Device for adjusting and fixing foundation bolt during concrete pouring

Through the combined device of the bracket, positioning plate and sliding seat, the problem of adjusting and fixing the anchor bolts when pouring concrete is solved, and the fast and accurate installation and adjustment of the anchor bolts is realized, which is suitable for the needs of different foundation pit sizes and heights.

CN221837620UActive Publication Date: 2024-10-15SICHUAN CLOUD WALL TECHNOLOGY CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323512276.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-22
Publication Date
2024-10-15
Estimated Expiration
2033-12-22

AI Technical Summary

Technical Problem

When pouring concrete, there are difficulties in quickly and accurately adjusting and fixing anchor bolts. The existing technology cannot fully solve the inconvenience of height and horizontal position adjustment and the problem of on-site clutter.

Method used

A device is designed that includes a bracket, a positioning plate and a sliding base. The bracket can be height-adjusted, the positioning plate can be rotated and fixed on the sliding base, and the sliding base moves on the bracket through a slide rail combination to achieve the horizontal positioning of the anchor bolts. and fixed, combined with push rods and hangers to improve operational convenience.

Benefits of technology

It realizes the rapid installation, adjustment and fixation of anchor bolts, meets the adaptability of different foundation pit sizes and heights, and ensures position accuracy and ease of operation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221837620U_ABST
    Figure CN221837620U_ABST
Patent Text Reader

Abstract

The utility model relates to a device for adjusting and fixing a foundation bolt during concrete pouring, which comprises a support used for being installed at a foundation pit and a positioning disc arranged on the support and used for fixing the foundation bolt to be poured, and a positioning groove used for fixing the foundation bolt to be poured is arranged on the positioning disc. The positioning disc is arranged on the sliding seat, and the positioning disc can rotate around the center on the sliding seat and is fixed. The sliding seat is arranged on the support through a plurality of sliding rail combinations, so that the positioning disc can move and be fixed in any direction in the horizontal plane relative to the support. According to the device, the foundation bolt can be quickly mounted, adjusted and fixed before foundation pouring, and convenience and rapidness are achieved. The support long cross beam is designed to be of a telescopic structure, can be suitable for different foundation pit opening sizes, and is wide in application range. The support is provided with a height adjusting section, adjustment is convenient to meet different basic dew heights, meanwhile, a lifting device is arranged to facilitate height fine adjustment, and the height and horizontal precision requirements are met.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to a device for adjusting and fixing anchor bolts when pouring concrete. Background Art

[0002] When many devices are installed on a foundation, the base needs to be fixed with anchor bolts. The foundation is poured concrete, and the anchor bolts are poured into the foundation while the concrete is being poured.

[0003] For example, transmission line towers are held in place by anchor bolts cast into the foundation.

[0004] Before pouring the foundation of the transmission line tower, anchor bolts need to be installed. The height and horizontal position of the anchor bolts have very high precision requirements. In conventional construction, a simple steel pipe bracket is usually set up. Multiple channel steels or other steel sections are placed on the top of the bracket to support the anchor bolt positioning plate. The anchor bolts are fixed with the positioning plate, and the position is adjusted by hammering. This method has the problems of inconvenient height and horizontal position adjustment and messy site. Many units have made device innovations, but they have only solved local problems and have not fully solved the various inconveniences existing in the existing technology.

[0005] In fact, in the installation of mechanical equipment, the requirements for anchor bolts are generally high, but there is currently no good device for how to efficiently fix the anchor bolts when pouring the foundation. Utility Model Content

[0006] In order to solve the above technical problems, the utility model provides a device for adjusting and fixing anchor bolts when pouring concrete, which can solve the problem of adjusting and fixing anchor bolts before foundation pouring, and the adjustment is accurate and fast.

[0007] The solution of the utility model includes a bracket for installation in a concrete foundation pit, and a positioning plate arranged on the bracket for fixing the anchor bolts to be cast, wherein the positioning plate is provided with a plurality of positioning grooves for passing the anchor bolts to be cast and fixing the anchor bolts to be cast.

[0008] The positioning plate is arranged on the slide seat, and the positioning plate can rotate along the center and be fixed on the slide seat.

[0009] The slide seat is arranged on the bracket through a plurality of slide rails, so that the positioning plate can be moved and fixed in any direction in the horizontal plane relative to the bracket.

[0010] In the device for adjusting and fixing anchor bolts when pouring concrete as described above, the positioning plate is a circular plate.

[0011] The width of the positioning groove is adapted to the diameter of the anchor bolt to be cast.

[0012] A plurality of positioning grooves are radially and equidistantly distributed on the disk from the center of the positioning disk; the center lines of the positioning grooves coincide with the virtual rays passing through the center of the positioning disk.

[0013] The number of the positioning grooves is at least 2, 4, 6, 8, or 10.

[0014] An anchor bolt lifting hole is arranged in the center of the positioning plate, and the lifting hole passes through each positioning slot.

[0015] A retaining ring is arranged on the circumference of the positioning plate.

[0016] Reinforcement ribs are designed between each positioning groove.

[0017] The device for adjusting and fixing the anchor bolts when pouring concrete as described above, wherein an opening concentric with the positioning plate is provided in the middle of the slide seat, and a step surface for supporting the positioning plate is provided around the opening;

[0018] There are a number of blocks around the opening for fixing the positioning plate to the middle of the slide seat in the horizontal direction, and the blocks are provided with fastening screws;

[0019] The outer circumferential surface of the positioning disk is provided with teeth, the sliding seat is provided with a gear which meshes with the teeth and drives the positioning disk to rotate, and the upper end of the gear shaft is provided with a knob adapted to a wrench.

[0020] As described above, the device for adjusting and fixing anchor bolts when pouring concrete, wherein the slide is arranged on the bracket through a combination of several slide rails, specifically: a first slide rail and a first slide groove combination are arranged, so that the slide moves on the bracket in a first direction; a second slide rail and a second slide groove combination are arranged, so that the slide moves on the bracket in a second direction perpendicular to the first direction.

[0021] The device for adjusting and fixing the anchor bolts when pouring concrete as described above, wherein the first slide rail is combined with the first slide groove, has a specific structure of: two first slide rails are provided, and both sides of the slide seat have first slide grooves that match the first slide rails;

[0022] The second slide rail and the second slide groove are combined, and the specific structure is: the two ends of the first slide rail have a second slide groove that fixes the same end of the two first slide rails together, and there are second slide rails on both sides of the bracket. The second slide rail and the second slide groove are perpendicular to the first slide rail, and the second slide groove cooperates with the second slide rail.

[0023] The device for adjusting and fixing the anchor bolts when pouring concrete as described above, wherein the bracket comprises at least four legs with adjustable heights, and a crossbeam is arranged between the legs, and the crossbeam is detachably connected to the legs through a connecting seat fixed to the upper end of the legs;

[0024] A second slide rail is arranged on the cross beams on both sides of the bracket;

[0025] The other two sides are telescopic beams with adjustable lengths. The two ends of the telescopic beams are connected to the supporting legs and are divided in the middle and inserted into the sleeves.

[0026] The device for adjusting and fixing the anchor bolts when pouring concrete as described above, wherein a reinforcement tripod is provided between the lower side of the support beam and the legs at both ends of the beam;

[0027] One end of the reinforced tripod on the lower side of the telescopic beam is hinged to the sleeve, and a slider is arranged at the other end. A longitudinal slide groove cooperating with the slider is arranged on the side of the leg, and a locking structure is arranged between the slider and the longitudinal slide groove.

[0028] The device for adjusting and fixing the anchor bolts during concrete pouring as described above, wherein the bracket is provided with a push rod, including a first push rod and a second push rod,

[0029] The base of the first push rod is movably arranged on the sleeve, and the telescopic end is fixed on the side of the slide seat;

[0030] The second push rod is perpendicular to the first push rod; the base of the second push rod is fixed on the second slide groove, and the telescopic end is fixed on the side of the slide seat.

[0031] As described above, the device for adjusting and fixing the anchor bolts when pouring concrete, wherein a hanger is arranged on the slide, the hanger has two pillars fixed on the slide, a cross bar is arranged at the upper end of the pillar, and a lifting pulley is arranged on the cross bar above the center of the opening.

[0032] As described above, the device for adjusting and fixing the anchor bolts when pouring concrete, wherein a protective cover is detachably provided above the positioning plate, the height of the protective cover is greater than the length of the anchor bolts to be poured above the positioning plate; the protective cover is buckled on the inner circular surface of the retaining ring.

[0033] Beneficial technical effects:

[0034] The device can solve the problems of rapid installation, adjustment and fixation of anchor bolts before foundation pouring.

[0035] The device is connected, installed and removed conveniently and quickly. In particular, the support beam and the support leg are connected in a manner of boss matching groove, which makes installation and removal convenient and quick.

[0036] The long crossbeam of the bracket is designed as a retractable structure, which can be adapted to different pit opening sizes and has a wide range of applications.

[0037] The bracket is equipped with a height adjustment section to facilitate adjustment to meet different foundation heights. At the same time, a lifting device is configured to facilitate height fine-tuning to meet the height and horizontal accuracy requirements.

[0038] The structure can easily adjust the horizontal positioning position and angular direction of the anchor bolts, which is convenient for operation and ensures control accuracy. BRIEF DESCRIPTION OF THE DRAWINGS

[0039] Figure 1 It is a schematic diagram of the device structure of the utility model;

[0040] Figure 2 This is a structural diagram of the support of the utility model;

[0041] Figure 3 This is a structural diagram of the utility model in which the crossbeam and the legs are connected via a connecting seat;

[0042] Figure 4 It is a schematic diagram of the support structure of the utility model;

[0043] Figure 5 This is a schematic diagram of the movement principle structure of the slide seat of the utility model;

[0044] Figure 6 This is a schematic diagram of the structure of the slide seat of the utility model;

[0045] Figure 7 It is a schematic diagram of the positioning plate structure;

[0046] Figure 8 Schematic diagram of positioning plate plus protective cover.

[0047] in:

[0048] Bracket 1; slide 2; positioning plate 3; protective cover 4; support column 6; second push rod 7; first push rod 8; anchor bolt 9; support leg 10; sleeve 11; short cross beam 12; telescopic beam 13; reinforcing beam 14; connecting seat 15; tripod 16; third slide slot 17; longitudinal slide slot 18;

[0049] Height adjustment section 101; lifting device 102; support 103;

[0050] Sleeve 151; positioning plate 152; support plate 153; boss 154; groove 155;

[0051] first slide 20; opening 21; step surface 22; level bubble 23; hanger support 24; block 25; gear 26; tooth 27; push rod connecting seat 28;

[0052] Positioning groove 30; reinforcing rib 31; anchor bolt lifting hole 32; retaining ring 33;

[0053] The second slide groove 50 ; the first slide rail 51 ; the baffle 52 ; the adjusting screw hole 53 ; and the pulley 60 . DETAILED DESCRIPTION

[0054] The device is installed at the concrete foundation pit through the bracket 1. The installed bracket is in the shape of a rectangular parallelepiped as a whole, wherein the telescopic beam 13 in the length direction realizes telescopic adjustment to adapt to the different sizes of the foundation pit openings.

[0055] The main structure of the bracket uses rectangular tubes in many places, which can actually be replaced with channel steel, I-beam or lattice structure. The connection method of each connection point of the main structure of the bracket is of course not limited to one, but other connection methods can be used, such as screw connection, clamp connection, etc.

[0056] The support includes four height-adjustable legs 10, which mainly bear vertical loads and are connected to the crossbeam and tripod 16 to increase the strength of the entire structure. The legs can be made of square tubes, rectangular tubes, channel steels, etc., or lattice structures.

[0057] The leg 10 has a height adjustment section, and the height adjustment section 101 is used to adjust the height when the exposed height of the foundation changes greatly. The height adjustment section 101 is exemplified as a circular tube, and can also be a square tube, rectangular tube, channel steel, etc., or a lattice structure.

[0058] The support leg has a lifting device 102, which is used to adjust the height of the support and adjust the horizontality of the plane on the support. A lifting mechanism such as a hand-cranked jack, a screw rod, a hydraulic jack, etc. can be used. When the adjustment range of the lifting device cannot meet the height adjustment, the height adjustment section needs to be replaced.

[0059] The supporting leg has a support 103, which is the component of the entire structure that contacts the ground. The main function of the support is to increase the contact area. The support is provided with a double fork that is hinged to the height adjustment section.

[0060] A crossbeam is arranged between the legs, and the crossbeam is detachably connected to the legs through a connection seat 15 fixed on the upper end of the legs; the connection seat 15 is a connector of the leg crossbeam connection point, and one example is that the crossbeam is detachably connected to the legs through a connection seat fixed on the upper end of the legs, wherein the connection seat includes a sleeve 151 for fixing with the upper end of the legs, and the upper end of the legs 10 is connected to the sleeve; a positioning plate 152 for extending into the end of the crossbeam to support the inner surface of the crossbeam, the positioning plate is a solid plate, and the upper edge supports the lower surface of the top plate of the inner cavity of the crossbeam; a support plate 153 for supporting the lower surface of the end of the crossbeam, and the crossbeams are all connected to the support plate, and a boss 154 is provided on the support plate, and a groove 155 matching the boss is provided at the end of the crossbeam, and the boss is inserted into the groove to fix the crossbeam and the connection seat in the horizontal direction. This method realizes quick connection. Of course, there is more than one way to achieve quick connection, and there can be other ways, such as quick-release screw connection.

[0061] The length direction of the bracket is a telescopic beam 13 with adjustable length. The two ends of the telescopic beam are connected to the upper ends of the adjacent legs through a connecting seat. The telescopic beam can be a square tube, a rectangular tube, a channel steel, an I-beam, etc., or a lattice structure. In this example, it is a rectangular tube. The telescopic beam adopts a three-section combination to achieve adjustable length to adapt to foundation pits of different sizes. The two ends of the telescopic beam are connected to the legs 10, and the middle is separated and inserted into the sleeve 11. The telescopic beam is used to strengthen the bracket structure.

[0062] The telescopic beams on both sides are connected to each other with a reinforcing beam 14, specifically, the reinforcing beam is connected to the sleeves on both sides, two reinforcing beams are arranged below the slide seat and avoid the positioning grooves and openings of the anchor bolts. Two supporting parts are arranged inside the telescopic beam to connect the reinforcing beam 14 to increase the structural strength.

[0063] A reinforcement tripod 16 is provided between the lower side of the crossbeam and the legs at both ends of the crossbeam; one end of the reinforcement tripod on the lower side of the telescopic beam is hinged to the sleeve, and a slider is provided at the other end, and a longitudinal slide groove 18 cooperating with the slider is provided on the side of the leg, and a locking structure, such as a screw locking structure, is provided between the slider and the longitudinal slide groove. When the bracket is adjusted in the length direction, the slider can be adjusted up and down to make the tripod adapt to the length of the telescopic beam.

[0064] The length direction of the bracket is a telescopic beam 13 with adjustable length, and the other direction is a short cross beam 12. The two ends of the short cross beam are connected to the connecting seats at the upper ends of the adjacent legs. The short cross beam can be made of square tubes, channel steels, etc., or a lattice structure. The example uses a rectangular tube.

[0065] A hanger support is provided on the slide, and the lower end of the hanger is connected to the hanger support. The hanger has two pillars 6 fixed on the slide, and a cross bar is provided on the upper end of the pillar, and the cross bar is placed above the center of the opening. The hanger is used to lift the anchor bolts, which is convenient for installing the anchor bolts in place and improving the safety of operation. A lifting pulley 60 is provided on the cross bar, and the pulley passes through the lifting rope. One end of the rope fixes the anchor bolt, and the other end is pulled by manpower or machinery to lift the anchor bolt. A small winch can also be directly installed on the upper end of the hanger to lift the anchor bolt.

[0066] A protective cover 4 is provided above the positioning plate. In order to completely buckle the anchor bolts, the height of the protective cover is greater than the length of the anchor bolts to be poured above the positioning plate; the protective cover is buckled on the inner circular surface of the retaining ring. The protective cover is buckled directly above the positioning plate, mainly to prevent cement slurry from contaminating the anchor bolts protruding from the foundation when pouring concrete.

[0067] The positioning plate is mainly used to position the anchor bolts to be cast and complete the fixation. The positioning plate 3 is set on the slide 2, and the positioning plate can be rotated and fixed along the center on the slide. The positioning plate 3 is a circular plate, but it does not have to be a circular plate. If it is a square, and the four corners of the square are set as large rounded corners, the function can also be achieved in the utility model, because the rotation angle requirement of the positioning plate is not large.

[0068] The positioning plate is provided with a plurality of positioning grooves 30 for passing the anchor bolts 9 to be cast and fixing the anchor bolts 9 to be cast. Since the number of anchor bolts can be 2, 4, 6, 8 or 10 (of course, the possibility of using 3 anchor bolts is not excluded), the number of positioning grooves includes at least 2, 4, 6, 8, and 10; but in most cases, 4 are used, and in some cases, 8 are used, so 8 positioning grooves are considered, and the 8 positioning grooves can take into account the situations of 4 and 8 anchor bolts at the same time. These positioning grooves 30 are radially and equidistantly distributed on the disc from the center of the positioning plate, wherein the midline of the positioning groove 30 coincides with the virtual ray passing through the center of the positioning plate, that is, the positioning grooves all point to the center of the positioning plate. This is to accommodate anchor bolts with different spacings. For example, when the anchor bolts require a large spacing, the anchor bolts fixed on the positioning plate will be closer to the edge of the positioning plate; and when the anchor bolts require a smaller spacing, the anchor bolts fixed on the positioning plate will be closer to the center of the positioning plate. Therefore, the positioning groove has a certain length to accommodate different distribution spacings of the anchor bolts, and the anchor bolts can be positioned at different positions in the positioning groove according to different spacings. The width of the positioning groove is adapted to the diameter of the anchor bolts to be cast; the positioning groove and the anchor bolt clearance match.

[0069] An anchor bolt hoisting hole 32 is provided at the center of the positioning plate, and the hoisting hole passes through each positioning slot. When installing the anchor bolt to the positioning plate, the anchor bolt is hoisted from the hoisting hole, the upper end of the anchor bolt is hoisted to be in a vertical state, and then the hoisted anchor bolt is moved horizontally into the positioning slot for fixation.

[0070] A retaining ring 33 is arranged around the circumference of the positioning plate; reinforcing ribs 31 are designed between each positioning groove, and the reinforcing ribs are connected to the retaining ring to jointly enhance the strength of the positioning plate. Of course, if the material of the positioning plate itself is strong enough, it is not necessary to set the retaining ring and reinforcing ribs.

[0071] The positioning disc is carried by the slide 2. An opening 21 concentric with the positioning disc is arranged in the middle of the slide, which is convenient for inserting the anchor bolts, and a step surface 22 for carrying the positioning disc is arranged around the opening to form a sink for installing the positioning disc, and the positioning disc is placed on the sink.

[0072] The positioning plate can be easily rotated when placed on the sink (there is a cushion layer with a very small friction coefficient between them to achieve easy sliding). The outer surface of the positioning plate is provided with a section of teeth 27, and the slide seat is provided with a gear 26 that meshes with the teeth. The lower end of the gear shaft is rotatably fixed on the slide seat, and the upper end of the gear shaft has a knob adapted to a wrench. The wrench is inserted into the knob, and the wrench can turn the small gear, so that the positioning plate can be easily rotated and the rotation angle of the positioning plate can be adjusted to meet the positioning plate angle fine-tuning and adjust the distribution angle of the anchor bolts. Of course, the method of driving the positioning plate to rotate can also be other methods, for example, a knocking block can be set on the retaining ring of the positioning plate, and it can also be rotated appropriately by gently tapping with a rubber hammer.

[0073] There are several blocks 25 around the opening, one example is 4 blocks evenly distributed, and there are fastening screws on the blocks. After the rotation angle of the positioning plate is adjusted to the right position, the front end of the fastening screw screwed into the block presses against the outer cylindrical surface of the retaining ring of the positioning plate to ensure that the positioning plate is stable and immovable.

[0074] The slide 2 is arranged on the bracket 1 through a combination of several slide rails, so that the positioning plate can be moved and fixed in any direction in the horizontal plane relative to the bracket 1. Specifically, a first slide rail and a first slide groove are arranged to make the slide move in a first direction on the bracket; a second slide rail and a second slide groove are arranged to make the slide move in a second direction perpendicular to the first direction on the bracket.

[0075] The first slide rail and the first slide groove are combined, and the specific structure is: two first slide rails 51 are provided, and first slide grooves 20 cooperating with the first slide rails are provided on both sides of the slide seat; the first slide groove is buckled downward, and the first slide groove is buckled on the first slide rail, so that the slide seat can move freely in the first direction (there is a cushion layer with a very small friction coefficient between them, which can achieve easy sliding).

[0076] The second slide rail is combined with the second slide groove 50, and the specific structure is: the two ends of the first slide rail have second slide grooves 50 for fixing the same ends of the two first slide rails together, the second slide grooves are perpendicular to the first slide rails 51, and the second slide grooves are buckled downward; the second slide rails are provided on both sides of the bracket, and the second slide grooves cooperate with the second slide rails. One example is that the short crossbeam 12 is directly used as the second slide rail, and another example is that a crossbeam parallel to the short crossbeam is set separately as the second slide rail, or the second slide rail is placed on the short crossbeam. One of the preferred examples is to set the short crossbeam 12 as the second slide rail, and the second slide groove matches the short crossbeam, and can slide back and forth on the short crossbeam (there is a cushion layer with a very small friction coefficient in between to achieve easy sliding, such as a polytetrafluoroethylene plate) to adjust the position of the slide seat. The second slide groove is also a crossbeam. Buckles are provided at both ends of the plane on the second slide groove. The buckles are two baffles 52. The first slide rail is placed between the two baffles. Screw holes are provided on the two baffles, and the first slide rail is provided with multiple adjustment screw holes 53. Therefore, the screw holes on the two baffles match the adjustment screw holes 53 on different first slide rails and pins are inserted to obtain different spacings between the two second slide grooves to adjust the overall length of the bracket, and the length adjustment function of the telescopic beam can also adapt to the different spacings between the two second slide grooves.

[0077] A level bubble 23 is provided at one corner of the slide 2 to facilitate leveling of the entire device, and a gear mounting hole is provided at another corner for mounting gears. Hanger supports 24 are provided at the other two opposite corners of the slide to connect the hangers. Each set of hanger supports has two holes arranged above and below. When installing the hanger, the hanger and the hanger support are first connected to one hole to facilitate rotating and erecting the hanger, and then connected to the other hole after the hanger is erected.

[0078] The bracket is provided with push rods, including a first push rod 8 and a second push rod 7. In this example, the first push rod and the second push rod are electric push rods. Of course, the first push rod and the second push rod can also be replaced by a screw structure.

[0079] The base of the first push rod 8 is movably arranged on the sleeve 11, and a third slide groove 17 is arranged on the upper surface of the middle section of one of the sleeves, and the base of the first push rod is installed in the third slide groove; when the slide moves in the left and right directions, the first push rod follows the movement, and the base of the first push rod remains in the third slide groove.

[0080] The extension direction of the second push rod 7 is perpendicular to that of the first push rod; and the base of the first push rod is fixed on the second slide groove.

[0081] The telescopic ends of the first push rod and the second push rod are fixed on the two sides of the slide. In one example, a push rod connecting seat 28 is provided on the side of the slide to connect the telescopic ends of the first push rod and the second push rod. The first push rod and the second push rod are telescopic to move the slide. The first push rod moves the slide forward and backward, and the second push rod moves the slide left and right. After moving into place, the fixed position is maintained by the push-pull rod.

[0082] Another example is that the slide is arranged on the bracket through a combination of several slide rails, so that the positioning plate can be moved and fixed in any direction in the horizontal plane relative to the bracket. The slide is fixed as a whole with the first slide rail, and buckles are provided at both ends of the upper plane of the second slide groove. The buckles are two baffles, and the first slide rail is placed between the two baffles. The first slide rail can slide relatively between the two baffles of the second slide groove, so that the slide can move in one direction; the second slide groove slides on the short crossbeam to move in the other direction. After moving into place, it is kept in a fixed position by a push-pull rod. Of course, there are other ways to realize the arbitrary horizontal movement of the slide with the positioning plate.

[0083] The operating steps of the device for adjusting and fixing the anchor bolts of the utility model are as follows:

[0084] 1. Assemble the bracket: select the appropriate height adjustment section according to the exposed height of the foundation, and adjust the distance between the two second chutes and the length of the telescopic beam column according to the size of the foundation pit. Install the telescopic beam and short beam.

[0085] 2. Install the slide: Place the second slide onto the short crossbeam (second slide rail), and then place the first slide rail on the second slide. Place the slide on the first slide rail, and buckle the first slide under the slide onto the first slide rail. Place a cushion layer on the slide disc sink first, and then place the positioning plate.

[0086] 3. Install the electric push rod: Install the electric push rod in two directions, and connect the top of the telescopic end of the electric push rod to the connecting seat on the slide.

[0087] 4. Install the hanger: Place the lower end of the hanger horizontally into the slide support, insert a bolt after the holes are aligned, rotate and stand up the hanger, then insert another bolt to fix the hanger, and insert the lifting rope onto the pulley.

[0088] 5. Install the anchor bolts: Use the lifting rope to lift the anchor bolts. The anchor bolts are inserted into the anchor bolt lifting holes from top to bottom, placed in the positioning plate, and then moved horizontally into the positioning grooves. The positions are adjusted according to the distribution size of the anchor bolts and then fixed. The fixing method is: insert the two nuts of the anchor bolts and fasten them to the positioning plate from the upper and lower surfaces of the positioning plate.

[0089] 6. Positioning adjustment: fine-tune the height of the bracket legs so that the level bubble on the slide is centered. Roughly adjust the slide to the center of the plane on the bracket, and adjust the overall structural position so that the center of the slide is roughly above the center of the foundation pit. Under the monitoring of the theodolite, adjust the two electric push rods to the center of the slide so that the center point of the anchor bolt distribution reaches the accurate position. Use a wrench to turn the pinion gear so that the distribution direction of the anchor bolt meets the requirements. Tighten the tightening screws on the blocks in the four directions of the slide to clamp the positioning plate. Finally, cover the protective cover on the positioning plate to prevent the concrete from sinking into the exposed part of the anchor bolt during concrete pouring.

[0090] After the above steps, the installation, adjustment and fixing of the anchor bolts are completed, and the device can be removed after the concrete pouring and formwork removal are completed.

[0091] The above is an exemplary description of the present invention, and the examples are not exhaustive. Many new examples can be formed under the inspiration of the idea of ​​the present invention. However, if the idea of ​​the present invention is adopted to form other examples, they will also fall within the protection scope of the present invention.

Claims

1. A device for adjusting and fixing anchor bolts when pouring concrete, comprising a bracket for installation at a concrete foundation pit, and a positioning plate arranged on the bracket for fixing the anchor bolts to be poured, characterized in that: The positioning plate is provided with a plurality of positioning grooves for passing the anchor bolts to be cast and fixing the anchor bolts to be cast; The positioning plate is arranged on the slide seat, and the positioning plate can rotate along the center and be fixed on the slide seat; The slide seat is arranged on the bracket through a plurality of slide rails, so that the positioning plate can be moved and fixed in any direction in the horizontal plane relative to the bracket.

2. The device for adjusting and fixing anchor bolts during concrete pouring as claimed in claim 1, characterized in that: The positioning plate is a circular plate. The width of the positioning groove is adapted to the diameter of the anchor bolt to be cast; A plurality of positioning grooves are radially and equidistantly distributed on the disk from the center of the positioning disk; the midlines of the positioning grooves coincide with the virtual rays passing through the center of the positioning disk; The number of the positioning slots is at least 2, 4, 6, 8 or 10; A foundation bolt lifting hole is set in the center of the positioning plate, and the lifting hole passes through each positioning slot; A retaining ring is arranged on the circumference of the positioning plate; Reinforcement ribs are designed between each positioning groove.

3. The device for adjusting and fixing anchor bolts during concrete pouring as claimed in claim 1, characterized in that: An opening concentric with the positioning plate is arranged in the middle of the slide seat, and a step surface for supporting the positioning plate is arranged around the opening; There are a number of blocks around the opening for fixing the positioning plate to the middle of the slide seat in the horizontal direction, and the blocks are provided with fastening screws; The outer circumferential surface of the positioning disk is provided with teeth, the sliding seat is provided with a gear which meshes with the teeth and drives the positioning disk to rotate, and the upper end of the gear shaft is provided with a knob adapted to a wrench.

4. The device for adjusting and fixing anchor bolts during concrete pouring as claimed in claim 1, characterized in that: The slide is arranged on the bracket through a combination of several slide rails, specifically: a first slide rail and a first slide groove combination are arranged to enable the slide to move in a first direction on the bracket; a second slide rail and a second slide groove combination are arranged to enable the slide to move in a second direction perpendicular to the first direction on the bracket.

5. The device for adjusting and fixing anchor bolts during concrete pouring as claimed in claim 4, characterized in that: The first slide rail is combined with the first slide groove, and the specific structure is: two first slide rails are provided, and both sides of the slide seat are provided with first slide grooves matching with the first slide rails; The second slide rail and the second slide groove are combined, and the specific structure is: the two ends of the first slide rail have a second slide groove that fixes the same end of the two first slide rails together, and there are second slide rails on both sides of the bracket. The second slide rail and the second slide groove are perpendicular to the first slide rail, and the second slide groove cooperates with the second slide rail.

6. The device for adjusting and fixing anchor bolts during concrete pouring as claimed in claim 1, characterized in that: The bracket includes at least four legs with adjustable heights, and a crossbeam is arranged between the legs. The crossbeam is detachably connected to the legs through a connecting seat fixed to the upper end of the legs, wherein the connecting seat includes a sleeve for fixing to the upper end of the legs, a positioning plate for extending into the end of the crossbeam to support the inner surface of the crossbeam, and a supporting plate for supporting the lower surface of the end of the crossbeam. The legs are connected to the sleeve, and the crossbeams are connected to the supporting plate. The supporting plate is provided with a boss, and the end of the crossbeam is provided with a groove matching the boss. A second slide rail is arranged on the cross beams on both sides of the bracket; The other two sides are telescopic beams with adjustable lengths. The two ends of the telescopic beams are connected to the supporting legs and are divided in the middle and inserted into the sleeves.

7. The device for adjusting and fixing anchor bolts during concrete pouring as claimed in claim 6, characterized in that: A reinforcement tripod is provided between the lower side of the beam and the legs at both ends of the beam; One end of the reinforced tripod on the lower side of the telescopic beam is hinged to the sleeve, and a slider is arranged at the other end. A longitudinal slide groove cooperating with the slider is arranged on the side of the leg, and a locking structure is arranged between the slider and the longitudinal slide groove.

8. The device for adjusting and fixing anchor bolts during concrete pouring as claimed in claim 6, characterized in that: The bracket is provided with push rods, including a first push rod and a second push rod; The base of the first push rod is movably arranged on the sleeve, and the telescopic end is fixed on the side of the slide seat; The second push rod is perpendicular to the first push rod; the base of the second push rod is fixed on the second slide groove, and the telescopic end is fixed on the side of the slide seat.

9. The device for adjusting and fixing anchor bolts during concrete pouring as claimed in claim 1, characterized in that: A hanger is arranged on the sliding seat. The hanger has two pillars fixed on the sliding seat. A cross bar is arranged at the upper ends of the pillars. A lifting pulley is arranged above the center of the opening on the cross bar.

10. The device for adjusting and fixing anchor bolts during concrete pouring as claimed in claim 1, characterized in that: A protective cover is detachably provided above the positioning plate, the height of which is greater than the length of the anchor bolt to be poured above the positioning plate; the protective cover is buckled on the inner circular surface of the retaining ring.