing system according to claim 1, characterized in that, The telescopic cover includes a first frame and a second frame. A hydraulic telescopic rod is installed between the first frame and the second frame. Both the first frame and the second frame are equipped with movable pulleys at their bottoms. The working base is equipped with a track that cooperates with the movable pulleys.

3. The RPC precast box culvert forming device with an integrated circulating thermal curing system according to claim 2, characterized in that, The first and second frames are equipped with fixing ears for securing the insulation film, and the insulation film is equipped with straps; a tension spring is provided between the top of the first and second frames, and several positioning blocks are provided on the tension spring. The positioning blocks and the insulation film are detachably connected by Velcro.

4. The RPC precast box culvert forming device with an integrated circulating thermal curing system according to claim 1, characterized in that, The heat exchanger unit adopts a plate heat exchanger or a tube heat exchanger and is configured as a counter-current heat exchange structure.

5. The RPC precast box culvert forming device with an integrated circulating thermal curing system according to claim 1, characterized in that, The thermal energy storage unit is a phase change thermal storage device, which is filled with paraffin or salt phase change thermal storage material, and the phase change temperature range is 60℃ to 120℃.

6. The RPC precast box culvert forming device with an integrated circulating thermal curing system according to claim 1, characterized in that, A preheating fan is installed on the preheating circulation pipeline. The air volume of the preheating fan is adjustable from 500 m³ / h to 2000 m³ / h, and the air pressure is adjustable from 200 Pa to 800 Pa. It is used to drive the hot air to circulate between the thermal energy storage unit and the maintenance space.

7. The RPC precast box culvert forming device with an integrated circulating thermal curing system according to claim 1, characterized in that, The intelligent control system is set to a phased control mode, including: During the curing phase, the controller controls the heat source supply system to supply heat to the curing space, maintaining the curing temperature at 80°C to 90°C, while simultaneously controlling the heat exchanger unit to transfer the discharged waste heat to the thermal energy storage unit. During the preheating stage, the controller controls the heat storage unit to release heat energy, and the hot air is delivered to the curing space by the preheating fan to preheat the newly molded components. The preheating temperature rise rate is 3℃ / min to 8℃ / min. During standby, the thermal energy storage unit maintains its thermal energy storage state, with the thermal storage temperature not lower than 60℃.

8. The RPC precast box culvert forming device with an integrated circulating thermal curing system according to claim 1, characterized in that, The temperature sensors include an exhaust temperature sensor located at the hot air outlet, a heat storage temperature sensor located in the heat storage unit, and a curing zone temperature sensor located in the cavity.