An adjustable tower crane attachment pre-embedded installation device and construction method
By using an adjustable tower crane attachment pre-embedded installation device, which employs a four-point short groove distributed pre-embedding and a four-way adjustment system, the safety and accuracy issues of the tower crane attachment pre-embedded structure are solved, achieving efficient and safe tower crane attachment installation, reducing costs and improving construction efficiency.
Patent Information
- Application Number
- CN202611435859.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-16
- Publication Date
- 2026-11-17
AI Technical Summary
The existing tower crane attachment trough pre-embedded structure has problems such as damaging the original reinforcement system of the shear wall, low installation accuracy, inability to adjust the tower crane attachment position after the structure is formed, poor safety, and high cost.
An adjustable tower crane attachment pre-embedded installation device is adopted, including H-shaped groove pre-embedded parts, temporary T-shaped connectors, working T-shaped connectors, anchoring components, etc. Through a four-point short groove distributed pre-embedded process and a four-way adjustment system, precise installation and multi-path force transmission are achieved. Combined with positioning molds and conversion plates, precise adjustment and efficient turnover are achieved.
It improves structural safety and installation accuracy, reduces costs, increases construction efficiency, enhances fatigue resistance and construction safety, is adaptable to shear wall structures of different thicknesses, has wide applicability, and the embedded parts can be 100% reused.
Smart Images

Figure CN123105482A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of installation technology for embedded parts of tower crane attachment legs in building construction, and more specifically, to an adjustable tower crane attachment embedded installation device and construction method. Background Technology
[0002] Currently, in the pre-installation of tower crane attachment supports at construction sites, although some projects have begun to try using H-channels, many potential problems have been found in actual field applications. For example, the construction process of pre-installing continuous H-channels and fixing with conventional T-bolts has several technical pain points and quality risks. 1. The traditional method of using halfen channels to install tower crane attachments is to pre-embed a full-length halfen channel. The channel crosses the shear wall and distributes horizontal reinforcement bars. During construction, in order to avoid the channel, the horizontal main reinforcement bars of the wall must be cut and bent, which seriously damages the original reinforcement system of the shear wall and reduces the overall seismic performance and structural integrity of the structure.
[0003] 2. The standard right-angle square head T-bolt only has one narrow side that contacts the rolled edge inside the slot to bear pressure. The tower crane is subjected to reciprocating alternating loads, gust impact loads and installation eccentric loads for a long time. The rolled edge inside the slot is prone to crushing and outward deformation. Under extreme working conditions, the embedded parts may fall out or fail, which poses a major safety hazard. It also has poor fatigue resistance and pull-out resistance.
[0004] 3. Traditional pre-embedded bolts are used to directly insert and position the high-strength T-bolts through the formwork. The opening size of the formwork is too large. During the concrete pouring process, the grout easily wraps around the bolt threads, causing the high-strength bolts to rust and become unusable. This results in high material costs and serious waste of resources.
[0005] 4. Conventional H-channels, after pre-installation, lack a precise four-way adjustment structure. Deviations in the concrete pouring, reinforcement arrangement, and formwork installation can easily cause the tower crane's attachment lugs to be suspended, misaligned, or shifted in position. On-site rectification can only be achieved through methods such as raising with pads, gas cutting, and manual grinding. This not only results in low construction efficiency but also poses a fire hazard. Furthermore, the uneven stress on the supports after rectification affects the accuracy of the tower crane's attachment installation and its operational safety.
[0006] 5. Conventional halfen channels only have a single set of straight anchor bars on the back, and the anchoring structure is simple. Under the alternating load of the tower crane, the weld between the anchor bar and the channel body is prone to tearing. The overall pull-out bearing capacity and fatigue bearing capacity of the embedded parts are insufficient, and they cannot meet the attachment force requirements of the tower crane under complex working conditions.
[0007] 6. Once the conventional HAFF channel is installed, the structure is fixed and cannot be adjusted for the horizontal and height of the tower crane attachment installation position. If there is a deviation in the pre-embedded points, it will be very easy to cause difficulties in the alignment of the tower crane attachment installation and excessive assembly deviation. This will not only greatly increase the difficulty of on-site rectification construction, but also lead to eccentric and uneven stress on the attachment support, and long-term use may result in loosening of the buried structure and failure of the pre-embedded parts, which are major safety hazards. Summary of the Invention
[0008] The present invention aims to provide an adjustable tower crane attachment pre-embedded installation device and construction method to solve the problems of existing tower crane attachment trough pre-embedded structures, such as damage to the original reinforcement system of shear walls, low installation accuracy, inability to adjust the tower crane attachment position after the structure is formed, poor safety, and high cost.
[0009] This invention is achieved using the following technical solution: This invention provides an adjustable tower crane attachment pre-embedded installation device, including a halfen groove pre-embedded part, a temporary T-shaped connector, a working T-shaped connector, a temporary T-shaped connector fastener, a working T-shaped connector fastener, an anti-rotation limit shim, a positioning mold, a conversion plate, and an anchoring component. The Huffen groove embedded part has a channel inside, and an opening is provided on one side of the Huffen groove embedded part, the opening connecting the outside of the Huffen groove embedded part to the channel. The opening side of the Huffen groove embedded part is provided with rolled edges, and the rolled edges are arranged in pairs symmetrically on both sides of the Huffen groove embedded part, and a groove is formed between the two pairs of rolled edges. The halfen groove embedded part includes a first end section, a middle section and a second end section along its length. The cross-section of the first end section is U-shaped. The cross-sections of the middle section and the second end section are both C-shaped with the rolled edge. The anchoring assembly is fixedly connected to the outside of the halfen groove embedded part; The HAFF channel embedded part is embedded in the shear wall concrete, and the HAFF channel embedded part is arranged horizontally. Both the temporary T-shaped connector and the working T-shaped connector are used to slide with the channel. The heads of the temporary T-shaped connector and the working T-shaped connector are used to slide and install themselves in the channel from the first end section. The rods of the temporary T-shaped connector and the working T-shaped connector are used to extend out from the slot opening. The four embedded parts of the halfen groove are respectively arranged at the four corners of the rectangle; The side wall facade construction formwork is provided with formwork fixing holes, and the temporary T-shaped connector rod is used to pass through the formwork fixing holes; The positioning mold is arranged on the outside of the side wall facade construction template and fits against it. The positioning mold is used to fix the four H-channel embedded parts. The positioning mold has two grooves that are in the same direction as the grooves of the H-channel embedded parts. The positioning mold has a limiting groove on the side away from the embedded part of the halfen groove, and the anti-rotation limiting shim is installed in the limiting groove. The shape of the anti-rotation limiting shim is adapted to the limiting groove. During the pre-embedding stage of the HAFF groove pre-embedded part, the rod of the temporary T-shaped connector passes through the side wall facade construction template, the positioning mold, the limiting groove and the anti-rotation limiting gasket, and is connected to the temporary T-shaped connector fastener. The anti-rotation limiting gasket is used to limit the rotation of the temporary T-shaped connector. After the embedded part of the H-channel is embedded, one side of the conversion plate is used to fit with the concrete structure, and the other side of the conversion plate is provided with a H-channel. The length direction of the H-channel is vertical. A vertical adjustment T-type connector is slidably installed in the H-channel. The head of the vertical adjustment T-type connector is slidably set in the H-channel. The rod of the vertical adjustment T-type connector passes through the mounting hole on the tower crane attachment support. A fastener for the vertical adjustment T-type connector is connected to the rod of the vertical adjustment T-type connector.
[0010] As a preferred technical solution: The temporary T-connector is a temporary T-bolt, the working T-connector is a working T-bolt, the temporary T-connector fastener is a temporary T-bolt fastening nut, the working T-connector fastener is a working T-bolt fastening nut, the vertical adjustment T-connector is a vertical adjustment T-bolt, the vertical adjustment T-connector fastener is a vertical adjustment T-bolt fastening nut, and the conversion plate is a conversion steel plate.
[0011] As a preferred technical solution: The anchoring assembly includes studs and barbed anchor claws; One end of the stud is fixed to the outer surface of the other side of the H-shaped groove embedded part, and the position of the stud is opposite to the position of the opening. One end of each of the multiple barbed anchor claws is fixed to the outer surface of the halfen groove pre-embedded part, and the multiple barbed anchor claws are arranged at intervals.
[0012] As a preferred technical solution: The barbed anchor claw is Y-shaped, with the straight shank end of the Y-shaped barbed anchor claw fixed to the HAFF groove pre-embedded part, and the barbed end of the Y-shaped barbed anchor claw being away from the HAFF groove pre-embedded part.
[0013] As a preferred technical solution: The inner side of the rolled edge is provided with a pressure-bearing inclined surface. The pressure-bearing inclined surface slopes from the side near the slot opening to the side near the side wall of the H-shaped groove embedded part. The thickness of the rolled edge near the slot opening is greater than the thickness of the rolled edge near the side wall of the H-shaped groove embedded part.
[0014] As a preferred technical solution: Both the temporary T-shaped connector and the working T-shaped connector have inclined mating surfaces at their heads. The inclined mating surfaces are adapted to the pressure-bearing inclined surfaces. When the connectors are assembled, the inclined mating surfaces are in contact with and abut against the pressure-bearing inclined surfaces. The inclined mating surfaces are inclined from the side near the rod of the connector towards the edge of the connector. The thickness of the edge of the head of both the temporary T-shaped connector and the working T-shaped connector is greater than the thickness of the side near the rod.
[0015] As a preferred technical solution: The inclination angles of both the pressure-bearing inclined surface and the inclined mating surface are 45°.
[0016] As a preferred technical solution: An anti-slip pad is provided between the anti-rotation limiting pad and the temporary T-shaped connector fastener. The rod of the temporary T-shaped connector passes through the anti-rotation limiting pad and the anti-slip pad in sequence, and is connected to the temporary T-shaped connector fastener.
[0017] As a preferred technical solution: The channel is a through channel, and the channel of the H-shaped groove is also a through channel. The heads of the temporary T-shaped connector and the working T-shaped connector are used to slide into the first end section of the H-shaped groove pre-embedded part.
[0018] The present invention further provides a construction method using the above-mentioned adjustable tower crane attachment pre-embedded installation device, comprising the following steps: S1: Factory prefabrication; According to the tower crane model and corresponding specifications, prefabricate the H-channel embedded parts. The inner side of the rolled edge of the H-channel embedded parts is machined with a pressure-bearing inclined surface, and the H-channel embedded parts are fixed with studs and barbed anchor claws on the outside. Batch processing of temporary T-connectors, working T-connectors, vertical adjustment T-connectors, and corresponding fasteners; The machining positioning mold, conversion plate, anti-rotation limiting pad and anti-slip pad are processed. The conversion plate has two vertical H-shaped grooves. S2: On-site rebar tying; On-site binding of shear wall reinforcement bars. After the shear wall reinforcement bar binding is completed, the lines are accurately laid out according to the tower crane attachment design points. The four H-channel embedded parts are distributed in a rectangular four-point distribution to avoid the horizontal stress reinforcement bars of the wall. The barbed anchor claws are bound and fixed to the vertical main reinforcement bars of the shear wall. S3: Mold positioning and template closing; Align the positioning mold with the pre-embedded point, and pass the temporary T-shaped connector rod through the template, positioning mold, anti-rotation limiting pad and anti-slip pad from one side of the side wall facade construction template. Use the temporary T-shaped connector fastener to lock the four H-shaped groove pre-embedded parts, and fill the cavity of the H-shaped groove pre-embedded parts with foam to seal and prevent grout leakage. S4: Layered concrete pouring; When pouring concrete for shear walls, the limiting and restraining effect of the mold is used to prevent the embedded parts of the Huffing groove from shifting, floating, or twisting under the weight of the concrete and the vibration load, thus ensuring the accuracy of the embedded parts. S5: Demolding and tooling turnover; After the concrete has been cured to the required standard, the side wall facade construction formwork is removed, the temporary T-shaped connector fasteners, positioning molds and temporary T-shaped connectors are removed, the surface laitance of the components is cleaned and then reused in the next construction section, the foam sealing the cavity of the Huffen channel embedded parts is cleaned, and the complete channel and the first end section are exposed. S6: Precise adjustment in both horizontal and vertical directions; The working T-shaped connector is slidably installed into the H-shaped groove embedded part. Its head is slidably installed into the groove from the first end section of the H-shaped groove embedded part and slid until it matches the rolled edge. The rod of the working T-shaped connector passes through the fixing hole on the conversion plate. After the working T-shaped connector is horizontally adjusted into place, the fastener of the working T-shaped connector is installed on the rod of the working T-shaped connector to fix the horizontal position of the conversion plate and the tower crane attachment support. Slide the vertical adjustment T-connector into the H-shaped groove on the conversion plate, and slide its head from the end of the H-shaped groove into the channel of the H-shaped groove. The vertical adjustment T-connector can slide vertically along the channel of the H-shaped groove to achieve vertical elevation adjustment. After the vertical adjustment T-connector is vertically adjusted into place, pass the rod of the vertical adjustment T-connector through the mounting hole on the tower crane attachment support, and install the fastener of the vertical adjustment T-connector on the rod of the vertical adjustment T-connector to fix the vertical position of the tower crane attachment support. S7: Overall installation and fixation; After the four-way position adjustment is completed, tighten all T-type connector fasteners, fix the tower crane attachment support and tower crane attachment connecting ear plate, install the tower crane attachment strut, adjust the tower body verticality, and complete the overall installation of the tower crane attachment legs.
[0019] In summary, due to the adoption of the above technical solution, the beneficial effects of the present invention are: 1. This invention adopts a four-point short groove dispersed pre-embedding process, which eliminates the need to cut the horizontal main reinforcement of the shear wall, fully preserves the integrity of the main structure's reinforcement, protects the main structure, improves structural safety, completely solves the industry common problem of broken reinforcement in traditional continuous H-shaped grooves, and ensures the seismic performance and overall stability of the shear wall structure.
[0020] 2. This invention uses a three-dimensional anchoring component to fix the external connection of the Huffen channel embedded part, realizing multi-path force transmission, eliminating problems such as anchor weld tearing and channel slippage and detachment, with excellent anchoring performance, strong fatigue bearing capacity, and good safety; the working T-bolt is fully fitted with the bearing slope of the rolled edge of the Huffen channel embedded part, greatly increasing the bearing area, which can effectively resist the alternating load of tower crane and the impact load of gust wind, and greatly improve the construction safety under extreme working conditions.
[0021] 3. This invention forms a four-way adjustment system by using the horizontal channels on the H-channel embedded parts and the vertical H-channels on the conversion steel plate to achieve precise four-way adjustment, controllable installation quality, and precise elimination of deviations in wall pouring, reinforcement, and formwork construction. It eliminates the need for on-site hot work, cutting, grinding, and rectification, and eliminates the need for leveling with shims. It completely solves quality problems such as suspended attachment supports, skewed force, and positional offset, significantly improving the installation accuracy of tower crane attachments. The installation accuracy of the H-channel embedded parts can be further improved by using positioning molds.
[0022] 4. The end of the channel of the H-shaped groove embedded part and the end of the H-shaped groove of the conversion steel plate of the present invention are both straight-insertion openings, which facilitates the insertion of T-bolt heads without rotation and locking, completely eliminating the hidden safety hazards of false locking and false locking of traditional bolts, eliminating safety hazards, and ensuring high assembly reliability; with the help of limit shims and shaping molds, the pre-embedding accuracy is high and the pre-embedding part forming quality is stable.
[0023] 5. The positioning mold and temporary T-bolts of this invention can be reused repeatedly. The high-strength working T-bolts are installed after the bolts are installed, eliminating the problem of thread sticking and scrapping. There is zero material consumption, resulting in significant cost reduction and efficiency improvement, and green turnover construction. The standardized and modular construction process is simple, which greatly shortens the construction period of tower crane attachment and installation, improves construction efficiency, and reduces labor and material costs.
[0024] 6. This invention is compatible with the attachment construction of mainstream tower crane series such as QTZ55, QTZ63, and QTZ70, and is suitable for shear wall structures of different thicknesses. It has wide versatility and strong adaptability. The standardized structure can be prefabricated in batches and quickly assembled on site, making it highly practical and valuable for promotion.
[0025] 7. Compared with traditional construction processes, this invention completely eliminates the problem of damage to the main structure's reinforcing steel, achieves a 100% pass rate for tower crane attachment installation accuracy, improves the pull-out resistance and fatigue resistance of embedded parts by more than 50%, allows for 100% reuse of components, reduces labor costs by 60%, and shortens the construction period by 40%. It effectively solves the industry problems of poor installation accuracy, low safety, high losses, and cumbersome rectification in traditional tower crane attachment installation, resulting in significant improvements in construction quality, safety, and economic benefits. Attached Figure Description
[0026] Figure 1 This is a layout diagram of the embedded part of the halfen groove according to the present invention.
[0027] Figure 2 for Figure 1 Cross-sectional view along the aa direction.
[0028] Figure 3 This is a schematic diagram of the anti-rotation limiting gasket of the present invention.
[0029] Figure 4 This is a schematic diagram of the temporary T-bolt described in this invention.
[0030] Figure 5 This is a schematic diagram of the structure of the halfen groove pre-embedded part described in this invention.
[0031] Figure 6 for Figure 5 Cross-sectional view along the aa direction.
[0032] Figure 7 for Figure 5 Cross-sectional view along the bb direction.
[0033] Figure 8 This is a structural schematic diagram of the working T-bolt described in this invention.
[0034] Figure 9 This is a schematic diagram of the installation of the conversion steel plate described in this invention.
[0035] Icons: 1-Hafen channel embedded part, 101-channel, 102-rolled edge, 103-pressure bearing slope, 104-opening, 105-slot, 106-side wall, 2-inclined mating surface, 3-stud, 4-temporary T-bolt, 5-limiting groove, 6-anti-rotation limiting washer, 7-anti-slip washer, 8-temporary T-bolt fastening nut, 9-side wall facade construction template, 10-positioning mold, 11-anti-rotation tongue and groove, 12-Hafen channel, 13-conversion steel plate, 14-working T-bolt fastening nut, 15-tower crane attachment support, 16-tower crane attachment connecting ear plate, 17-barbed anchor claw, 18-working T-bolt, 19-vertical adjustment T-bolt, 20-vertical adjustment T-bolt fastening nut. Detailed Implementation
[0036] To make the objectives, technical solutions, and advantages of the embodiments of the present invention clearer, the technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.
[0037] Example 1 like Figures 1-9As shown, this embodiment proposes an adjustable tower crane attachment pre-embedded installation device, including a halfen groove pre-embedded part 1, a temporary T-bolt 4, a working T-bolt 18, a temporary T-bolt fastening nut 8, a working T-bolt fastening nut 14, an anti-rotation limit washer 6, an anti-slip washer 7, a positioning mold 10, a conversion steel plate 13, and an anchoring assembly.
[0038] Preferably, the temporary T-bolt 4 is a plastic bolt, which includes a temporary T-bolt head and a temporary T-bolt shank. The working T-bolt 18 is a high-strength bolt made of steel, such as a grade 10.9 reinforced bolt, and includes a working T-bolt head and a working T-bolt shank.
[0039] The interior of the HAFF groove embedded part 1 is provided with a channel 101, and the channel 101 is a through channel. like Figures 5-7 As shown, the Huffen groove embedded part 1 has an opening 104 on one side, and the opening 104 connects the outside of the Huffen groove embedded part 1 to the groove 101. The opening side of the Huffen groove embedded part 1 is provided with a rolled edge 102. The rolled edges 102 are arranged in pairs symmetrically on the two side walls 106 of the Huffen groove embedded part 1, and a groove 105 is formed between the two pairs of rolled edges 102. The hapten groove embedded part 1 includes, along its length, a first end section, a middle section, and a second end section. The cross-section of the first end section is U-shaped (the rolled edge 102 is not mentioned here). Figure 6 As shown; the cross-sections of the middle section and the second end section are both C-shaped with the rolled edge 102, as shown. Figure 7 As shown.
[0040] The rolled edge 102 and the halfen groove embedded part 1 are an integral structure.
[0041] The anchoring assembly is fixedly connected to the outside of the HAFF groove embedded part 1, and the anchoring assembly includes a stud 3 and a barbed anchor claw 17; One end of the stud 3 is welded and fixed to the other outer surface of the Huffen groove pre-embedded part 1 (i.e., the back side of the Huffen groove pre-embedded part 1), and the position of the stud 3 is opposite to the position of the opening 104. One end of each of the barbed anchor claws 17 is welded and fixed to the outer surface of the HAFF groove embedded part 1, and the barbed anchor claws 17 are arranged at intervals. The barbed anchor claw 17 is Y-shaped. The straight shank end of the Y-shaped barbed anchor claw 17 is welded and fixed to the HAFF groove pre-embedded part 1. The barbed end of the Y-shaped barbed anchor claw 17 is away from the HAFF groove pre-embedded part 1. The stud 3 and the barbed anchor claw 17 cooperate to form a barbed anti-detachment structure after the concrete is formed, preventing the pull-out and slippage of the HAFF groove embedded part 1.
[0042] Both the temporary T-bolt 4 and the working T-bolt 18 are in sliding fit with the channel 101. The temporary T-bolt 4 is temporarily installed in the channel 101 and will be removed later. After removal, the working T-bolt 18 will be installed in the channel 101. The temporary T-bolt 4 is only used for temporary positioning and is not subjected to force. After demolding, it can be completely extracted and recycled. The working T-bolt 18 is subjected to force.
[0043] The temporary T-bolt head and the working T-bolt head are slidably disposed in the channel 101 from the first end section, and the temporary T-bolt shank and the working T-bolt shank extend from the slot 105; When assembling the temporary T-bolt 4 and the working T-bolt 18, the bolt head is slid into the channel 101 from the first end section of the H-channel embedded part 1, while the bolt shank slides into the slot opening. Since the H-channel embedded part 1 is sealed at both ends by concrete after embedding, it is impossible to slide the T-bolt from the end of the H-channel embedded part 1. In traditional construction, the head of the T-bolt can only be inserted into the channel from the slot opening and then rotated. However, this invention only provides a rolled edge 102 in the middle section and the second end section of the H-channel embedded part 1, without a rolled edge 102 in the first end section, leaving installation space for the temporary T-bolt 4 and the working T-bolt 18. The heads of the temporary T-bolt 4 and the working T-bolt 18 can directly enter from the first end section of the H-channel embedded part 1. The temporary T-bolt 4 and the working T-bolt 18 are slid along the channel 101 to the middle and second end sections with the rolled edge 102. In this way, the heads of the temporary T-bolt 4 and the working T-bolt 18 will directly engage with the inner side of the rolled edge 102 without rotating the bolts. This method can increase the size of the temporary T-bolt 4 and the working T-bolt 18, increase their contact area with the rolled edge 102, ensure uniform pressure, and prevent the bolts from easily coming out of the Huffen groove embedded part 1.
[0044] The inner side of the rolled edge 102 is provided with a pressure-bearing inclined surface 103. The pressure-bearing inclined surface 103 is inclined from the side near the slot 105 to the side near the side wall 106 of the H-channel embedded part 1. The thickness of the rolled edge 102 on the side near the slot 105 is greater than the thickness of the rolled edge 102 on the side wall 106 of the H-channel embedded part 1.
[0045] The heads of both the temporary T-bolt 4 and the working T-bolt 18 are provided with inclined mating surfaces 2, which are adapted to the bearing inclined surface 103. When the bolts are assembled, the inclined mating surfaces 2 and the bearing inclined surface 103 are in contact and abut against each other. The inclined mating surfaces 2 are inclined from the side near the bolt shank towards the bolt edge. The thickness of the edge of the head of both the temporary T-bolt 4 and the working T-bolt 18 is greater than the thickness of the side near the shank.
[0046] Unlike traditional right-angle square-head bolts in the national standard, the temporary T-bolt 4 and the working T-bolt 18 can be directly slid into the groove from the first end section of the embedded part 1 in the hamfen groove, without the need for 90° rotation and locking in the groove. This eliminates hidden dangers such as false locking, false locking, and improper installation. The bolts are fully in contact with the inclined surface of the groove to bear pressure, doubling the pressure-bearing area and ensuring uniform and stable stress distribution, making them suitable for the reciprocating alternating load conditions of tower cranes.
[0047] The inclination angles of the pressure-bearing inclined surface 103 and the inclined mating surface 2 are both 45°.
[0048] The root of the rolled edge 102 of the Huffen groove embedded part 1 has a built-in continuous bearing reinforcement, which greatly improves the rigidity of the groove 105, avoids the groove edge crushing and outward deformation under load, realizes multi-path force transmission, and significantly improves the pull-out resistance and fatigue resistance of the embedded part.
[0049] The HAFF channel embedded part 1 is embedded in the shear wall concrete and is arranged horizontally, that is, the length direction of the HAFF channel embedded part 1 is horizontal. The groove 105 of the HAFF channel embedded part 1 faces the side wall facade construction formwork 9. After the HAFF channel embedded part 1 is embedded, the lateral position of the working T-bolt 18 can be adjusted by moving the bolt in the channel 101.
[0050] The side wall facade construction template 9 has template fixing holes, which are through holes that penetrate the surface of the side wall facade construction template 9. After the head of the temporary T-bolt is slidably installed in the channel 101, the shank of the temporary T-bolt passes through the template fixing hole from one side of the side wall facade construction template 9.
[0051] The four H-channel embedded parts 1 are arranged at the four corners of the rectangle, independently designed and dispersedly embedded, which can avoid the horizontal reinforcing bars in the shear wall. There is no need to cut or bend the main reinforcing bars of the wall, avoiding damage to the original reinforcement system of the shear wall, and completely preserving the integrity of the original reinforcement and the seismic performance of the structure. The length of a single H-channel embedded part 1 is controlled between 120 and 180 mm. The short channel is compact and the embedded point is flexible, completely abandoning the traditional full-length H-channel structure. It can be adapted to three specifications of channel body: 38×23, 40×28, and 52×34 according to different tower crane models such as QTZ55, QTZ63, and QTZ70, and has extremely strong versatility.
[0052] The positioning mold 10 is arranged on the outside of the side wall facade construction template 9 and fits against it. The positioning mold 10 is used to fix the four H-channel embedded parts 1. The positioning mold 10 has two long grooves that are in the same direction as the grooves 101 of the H-channel embedded parts 1. One of the grooves coincides with the groove openings 105 of two H-channel embedded parts 1, and the other groove coincides with the groove openings 105 of the other two H-channel embedded parts 1.
[0053] The positioning mold 10 has a limiting groove 5 on the side away from the HAFF groove embedded part 1. The limiting groove 5 is connected to the groove on the positioning mold 10. The anti-rotation limiting pad 6 is installed in the limiting groove 5. The shape of the anti-rotation limiting pad 6 is adapted to the limiting groove 5. During the pre-embedding stage of the HAFF groove pre-embedded part 1, the temporary T-bolt rod passes through the side wall facade construction template 9, the groove on the positioning mold 10, the limiting groove 5, and the anti-rotation limiting shim 6. The anti-rotation limiting shim 6 is used to limit the rotation of the temporary T-bolt 4. The temporary T-bolt shank is provided with an anti-rotation tongue and groove 11, and the inner side of the anti-rotation limiting washer 6 is engaged in the anti-rotation tongue and groove 11, thereby restricting the rotation of the temporary T-bolt 4.
[0054] The size of the temporary T-bolt 4 is smaller than that of the working T-bolt 18. Therefore, during the pre-embedding stage, the diameter of the opening (i.e., the template fixing hole) of the side wall facade construction template 9 is greatly reduced, which can effectively reduce concrete leakage.
[0055] After the temporary T-bolt shank passes through the anti-rotation limiting washer 6, it passes through the anti-slip washer 7, and then the temporary T-bolt nut 8 is connected to the temporary T-bolt shank via a threaded connection.
[0056] The positioning mold 10 can simultaneously limit the four embedded parts 1 of the H-channel, effectively controlling the floating, twisting and offset of the embedded parts 1 during the casting process, and ensuring the accuracy of the embedded points.
[0057] The positioning mold 10 is a plastic mold with an ABS injection molded one-piece structure.
[0058] After the embedded part 1 of the halfen channel is embedded, the temporary T-bolt fastening nut 8, the anti-slip washer 7, the anti-rotation limiting washer 6, the positioning mold 10, the temporary T-bolt 4 and the side wall facade construction template 9 are removed.
[0059] The working T-bolt 18 is installed in the Huffen groove embedded part 1, and its head is slid from the first end section of the Huffen groove embedded part 1 into the groove 101. The working T-bolt 18 can move in the groove 101. Since the Huffen groove embedded part 1 is arranged horizontally, the lateral position of the working T-bolt 18 can be adjusted.
[0060] The working T-bolt shank passes through the fixing hole on the conversion steel plate 13, and then the working T-bolt fastening nut 14 is connected to the working T-bolt shank via a thread.
[0061] After the embedded part 1 of the H-channel is embedded, one side of the conversion steel plate 13 is used to fit with the concrete structure. The other side of the conversion steel plate 13 is provided with two H-channels 12. The length direction of the H-channels 12 is vertical, that is, perpendicular to the length direction of the channel 101 of the embedded part 1 of the H-channel. A vertical adjustment T-bolt 19 is slidably installed in the H-channel 12. The head of the vertical adjustment T-bolt 19 is slidably set in the H-channel 12. The rod of the vertical adjustment T-bolt 19 passes through the mounting hole on the tower crane attachment support 15. Then, a vertical adjustment T-bolt fastening nut 20 is threadedly connected to the rod of the vertical adjustment T-bolt 19. Therefore, the vertical position of the vertical adjustment T-bolt 19 can be adjusted.
[0062] The conversion steel plate 13, the vertical adjustment T-bolt 19, the halfen groove embedded part 1, and the working T-bolt 18 cooperate to achieve precise four-way adjustment. After the embedded part 1 of the HAFF slot is installed and fixed, the horizontal position is adjusted by sliding the working T-bolt 18 in the slot 101. Then, the conversion steel plate 13 is fixed by the working T-bolt 18, thereby accurately determining the horizontal installation benchmark required for the tower crane attachment support 15. After the horizontal position is fixed, the HAFF slot 12 on the conversion steel plate 13 is used in conjunction with the vertical adjustment T-bolt 19 to achieve vertical adjustment, that is, height direction movement adjustment, accurately locking the vertical installation position of the tower crane attachment support 15, realizing precise micro-adjustment and adaptation in both horizontal and vertical directions, completely eliminating construction deviations caused by wall concrete pouring, rebar binding, and formwork installation, and preventing the tower crane attachment connection ear plate 16 from being suspended or under skewed force. No on-site hot work, cutting, grinding and rectification are required, and the installation accuracy and overall construction quality of the tower crane attachment support leg are fully guaranteed.
[0063] Example 2 This embodiment proposes a construction method for using the adjustable tower crane attachment pre-embedded installation device described in Embodiment 1, including the following steps: S1: Factory prefabrication; According to the tower crane model and corresponding specifications, prefabricate multiple (four) H-channel embedded parts 1. The inner side of the rolled edge 102 of the H-channel embedded part 1 is processed with a pressure-bearing inclined surface 103, and the studs 3 and barbed anchor claws 17 are welded on the H-channel embedded part 1. Batch processing of temporary T-bolts 4, working T-bolts 18, and vertical adjusting T-bolts 19, as well as corresponding nuts; The machining positioning mold 10, the conversion steel plate 13, the anti-rotation limiting pad 6 and the anti-slip pad 7 are processed. The conversion steel plate 13 has two vertical hamfer grooves 12.
[0064] S2: On-site rebar tying; On-site binding of shear wall reinforcement bars. After the shear wall reinforcement bar binding is completed, the lines are accurately laid out according to the tower crane attachment design points. The four H-channel embedded parts 1 are distributed in a rectangular four-point distribution to accurately avoid the horizontal load-bearing reinforcement bars of the wall. The barbed anchor claws 17 are bound and fixed to the vertical main reinforcement bars of the shear wall to ensure that the anchoring components and the main reinforcement bars form an integral load-bearing system.
[0065] S3: Mold positioning and template closing; Align the positioning mold 10 with the pre-embedded point, and use the small temporary T-bolt rod to pass through the template 9 on one side of the side wall facade construction template 9, the positioning mold 10, the anti-rotation limiting shim 6 and the anti-slip shim 7. Simultaneously use the temporary T-bolt to tighten the nuts 8 to lock the four H-channel pre-embedded parts 1. Fill the cavity of the H-channel pre-embedded parts 1 with foam to seal and prevent grout leakage, so as to ensure that there is no displacement or deflection during the pouring process of the channel.
[0066] S4: Layered concrete pouring; The shear wall concrete is poured in layers and symmetrically, and the vibration construction is carried out in a standardized manner. Relying on the limiting and restraining effect of the mold 10, the embedded part 1 of the halfen groove is prevented from shifting, floating, or twisting under the action of the concrete's own weight and vibration load, thus ensuring the accuracy of the embedded part.
[0067] S5: Demolding and tooling turnover; After the concrete has been cured to the required standard, the side wall facade construction formwork 9 is removed, the temporary T-bolt fastening nut 8, the positioning mold 10 and the temporary T-bolt 4 are removed, the surface laitance of the components is cleaned and then reused in the next construction section, the foam sealing inside the cavity of the Huffen channel embedded part 1 is cleaned, and the complete channel 101 and the first end section (i.e. the end inlet opening) are exposed.
[0068] S6: Precise adjustment in both horizontal and vertical directions; The working T-bolt 18 is slidably installed into the H-channel embedded part 1, and its head is slidably installed from the first end section of the H-channel embedded part 1 into the channel 101 of the H-channel embedded part 1, and slid until it mates with the rolled edge 102. The working T-bolt shank passes through the fixing hole on the conversion steel plate 13. After the working T-bolt 18 is horizontally adjusted into place, the working T-bolt fastening nut 14 is installed on the working T-bolt shank, thereby fixing the horizontal position of the conversion steel plate 13 (and the tower crane attachment support 15). The vertical adjustment T-bolt 19 is slidably inserted into the ferrule 12 on the conversion steel plate 13, and its head is slidably inserted into the channel of the ferrule 12 from the end of the ferrule 12. The vertical adjustment T-bolt 19 can slide vertically along the channel of the ferrule 12 to achieve vertical elevation adjustment. After the vertical adjustment T-bolt 19 is vertically adjusted into place, the shank of the vertical adjustment T-bolt is passed through the mounting hole on the tower crane attachment support 15, and the vertical adjustment T-bolt fastening nut 20 is installed on the shank of the vertical adjustment T-bolt to fix the vertical position of the tower crane attachment support 15. In this way, the four-way fine-tuning eliminates various construction deviations, ensures that the attachment support is accurately aligned and centered in terms of force, and completes the adjustment of the elevation and horizontal position of the tower crane attachment support 15 to the design position, thus establishing the installation benchmark for the tower crane attachment support 15.
[0069] S7: Overall installation and fixation; After the four-way position adjustment is completed, tighten all T-bolts and fastening nuts to fix the tower crane attachment support 15 and the tower crane attachment connecting ear plate 16 (the tower crane attachment connecting ear plate 16 and the tower crane attachment support 15 are fixed as one piece, for example, by welding). Install the tower crane attachment struts, adjust the verticality of the tower body, and complete the overall installation of the tower crane attachment legs.
[0070] The above description is merely a preferred embodiment of the present invention and is not intended to limit the invention. Various modifications and variations can be made to the present invention by those skilled in the art. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the scope of protection of the present invention.
Claims
1. An adjustable tower crane attachment pre-embedded installation device, characterized in that: This includes H-channel embedded parts, temporary T-connectors, working T-connectors, temporary T-connector fasteners, working T-connector fasteners, anti-rotation limit shims, positioning molds, conversion plates, and anchoring components. The Huffen groove embedded part has a channel inside, and an opening is provided on one side of the Huffen groove embedded part, the opening connecting the outside of the Huffen groove embedded part to the channel. The opening side of the Huffen groove embedded part is provided with rolled edges, and the rolled edges are arranged in pairs symmetrically on both sides of the Huffen groove embedded part, and a groove is formed between the two pairs of rolled edges. The halfen groove embedded part includes a first end section, a middle section and a second end section along its length. The cross-section of the first end section is U-shaped. The cross-sections of the middle section and the second end section are both C-shaped with the rolled edge. The anchoring assembly is fixedly connected to the outside of the halfen groove embedded part; The HAFF channel embedded part is embedded in the shear wall concrete, and the HAFF channel embedded part is arranged horizontally. Both the temporary T-shaped connector and the working T-shaped connector are used to slide with the channel. The heads of the temporary T-shaped connector and the working T-shaped connector are used to slide and install themselves in the channel from the first end section. The rods of the temporary T-shaped connector and the working T-shaped connector are used to extend out from the slot opening. The four embedded parts of the halfen groove are respectively arranged at the four corners of the rectangle; The side wall facade construction formwork is provided with formwork fixing holes, and the temporary T-shaped connector rod is used to pass through the formwork fixing holes; The positioning mold is arranged on the outside of the side wall facade construction template and fits against it. The positioning mold is used to fix the four H-channel embedded parts. The positioning mold has two grooves that are in the same direction as the grooves of the H-channel embedded parts. The positioning mold has a limiting groove on the side away from the embedded part of the halfen groove, and the anti-rotation limiting shim is installed in the limiting groove. The shape of the anti-rotation limiting shim is adapted to the limiting groove. During the pre-embedding stage of the HAFF groove pre-embedded part, the rod of the temporary T-shaped connector passes through the side wall facade construction template, the positioning mold, the limiting groove and the anti-rotation limiting gasket, and is connected to the temporary T-shaped connector fastener. The anti-rotation limiting gasket is used to limit the rotation of the temporary T-shaped connector. After the embedded part of the H-channel is embedded, one side of the conversion plate is used to fit with the concrete structure, and the other side of the conversion plate is provided with a H-channel. The length direction of the H-channel is vertical. A vertical adjustment T-type connector is slidably installed in the H-channel. The head of the vertical adjustment T-type connector is slidably set in the H-channel. The rod of the vertical adjustment T-type connector passes through the mounting hole on the tower crane attachment support. A fastener for the vertical adjustment T-type connector is connected to the rod of the vertical adjustment T-type connector.
2. The adjustable tower crane attachment pre-embedded installation device according to claim 1, characterized in that: The temporary T-connector is a temporary T-bolt, the working T-connector is a working T-bolt, the temporary T-connector fastener is a temporary T-bolt fastening nut, the working T-connector fastener is a working T-bolt fastening nut, the vertical adjustment T-connector is a vertical adjustment T-bolt, the vertical adjustment T-connector fastener is a vertical adjustment T-bolt fastening nut, and the conversion plate is a conversion steel plate.
3. The adjustable tower crane attachment pre-embedded installation device according to claim 1, characterized in that: The anchoring assembly includes studs and barbed anchor claws; One end of the stud is fixed to the outer surface of the other side of the H-shaped groove embedded part, and the position of the stud is opposite to the position of the opening. One end of each of the multiple barbed anchor claws is fixed to the outer surface of the halfen groove pre-embedded part, and the multiple barbed anchor claws are arranged at intervals.
4. The adjustable tower crane attachment pre-embedded installation device according to claim 3, characterized in that: The barbed anchor claw is Y-shaped, with the straight shank end of the Y-shaped barbed anchor claw fixed to the HAFF groove pre-embedded part, and the barbed end of the Y-shaped barbed anchor claw being away from the HAFF groove pre-embedded part.
5. The adjustable tower crane attachment pre-embedded installation device according to claim 1, characterized in that: The inner side of the rolled edge is provided with a pressure-bearing inclined surface. The pressure-bearing inclined surface slopes from the side near the slot opening to the side near the side wall of the H-shaped groove embedded part. The thickness of the rolled edge near the slot opening is greater than the thickness of the rolled edge near the side wall of the H-shaped groove embedded part.
6. The adjustable tower crane attachment pre-embedded installation device according to claim 5, characterized in that: Both the temporary T-shaped connector and the working T-shaped connector have inclined mating surfaces at their heads. The inclined mating surfaces are adapted to the pressure-bearing inclined surfaces. When the connectors are assembled, the inclined mating surfaces are in contact with and abut against the pressure-bearing inclined surfaces. The inclined mating surfaces are inclined from the side near the rod of the connector towards the edge of the connector. The thickness of the edge of the head of both the temporary T-shaped connector and the working T-shaped connector is greater than the thickness of the side near the rod.
7. The adjustable tower crane attachment pre-embedded installation device according to claim 6, characterized in that: The inclination angles of both the pressure-bearing inclined surface and the inclined mating surface are 45°.
8. The adjustable tower crane attachment pre-embedded installation device according to claim 1, characterized in that: An anti-slip pad is provided between the anti-rotation limiting pad and the temporary T-shaped connector fastener. The rod of the temporary T-shaped connector passes through the anti-rotation limiting pad and the anti-slip pad in sequence, and is connected to the temporary T-shaped connector fastener.
9. The adjustable tower crane attachment pre-embedded installation device according to claim 1, characterized in that: The channel is a through channel, and the channel of the H-shaped groove is also a through channel. The heads of the temporary T-shaped connector and the working T-shaped connector are used to slide into the first end section of the H-shaped groove pre-embedded part.
10. A construction method using the adjustable tower crane attachment pre-embedded installation device according to any one of claims 1-9, characterized in that: Includes the following steps: S1: Factory prefabrication; According to the tower crane model and corresponding specifications, prefabricate the H-channel embedded parts. The inner side of the rolled edge of the H-channel embedded parts is machined with a pressure-bearing inclined surface, and the H-channel embedded parts are fixed with studs and barbed anchor claws on the outside. Batch processing of temporary T-connectors, working T-connectors, vertical adjustment T-connectors, and corresponding fasteners; The machining positioning mold, conversion plate, anti-rotation limiting pad and anti-slip pad are processed. The conversion plate has two vertical H-shaped grooves. S2: On-site rebar tying; On-site binding of shear wall reinforcement bars. After the shear wall reinforcement bar binding is completed, the lines are accurately laid out according to the tower crane attachment design points. The four H-channel embedded parts are distributed in a rectangular four-point distribution to avoid the horizontal stress reinforcement bars of the wall. The barbed anchor claws are bound and fixed to the vertical main reinforcement bars of the shear wall. S3: Mold positioning and template closing; Align the positioning mold with the pre-embedded point, and pass the temporary T-shaped connector rod through the template, positioning mold, anti-rotation limiting pad and anti-slip pad from one side of the side wall facade construction template. Use the temporary T-shaped connector fastener to lock the four H-shaped groove pre-embedded parts, and fill the cavity of the H-shaped groove pre-embedded parts with foam to seal and prevent grout leakage. S4: Layered concrete pouring; When pouring concrete for shear walls, the limiting and restraining effect of the mold is used to prevent the embedded parts of the Huffing groove from shifting, floating, or twisting under the weight of the concrete and the vibration load, thus ensuring the accuracy of the embedded parts. S5: Demolding and tooling turnover; After the concrete has been cured to the required standard, the side wall facade construction formwork is removed, the temporary T-shaped connector fasteners, positioning molds and temporary T-shaped connectors are removed, the surface laitance of the components is cleaned and then reused in the next construction section, the foam sealing the cavity of the Huffen channel embedded parts is cleaned, and the complete channel and the first end section are exposed. S6: Precise adjustment in both horizontal and vertical directions; The working T-shaped connector is slidably installed into the H-shaped groove embedded part. Its head is slidably installed into the groove from the first end section of the H-shaped groove embedded part and slid until it matches the rolled edge. The rod of the working T-shaped connector passes through the fixing hole on the conversion plate. After the working T-shaped connector is horizontally adjusted into place, the fastener of the working T-shaped connector is installed on the rod of the working T-shaped connector to fix the horizontal position of the conversion plate and the tower crane attachment support. Slide the vertical adjustment T-connector into the H-shaped groove on the conversion plate, and slide its head from the end of the H-shaped groove into the channel of the H-shaped groove. The vertical adjustment T-connector can slide vertically along the channel of the H-shaped groove to achieve vertical elevation adjustment. After the vertical adjustment T-connector is vertically adjusted into place, pass the rod of the vertical adjustment T-connector through the mounting hole on the tower crane attachment support, and install the fastener of the vertical adjustment T-connector on the rod of the vertical adjustment T-connector to fix the vertical position of the tower crane attachment support. S7: Overall installation and fixation; After the four-way position adjustment is completed, tighten all T-type connector fasteners, fix the tower crane attachment support and tower crane attachment connecting ear plate, install the tower crane attachment strut, adjust the tower body verticality, and complete the overall installation of the tower crane attachment legs.