Building construction guardrail
By designing a spray structure and a spring clamp assembly structure on the construction guardrail, the problems of dust diffusion and difficulty in assembly are solved, effective dust reduction and efficient assembly are achieved, and the construction environment and efficiency are improved.
Patent Information
- Application Number
- CN202323467132.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-19
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2033-12-19
AI Technical Summary
The existing building construction guardrails cannot effectively isolate dust during the construction process, causing the dust to spread outward and affecting the sanitation of the working environment. The laying of sprinkler water pipes is cumbersome and affects construction efficiency.
A construction guardrail is designed, with a sprinkler structure at the top, including a support frame, a folding pipe, a connector, a cover, a nozzle and a water pipe. Through the rotation of the connector and cover, water can be introduced and sprayed, and dust can be reduced; At the same time, the spring and clamp structure is used to facilitate assembly and fixation, and improve construction efficiency.
It achieves effective dust reduction, reduces dust diffusion, improves operating environment hygiene, simplifies the assembly and fixation process of the device, and improves construction efficiency.
Smart Images

Figure CN221823551U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of building construction, in particular to a building construction guardrail. Background Art
[0002] Construction guardrail is a facility used to protect the safety of construction sites. It is usually made of metal materials and is generally not less than 1.2 meters high. It can block the movement of objects and people to avoid accidents. It is usually composed of columns, cross bars, vertical bars, support bars and bases. The columns and cross bars are usually connected by welding or bolts, and the vertical bars and support bars are connected to the columns and cross bars by bolts. The base is usually cast in concrete, which can increase the stability and load-bearing capacity of the guardrail.
[0003] China Patent Authorization Announcement No. CN213477890U, Announcement Date June 18, 2021, discloses a construction guardrail, which includes a column and a grid, the grid is arranged between two of the columns, and the grid and the column are detachably connected by a connecting assembly, the connecting assembly is arranged on the side wall of the grid through an installation assembly, and the connecting assembly is connected to the side wall of the column through a fastener. This application has the effect of being detachable for easy transportation and saving storage;
[0004] The existing technical solutions have the following defects: when the device is in use, it is not convenient to isolate dust. Since the dust content is relatively high during the construction process, and the device can only block the movement of objects and personnel, it cannot have a good effect on the dust. Therefore, in order to prevent the dust from spreading outward, some construction sites will additionally lay a sprinkler water pipe on the top of the device. The laying process is cumbersome, which affects the efficiency of the device construction. Utility Model Content
[0005] The purpose of the utility model is to provide a building construction guardrail to solve the problems raised in the above background technology.
[0006] In order to solve the above technical problems, the utility model provides the following technical solutions: a construction guardrail, comprising a guardrail and a fixed frame, a spray structure is arranged at the top of the guardrail, fixed structures are arranged on both sides of the guardrail, a fixed frame is arranged on one side of the fixed structure, the spray structure comprises a support frame, a folding pipe, a first connecting head, a second connecting head, a cover shell, a nozzle and a water pipe, the support frame is fixed at the top of the guardrail, and a water pipe is fixed inside the support frame.
[0007] Preferably, a nozzle is fixed at the top of each water pipe, a folding tube is fixed at one side of the water pipe, a first connector is installed at one side of the folding tube, a cover is sleeved on the outer side of the first connector, and a second connector is arranged at one side of the first connector. By inserting the second connector into the cover, the cover is rotated to connect adjacent water pipes, so that water is introduced into the water pipe and sprayed out by the nozzle to reduce dust in the air around the device.
[0008] Preferably, an outer wall of the second connector is provided with an external thread, and an inner wall of the housing is provided with an internal thread matching the external thread.
[0009] Preferably, a fixing plate is fixed to the bottom end of the fixing frame, a reflective strip is fixed to the bottom end of one side of the guardrail, and a fence net is fixed inside the guardrail.
[0010] Preferably, springs are installed at both ends of the insert block, a clamp block is fixed at the top of the spring, and clamping slots are provided at both ends of the slot. The insert block is inserted into the slot, and the spring pushes the clamp block into the clamping slot, so that the position between the guardrail and the fixing frame is fixed.
[0011] Preferably, springs are installed at both ends of the insert block, a clamping block is fixed to the top of the spring, and clamping grooves are provided inside both ends of the slot.
[0012] Preferably, a sliding structure is formed between the card slot and the card block, and a sliding structure is formed between the insertion block and the slot.
[0013] Compared with the prior art, the utility model has the following beneficial effects: the building construction guardrail has a reasonable structure and has the following advantages:
[0014] (1) By inserting the second connector into the interior of the housing, rotating the housing to connect the adjacent water pipes, water is introduced into the interior of the water pipes and sprayed out by the nozzles to reduce dust in the air around the device, thereby realizing the spray dust reduction function of the device, making it easier for the device to block dust, reduce the spread of dust, improve the hygiene of the working environment, avoid environmental pollution, and enhance the functionality of the device;
[0015] (2) The block is inserted into the slot and the spring pushes the block into the slot, so that the position between the guardrail and the fixing frame is fixed. This realizes the easy assembly function of the device, facilitates the quick assembly and fixation of the device, reduces the time consumed in assembling the device, and improves the construction efficiency of the device. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 This is a front view structural schematic diagram of the utility model;
[0017] Figure 2It is a schematic diagram of the top view structure of the utility model;
[0018] Figure 3 This is a schematic diagram of the front cross-sectional structure of the spray structure of the utility model;
[0019] Figure 4 It is a schematic diagram of a top view cross-sectional structure of the fixing structure of the utility model.
[0020] Explanation of the reference numerals in the figure: 1. guardrail; 2. reflective strip; 3. fixing frame; 4. fixing structure; 401. plug-in block; 402. slot; 403. card slot; 404. spring; 405. card block; 5. spray structure; 501. support frame; 502. folding tube; 503. first connector; 504. second connector; 505. cover; 506. nozzle; 507. water pipe; 6. partition net; 7. fixing plate. DETAILED DESCRIPTION
[0021] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by technicians in the technical field of this application; the terms used in the specification of the application herein are only for the purpose of describing specific embodiments and are not intended to limit this application; the terms "including" and "having" and any variations thereof in the specification and claims of this application and the above-mentioned drawings are intended to cover non-exclusive inclusions. The terms "first", "second", etc. in the specification and claims of this application or the above-mentioned drawings are used to distinguish different objects, not to describe a specific order.
[0022] Reference to "embodiments" herein means that a particular feature, structure, or characteristic described in conjunction with the embodiments may be included in at least one embodiment of the present application. The appearance of the phrase in various locations in the specification does not necessarily refer to the same embodiment, nor is it an independent or alternative embodiment that is mutually exclusive with other embodiments. It is explicitly and implicitly understood by those skilled in the art that the embodiments described herein may be combined with other embodiments.
[0023] The utility model embodiment provides a building construction guardrail, such as Figure 1-4 As shown, a construction guardrail includes a guardrail 1 and a fixing frame 3, a spray structure 5 is arranged at the top of the guardrail 1, fixing structures 4 are arranged on both sides of the guardrail 1, a fixing frame 3 is arranged on one side of the fixing structure 4, the spray structure 5 includes a support frame 501, a folding tube 502, a first connecting head 503, a second connecting head 504, a cover shell 505, a nozzle 506 and a water pipe 507, the support frame 501 is fixed to the top of the guardrail 1, a water pipe 507 is fixed inside the support frame 501, a fixing plate 7 is fixed to the bottom end of the fixing frame 3, a reflective strip 2 is fixed to the bottom end of one side of the guardrail 1, and a fence net 6 is fixed inside the guardrail 1.
[0024] Specifically, in this embodiment, the fixing frame 3 is fixed to the ground by inserting the bolts through the fixing plate 7 into the ground, and then the guardrail 1 is inserted between the two sets of fixing frames 3, so that the fixing structure 4 fixes the position of the guardrail 1, and the spray structure 5 is connected to the water pipe to spray the dust, and the reflective strip 2 is used to facilitate vehicles and pedestrians in the distance to find the device in time.
[0025] In a further preferred embodiment of the present invention, Figure 1-4 As shown: a nozzle 506 is fixed to the top of the water pipe 507, a folding tube 502 is fixed to one side of the water pipe 507, a first connector 503 is installed on one side of the folding tube 502, a cover shell 505 is sleeved on the outer side of the first connector 503, a second connector 504 is arranged on one side of the first connector 503, an outer wall of the second connector 504 is arranged with an external thread, and the inside of the cover shell 505 is arranged with an internal thread that cooperates with the external thread.
[0026] Specifically, in this embodiment, by aligning and inserting the second connecting head 504 into the interior of the cover shell 505, rotating the cover shell 505, so that the second connecting head 504 is connected and fixed to the first connecting head 503, the adjacent water pipes 507 are connected, and water is introduced into the interior of the water pipe 507 through the folding tube 502 and sprayed out by the nozzle 506, so as to reduce dust in the air around the device and prevent the spread of dust. The folding tube 502 facilitates the movement of the position of the second connecting head 504 and the first connecting head 503.
[0027] In a further preferred embodiment of the present invention, Figure 1-4 As shown: springs 404 are installed at both ends of the plug block 401, a clamping block 405 is fixed on the top of the spring 404, and clamping slots 403 are opened inside the two ends of the slot 402. Springs 404 are installed at both ends of the plug block 401, a clamping block 405 is fixed on the top of the spring 404, and clamping slots 403 are opened inside the two ends of the slot 402. A sliding structure is formed between the clamping slot 403 and the clamping block 405, and a sliding structure is formed between the plug block 401 and the slot 402.
[0028] Specifically, in this embodiment, the protective fence 1 is lifted to align the insert block 401 and insert it into the slot 402 to limit the position of the protective fence 1. At the same time, the spring 404 pushes the block 405 to be inserted into the slot 403 to fix the position between the insert block 401 and the slot 402, so that the position between the protective fence 1 and the fixing frame 3 is fixed.
[0029] It should be noted that, for the above-mentioned embodiments, for the sake of simplicity, they are all described as a series of action combinations, but those skilled in the art should know that the utility model is not limited by the described action sequence, because according to the utility model, some steps may be performed in other sequences or simultaneously. Secondly, those skilled in the art should also know that the embodiments described in the specification are all preferred embodiments, and the actions and modules involved are not necessarily required by the utility model.
[0030] In the several embodiments provided in the present application, it should be understood that the disclosed devices can be implemented in other ways. For example, the device embodiments described above are merely schematic, such as the division of the above-mentioned units. There may be other division methods in actual implementation, such as multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or communication connection shown or discussed can be through some interfaces, and the indirect coupling or communication connection between devices or units can be in the form of telecommunication or other forms.
[0031] The units described above as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.
[0032] The above embodiments are only used to illustrate the technical solutions of the utility model, rather than to limit the protection scope of the utility model. Obviously, the described embodiments are only some embodiments of the utility model, rather than all embodiments. Based on these embodiments, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the utility model. Although the utility model has been described in detail with reference to the above embodiments, ordinary technicians in this field can still combine, add, delete or make other adjustments to the features in the various embodiments of the utility model according to the circumstances without conflict, without making creative work, so as to obtain different other technical solutions that do not deviate from the concept of the utility model in essence, and these technical solutions also belong to the scope of protection of the utility model.
Claims
1. A construction guardrail, Features: It comprises a guardrail (1) and a fixing frame (3); A spray structure (5) is provided at the top of the guardrail (1), and fixing structures (4) are provided on both sides of the guardrail (1); A fixing frame (3) is provided on one side of the fixing structure (4); The spray structure (5) comprises a support frame (501), a folding tube (502), a first connector (503), a second connector (504), a cover (505), a nozzle (506) and a water pipe (507); The support frame (501) is fixed on the top of the guardrail (1), and a water pipe (507) is fixed inside the support frame (501).
2. A construction guardrail according to claim 1, Features: A nozzle (506) is fixed at the top of each of the water delivery pipes (507); A folding tube (502) is fixed on one side of the water delivery tube (507), and a first connector (503) is installed on one side of the folding tube (502); A cover shell (505) is sleeved on the outer side of the first connector (503), and a second connector (504) is arranged on one side of the first connector (503).
3. A construction guardrail according to claim 1, Features: An external thread is provided on the outer wall of the second connector (504), and an internal thread matching the external thread is provided inside the housing (505).
4. A construction guardrail according to claim 1, Features: A fixing plate (7) is fixed to the bottom end of the fixing frame (3), a reflective strip (2) is fixed to the bottom end of one side of the guardrail (1), and a fence net (6) is fixed inside the guardrail (1).
5. A construction guardrail according to claim 1, Features: The fixing structure (4) comprises an insert block (401), a slot (402), a clamping slot (403), a spring (404) and a clamping block (405); the insert block (401) is fixed on both sides of the guardrail (1); and the slot (402) is sleeved on the outer side of the insert block (401).
6. A construction guardrail according to claim 5, Features: Springs (404) are installed at both ends of the insert block (401), a clamping block (405) is fixed at the top of the spring (404), and clamping grooves (403) are opened inside the two ends of the slot (402).
7. A construction guardrail according to claim 5, Features: A sliding structure is formed between the card slot (403) and the card block (405), and a sliding structure is formed between the insertion block (401) and the slot (402).