Box transformer substation foundation convenient to assemble

By prefabricating the support piers, support columns and installation platform of the box transformer foundation off-site and assembling it on-site, the traditional long construction time problem is solved, achieving rapid assembly and improving structural safety.

CN221798503UActive Publication Date: 2024-10-01KUNMING TIEXIN PREFABRICATED BUILDING OPERATION MANAGEMENT CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323540906.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-25
Publication Date
2024-10-01
Estimated Expiration
2033-12-25

AI Technical Summary

Technical Problem

The traditional box-type transformer foundation construction requires on-site pouring and waiting for the cement to solidify, resulting in extended construction time and construction period.

Method used

An external prefabricated box-type transformer foundation design is adopted, including support piers, support columns, support frames and installation platforms. Through the design of tapered holes and reinforcing bars, cement mortar is pre-poured off-site and assembled on site, and limit nuts are used to fix the reinforcing bars. to improve structural safety.

Benefits of technology

It greatly shortens the construction period, simplifies the overall structure, facilitates promotion and use, and improves the stability and safety of the installation platform.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221798503U_ABST
    Figure CN221798503U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of box transformer substation foundation construction, in particular to a box transformer substation foundation convenient to assemble, which comprises four supporting piers, an oil collecting pool is arranged on one sides of the two supporting piers, supporting columns are fixedly connected to the top surfaces of the four supporting piers, and supporting frames are arranged at the top ends of the four supporting piers. A mounting platform is fixedly connected to the top face of the supporting frame, and limiting grooves are formed in one sides of the top faces of the four supporting columns. Compared with the prior art, the box transformer substation foundation has the advantages that the four supporting piers, the supporting columns, the supporting frame and the mounting platform are arranged and connected with one another to be assembled into the box transformer substation foundation, the four reinforcing ribs are arranged in the four supporting columns, the top ends of the reinforcing ribs are fixedly connected with the supporting frame through cement mortar, and therefore a user can conveniently assemble the box transformer substation foundation; and the whole components are prefabricated off site and then transported to the site to be assembled, so that the construction period is greatly shortened, the whole structure is simple, and popularization and use are facilitated.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of box-type transformer foundation construction, in particular to a box-type transformer foundation which is easy to assemble. Background Art

[0002] A box-type transformer is a box-type substation. Simply put, it is a substation installed in a house made of colored steel plates, so that the box-type substation can be moved and relocated as a whole. The box-type transformer foundation is the installation foundation of the box-type substation. This foundation is designed according to the size, weight, cable installation, operation, maintenance and overhaul of the box-type transformer. By pre-embedding steel plates on the box-type transformer foundation, a balanced and stable foundation is provided for the installation of the box-type transformer.

[0003] Traditional box-type transformer foundations are generally constructed by on-site pouring, but the template needs to be installed in the early stage of pouring, and it takes a certain amount of time to wait for the cement to solidify after pouring, which undoubtedly increases the overall construction time and prolongs the construction period. Based on this, a box-type transformer foundation that is easy to assemble is proposed. By adopting external prefabrication, the box-type transformer foundation is pre-constructed and then assembled directly on site, which greatly shortens the construction time. Utility Model Content

[0004] The purpose of the utility model is to overcome the shortcomings of the prior art, provide a box-type transformer foundation that is easy to assemble, and effectively solve the deficiencies of the prior art.

[0005] In order to achieve the above-mentioned purpose, an embodiment of the utility model on one hand provides a box-type transformer foundation that is easy to assemble, including four supporting piers, two of which are provided with oil collecting tanks on one side, the top surfaces of the four supporting piers are fixedly connected with supporting columns, and the tops of the four are provided with supporting frames, the top surfaces of the supporting frames are fixedly connected with mounting platforms, one side of the top surfaces of the four supporting columns are provided with limiting grooves, and the four corners of the bottom surface of the supporting frame are provided with raised portions that match the limiting grooves, the top surface of the supporting frame close to the supporting columns is provided with four conical holes, and the interior of the four supporting columns is provided with four reinforcing ribs, and their top ends respectively enter into the interiors of the multiple conical holes.

[0006] Preferably, any of the above schemes is that the bottom surfaces of the four supporting piers and the oil collecting pool are provided with cushion layers, the five cushion layers are buried in the soil, and the adjacent sides of the four supporting piers are fixedly connected with protective nets. By using this scheme, it is convenient to enclose the positions of the four supporting piers and form a protective barrier in the later stage. At the same time, the cushion layer facilitates increasing the contact area between the four supporting piers and the oil collecting pool and the soil to avoid settlement. When the soil is backfilled in the later stage, the supporting piers are completely covered and a part of the supporting columns are buried.

[0007] Preferably, any of the above schemes has four corners extending outwards. This scheme facilitates the formation of a cantilever beam structure, thereby facilitating stable support of both ends of the installation platform and improving structural safety.

[0008] Preferably, any of the above schemes is provided with a slot in the middle of the installation platform away from the top surface of the oil collecting tank, ladders are provided on the inner wall of the slot and at the two corners of the installation platform, and guardrails are fixedly connected on both sides of the installation platform. This scheme facilitates the user to climb up to the top surface of the installation platform by means of the ladder.

[0009] Preferably, any of the above schemes is that the interiors of the multiple conical holes are filled with cement mortar. Due to the unique conical structure of the multiple conical holes, when the cement mortar solidifies, it is convenient to stably connect the support frame with the four support columns and multiple reinforcing ribs, thereby facilitating stable support of the support frame and the installation platform.

[0010] Preferably, any of the above schemes has the top ends of the plurality of reinforcing ribs threadedly connected with limiting nuts. By using this scheme, the top ends of the reinforcing ribs can be easily fixed, and by rotating the limiting nuts, the pressure on the solidified cement mortar can be increased, thereby improving the safety of the structure.

[0011] The utility model has the following advantages:

[0012] 1. The easy-to-assemble box-type transformer foundation is assembled into a box-type transformer foundation by setting four supporting piers, supporting columns, supporting frames and installation platforms. Four supporting piers, supporting columns, supporting frames and installation platforms are connected to each other, and four reinforcing ribs are arranged inside the four supporting columns. At the same time, the tops of multiple reinforcing ribs are fixedly connected to the supporting frames by cement mortar, which is convenient for users to assemble. The overall components are prefabricated off-site and then transported to the site for assembly, which greatly shortens the construction period. The overall structure is simple and easy to promote and use.

[0013] 2. The easy-to-assemble box-type transformer foundation is provided with a support frame and an installation platform, both of which are directly cast as a whole during prefabrication, and the four corners of the support frame are extended outward, so as to facilitate stable support of the two ends of the installation platform. By providing two guardrails and three ladders, it is convenient for users to climb onto the installation platform for the early installation and later maintenance of the box-type transformer. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 This is a schematic diagram of the structure of the utility model from a first perspective;

[0015] Figure 2 It is a schematic diagram of the cutaway structure of the utility model;

[0016] Figure 3 This is a schematic diagram of the support pier structure of the utility model;

[0017] Figure 4 This is a schematic diagram of the installation platform structure of the utility model;

[0018] Figure 5 This is a schematic diagram of the support frame structure of the utility model;

[0019] Figure 6 It is a schematic diagram of the cross-section structure of the connection position between the support frame and the support pier of the utility model;

[0020] Figure 7 This is a schematic diagram of the reinforcing rib placement structure of the utility model.

[0021] In the figure: 1-support pier, 2-pad, 3-support column, 4-ladder, 5-slot, 6-installation platform, 7-support frame, 8-protection net, 9-guardrail, 10-oil collecting tank, 11-limiting nut, 12-limiting groove, 13-reinforcement rib, 14-protrusion, 15-conical hole. DETAILED DESCRIPTION

[0022] The present invention is further described below in conjunction with the accompanying drawings, but the protection scope of the present invention is not limited to the following description.

[0023] like Figures 1 to 7 As shown, a box-type transformer foundation which is easy to assemble includes four supporting piers 1, one side of two supporting piers 1 is provided with an oil collecting tank 10, the top surfaces of the four supporting piers 1 are fixedly connected with supporting columns 3, and the tops of the four are provided with supporting frames 7, the top surfaces of the supporting frames 7 are fixedly connected with a mounting platform 6, one side of the top surfaces of the four supporting columns 3 are provided with limiting grooves 12, the four corners of the bottom surface of the supporting frame 7 are provided with raised portions 14 which match the limiting grooves 12, the top surface of the supporting frame 7 close to the supporting columns 3 is provided with four conical holes 15, the interior of the four supporting columns 3 is provided with four reinforcing ribs 13, and the top ends thereof respectively enter into the interior of the multiple conical holes 15.

[0024] The bottom surfaces of the four supporting piers 1 and the oil collecting pool 10 are provided with cushion layers 2, and the five cushion layers 2 are all buried in the soil. The adjacent sides of the four supporting piers 1 are fixedly connected with protective nets 8. As an optional technical solution of the utility model, this facilitates the encirclement of the positions of the four supporting piers 1 and facilitates the formation of a protective barrier in the later stage. At the same time, the cushion layer 2 facilitates increasing the contact area between the four supporting piers 1 and the oil collecting pool 10 and the soil to avoid settlement. When the soil is backfilled in the later stage, the supporting piers 1 are completely covered and a portion of the supporting columns 3 are buried.

[0025] The four corners of the support frame 7 are extended outwards, which is an optional technical solution of the present invention. This facilitates the formation of a cantilever beam structure, facilitates stable support of both ends of the installation platform 6, and improves structural safety.

[0026] A slot 5 is provided in the middle of the installation platform 6 away from the top surface of the oil collecting tank 10, and ladders 4 are provided on the inner wall of the slot 5 and the two corners of the installation platform 6. Guardrails 9 are fixedly connected on both sides of the installation platform 6. As an optional technical solution of the utility model, it is convenient for users to climb up to the top surface of the installation platform 6 through the ladder 4.

[0027] The interiors of the multiple conical holes 15 are filled with cement mortar. As an optional technical solution of the utility model, due to the unique conical structure of the multiple conical holes 15, when the cement mortar solidifies, it is convenient to stably connect the support frame 7 with the four support columns 3 and the multiple reinforcing ribs 13, thereby facilitating stable support of the support frame 7 and the installation platform 6.

[0028] The top ends of the plurality of reinforcing ribs 13 are all threadedly connected with limiting nuts 11, which is an optional technical solution of the present invention. This facilitates fixing the top ends of the reinforcing ribs 13. By rotating the limiting nuts 11, the pressure on the solidified cement mortar is increased, thereby facilitating improving the safety of the structure.

[0029] The easy-to-assemble box-type transformer foundation requires the following steps when used:

[0030] 1) During assembly, the installation site is cleaned, the soil is cleaned to form an installation tunnel, and then compacted, and plain concrete is poured in advance inside the tunnel;

[0031] 2) After the plain concrete solidifies, the four support piers 1, the support column 3 and the oil collecting tank 10 are hoisted. After the hoisting is completed, the excavated soil is backfilled, the position near the support pier 1 is vibrated, and then the soil layer is leveled;

[0032] 3) pouring a certain thickness of cement mortar on the top surface of the four supporting piers 1, hoisting the supporting frame 7 and the mounting platform 6 as a whole, and making the multiple reinforcing ribs 13 enter the interior of the multiple tapered holes 15 respectively;

[0033] 4) Fill the multiple tapered holes 15 with cement mortar, and leave a certain length for the multiple reinforcing ribs 13;

[0034] 5) After the mortar inside the tapered hole 15 solidifies, the limit nut 11 is threadedly connected to the reinforcing rib 13, and finally the remaining position of the tapered hole 15 is completely poured and filled with mortar again.

[0035] To sum up, when the user uses it, four support piers 1, a support frame 7 and an installation platform 6 are set, and the three are connected to each other to assemble into a box-type transformer foundation, and four reinforcing ribs 13 are set inside the four support piers 1, and the tops of multiple reinforcing ribs 13 are fixedly connected to the support frame 7 by cement mortar, which is convenient for users to assemble, and the overall components are prefabricated off-site and then transported to the site for assembly, which greatly shortens the construction period. The overall structure is simple and easy to promote and use, and then by setting the support frame 7 and the installation platform 6, both are directly cast as a whole during prefabrication, and the four corners of the support frame 7 are extended outward, which is convenient for stabilizing the two end positions of the installation platform 6. By setting two guardrails 9 and three ladders 4, it is convenient for users to climb onto the installation platform 6 to perform early installation and later maintenance of the box-type transformer.

[0036] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A box-type transformer foundation that is easy to assemble, characterized by: It includes four supporting piers, one side of two of the supporting piers is provided with an oil collecting tank, the top surfaces of the four supporting piers are fixedly connected with supporting columns, and the tops of the four are provided with supporting frames, the top surfaces of the supporting frames are fixedly connected with a mounting platform, one side of the top surfaces of the four supporting columns are provided with limiting grooves, the four corners of the bottom surface of the supporting frame are provided with raised parts matching with the limiting grooves, the top surface of the supporting frame close to the supporting columns is provided with four conical holes, the interior of the four supporting columns is provided with four reinforcing ribs, and the top ends of the four supporting columns respectively enter into the interiors of the multiple conical holes.

2. The easy-to-assemble box-type transformer foundation according to claim 1 is characterized in that: The bottom surfaces of the four supporting piers and the oil collecting pool are all provided with cushion layers, the five cushion layers are all buried in the soil, and the adjacent side surfaces of the four supporting piers are all fixedly connected with protective nets.

3. The easy-to-assemble box-type transformer foundation according to claim 2 is characterized in that: The four corners of the support frame all extend outwards.

4. The easy-to-assemble box-type transformer foundation according to claim 3 is characterized in that: A notch is provided in the middle of the installation platform away from the top surface of the oil collecting tank, ladders are provided on the inner wall of the notch and at two corners of the installation platform, and guardrails are fixedly connected to both sides of the installation platform.

5. The easy-to-assemble box-type transformer foundation according to claim 4 is characterized in that: The interiors of the plurality of tapered holes are all filled with cement mortar.

6. The easy-to-assemble box-type transformer foundation according to claim 5 is characterized in that: The top ends of the plurality of reinforcing ribs are all threadedly connected with limiting nuts.