Simple scaffold capable of being moved integrally
By adding reinforcement rods in the construction of thin-walled retaining walls and using a crane for overall hoisting, the problem of long erection and dismantling time of traditional scaffolding has been solved, and the support system has been achieved with flexibility, high stability and low cost, and improved the efficiency of the support system. Construction efficiency.
Patent Information
- Application Number
- CN202323564899.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-26
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2033-12-26
AI Technical Summary
In the construction of thin-walled retaining walls, the erection and dismantling of traditional scaffolding takes up a lot of time and increases the construction cost. There are no reports on related rapid support systems in the existing technology.
By adding reinforcement rods to the crossbars and vertical poles of the scaffolding, and using a crane for overall lifting, combined with the design of fasteners and lifting nodes, the overall movement and reuse of the scaffolding can be achieved, simplifying the erection and dismantling process.
It reduces repeated erection time, improves work efficiency, reduces construction costs, realizes a support system with flexible erection, high stability and good safety, and saves labor and machinery costs.
Smart Images

Figure CN221823329U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of thin-wall retaining wall engineering scaffold construction, and more specifically relates to a simple scaffold which can be moved as a whole. Background Art
[0002] During the construction of thin-wall retaining walls, if the traditional scaffolding overlapping method is used, the scaffolding needs to be re-erected for each pouring of a retaining wall, and the scaffolding of the poured retaining wall needs to be dismantled. The scaffolding erection and dismantling takes up a lot of time in the retaining wall construction, which increases the construction cost. This technology does not require repeated scaffolding erection and can be reused, which saves costs and is simple and flexible.
[0003] The utility model is different from the solutions adopted in other projects, and there is no related report in the construction of the same type of template rapid support system in China. Summary of the invention
[0004] The purpose of this utility model patent is to reduce the time of repeated scaffolding erection, utilize the existing crane for hoisting, improve the connection process of the support system, so that the support system can achieve the excellent performance of flexible erection, good stability, high safety and low construction cost, thereby greatly improving work efficiency.
[0005] In order to achieve the above purpose, the utility model is implemented by adopting the following technical scheme: when setting up the first warehouse retaining wall formwork scaffolding, reinforcement rods 4 are respectively added to the crossbars 1 and the vertical rods 2, and the scaffolding is hoisted as a whole to the second warehouse by a crane.
[0006] Furthermore, the reinforcement rod 4 is connected to the crossbar 1 and the vertical rod 2 by fasteners to ensure the integrity of the overall structure.
[0007] Furthermore, a hoisting node 6 is provided at the outermost connection of the large crossbar 1, the small crossbar 1 and the vertical pole 2 at the uppermost end of the scaffolding for connecting with the sling to ensure the integrity and balance of the scaffolding.
[0008] Furthermore, the position of the lifting node 6 is adjustable.
[0009] Furthermore, after the scaffolding is hoisted, embedded fasteners and pads 5 are preset.
[0010] Furthermore, the scaffold is provided with a scissor brace 3 to connect the crossbar 1 and the vertical bar 2 of the scaffold, thereby enhancing the overall stability of the scaffold.
[0011] Beneficial effects of the utility model:
[0012] The purpose of this utility model patent is to reduce the time of repeated scaffolding erection, utilize the existing crane for hoisting, improve the connection process of the support system, so that the support system can achieve the excellent performance of flexible erection, good stability, high safety and low construction cost, thereby greatly improving work efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1 This is a large sample diagram of the utility model.
[0014] Figure 2 It is a three-dimensional schematic diagram of the utility model.
[0015] In the figure, 1 is horizontal bar, 2 is vertical bar, 3 is scissors brace, 4 is horizontal reinforcement bar, 5 is pad, and 6 is lifting node. DETAILED DESCRIPTION
[0016] The present invention will be described in detail below in conjunction with the accompanying drawings, and the technical solutions in the embodiments of the present invention will be clearly and completely described. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0017] like Figure 1 , Figure 2 As shown, this technology mainly consists of two parts: a ground-type scaffolding and a reinforcement device. When setting up the scaffolding in the first warehouse, a transverse steel pipe reinforcement rod 4 and a scissor brace 3 are added in the middle of the original scaffolding support rod to reduce the spacing, make the scaffolding structure more solid, and improve the integrity; the added steel pipe reinforcement rod 4 is connected to the scaffolding using fasteners to meet the hoisting requirements to ensure the integrity of the overall structure without deformation or tilt. The reinforcement position is shown in the figure. After the construction of the first warehouse is completed, a hoisting point is set at the connection of the outermost ends of the large cross bar 1, the small cross bar 1, and the vertical bar 2 at the top of the scaffolding. After the scaffolding board and the scaffolding connector are disassembled as a whole, one end of the sling is connected and fixed to the four hoisting points with a sling, and the other ends of the sling are connected to each other to ensure that the scaffolding rises vertically as a whole without tilting during hoisting. After connecting the hoisting points, the existing crane is used to hoist the disassembled scaffolding as a whole to the predetermined position of the second warehouse. After the scaffolding is hoisted to the predetermined position, embedded fasteners and pads 5 are set to ensure the stability of the scaffolding. The scaffolding is fully inspected, reinforced and corrected. When everything meets the requirements, the second warehouse construction can be carried out.
[0018] The utility model is an overall movement of the scaffolding, which can be widely used in the formwork support system, saving the time and cost of scaffolding erection in the process, and is quick to use, thereby improving its utilization rate and saving a lot of labor, machinery and time costs.
[0019] The specific working process is as follows:
[0020] In the first step, at the beginning, the first warehouse retaining wall formwork scaffolding is built in a traditional way, and then reinforcement rods 4 are added to the horizontal rods 1 and the vertical rods 2 respectively to reduce the spacing between the support rods, enhance the supporting force, and enhance the overall continuity and stability.
[0021] The second step is to use the existing crane on site to operate after the construction of the first warehouse retaining wall is completed. First, the top cross bar 1, small cross bar 1, and the outermost end of the vertical bar 2 of the scaffolding are connected to set the lifting node 6, and then one end of the sling is connected and fixed to the four lifting points, and the other ends of the sling are connected to each other.
[0022] The third step is to use a crane to lift the scaffolding of the first warehouse as a whole, lift it vertically and move it to the predetermined position of the second warehouse after the lifting point is connected and fixed to the lifting cable.
[0023] The fourth step is to make necessary adjustments after moving to the second warehouse, including fine-tuning the position of the scaffolding, setting necessary embedded fasteners and scissor braces 3 to ensure the stability of the scaffolding, and comprehensively checking and reinforcing the scaffolding to meet the construction requirements before starting the construction of the second warehouse.
[0024] It should be understood that the above specific embodiments of the present invention are only used to illustrate or explain the principles of the present invention, and do not constitute a limitation on the present invention. Therefore, any modifications, equivalent substitutions, improvements, etc. made without departing from the spirit and scope of the present invention should be included in the protection scope of the present invention. In addition, the claims attached to the present invention are intended to cover all changes and modifications that fall within the scope and boundaries of the attached claims, or the equivalent forms of such scope and boundaries.
Claims
1. A simple scaffold that can be moved as a whole, characterized by: When the scaffold is used to erect the first warehouse retaining wall formwork scaffold, reinforcing rods (4) are respectively added to the crossbars (1) and the vertical rods (2), and the scaffold is hoisted as a whole to the second warehouse using a crane; The reinforcement rod (4) is connected to the crossbar (1) and the vertical rod (2) by fasteners to ensure the integrity of the overall structure; A hoisting node (6) is provided at the outermost connection of the large crossbar (1), the small crossbar (1) and the vertical pole (2) at the uppermost end of the scaffolding, and is used to connect with the sling to ensure the integrity and balance of the scaffolding; The position of the lifting node (6) is adjustable; After the scaffolding is hoisted, embedded fasteners and pads (5) are preset; The scaffold is provided with scissor braces (3) to connect the crossbars (1) and the vertical bars (2) of the scaffold, thereby enhancing the overall stability of the scaffold.