Bridge construction monitoring device

By introducing an electric telescopic rod and cleaning mechanism into the bridge construction monitoring device, the problem of dust-proof filter plates adsorbing impurities is solved, automatic cleaning and height adjustment are realized, costs and operational complexity are reduced, and the bridge deformation detection process is simplified.

CN221831878UActive Publication Date: 2024-10-15JIANGSU DONGNAN TRAFFIC ENG CONSULTATION JIANLI CO LT
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202420365843.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-27
Publication Date
2024-10-15
Estimated Expiration
2034-02-27

AI Technical Summary

Technical Problem

The dust-proof filter plate of the existing bridge construction deformation monitoring device will absorb a large amount of dust and other impurities under long-term use, affecting the detection effect. It also lacks a quick cleaning device and requires manual cleaning. The height adjustment and fixed base structures are complex, resulting in The cost is higher.

Method used

A bridge construction monitoring device is designed, which uses an electric telescopic rod and a cleaning mechanism. The screw drives the threaded block and the connecting plate to drive the cleaning plate to move, thereby cleaning the impurities on the filter plate, simplifying the cleaning process, and adjusting it through the electric telescopic rod. The height of the detection device and the positioning bolts fix the base plate, which reduces the complexity and cost of operation.

Benefits of technology

It realizes the rapid cleaning of impurities on the filter plate without manual operation, simplifies operation, reduces manual labor requirements, and reduces costs and operational complexity through the use of electric telescopic rods and positioning bolts.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221831878U_ABST
    Figure CN221831878U_ABST
Patent Text Reader

Abstract

The utility model discloses a bridge construction monitoring device, and relates to the technical field of bridge construction, the bridge construction monitoring device comprises an embedded part, the top of the embedded part is provided with a bottom plate, the outer wall of the top of the bottom plate is fixedly provided with a first electric telescopic rod, the output end of the first electric telescopic rod is fixedly provided with a mounting box, and the mounting box is internally provided with a bridge deformation detection device. According to the device, under the cooperative action of a cleaning plate and the like, a motor is controlled to be started, the output end of the motor drives a screw rod to rotate, the screw rod rotates to drive two threaded blocks and two connecting plates to get close to each other, and the two connecting plates get close to each other to drive two rotating plates to rotate and push a pushing plate and the cleaning plate to move; and the cleaning plate moves to clean impurities adsorbed on the filter plate, so that the filter plate does not need to be cleaned, the operation is simple and convenient, and the manual labor force is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of bridge construction, and in particular to a bridge construction monitoring device. Background Art

[0002] Bridge construction refers to bridge construction technology and construction organization, construction management, construction quality, etc. With the rapid development of my country's transportation industry, large-span, high-difficulty, large and complex bridges are being built and planned more and more. Bridges will have different deformations during construction and after completion, so real-time monitoring and maintenance of bridges are required.

[0003] After searching, the Chinese patent authorization announcement number CN214893209U discloses a bridge construction deformation monitoring device, including embedded parts, a base, a placement box with a detection hole on the top, and a bridge deformation detection device arranged in the placement box.

[0004] A bridge construction deformation monitoring device in the above patent has the following shortcomings: although the bridge construction deformation monitoring device can fix and adjust the height of the bridge deformation detection device to detect the bridge deformation, the dust filter plate on the device will be adsorbed with a large amount of dust and other impurities after long-term use, which will affect the bridge deformation detection device. At this time, it needs to be cleaned, and there is no device for quick cleaning on the dust filter plate. Therefore, manual cleaning is often required when cleaning it, which is troublesome. In addition, the structure for adjusting the height and fixing the base on the device is relatively complicated, which will lead to higher cost. Utility Model Content

[0005] The purpose of the utility model is to solve or at least alleviate the problem in the prior art that, after long-term use, a large amount of dust and other impurities will be adsorbed on the dust filter plate on the device, which will affect the bridge deformation detection device and need to be cleaned. However, there is no device for quickly cleaning the dust filter plate, so manual cleaning is often required when cleaning it, which is quite troublesome.

[0006] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a bridge construction monitoring device, comprising an embedded part, a base plate is provided on the top of the embedded part, a first electric telescopic rod is fixedly installed on the top outer wall of the base plate, an installation box is fixedly installed on the output end of the first electric telescopic rod, a bridge deformation detection device is provided in the installation box, a detection hole is opened on the top outer wall of the installation box, a filter plate is provided in the detection hole, and a cleaning mechanism is provided on the top outer wall of the installation box.

[0007] The cleaning mechanism includes a protective box, in which a screw is rotatably installed, the screw is a bidirectional screw, and two threaded blocks are symmetrically threaded on the screw, one side outer wall of the two threaded blocks are fixedly installed with connecting plates, the top outer walls of the two connecting plates are rotatably installed with rotating plates, one end of the two rotating plates are cross-installed, and a push plate is fixedly installed on one of the rotating plates, a cleaning plate is fixedly installed on the outer wall of one side of the push plate, and a driving mechanism is provided at one end of the screw.

[0008] By adopting the above technical solution, the rotation of the screw will drive the two threaded blocks and the two connecting plates to approach each other. The two connecting plates approaching each other will drive the two rotating plates to rotate and push the pushing plate and the cleaning plate to move. The cleaning plate moves to clean the impurities adsorbed on the filter plate, and there is no need to clean it. It is simple and convenient, and reduces manual labor.

[0009] Optionally, the driving mechanism includes a support plate, the support plate is fixedly mounted on one side outer wall of the protective box, a motor is fixedly mounted on the top outer wall of the support plate, and the motor is fixedly connected to one end of the screw rod.

[0010] By adopting the above technical solution, the output end of the motor will drive the screw to rotate by controlling the starting motor.

[0011] Optionally, the cleaning plate is located on one side of the filter plate, and the width of the cleaning plate is greater than the width of the filter plate.

[0012] By adopting the above technical solution, a cleaning function can be achieved by arranging a cleaning plate.

[0013] Optionally, second electric telescopic rods are fixedly mounted on both inner walls of the mounting box, and abutment plates are fixedly mounted on the output ends of the two second electric telescopic rods. The two abutment plates are located on both sides of the bridge deformation detection device and are in contact with it.

[0014] By adopting the above technical solution, by controlling and starting the two second electric telescopic rods, the output ends of the two second electric telescopic rods will drive the two abutment plates to approach each other, thereby fixing bridge deformation detection devices of different sizes and preventing the bridge deformation detection devices from shaking.

[0015] Optionally, a protective pad is provided on one side of the outer wall of the two abutment plates close to each other, and a long groove is opened on one side of the outer wall of the protection box, and the two threaded blocks are slidably installed in the long groove.

[0016] By adopting the above technical solution, a protective effect can be achieved by arranging a protective pad.

[0017] Optionally, an installation groove is provided on one side outer wall of the installation box, a box door is hingedly connected in the installation groove, and a handle is fixedly installed on one side outer wall of the box door.

[0018] By adopting the above technical solution, the box door can be opened by pulling the handle, and the situation inside the installation box can be observed at this time.

[0019] Optionally, two telescopic rods are symmetrically fixedly mounted on the top outer wall of the bottom plate, and output ends of the two telescopic rods are fixedly mounted on the bottom outer wall of the installation box.

[0020] By adopting the above technical solution, the telescopic rod is provided so as to play a role of auxiliary support.

[0021] Optionally, fixing seats are fixedly installed on the outer walls on both sides of the base plate, positioning bolts are threaded on the two fixing seats, the two positioning bolts are threadedly connected to the embedded parts, and positioning knobs are fixedly installed on one end of the top of the two positioning bolts.

[0022] By adopting the above technical solution, by rotating the positioning knob, the positioning bolt will also be driven to rotate and move downward, so that the base plate can be installed and fixed.

[0023] In summary, the beneficial effects of this application are as follows:

[0024] 1. The new type of the present application adopts the cooperation of the cleaning plate, etc., by controlling the starting motor, the output end of the motor will drive the screw to rotate, the rotation of the screw will drive the two threaded blocks and the two connecting plates to approach each other, the two connecting plates approach each other, which will drive the two rotating plates to rotate and push the pushing plate and the cleaning plate to move, the cleaning plate moves to clean the impurities adsorbed on the filter plate, and there is no need to clean it, which is simple and convenient, and reduces manual labor.

[0025] 2. The new type of the present application adopts the cooperation of positioning bolts, etc., by controlling and starting the first electric telescopic rod, the output end of the first electric telescopic rod will drive the installation box to move upward, so that the height of the bridge deformation detection device can be adjusted, and by turning the positioning knob, the positioning bolt will also be driven to rotate and move downward, so that the base plate can be installed and fixed, and the cost is relatively low. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Figure 1 It is a schematic diagram of the entire application;

[0027] Figure 2 This is a schematic diagram of the installation box for this application;

[0028] Figure 3 It is a schematic diagram of the cleaning board of this application.

[0029] Explanation of the accompanying drawings: In the figure: 1. embedded parts; 2. fixing seat; 3. bottom plate; 4. positioning bolt; 5. positioning knob; 6. telescopic rod; 7. first electric telescopic rod; 8. installation box; 9. installation slot; 10. box door; 11. handle; 12. protection box; 13. support plate; 14. motor; 15. long slot; 16. detection hole; 17. filter plate; 18. bridge deformation detection device; 19. second electric telescopic rod; 20. abutment plate; 21. screw; 22. threaded block; 23. connecting plate; 24. rotating plate; 25. pushing plate; 26. cleaning plate. DETAILED DESCRIPTION

[0030] The following is combined with Figure 1-3 This application is described in further detail.

[0031] See also Figure 1-3 The bridge construction monitoring device includes an embedded part 1. A base plate 3 is provided on the top of the embedded part 1. A first electric telescopic rod 7 is fixedly installed on the top outer wall of the base plate 3. An installation box 8 is fixedly installed on the output end of the first electric telescopic rod 7. The installation box 8 can be driven to move by setting the first electric telescopic rod 7. A bridge deformation detection device 18 is provided in the installation box 8. A detection hole 16 is opened on the top outer wall of the installation box 8. A filter plate 17 is provided in the detection hole 16. By setting the filter plate 17, dust can be blocked and filtered. A cleaning mechanism is provided on the top outer wall of the installation box 8; the cleaning mechanism can play a cleaning role.

[0032] The cleaning mechanism includes a protective box 12, in which a screw 21 is rotatably installed. The screw 21 is a bidirectional screw, and two threaded blocks 22 are symmetrically threaded on the screw 21. By setting the screw 21, the two threaded blocks 22 can be driven to move closer to or away from each other. A connecting plate 23 is fixedly installed on the outer wall of one side of the two threaded blocks 22, and a rotating plate 24 is rotatably installed on the top outer wall of the two connecting plates 23. One end of the two rotating plates 24 is cross-installed, and a push plate 25 is fixedly installed on one of the rotating plates 24. The push plate 25 is set to assist movement. A cleaning plate 26 is fixedly installed on the outer wall of one side of the push plate 25, and a driving mechanism is set at one end of the screw 21.

[0033] When in use, the screw rod 21 rotates, thereby driving the two threaded blocks 22 and the two connecting plates 23 to approach each other. The two connecting plates 23 approach each other, thereby driving the two rotating plates 24 to rotate and push the pushing plate 25 and the cleaning plate 26 to move. The cleaning plate 26 moves to clean the impurities adsorbed on the filter plate 17, and there is no need to clean it. It is simple and convenient, and reduces labor.

[0034] Reference Figure 1 and Figure 2 The driving mechanism includes a support plate 13, which is fixedly mounted on one side outer wall of the protection box 12. A motor 14 is fixedly mounted on the top outer wall of the support plate 13, and the motor 14 is fixedly connected to one end of the screw 21. By controlling the start of the motor 14, the output end of the motor 14 will drive the screw 21 to rotate.

[0035] Reference Figure 2 and Figure 3 The cleaning plate 26 is located on one side of the filter plate 17, and the width of the cleaning plate 26 is greater than the width of the filter plate 17. The cleaning plate 26 is provided to achieve a cleaning effect.

[0036] Reference Figure 2 The inner walls on both sides of the installation box 8 are fixedly mounted with second electric telescopic rods 19, and the output ends of the two second electric telescopic rods 19 are fixedly mounted with abutment plates 20, which are located on both sides of the bridge deformation detection device 18 and in contact with it. By controlling and starting the two second electric telescopic rods 19, the output ends of the two second electric telescopic rods 19 will drive the two abutment plates 20 to approach each other, so that the bridge deformation detection devices 18 of different sizes can be fixed, and the bridge deformation detection device 18 can also be prevented from shaking.

[0037] Reference Figure 2 and Figure 3 The outer walls of the two abutment plates 20 close to each other are provided with protective pads, and the outer wall of one side of the protection box 12 is provided with an elongated groove 15, and the two threaded blocks 22 are slidably installed in the elongated groove 15. The protective pads can play a protective role.

[0038] Reference Figure 1 An installation slot 9 is provided on one side outer wall of the installation box 8, a box door 10 is hingedly connected in the installation slot 9, and a handle 11 is fixedly installed on one side outer wall of the box door 10. By pulling the handle 11, the box door 10 can be opened, and the situation inside the installation box 8 can be observed.

[0039] Reference Figure 1 Two telescopic rods 6 are symmetrically fixedly installed on the top outer wall of the bottom plate 3, and the output ends of the two telescopic rods 6 are fixedly installed on the bottom outer wall of the installation box 8. The telescopic rods 6 can play an auxiliary supporting role.

[0040] Reference Figure 1The outer walls of both sides of the bottom plate 3 are fixedly mounted with fixing seats 2, and positioning bolts 4 are screwed on the two fixing seats 2. The two positioning bolts 4 are threadedly connected to the embedded parts 1, and positioning knobs 5 are fixedly mounted on one end of the top of the two positioning bolts 4. By rotating the positioning knobs 5, the positioning bolts 4 are also driven to rotate and move downward, so that the bottom plate 3 can be installed and fixed.

[0041] The implementation principle of the present application is as follows: when in use, firstly, the first electric telescopic rod 7 is controlled to be started, and the output end of the first electric telescopic rod 7 will drive the installation box 8 to move upward, so that the height of the bridge deformation detection device 18 can be adjusted, and the two second electric telescopic rods 19 are controlled to be started, and the output ends of the two second electric telescopic rods 19 will drive the two abutment plates 20 to approach each other, so that the bridge deformation detection devices 18 of different sizes can be fixed, and the bridge deformation detection device 18 can also be prevented from shaking;

[0042] By rotating the positioning knob 5, the positioning bolt 4 is driven to rotate and move downward, so that the base plate 3 can be installed and fixed;

[0043] When it is necessary to clean the impurities on the filter plate 17, by controlling the starting motor 14, the output end of the motor 14 will drive the screw 21 to rotate, and the rotation of the screw 21 will drive the two threaded blocks 22 and the two connecting plates 23 to approach each other. The two connecting plates 23 approach each other, which will drive the two rotating plates 24 to rotate and push the pushing plate 25 and the cleaning plate 26 to move. The cleaning plate 26 moves to clean the impurities adsorbed on the filter plate 17, and there is no need to clean it. It is simple and convenient, and reduces manual labor.

[0044] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A bridge construction monitoring device, comprising an embedded part (1), wherein a bottom plate (3) is provided on the top of the embedded part (1), a first electric telescopic rod (7) is fixedly mounted on the top outer wall of the bottom plate (3), an installation box (8) is fixedly mounted on the output end of the first electric telescopic rod (7), a bridge deformation detection device (18) is arranged in the installation box (8), a detection hole (16) is opened on the top outer wall of the installation box (8), a filter plate (17) is arranged in the detection hole (16), Features: The top outer wall of the installation box (8) is provided with a cleaning mechanism; The cleaning mechanism comprises a protective box (12), a screw (21) is rotatably mounted in the protective box (12), the screw (21) is a bidirectional screw, and two threaded blocks (22) are symmetrically threaded on the screw (21), a connecting plate (23) is fixedly mounted on one side outer wall of the two threaded blocks (22), a rotating plate (24) is rotatably mounted on the top outer wall of the two connecting plates (23), one end of the two rotating plates (24) is cross-mounted, and a push plate (25) is fixedly mounted on one of the rotating plates (24), a cleaning plate (26) is fixedly mounted on one side outer wall of the push plate (25), and a driving mechanism is provided at one end of the screw (21).

2. The bridge construction monitoring device according to claim 1, Features: The driving mechanism comprises a support plate (13), wherein the support plate (13) is fixedly mounted on an outer wall of one side of the protection box (12), and a motor (14) is fixedly mounted on the top outer wall of the support plate (13), wherein the motor (14) is fixedly connected to one end of a screw rod (21).

3. The bridge construction monitoring device according to claim 1, Features: The cleaning plate (26) is located on one side of the filter plate (17), and the width of the cleaning plate (26) is greater than the width of the filter plate (17).

4. The bridge construction monitoring device according to claim 1, Features: Second electric telescopic rods (19) are fixedly mounted on the inner walls of both sides of the installation box (8), and abutment plates (20) are fixedly mounted on the output ends of the two second electric telescopic rods (19), and the two abutment plates (20) are located on both sides of the bridge deformation detection device (18) and are in contact with it.

5. The bridge construction monitoring device according to claim 4, Features: The outer walls of one side of the two abutment plates (20) close to each other are both provided with a protective pad, and the outer wall of one side of the protection box (12) is provided with a long groove (15), and the two threaded blocks (22) are both slidably installed in the long groove (15).

6. The bridge construction monitoring device according to claim 1, Features: An installation groove (9) is provided on one side outer wall of the installation box (8), a box door (10) is hingedly connected inside the installation groove (9), and a handle (11) is fixedly mounted on one side outer wall of the box door (10).

7. The bridge construction monitoring device according to claim 1, Features: Two telescopic rods (6) are symmetrically and fixedly mounted on the top outer wall of the bottom plate (3), and the output ends of the two telescopic rods (6) are both fixedly mounted on the bottom outer wall of the mounting box (8).

8. The bridge construction monitoring device according to claim 1, Features: The outer walls on both sides of the bottom plate (3) are fixedly mounted with fixing seats (2), and positioning bolts (4) are screwed onto the two fixing seats (2). The two positioning bolts (4) are threadedly connected to the embedded parts (1), and positioning knobs (5) are fixedly mounted on one end of the top of the two positioning bolts (4).

Citation Information

Cited By

  • Visual bridge deformation monitoring equipment

    CN119146873A