Concrete shear wall internal and external corner template reinforcing system
By using latches to fix the tie rods in the building formwork reinforcement system, the problems of wood consumption and resource waste in traditional technology are solved, and the effects of facilitating subsequent construction and reducing costs are achieved.
Patent Information
- Application Number
- CN202322906074.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-10-27
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2033-10-27
AI Technical Summary
The traditional building formwork reinforcement system consumes a lot of wood, and the construction environment restrictions lead to a waste of resources. In the existing technology, the nuts are exposed and are inconvenient for subsequent construction.
Bolts are used instead of nuts to fix the tie rods. Rectangular main flutes, L-shaped female angle main flutes and positive angle main flutes are used to achieve internal fixation of the tie rods through holes and pins. Metal materials and rubber sleeves are combined to reduce costs.
The tie rods are not exposed to the outside, which facilitates subsequent construction, reduces construction costs, and improves equipment turnover times and construction efficiency.
Smart Images

Figure CN221799144U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of shear wall reinforcement, in particular to a concrete shear wall positive and negative corner formwork reinforcement system. Background Art
[0002] In my country's construction industry, most buildings that use reinforced concrete structures as their building bodies still use wooden formwork reinforcement systems. However, the traditional formwork system consumes a lot of wood, which not only does not conform to the country's development concept of low-carbon environmental protection and green construction, but also increases construction costs. In the past, in the process of domestic building formwork reinforcement construction, the most commonly used building formwork reinforcement materials were round tubes and wooden squares. Due to the properties of the wooden squares themselves, they cannot be applied to all construction environments. They are often cut and truncated according to different construction environments to meet construction requirements, which requires the felling of a large number of trees and wastes resources.
[0003] The Chinese utility model patent with announcement number CN210713827U discloses a reinforcement device for the Yin-Yang corner formwork, including two L-shaped square steels, a C-shaped pressure plate and tension screws. The two L-shaped square steels are respectively arranged on the outer sides of the Yin-Yang corner back ribs of the formwork, and the two L-shaped square steels are fastened by tension screws. C-shaped pressure plates are respectively provided on both sides of the tension screws and fixed by nuts; the thickness of the C-shaped pressure plate is 3-5mm.
[0004] The above patent can effectively control the angle of the shear wall corner formwork and reduce the expansion and explosion of the formwork at the corners, thereby improving the quality of the concrete structure. However, after its construction is completed, the tie rods and nuts are exposed to the outside, which is not convenient for subsequent construction. Utility Model Content
[0005] In view of the problems existing in the prior art, the purpose of the utility model is to provide a concrete shear wall corner formwork reinforcement system, which uses pins instead of nuts to fix the tie rods so that the tie rods are not exposed outside the main ribs, thereby facilitating subsequent construction.
[0006] To solve the above problems, the utility model adopts the following technical solutions.
[0007] A concrete shear wall corner formwork reinforcement system includes a main rib, a tie rod and a latch, wherein the main rib of the building is a rectangular body; the main rib of the outer corner is a rectangular body with one end protruding; the main rib of the building and the main rib of the outer corner are respectively arranged on both sides of the outer corner of the concrete; the inner corner main rib is L-shaped, and the inner corner main rib is arranged at the inner corner end of the concrete; a plurality of holes are opened inside the main ribs; after a plurality of groups of tie rods penetrate the concrete, the two ends extend to the holes of the outer corner main rib of the concrete and the holes of the inner corner main rib respectively; the latch longitudinally penetrates the main rib and the tie rod and is fixed in the hole; the outer corner tie rod transversely penetrates the protruding end of the outer corner main rib and extends to the hole inside the main rib of the building, a latch longitudinally penetrates the main rib of the building and the outer corner tie rod and is fixed inside the hole, the outer peripheral thread of the outer corner tie rod that penetrates one end of the outer corner main rib is connected with a nut, and the nut abuts against the outer corner main rib.
[0008] Furthermore, a template is fixed on the outer periphery of the concrete.
[0009] Furthermore, square steel is fixed between the main ribs and the template.
[0010] Furthermore, rubber sleeves are fixed to the outer peripheries of both ends of the pull rod.
[0011] Compared with the prior art, the beneficial effects of the present invention are as follows:
[0012] 1. The utility model uses a pin instead of a nut to fix the tie rod, so that the tie rod is not exposed outside the main rib, which is convenient for subsequent construction.
[0013] 2. The utility model uses metal materials to replace the wooden materials used in traditional technologies, which increases the turnover times of the entire device and reduces the cost of multiple constructions. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 It is a schematic diagram of the structure of the utility model;
[0015] Figure 2 This is a structural diagram of the main rib of the building;
[0016] Figure 3 This is a schematic diagram of the structure of the main rib of the positive corner;
[0017] Figure 4 This is a structural diagram of the main rib of the inner corner;
[0018] Figure 5 Schematic diagram of the structure inside the hole.
[0019] Description of the numbers in the figure:
[0020] 1. Main ribs of the building; 2. Main ribs of the outer corners; 3. Main ribs of the inner corners; 4. Square steel; 5. Formwork; 6. Concrete; 7. Tie rods; 8. Tie rods of the outer corners; 9. Nuts; 10. Holes; 11. Pins. DETAILED DESCRIPTION
[0021] The technical solutions in the embodiments of the utility model will be clearly and completely described below in conjunction with the drawings in the embodiments of the utility model; it is obvious that the described embodiments are only part of the embodiments of the utility model, rather than all of the embodiments, and all other embodiments obtained by ordinary technicians in this field based on the embodiments of the utility model without making creative work are within the scope of protection of the utility model.
[0022] like Figure 1-Figure 5 As shown, the concrete shear wall corner formwork reinforcement system of this embodiment includes main ribs, tie rods 7 and latches 11. The main rib 1 is a rectangular body; the main rib 2 is a rectangular body with one end protruding; the main rib 1 and the main rib 2 are respectively arranged on both sides of the outer corner of the concrete 6; the main rib 3 is L-shaped, and the main rib 3 is arranged at the inner corner end of the concrete 6; a plurality of holes 10 are opened inside the main ribs; a plurality of tie rods 7 penetrate the concrete 6 and extend to the concrete 6 at both ends. The outer corner main rib is in the hole 10 and the inner corner main rib 3 is in the hole 10; the latch 11 longitudinally penetrates the main rib and the tie rod 7 and is fixed in the hole 10; the outer corner tie rod 8 transversely penetrates the protruding end of the outer corner main rib 2 and extends to the hole 10 inside the building main rib 1. The latch 11 longitudinally penetrates the building main rib 1 and the outer corner tie rod 8 and is fixed in the hole 10. The outer peripheral thread of the outer corner tie rod 8 penetrates one end of the outer corner main rib 2 and is connected with a nut 9, which is in contact with the outer corner main rib 2.
[0023] When using the utility model, firstly place the building main rib 1, the external corner main rib 2 and the internal corner main rib 3 against the outer periphery of the concrete 6, then use multiple sets of tie rods 7 to penetrate the building main rib 1, the internal corner main rib 3, the concrete 6 and the external corner main rib 2, the internal corner main rib 3, the concrete 6 respectively, and point the openings at both ends of the tie rods 7 upward, then use the latch 11 to insert into the hole 10 and the opening of the tie rods 7, thus completing the fixation between the building main rib 1 and the internal corner main rib 3, and between the external corner main rib 2 and the internal corner main rib 3; then use the external corner tie rod 8 to horizontally penetrate the protruding end of the external corner main rib 2 and the side wall of the building main rib 1, so that one end of the external corner tie rod 8 extends into the hole 10, then use the latch 11 to penetrate one end of the hole 10 of the external corner tie rod 8, and use the nut 9 to fix one end of the external corner main rib 2, thus completing the fixation between the building main rib 1 and the external corner main rib 2.
[0024] Furthermore, a formwork 5 is fixed to the outer periphery of the concrete 6 .
[0025] The template 5 limits and positions the concrete 6, ensuring the engineering quality and construction safety of the concrete 6, speeding up the construction progress and reducing the engineering cost.
[0026] Furthermore, square steel 4 is fixed between the main rib and the template 5 .
[0027] The square steel 4 is made of hot-dip galvanized steel, which is light in weight, has a large bearing capacity and a long service life. It can be used for more than 500 times and is fully capable of withstanding the impact during the pouring of concrete 6 and is stable and not deformed.
[0028] Furthermore, rubber sleeves are fixed to the outer peripheries of both ends of the pull rod 7 .
[0029] The method of using the utility model is:
[0030] When using the utility model, firstly place the building main rib 1, the external corner main rib 2 and the internal corner main rib 3 against the outer periphery of the concrete 6, then use multiple sets of tie rods 7 to penetrate the building main rib 1, the internal corner main rib 3, the concrete 6 and the external corner main rib 2, the internal corner main rib 3, the concrete 6 respectively, and point the openings at both ends of the tie rods 7 upward, then use the latch 11 to insert into the hole 10 and the opening of the tie rods 7, thus completing the fixation between the building main rib 1 and the internal corner main rib 3, and between the external corner main rib 2 and the internal corner main rib 3; then use the external corner tie rod 8 to horizontally penetrate the protruding end of the external corner main rib 2 and the side wall of the building main rib 1, so that one end of the external corner tie rod 8 extends into the hole 10, then use the latch 11 to penetrate one end of the hole 10 of the external corner tie rod 8, and use the nut 9 to fix one end of the external corner main rib 2, thus completing the fixation between the building main rib 1 and the external corner main rib 2.
[0031] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A concrete shear wall corner formwork reinforcement system, characterized in that: It comprises a main rib, a pull rod (7) and a latch (11), wherein the main rib (1) of the building is a rectangular body; the main rib (2) of the outer corner is a rectangular body with one end protruding; The main ribs (1) and the main ribs (2) at the outer corners of the concrete (6) are respectively arranged on both sides; the main ribs (3) at the inner corners are L-shaped and arranged at the inner corners of the concrete (6); a plurality of holes (10) are provided inside the main ribs; after the plurality of groups of pull rods (7) penetrate the concrete (6), the two ends respectively extend into the holes (10) of the main ribs at the outer corners of the concrete (6) and the holes (10) of the main ribs at the inner corners (3); the latches (11) penetrate longitudinally through the main ribs (11) and the inner corners of the concrete (6). The outer peripheral thread of the external corner tie rod (8) passes through the protruding end of the external corner main rib (2) and extends into the hole (10) inside the building main rib (1). A latch (11) passes through the building main rib (1) and the external corner tie rod (8) and is fixed inside the hole (10). The external corner tie rod (8) passes through one end of the external corner main rib (2) and is threadedly connected to a nut (9). The nut (9) is in contact with the external corner main rib (2).
2. A concrete shear wall corner formwork reinforcement system according to claim 1, characterized in that: A template (5) is fixed on the outer periphery of the concrete (6).
3. A concrete shear wall corner formwork reinforcement system according to claim 2, characterized in that: A square steel (4) is fixed between the main rib and the template (5).
4. A concrete shear wall corner formwork reinforcement system according to claim 1, characterized in that: Rubber sleeves are fixed to the outer peripheries of both ends of the pull rod (7).