Cast-in-place concrete plate hanging formwork supporting device for shore connection approach bridge
By erecting top beams, bottom beams and connecting rods on the high-altitude working platform, and arranging casing support devices at the connecting rods, the problem of the complicated dismantling process of high-altitude working platforms in the existing technology is solved, and safe and efficient dismantling is achieved. Effect.
Patent Information
- Application Number
- CN202323527201.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-22
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2033-12-22
AI Technical Summary
In the existing technology, the dismantling process of high-altitude working platforms is complicated, requiring the cooperation of multiple equipment and manpower, and cutting is required when dismantling the steel corbels, which can easily cause the concrete bottom form to fall, making it difficult to dismantle safely and efficiently.
Design a cast-in-place concrete slab hanging form support device for the approach bridge to the shore. By erecting top beams, bottom beams and connecting rods between the two pile foundations, laying the formwork, and setting casings at the connecting rods, a disassembly connection is formed to simplify dismantling. process.
It simplifies the dismantling process of high-altitude working platforms, reduces equipment and manpower requirements, improves the safety and efficiency of dismantling, and avoids the risk of the concrete bottom form falling caused by cutting steel corbels.
Smart Images

Figure CN221822745U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of formwork support devices, in particular to a cast-in-place concrete slab hanging formwork support device for a bank approach bridge. Background Art
[0002] The basic components of a high-pile wharf are pile foundation, superstructure and shore connection structure. The shore connection structure usually takes the form of an approach bridge. Normally, the pile foundation of the approach bridge consists of piles and pedestals, and the pile foundation is an independent vertical single-root foundation form such as precast concrete piles or bored piles. When the cast-in-place concrete of the upper structure such as the approach bridge surface layer is constructed, the vertical foundation structure cannot provide lateral support for the working surface. Generally, it is necessary to complete the construction of the upper structure by setting up a working platform to form a bottom membrane support device.
[0003] Usually, the high-altitude working platform is built by welding steel brackets to set up steel sections, and then the bottom formwork and side formwork of the cast-in-place concrete structure are set up on the supporting platform to support the formwork. However, this support method is difficult to remove the bottom formwork. After the entire construction platform is dismantled, it is necessary to remove the upper support by cutting the steel brackets to complete the removal of the bottom formwork of the concrete structure. During the entire dismantling process, a crane is required to cooperate with the operation to assist in supporting the bottom formwork to prevent the bottom formwork from falling rapidly after the steel brackets are cut. The whole process requires the use of more equipment and manpower to cooperate, which is relatively complicated. Utility Model Content
[0004] In view of the deficiencies existing in the prior art, the utility model provides a supporting device for a hanging formwork of a cast-in-place concrete slab of a bank approach bridge, which solves the problem of a relatively complicated dismantling process in the prior art.
[0005] According to an embodiment of the utility model, a cast-in-place concrete slab hanging formwork support device for a shore approach bridge comprises a pair of first pile foundations, on the caps of the two first pile foundations have been cast formed concrete layers, and a number of top beams are overlapped between the two concrete layers, a number of bottom beams are arranged below the top beams, a number of connecting rods are installed on the bottom beams, the top beams are connected to the bottom beams through the connecting rods, a number of formworks are laid on the bottom beams, and the connecting rods are respectively sleeved with sleeves located between the formworks and the top beams.
[0006] In this embodiment, when constructing a bridge, a supporting device is set up between a pair of first pile foundations, a concrete layer that has been formed and reaches the designed strength has been cast on the pedestals of the two first pile foundations, and a number of top beams are placed between the two first pile foundations. The two ends of the top beams are overlapped on the concrete layer, and a number of bottom beams are arranged under the top beams. Then, they are connected by a number of connecting rods to form a tension relationship. Subsequently, a number of templates are laid on a number of base materials, and finally, sleeves are respectively arranged outside all the connecting rods. The position of the sleeves is where the connecting rods are between the templates and the top beams, so as to facilitate the later demolding.
[0007] Furthermore, a plurality of first cross beams are arranged below the plurality of templates, and the plurality of first cross beams are placed on the plurality of bottom beams.
[0008] Furthermore, two ends of each connecting rod are detachably connected to a top beam located directly above the connecting rod and a bottom beam located directly below the connecting rod.
[0009] Furthermore, two ends of each connecting rod respectively penetrate a top beam located directly above it and a bottom beam located directly below it and are connected to nuts.
[0010] Furthermore, a plurality of second cross beams are laterally fixedly connected to the plurality of top beams.
[0011] Furthermore, both ends of the plurality of bottom beams are respectively fixedly connected with reinforcement beams, and one end of the reinforcement beam is connected to the closest top beam.
[0012] Furthermore, a second pile foundation is arranged between the two first pile foundations, a plurality of support columns are fixedly connected to the base of the second pile foundation, and one end of the plurality of support columns is fixedly connected to the top beam directly above.
[0013] Furthermore, third cross beams located above the concrete layer are respectively placed below both ends of the plurality of top beams.
[0014] Compared with the prior art, the utility model has the following beneficial effects:
[0015] The method solves the problem of complicated demolition process in the prior art by overlapping a number of top beams between two first pile foundations, setting a number of bottom beams under the top beams, connecting them with connecting rods, then laying a number of templates on the bottom beams, and finally setting sleeves where all the connecting rods are between the templates and the top beams. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 The overall structure of the embodiment of the utility model is shown in FIG. Figure 1
[0017] Figure 2The overall structure of the embodiment of the utility model is shown in FIG. Figure 2 ;
[0018] In the above drawings: 1, first pile foundation; 2, concrete layer; 3, top beam; 4, bottom beam; 5, connecting rod; 6, formwork; 7, casing; 8, first cross beam; 9, second cross beam; 10, reinforcement beam; 11, second pile foundation; 12, support column; 13, third cross beam; DETAILED DESCRIPTION
[0019] The technical solution of the present utility model is further described below in conjunction with the accompanying drawings and embodiments.
[0020] In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise", "axial", "radial", "circumferential" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.
[0021] like Figure 1-2 As shown, this embodiment provides a supporting device for hanging formwork of cast-in-place concrete slab of shore approach bridge, which includes a pair of first pile foundations 1, and formed concrete layers 2 have been cast on the caps of the two first pile foundations 1, and a number of top beams 3 are overlapped between the two concrete layers 2, and a number of bottom beams 4 are arranged below the top beams 3, and a number of connecting rods 5 are installed on the bottom beams 4. The top beams 3 are connected to the bottom beams 4 through the connecting rods 5, and a number of templates 6 are laid on the bottom beams 4. The connecting rods 5 are respectively sleeved with sleeves 7 located between the templates 6 and the top beams 3.
[0022] In the above embodiments, when the bridge is constructed, a supporting device is set up between a pair of first pile foundations 1, and a concrete layer 2 that has been formed and reaches the designed strength has been cast on the caps of the two first pile foundations 1. A number of top beams 3 are placed between the two first pile foundations 1, and the two ends of the top beams 3 are overlapped on the concrete layer 2. A number of bottom beams 4 are arranged under the top beams 3, and then they are connected by a number of connecting rods 5 to form a tension, and then a number of templates 6 are laid on the base materials, and finally, sleeves 7 are respectively sleeved outside all the connecting rods 5. The position of the sleeve 7 is where the connecting rod 5 is between the template 6 and the top beam 3, which is convenient for later demolding.
[0023] This embodiment solves the problem of complicated demolition process in the prior art by overlapping a number of top beams 3 between two first pile foundations 1, disposing a number of bottom beams 4 below the top beams 3, and then connecting them with connecting rods 5, then laying a number of templates 6 on the bottom beams 4, and finally sleeves 7 where the connecting rods 5 are between the templates 6 and the top beams 3.
[0024] like Figure 1 , 2 As shown, a plurality of first cross beams 8 are further arranged under the plurality of the formworks 6, and the plurality of the first cross beams 8 are placed on the plurality of the bottom beams 4. When the plurality of formworks 6 are laid, placing a plurality of first cross beams 8 thereunder can protect the formworks 6 and mitigate the impact force generated by the external impact on the formwork 6 during the formwork process.
[0025] like Figure 1 As shown, the two ends of each connecting rod 5 are detachably connected to the top beam 3 located directly above it and the bottom beam 4 located directly below it, respectively. The bottom beam 4 and the top beam 3 are detachably connected together through the connecting rod 5, so that they can be easily removed after pouring concrete.
[0026] like Figure 1 As shown, the two ends of each connecting rod 5 respectively penetrate the top beam 3 located directly above it and the bottom beam 4 located directly below it and are connected with nuts. After one end of each connecting rod 5 penetrates the top beam 3 located directly above, a nut will be screwed on it to prevent the connecting rod 5 from falling, and the other end of the connecting rod 5 penetrates the bottom beam 4 located directly below and a nut will be screwed on it to support the bottom beam 4 directly above. The weight of the bottom beam 4 will press on the nut below, thereby applying gravity to the connecting rod 5, and then the nut on the top beam 3 on the connecting rod 5 is pressed against the top beam 3.
[0027] like Figure 1 As described above, several second cross beams 9 are also transversely fixedly connected to the several top beams 3. By fixing the several top beams 3 together through the second cross beams 9, the overall firmness can be improved and the bending of a single top beam 3 due to its weight when pouring concrete can be reduced.
[0028] like Figure 1 As shown, both ends of several bottom beams 4 are fixedly connected with reinforcement beams 10, one end of the reinforcement beam 10 is connected to the closest top beam 3, and several bottom beams 4 and the closest top beam 3 are fixedly connected together through the reinforcement beam 10, thereby further improving the overall stability.
[0029] like Figure 1As shown, a second pile foundation 11 is also arranged between the two first pile foundations 1, and a plurality of support columns 12 are fixedly connected to the base of the second pile foundation 11, and one end of the plurality of support columns 12 is fixedly connected to the top beam 3 directly above. A plurality of support columns 12 are arranged between the second pile foundation 11 and the top beam 3, which can provide support and prevent the top beam 3 from being bent from the center due to the top beam 3 being too long and too much concrete being poured.
[0030] like Figure 1 As shown, third cross beams 13 located above the concrete layer 2 are respectively placed below the two ends of several of the top beams 3, and the third cross beams 13 are placed on the concrete layer 2, and the two ends of several top beams 3 are overlapped on the third cross beams 13. This makes it convenient to smooth the poured concrete and prevents the top beams 3 from damaging the concrete layer 2 due to pressure.
[0031] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the utility model rather than to limit it. Although the utility model has been described in detail with reference to the preferred embodiments, ordinary technicians in the field should understand that the technical solution of the utility model can be modified or replaced by equivalents without departing from the purpose and scope of the technical solution of the utility model, which should be included in the scope of the claims of the utility model.
Claims
1. A cast-in-place concrete slab hanging formwork support device for a shore approach bridge, characterized in that: The invention comprises a pair of first pile foundations (1), on the caps of the two first pile foundations (1), respectively, formed concrete layers (2) have been cast, and a plurality of top beams (3) are overlapped between the two concrete layers (2), a plurality of bottom beams (4) are arranged below the plurality of top beams (3), a plurality of connecting rods (5) are installed on the plurality of bottom beams (4), the plurality of top beams (3) are connected to the plurality of bottom beams (4) through the plurality of connecting rods (5), a plurality of templates (6) are laid on the plurality of bottom beams (4), and a plurality of connecting rods (5) are respectively sleeved with sleeves (7) located between the plurality of templates (6) and the plurality of top beams (3).
2. The cast-in-place concrete slab hanging formwork support device for the shore approach bridge as claimed in claim 1, characterized in that: A plurality of first cross beams (8) are also arranged below the plurality of templates (6), and the plurality of first cross beams (8) are placed on the plurality of bottom beams (4).
3. The cast-in-place concrete slab hanging formwork support device for the shore approach bridge according to claim 1, characterized in that: The two ends of each connecting rod (5) are respectively detachably connected to a top beam (3) located directly above it and a bottom beam (4) located directly below it.
4. The cast-in-place concrete slab hanging formwork support device for the shore approach bridge as claimed in claim 3, characterized in that: The two ends of each connecting rod (5) respectively penetrate a top beam (3) located directly above it and a bottom beam (4) located directly below it and are then connected to nuts.
5. The cast-in-place concrete slab hanging formwork support device for the shore approach bridge according to claim 1, characterized in that: A plurality of second cross beams (9) are also transversely fixedly connected to the plurality of top beams (3).
6. The cast-in-place concrete slab hanging formwork support device for the shore approach bridge as claimed in claim 1, characterized in that: Both ends of the plurality of bottom beams (4) are respectively fixedly connected to a reinforcement beam (10), and one end of the reinforcement beam (10) is connected to the closest top beam (3).
7. The supporting device for the cast-in-place concrete slab of the shore approach bridge according to claim 1, characterized in that: A second pile foundation (11) is also arranged between the two first pile foundations (1), a plurality of support columns (12) are fixedly connected to the support platform of the second pile foundation (11), and one end of the plurality of support columns (12) is fixedly connected to the top beam (3) directly above.
8. The supporting device for cast-in-place concrete slab of the shore approach bridge according to claim 1, characterized in that: A third cross beam (13) located above the concrete layer (2) is placed below both ends of the plurality of top beams (3).